Other: DCL-16-023, Response to NRC Letter Dated February 2, 2016, Requests for Additional Information for the Review of the License Renewal Application - Set 39, ML100710113, ML100710114, ML101690321, ML101890832, ML101960644, ML110460718, ML13135A010, ML15037A540, ML15233A518, ML15243A582, ML15275A094, ML15275A130, ML16271A439
|
MONTHYEARML1007101142010-03-10010 March 2010 Task Order No. 002 Under Delivery Order No. NRC-03-10-070 Project stage: Other ML1007101132010-03-10010 March 2010 Task Order No. 002 Under Delivery Order No. NRC-03-10-070 Project stage: Other ML1013201872010-05-18018 May 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application Project stage: RAI ML1013806142010-05-24024 May 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Scoping and Screening Methodology Project stage: RAI DCL-10-066, License Amendment Request 10-03, Damping Values for the Seismic Design and Analysis of the Reactor Vessel Integrated Head Assembly2010-06-14014 June 2010 License Amendment Request 10-03, Damping Values for the Seismic Design and Analysis of the Reactor Vessel Integrated Head Assembly Project stage: Request ML1015404192010-06-14014 June 2010 Letter Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Programs Project stage: RAI DCL-10-067, Response to License Renewal Application (LRA) Request for Additional Information & LRA Errata2010-06-18018 June 2010 Response to License Renewal Application (LRA) Request for Additional Information & LRA Errata Project stage: Request ML1016201872010-06-21021 June 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Programs Project stage: RAI ML1016901302010-06-29029 June 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Programs Project stage: RAI ML1017601042010-07-0606 July 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application Project stage: RAI DCL-10-073, Response to NRC Request for Additional Information on License Renewal Application2010-07-0707 July 2010 Response to NRC Request for Additional Information on License Renewal Application Project stage: Response to RAI ML1017602432010-07-14014 July 2010 RAI Related to the Review of the DCPP LRA - Aging Management Programs Project stage: RAI ML1018301312010-07-15015 July 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Scoping and Screening and Aging Management Review Project stage: RAI ML1018908322010-07-16016 July 2010 Audit Report Regarding the Diablo Canyon Nuclear Power Plant License Renewal Application Scoping and Screening Methodology Project stage: Other DCL-10-077, Response to NRC Letter Dated June 21, 2010 Request for Additional Information (Set 5) for License Renewal Application2010-07-19019 July 2010 Response to NRC Letter Dated June 21, 2010 Request for Additional Information (Set 5) for License Renewal Application Project stage: Request ML1018700882010-07-19019 July 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Programs Project stage: RAI ML1018301442010-07-20020 July 2010 RAI Related to the Review of the DCPP LRA - Aging Management Programs and Aging Management Review Project stage: RAI ML1018802552010-07-20020 July 2010 RAI Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Reactor Vessel Internals Project stage: RAI ML1019004702010-07-20020 July 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 & 2, LRA (Tac Nos. ME2896, and ME2897) - Scoping and Screening Project stage: RAI ML1018807352010-07-22022 July 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application - Aging Management Review and Aging Management Programs Project stage: RAI ML1018900212010-07-22022 July 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application - Aging Management Review and Time Limited Aging Analysis Project stage: RAI DCL-10-091, Response to NRC Letter Dated June 18, 2010, Request for Additional Information (High Energy Piping) for License Renewal Application2010-07-28028 July 2010 Response to NRC Letter Dated June 18, 2010, Request for Additional Information (High Energy Piping) for License Renewal Application Project stage: Request ML1020004882010-08-0303 August 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Review and Aging Management Programs Project stage: RAI ML1020402512010-08-0909 August 2010 RAI Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Scoping and Screening and Aging Management Review Project stage: RAI ML1016903212010-08-11011 August 2010 Audit Report for Plant Aging Management Programs for DCPP, Units 1 and 2 Project stage: Other ML1019606442010-08-13013 August 2010 Safety Project Manager Change for the License Renewal Project for Diablo Canyon Nuclear Power Plant Project stage: Other DCL-2010-536, Submittal of National Marine Fisheries Service (NMFS) Marine Mammal and Marine Turtle Stranding Report for a Sea Turtle Discovered in the Diablo Canyon Intake Structure2010-08-25025 August 2010 Submittal of National Marine Fisheries Service (NMFS) Marine Mammal and Marine Turtle Stranding Report for a Sea Turtle Discovered in the Diablo Canyon Intake Structure Project stage: Request ML1021705242010-08-25025 August 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Metal Fatigue Project stage: RAI ML1020107002010-08-26026 August 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Time Limited Aging Analyses and Aging Management Programs Project stage: RAI ML1022402772010-08-26026 August 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC ME2896 and ME2897) - Aging Management Programs Project stage: RAI ML1022905422010-08-30030 August 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Review and Time Limited Aging Analyses Project stage: RAI DCL-10-113, Response to NRC Letter Dated August 3, 2010, Request for Additional Information (Set 16) for the License Renewal Application2010-08-30030 August 2010 Response to NRC Letter Dated August 3, 2010, Request for Additional Information (Set 16) for the License Renewal Application Project stage: Request ML1023607492010-09-0101 September 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Programs Project stage: RAI ML1024300272010-09-13013 September 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. Me 2869 and ME2897) - Scoping and Screening Project stage: RAI ML1024600502010-09-17017 September 2010 RAI Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 & ME2897) Aging Management Programs Project stage: RAI ML1025202782010-09-17017 September 2010 RAI Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Scoping and Screening Project stage: RAI DCL-10-121, Response to NRC Letter Dated August 25, 2010, Request for Additional Information (Set 19) for License Renewal Application2010-09-22022 September 2010 Response to NRC Letter Dated August 25, 2010, Request for Additional Information (Set 19) for License Renewal Application Project stage: Request ML1025102972010-09-23023 September 2010 RAI Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Time Limited Aging Analyses Project stage: RAI DCL-10-120, Response to NRC Letter Dated August 26, 2010, Request for Additional Information (Set 17) for License Renewal Application2010-09-24024 September 2010 Response to NRC Letter Dated August 26, 2010, Request for Additional Information (Set 17) for License Renewal Application Project stage: Request ML1024601512010-09-28028 September 2010 Summary of Telephone Conference Call Held on 9/2/10 Between Us NRC and Pacific Gas and Electric Company Concerning the Response to RAIs Related to the Diablo Canyon Nuclear Power Plant Units 1 and 2 LRA Project stage: RAI ML1025202642010-09-29029 September 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application - Aging Management Review Project stage: RAI ML1026605412010-09-30030 September 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Fire Protection Project stage: RAI DCL-10-126, Response to NRC Letter Dated September 1, 2010, Request for Additional Information(Set 22) for the Diablo Canyon License Renewal Application2010-09-30030 September 2010 Response to NRC Letter Dated September 1, 2010, Request for Additional Information(Set 22) for the Diablo Canyon License Renewal Application Project stage: Request ML1029806892010-11-0202 November 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Time Limited Aging Analysis Project stage: RAI ML1029306302010-11-0303 November 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application - Aging Management Programs Project stage: RAI ML1034104342010-12-20020 December 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC ME2896 and ME2897) - Time Limited Aging Analysis Project stage: RAI ML1034810132010-12-20020 December 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Program and Time Limited Aging Analysis Project stage: RAI ML1035603212011-01-10010 January 2011 12/8/10 Summary of Telephone Conference Call Held Btw the USNRC and Pacific Gas and Electric Company Concerning Requests for Additional Information Response Related to the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Ap Project stage: RAI ML1034904172011-01-10010 January 2011 12/1/10 Summary of Telephone Conference Call Held Btw the USNRC and Pacific Gas and Electric Company Concerning Draft Request for Additional Information Related to the Diablo Canyon Nuclear Power Plant, Units 1 and 2, LRA Project stage: Draft RAI ML1034306232011-01-11011 January 2011 Summary of Telephone Conference Call Held Between NRC and PG&E Concerning Request for Additional Information Related Tot the Diablo Canyon Nuclear Power Plant, Units 1 and 2, LRA (TAC Nos. ME2896 & ME2897) Project stage: RAI 2010-07-07
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 13, 2010 Mr. John Conway Senior Vice President Generation and Chief Nuclear Officer Pacific Gas and Electric Company 77 Beale Street, MC B32 San Francisco, CA 94105
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE REVIEW OF THE DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME2896 AND ME2897) - SCOPING AND SCREENING
Dear Mr. Conway:
By letter dated November 23, 2009, Pacific Gas & Electric Company submitted an application pursuant to Title 10 of the Code of Federal Regulations, Part 54, to renew the operating licenses for Diablo Canyon Nuclear Power Plant, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.
The request for additional information was discussed with Mr. Terry Grebel, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301~415-1045 or bye-mail at NathanieI.Ferrer@nrc.gov.
Sincerely, Nathaniel Ferrer, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323
Enclosure:
As stated cc w/encl: Distribution via Listserv
Diablo Canyon Nuclear Power Plant, Units 1 and 2 License Renewal Application Request for AdditionaJlnfonnation Set 22 Aging Management Programs - Clarification on Responses Based on the staffs review of Pacific Gas & Electric Company's (the applicant) responses dated July 7 and July 19, 2010, and as discussed in telephone conferences held on August 12 and August 18, 2010, please provide responses to the following:
RAJ 2.1-2 (Follow-Up)
In the June 18, 2010, response to RAI 2.1-2, the applicant added additional systems to the scope of license renewal, which included the sanitary sewage system. The U.S. Nuclear Regulatory Commission (the staff) made the following observations:
- The system description for the sanitary sewage system was provided in the June 18, 2010, letter; however, the response was unclear in assisting the staff to identify the license renewal boundary to confirm that the correct components were captured in scope in the license renewal application (LRA) Table 2.3.3-18. The staff requests that the applicant provide supplemental information to identify the license renewal boundary for the sanitary sewage system.
- On license renewal boundary drawing LR-DCPP-15-106715-02, the applicant shows the service water loop at location 29-E through A in scope for license renewal. However, the heat exchanger in that loop was not identified in LRA Table 2.3.3-18. The staff requests that the applicant justify the exclusion of the heat exchanger from the scope of license renewal.
RAJ 2.3-2 (Follow-Up)
In the June 18,2010, response to RAI2.3-2, the applicant stated that the guard pipe was within the scope of license renewal with a fire barrier intended function under Title 10 of the Code of Federal Regulations (10 CFR) 54.4(a)(3). The staff verified that on the revised license renewal boundary drawings the guard pipe was placed in scope and added to the LRA tables; however, on the revised license renewal boundary drawing for Unit 1 (LR-DCPP-08-106708-05), the manual regulator, an open diaphragm valve and closed diaphragm valve, were not depicted in scope for license renewal. On license renewal boundary drawing for Unit 2 (LR-DCPP-08 1077708-05), the same components are captured in scope for 10 CFR 54.4(a)(2). The staff requests that the applicant justify the exclusion of the above Unit 1 components from the scope of license renewal.
RAJ 2.3-3 (Follow-Up)
In the June 18, 2010, response to RAI2.3-3, the applicant added the oily water and turbine sump system to the scope of license renewal. Indications in the license renewal boundary drawings and the Final Safety Analysis Report show that there are fluid-filled components ENCLOSURE
- 2 (i.e., sumps, pumps, and piping) in the underground manholes for electrical systems and fuel oil transfer pump vaults. These fluid-filled components are potentially in the same space as safety related systems, structures, and components (SSCs) in scope for license renewal and may need to be included in the scope of license renewal in accordance with 10 CFR 54.4(a)(2). The staff requests that the applicant justify its exclusion of the fluid-filled components located in the underground manholes from scope of license renewal.
RAI 2.3-5 (Follow-Up)
In the June 18, 2010. response to RAI 2.3-5. the applicant added long term cooling as a system intended function for the condensate. makeup water. and fire protection systems. The applicant revised the systems' scoping boundaries to include additional components into the scope of license renewal required to perform this system intended function of long term cooling. Some of the systems' components required to perform this function were already in scope of license renewal, and assigned a component intended function of "leakage boundary."
In order to support the long term cooling system intended function. certain SSCs in the flow paths now have additional component intended functions. For example, strainers in the makeup water system should now have a component intended function of "filter," in order to maintain the flow path for long term cooling. The staff requests that the applicant evaluate all components in the above systems included in the revised long term cooling flow paths and provide any additional intended functions.
. ML102430027 OFFICE LA:RPOB:DLR PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME YEdmonds NFerrer DWrona NFerrer (Signature)
DATE 9/3/10 9/3/10 9/13/10 9/13/10
Letter to John Conway from Nathaniel Ferrer dated September 13, 2010
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE REVIEW OF THE DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME2896 AND ME2897) - SCOPING AND SCREENING DISTRIBUTION:
HARDCOPY:
DLRRF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource RKuntz EKeegan AJones,OGC LLake, RII MSykes, RII TMorrissey, RII RReyes, RI