Other: DCL-16-023, Response to NRC Letter Dated February 2, 2016, Requests for Additional Information for the Review of the License Renewal Application - Set 39, ML100710113, ML100710114, ML101690321, ML101890832, ML101960644, ML110460718, ML13135A010, ML15037A540, ML15233A518, ML15243A582, ML15275A094, ML15275A130, ML16271A439
|
MONTHYEARML1007101142010-03-10010 March 2010 Task Order No. 002 Under Delivery Order No. NRC-03-10-070 Project stage: Other ML1007101132010-03-10010 March 2010 Task Order No. 002 Under Delivery Order No. NRC-03-10-070 Project stage: Other ML1013201872010-05-18018 May 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application Project stage: RAI ML1013806142010-05-24024 May 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Scoping and Screening Methodology Project stage: RAI DCL-10-066, License Amendment Request 10-03, Damping Values for the Seismic Design and Analysis of the Reactor Vessel Integrated Head Assembly2010-06-14014 June 2010 License Amendment Request 10-03, Damping Values for the Seismic Design and Analysis of the Reactor Vessel Integrated Head Assembly Project stage: Request ML1015404192010-06-14014 June 2010 Letter Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Programs Project stage: RAI DCL-10-067, Response to License Renewal Application (LRA) Request for Additional Information & LRA Errata2010-06-18018 June 2010 Response to License Renewal Application (LRA) Request for Additional Information & LRA Errata Project stage: Request ML1016201872010-06-21021 June 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Programs Project stage: RAI ML1016901302010-06-29029 June 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Programs Project stage: RAI ML1017601042010-07-0606 July 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application Project stage: RAI DCL-10-073, Response to NRC Request for Additional Information on License Renewal Application2010-07-0707 July 2010 Response to NRC Request for Additional Information on License Renewal Application Project stage: Response to RAI ML1017602432010-07-14014 July 2010 RAI Related to the Review of the DCPP LRA - Aging Management Programs Project stage: RAI ML1018301312010-07-15015 July 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Scoping and Screening and Aging Management Review Project stage: RAI ML1018908322010-07-16016 July 2010 Audit Report Regarding the Diablo Canyon Nuclear Power Plant License Renewal Application Scoping and Screening Methodology Project stage: Other DCL-10-077, Response to NRC Letter Dated June 21, 2010 Request for Additional Information (Set 5) for License Renewal Application2010-07-19019 July 2010 Response to NRC Letter Dated June 21, 2010 Request for Additional Information (Set 5) for License Renewal Application Project stage: Request ML1018700882010-07-19019 July 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Programs Project stage: RAI ML1018301442010-07-20020 July 2010 RAI Related to the Review of the DCPP LRA - Aging Management Programs and Aging Management Review Project stage: RAI ML1018802552010-07-20020 July 2010 RAI Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Reactor Vessel Internals Project stage: RAI ML1019004702010-07-20020 July 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 & 2, LRA (Tac Nos. ME2896, and ME2897) - Scoping and Screening Project stage: RAI ML1018807352010-07-22022 July 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application - Aging Management Review and Aging Management Programs Project stage: RAI ML1018900212010-07-22022 July 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application - Aging Management Review and Time Limited Aging Analysis Project stage: RAI DCL-10-091, Response to NRC Letter Dated June 18, 2010, Request for Additional Information (High Energy Piping) for License Renewal Application2010-07-28028 July 2010 Response to NRC Letter Dated June 18, 2010, Request for Additional Information (High Energy Piping) for License Renewal Application Project stage: Request ML1020004882010-08-0303 August 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Review and Aging Management Programs Project stage: RAI ML1020402512010-08-0909 August 2010 RAI Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Scoping and Screening and Aging Management Review Project stage: RAI ML1016903212010-08-11011 August 2010 Audit Report for Plant Aging Management Programs for DCPP, Units 1 and 2 Project stage: Other ML1019606442010-08-13013 August 2010 Safety Project Manager Change for the License Renewal Project for Diablo Canyon Nuclear Power Plant Project stage: Other DCL-2010-536, Submittal of National Marine Fisheries Service (NMFS) Marine Mammal and Marine Turtle Stranding Report for a Sea Turtle Discovered in the Diablo Canyon Intake Structure2010-08-25025 August 2010 Submittal of National Marine Fisheries Service (NMFS) Marine Mammal and Marine Turtle Stranding Report for a Sea Turtle Discovered in the Diablo Canyon Intake Structure Project stage: Request ML1021705242010-08-25025 August 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Metal Fatigue Project stage: RAI ML1020107002010-08-26026 August 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Time Limited Aging Analyses and Aging Management Programs Project stage: RAI ML1022402772010-08-26026 August 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC ME2896 and ME2897) - Aging Management Programs Project stage: RAI ML1022905422010-08-30030 August 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Review and Time Limited Aging Analyses Project stage: RAI DCL-10-113, Response to NRC Letter Dated August 3, 2010, Request for Additional Information (Set 16) for the License Renewal Application2010-08-30030 August 2010 Response to NRC Letter Dated August 3, 2010, Request for Additional Information (Set 16) for the License Renewal Application Project stage: Request ML1023607492010-09-0101 September 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Programs Project stage: RAI ML1024300272010-09-13013 September 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. Me 2869 and ME2897) - Scoping and Screening Project stage: RAI ML1024600502010-09-17017 September 2010 RAI Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 & ME2897) Aging Management Programs Project stage: RAI ML1025202782010-09-17017 September 2010 RAI Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Scoping and Screening Project stage: RAI DCL-10-121, Response to NRC Letter Dated August 25, 2010, Request for Additional Information (Set 19) for License Renewal Application2010-09-22022 September 2010 Response to NRC Letter Dated August 25, 2010, Request for Additional Information (Set 19) for License Renewal Application Project stage: Request ML1025102972010-09-23023 September 2010 RAI Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Time Limited Aging Analyses Project stage: RAI DCL-10-120, Response to NRC Letter Dated August 26, 2010, Request for Additional Information (Set 17) for License Renewal Application2010-09-24024 September 2010 Response to NRC Letter Dated August 26, 2010, Request for Additional Information (Set 17) for License Renewal Application Project stage: Request ML1024601512010-09-28028 September 2010 Summary of Telephone Conference Call Held on 9/2/10 Between Us NRC and Pacific Gas and Electric Company Concerning the Response to RAIs Related to the Diablo Canyon Nuclear Power Plant Units 1 and 2 LRA Project stage: RAI ML1025202642010-09-29029 September 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application - Aging Management Review Project stage: RAI ML1026605412010-09-30030 September 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Fire Protection Project stage: RAI DCL-10-126, Response to NRC Letter Dated September 1, 2010, Request for Additional Information(Set 22) for the Diablo Canyon License Renewal Application2010-09-30030 September 2010 Response to NRC Letter Dated September 1, 2010, Request for Additional Information(Set 22) for the Diablo Canyon License Renewal Application Project stage: Request ML1029806892010-11-0202 November 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Time Limited Aging Analysis Project stage: RAI ML1029306302010-11-0303 November 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application - Aging Management Programs Project stage: RAI ML1034104342010-12-20020 December 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC ME2896 and ME2897) - Time Limited Aging Analysis Project stage: RAI ML1034810132010-12-20020 December 2010 Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Program and Time Limited Aging Analysis Project stage: RAI ML1035603212011-01-10010 January 2011 12/8/10 Summary of Telephone Conference Call Held Btw the USNRC and Pacific Gas and Electric Company Concerning Requests for Additional Information Response Related to the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Ap Project stage: RAI ML1034904172011-01-10010 January 2011 12/1/10 Summary of Telephone Conference Call Held Btw the USNRC and Pacific Gas and Electric Company Concerning Draft Request for Additional Information Related to the Diablo Canyon Nuclear Power Plant, Units 1 and 2, LRA Project stage: Draft RAI ML1034306232011-01-11011 January 2011 Summary of Telephone Conference Call Held Between NRC and PG&E Concerning Request for Additional Information Related Tot the Diablo Canyon Nuclear Power Plant, Units 1 and 2, LRA (TAC Nos. ME2896 & ME2897) Project stage: RAI 2010-07-07
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 August 9,2010 Mr. John Conway Senior Vice President Generation and Chief Nuclear Officer Pacific Gas and Electric Company 77 Beale Street, MC B32 San Francisco, CA 94105
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE REVIEW OF THE DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME2896 AND ME2897) - SCOPING AND SCREENING AND AGING MANAGEMENT REVIEW
Dear Mr. Conway:
By letter dated November 23, 2009, Pacific Gas & Electric Company submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the operating licenses for Diablo Canyon Nuclear Power Plant, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.
The request for additional information was discussed with Mr. Terry Grebel, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-1045 or bye-mail at nathanieLferrer@nrc.gov.
Sincerely, Nathaniel Ferrer, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323
Enclosure:
As stated cc w/encl: Distribution via Listserv
Diablo Canyon Nuclear Power Plant, Units 1 and 2 License Renewal Application Request for Additional Information Set 18 Scoping and Screening/Aging Management Review RAI 2.3.3.6-02 On LRA drawing LR-DCPP-11-107711-05 at location 59-B, the applicant depicts piping from the isolation valve that leads to the gaseous radwaste vent header as not within the scope of license renewal (i.e., not highlighted), However, on the continuation LRA drawing LR-DCPP-24 106724-03 at location 31-B, the piping is shown as in scope for 10 CFR 54.4(a)(2), The staff requests that the applicant clarify its exclusion of the non-highlighted piping section at the above location on LRA drawing LR-DCPP-11-107711-05, RAI2.3.3.7-02 In license renewal application (LRA) Section 2,3.3.7 the applicant states, 'The safety-related components which are served by the backup air/nitrogen system include valves for charging/spray capability, steam dump capability, RCS boration sample capability, the RCS power-operated relief valves for overpressure protection, the letdown isolation valves, and fire water containment isolation valves~' The applicant continues with, 'The backup air/nitrogen supply system provides compressed gas to safety-related air operated components that are required to perform an active safety-related function after the loss of the compressed air system:'
Letdown isolation valves LCV-459 and LCV-460 are shown in scope of license renewal under 10 CFR 54.4(a)(1) on LRA drawing LR-DCPP-08-106708-03 (at location 32-A). However, the backup nitrogen supply to the valves' air operators is depicted as not in scope of license renewal on LRA drawing LR-DCPP-25-106725-31 (at location 311-C). Since the DCPP LRA description for the compressed gas system specifically includes the letdown isolation valves as one of the safety-related components served by backup gas, then the gas components should be included in the scope of the license renewal under 10 CFR 54.4 (a)(1). The staff requests that the applicant justify excluding the backup air to the letdown isolation valves from scope of license renewal RAI 2.3.3.7-03 The applicant depicts water traps and oil filters in the compress gas system on LRA drawings as not in the scope of license renewal. By the nature of these components, the water traps and oil filters would contain fluid under system pressure. In accordance with the applicanfs methodology as stated in DCPP LRA Section 2.1.2.2, fluid-filled components in the vicinity of SSCs in scope of license renewal under 10 CFR 54.4(a)(1) should be included in the scope of license renewal. The staff requests that the applicant justify the exclusion of these components from the scope of license renewal.
-2 RAI3.1.2.2.14-1 SRP-LR Section 3.1.2.2.14 states that wall thinning due to flow accelerated corrosion (FAG) could occur in steel feedwater inlet rings and supports. GALL Report, item IV.D1-26, references NRC IN 91-19, "Steam Generator Feedwater Distribution Piping Damage," for evidence of wall thinning due to flow accelerated corrosion in these steam generator components and recommends that a plant-specific AMP is to be evaluated because existing programs may not be capable of mitigating or detecting wall thinning due to flow-accelerated corrosion. LRA Section 3.1.2.2.14 addresses wall thinning of steam generator steel feedwater inlet rings and supports due to the aging mechanism of FAC.
The applicant states that since NRC IN 91-19 is specific to Combustion Engineering steam generators and because it does not have this design of steam generator, no action is required.
The applicant also states in plant-specific note 2 of LRA Table 3.1.2-4 that this form of degradation has been detected only in certain Combustion Engineering pre-System 80 steam generators and that its replacement steam generators are Westinghouse Model 54. The applicant further states that no operating experience at DCPP or other units with Westinghouse Model 54 steam generators suggests that wall thinning of the feedwater rings is occurring; therefore it has determined that this condition is not applicable and no further evaluation is required. The staff does not consider IN 91-19 to be limited to Combustion Engineering steam generators; therefore, the applicant should clarify why no action is required for addressing FAC of the feedwater ring. The staff notes that the applicants description of the new steam generator design in the LRA Sections 2.3.1.4 and 82.1.8 does not provide sufficient details about the feedwater inlet ring and supports to judge whether FAC could potentially occur in the new steam generator design.
The applicant states that it will conservatively credit its Water Chemistry Program (82.1.2) and Steam Generator Tubing Integrity Program (82.1.8) to manage wall thinning due to flow accelerated corrosion of the feedwater inlet ring and supports. Moreover, in LRA Table 3.1.2-4, the staff notes that the applicant manages the carbon steel steam generator separators in the same way as the feedwater ring, without providing sufficient explanation. With respect to secondary side steam generator internals, it is not clear to the staff whether all of them are included within the scope of the Steam Generator Tube Integrity Program.
- 1. Please justify why FAC will not be a concern for these steam generator parts during the period of extended operation.
- 2. Please confirm that all secondary side steam generator internals, especially the feedwater ring and separators, are included within the scope of your Steam Generator Tube Integrity Program.
' ML102040251 OFFICE LA:DLR PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME YEdmonds NFerrer DWrona NFerrer IDATE 8/2/10 8/4/10 816110 10
Letter to John Conway from Nathaniel Ferrer Last dated August 9,2010.
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE REVIEW OF THE DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME2896 AND ME2897)-SCOPING AND SCREENING AND AGING MANAGEMENT REVIEW DISTRIBUTION:
HARDCOPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlrResource RidsNrrDlrRpb1 RidsNrrDlrRpb2 RidsNrrDlrRarb RidsNrrDlrRapb RidsNrrDlrRasb RidsNrrDlrRerb RidsNrrDlrRpob RidsOgcMailRoom Resource N. Ferrer K. Green A. Stuyvenberg D. Wrona A. Wang M. Peck, RIV T. Brown, RI G. Miller, RIV N. O'Keefe, RIV I. Couret, OPA V. D ricks, OPA W. Maier, RIV J. Weil, OCA E. Williamson, OGC S. Uttal, OGC R. Rihm, EDO