Mid-Cycle Performance Review and Inspection Plan
ML092440263
Person / Time
Site: Dresden  
(DPR-019, DPR-025)
Issue date: 09/01/2009
From: Khadijah West
Division Reactor Projects III
To: Pardee C
Exelon Generation Co, Exelon Nuclear
References
FOIA/PA-2010-0209
Download: ML092440263 (7)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 September 1, 2009 Mr. Charles G. Pardee Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO), Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

DRESDEN NUCLEAR POWER SATION

Dear Mr. Pardee:

On August 20, 2009, the NRC staff completed its performance review of the Dresden Nuclear Power Station. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from July 1, 2008, through June 30, 2009. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include security information.

A separate letter designated and marked as "Official Use Only--Security Information" will include the security cornerstone review and resultant inspection plan.

Plant performance for the most recent quarter at the Dresden Nuclear Power Station was within the Licensee Response column of the NRC=s Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.

There were five inspection findings during the assessment period with documented cross-cutting aspects in the area of Problem Identification and Resolution (PI&R). There is a cross-cutting theme with four of these findings, which affected multiple cornerstones (i.e., Initiating Events, Mitigating Systems, and Barrier Integrity). This cross-cutting theme involves the stations ability to take appropriate corrective actions to address safety issues and adverse trends in a timely manner, commensurate with their safety significance and complexity, P.1(d). In evaluating your scope of efforts and progress in addressing the cross-cutting theme, we determined that you have appropriately identified the cross-cutting theme and have scheduled or taken a range of corrective actions to address the issue. Based on the recent time-frame associated with some of these performance issues, corrective actions have not reasonably been in place long enough to determine their effectiveness. Therefore, the staff has concluded that a substantive cross-cutting issue in PI&R is not warranted at this time. We will continue to monitor the effectiveness of these corrective actions as part of our ongoing assessments.

C. Pardee On August 19, 2009, we issued a preliminary White inspection finding related to an inadvertent rod withdrawal event that occurred at Dresden on November 3, 2008 (ML092320164). This finding was not included within this assessment since the final significance had not yet been determined. Following the final significance determination, the finding will be included in the assessment process and additional inspection(s) will be conducted, as appropriate.

The enclosed inspection plan details the inspections, less those related to physical protection scheduled through December 31, 2010. The inspections scheduled include: licensed operator initial and requalification, emergency preparedness, biennial problem identification and resolution, component design basis, ground water protection initiative, and outage related inspections. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the End-of-Cycle review.

In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

As you may know, the NRC is currently evaluating the scope and frequency of all the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible.

Please contact me at (630) 829-9600 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

K. Steven West, Director Division of Reactor Projects Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25

Enclosure:

Dresden Power Station Inspection/Activity Plan DISTRIBUTION:

See next page

Letter to C. Pardee from K. West dated September 1, 2009

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

DRESDEN NUCLEAR POWER SATION cc w/encl:

Site Vice President - Dresden Nuclear Power Station Plant Manager - Dresden Nuclear Power Station Manager Regulatory Assurance - Dresden Nuclear Power Station Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden, and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General J. Klinger, State Liaison Officer, Illinois Emergency Management Agency Chairman, Illinois Commerce Commission Will County Executive Will County Sheriff Director, Will County Emergency Management Agency Mayor of Joliet City Manager of Joliet Kendall County Board Chairman Kendall County Sheriff Grundy County Board Chairman Grundy County Sheriff Grundy County Emergency Management Agency Mayor of Morris Minooka Village President Mayor of Coal City Mayor of Carbon Hill Mayor of Diamond Mayor of Braidwood Mayor of Wilmington Channahon Village President Channahon Village Administrator Mayor of Shorewood Shorewood Village Administrator Mayor of Elwood G. Mortensen, INPO

C. Pardee On August 19, 2009, we issued a preliminary White inspection finding related to an inadvertent rod withdrawal event that occurred at Dresden on November 3, 2008 (ML092320164). This finding was not included within this assessment since the final significance had not yet been determined. Following the final significance determination, the finding will be included in the assessment process and additional inspection(s) will be conducted, as appropriate.

The enclosed inspection plan details the inspections, less those related to physical protection scheduled through December 31, 2010. The inspections scheduled include: licensed operator initial and requalification, emergency preparedness, biennial problem identification and resolution, component design basis, ground water protection initiative, and outage related inspections. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the End-of-Cycle review.

In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

As you may know, the NRC is currently evaluating the scope and frequency of all the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible.

Please contact me at (630) 829-9600 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

K. Steven West, Director Division of Reactor Projects Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25

Enclosure:

Dresden Power Station Inspection/Activity Plan DISTRIBUTION:

See next page DOCUMENT NAME: G:\\Branch TSS\\ALL MOC\\midcycle 2008 to 2009\\Mid-cycle letters\\Dresden 2009 MOC Letter.doc Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" =

Copy with attach/encl "N" = No copy OFFICE RIII E

RIII NAME MRing KSWest DATE 09/02/09 09/02/09 OFFICIAL RECORD COPY

Letter to C. Pardee from K. West dated September 1, 2009

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

DRESDEN NUCLEAR POWER SATION DISTRIBUTION:

Susan Bagley RidsNrrDorlLpl3-2 RidsNrrPMDresden Resource RidsNrrDirslpob Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports Resource

Inspection / Activity Plan 09/01/2009 - 12/31/2010 Planned Dates Start End Inspection Activity Title No. of Staff on Site Dresden BI ENG

- ENGINEERING INSERVICE INSPECTION 1

IP Inservice Inspection Activities - BWR 7111108G 11/09/2009 11/20/2009 RENEWAL

- LICENSE RENEWAL 71003 - PHASE 1&2 - U2 5

IP Post-Approval Site Inspection for License Renewal 71003 10/05/2009 11/20/2009 BI RP

- RADIATION PROTECTION BASELINE INSPECTION 1

IP Access Control to Radiologically Significant Areas 7112101 11/16/2009 11/20/2009 IP ALARA Planning and Controls 7112102 11/16/2009 11/20/2009 IP Occupational Exposure Control Effectiveness 71151-OR01 11/16/2009 11/20/2009 BI RP

- RADIATION PROTECTION BASELINE INSPECTION 1

IP Radiation Monitoring Instrumentation and Protective Equipment 7112103 02/08/2010 02/12/2010 RENEWAL

- LICENSE RENEWAL 71003 - PHASE 3 - U2 1

IP Post-Approval Site Inspection for License Renewal 71003 02/08/2010 02/12/2010 BI EP

- EP ROUTINE INSPECTION / PI VERIFICATION 2

IP Alert and Notification System Testing 7111402 02/08/2010 02/12/2010 IP Emergency Response Organization Augmentation Testing 7111403 02/08/2010 02/12/2010 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 02/08/2010 02/12/2010 IP Drill/Exercise Performance 71151-EP01 02/08/2010 02/12/2010 IP ERO Drill Participation 71151-EP02 02/08/2010 02/12/2010 IP Alert & Notification System 71151-EP03 02/08/2010 02/12/2010 ISFSI

- ISFSI INSPECTION 1

IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 03/01/2010 07/31/2010 FY 2010

- DRESDEN INIT PREP FEB/2010 3

OL - INITIAL EXAM - MAR 2010 - DRES W90218 02/08/2010 02/12/2010 BI PI&R

- BIENNIAL PI&R INSPECTION 6

IP Identification and Resolution of Problems 71152B 03/01/2010 03/19/2010 FY 2010

- DRESDEN INIT EXAM MARCH/2010 2

OL - INITIAL EXAM - MAR 2010 - DRES W90218 03/08/2010 03/19/2010 BI ENG

- COMPONENT DESIGN BASIS INSPECTION 6

IP Component Design Bases Inspection 7111121 04/19/2010 05/21/2010 BI RP

- RADIATION PROTECTION BASELINE INSPECTION 1

IP Access Control to Radiologically Significant Areas 7112101 05/03/2010 05/07/2010 IP ALARA Planning and Controls 7112102 05/03/2010 05/07/2010 IP Reactor Coolant System Activity 71151-BI01 05/03/2010 05/07/2010 BI OL

- LIC. OPERATOR REQUAL. PROGRAM EVALUATION 2

IP Licensed Operator Requalification Program 7111111B 05/24/2010 05/28/2010

Inspection / Activity Plan 09/01/2009 - 12/31/2010 Planned Dates Start End Inspection Activity Title No. of Staff on Site Dresden BI RP

- RADIATION PROTECTION BASELINE INSPECTION 1

IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 7112203 08/16/2010 08/20/2010 IP RETS/ODCM Radiological Effluent 71151-PR01 08/16/2010 08/20/2010 RENEWAL

- LICENSE RENEWAL 71003 - PHASE 1 - U3 7

IP Post-Approval Site Inspection for License Renewal 71003 10/18/2010 10/29/2010 RENEWAL

- LICENSE RENEWAL 71003 - PHASE 2 - U3 3

IP Post-Approval Site Inspection for License Renewal 71003 11/01/2010 11/19/2010 BI ENG

- ENGINEERING INSERVICE INSPECTION 1

IP Inservice Inspection Activities - BWR 7111108G 11/01/2010 11/19/2010 BI RP

- RADIATION PROTECTION BASELINE INSPECTION 1

IP ALARA Planning and Controls 7112102 11/15/2010 11/19/2010 IP Occupational Exposure Control Effectiveness 71151-OR01 11/15/2010 11/19/2010