ML091250363
| ML091250363 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley |
| Issue date: | 05/14/2009 |
| From: | David Wrona License Renewal Projects Branch 2 |
| To: | Sena P FirstEnergy Nuclear Operating Co |
| Sayoc, Manny, NRR/DLR/RPB2 415-1924 | |
| Shared Package | |
| ML091250329 | List: |
| References | |
| TAC MD6595, TAC MD6596 | |
| Download: ML091250363 (6) | |
Text
May 14, 2009 Peter P. Sena III Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB-1 Shippingport, PA 15077
SUBJECT:
NOTICE OF AVAILABILITY OF THE FINAL PLANT-SPECIFIC SUPPLEMENT 36 TO THE GENERIC ENVIRONMENTAL IMPACT STATEMENT FOR LICENSE RENEWAL OF NUCLEAR PLANTS REGARDING BEAVER VALLEY POWER STATION, UNITS 1 AND 2 (TAC NOS. MD6595 AND MD6596)
Dear Mr. Sena:
The U.S. Nuclear Regulatory Commission (NRC) staff has completed the final plant-specific Supplement 36 to NUREG-1437, ?Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS),@ regarding the renewal of operating licenses DPR-66 and NPF-73 for an additional 20 years of operation for the Beaver Valley Power Station, Units 1 and
- 2. Enclosed is a copy of the final supplement and the associated Federal Register Notice of Availability. This notice advises the public that the final supplement is publicly available at the NRC Public Document Room (PDR) or from the NRC=s Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC website at http://adamswebsearch.nrc.gov/dologin.htm. The Accession Number for the final Supplement 36 to the GEIS is ML091260011. In addition, the following libraries have agreed to make the final Supplemental Environmental Impact Statement (SEIS) available for public inspection:
Beaver Area Memorial Library,100 College Ave., Beaver, PA 15009-2704, telephone 724-775-1132 Beaver County Library System, 1 Campus Drive, Monaca, PA 15061, telephone 724-728-3737 As discussed in Section 9.3 of the final supplement, the staff recommends that the Commission determine that the adverse environmental impacts of license renewal for the Beaver Valley Power Station, Units 1 and 2 are not so great that preserving the option of license renewal for energy planning decision makers would be unreasonable. This recommendation is based on:
(1) the analysis and findings in the GEIS; (2) the Environmental Report submitted by FirstEnergy Nuclear Operating Company; (3) consultation with Federal, State, and local agencies; (4) the NRC staff=s own independent review; and (5) the NRC staff=s consideration of public comments during the scoping period and the draft SEIS comment period.
P. Sena A separate Notice of Availability of the final supplemental environmental impact statement will be placed in the Federal Register through the U.S. Environmental Protection Agency. If you have any questions regarding this matter, please contact the NRC License Renewal Project Manager, Mr. Emmanuel Sayoc, at 301-415-1924 or by e-mail at Emmanuel.Sayoc@nrc.gov, or Mr. Kent Howard, at 301-415-2989 or by e-mail at Kent.Howard@nrc.gov.
Sincerely,
/RA/
David J. Wrona, Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412
Enclosures:
As stated cc w/encl: See next page
P. Sena A separate Notice of Availability of the final supplemental environmental impact statement will be placed in the Federal Register through the U.S. Environmental Protection Agency. If you have any questions regarding this matter, please contact the NRC License Renewal Project Manager, Mr. Emmanuel Sayoc, at 301-415-1924 or by e-mail at Emmanuel.Sayoc@nrc.gov, or Mr. Kent Howard, at 301-415-2989 or by e-mail at Kent.Howard@nrc.gov.
Sincerely,
/RA/
David J. Wrona, Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412
Enclosures:
As stated cc w/encl: See next page DISTRIBUTION:
See next page ADAMS Accession Numbers: Pkg: ML091250329, Ltr: ML091250363, FRN: ML091260010, FINAL SEIS: ML091260011 OFFICE LA:DLR PM:DLR:RPB2 PM:DLR:RPB2 OGC (NLO)
BC:DLR:RPB2 NAME SFigueroa ESayoc KHoward LSubin DWrona DATE 05/14/09 05/7/09 05/07/09 05/05/09 05/14/09 OFFICIAL RECORD COPY
Letter to P. Sena from D. Wrona dated May 14, 2009 DISTRIBUTION:
SUBJECT:
NOTICE OF AVAILABILITY OF THE FINAL PLANT-SPECIFIC SUPPLEMENT 36 TO THE GENERIC ENVIRONMENTAL IMPACT STATEMENT FOR LICENSE RENEWAL OF NUCLEAR PLANTS REGARDING BEAVER VALLEY POWER STATION, UNITS 1 AND 2 (TAC NOS. MD6595 AND MD6596)
E-MAIL RidsNrrDlrRpb2 RidsNrrDlrRerb R. Schaaf K. Howard E. Sayoc N. Morgan D. Werkheiser L. Subin N. Sheehan R. Barkley M. McLaughlin E. Brenner D. Screnci E. Dacus N. McNamara D. McIntyre RidsOGCMailRoom
Beaver Valley Power Station, Units 1 and 2 cc:
Joseph J. Hagan President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH 44308 James H. Lash Senior Vice President of Operations and Chief Operating Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 David W. Jenkins, Attorney FirstEnergy Corporation Mail Stop A-GO-15 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308 Ohio EPA-DERR ATTN: Zack A. Clayton P.O. Box 1049 Columbus, OH 43266-0149 Director, Fleet Regulatory Affairs FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308 Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-A P.O. Box 4, Route 168 Shippingport, PA 15077 Richard Anderson Vice President, Nuclear Support FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Commissioner James R. Lewis West Virginia Division of Labor 749-B, Building No. 6 Capitol Complex Charleston, WV 25305 Director, Utilities Department Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Beaver Valley Power Station, Units 1 and 2 cc:
Jennifer Kagel Pennsylvania Field Office 315 South Allen St. Suite 322 State College, PA 16801-4850 Director, Pennsylvania Emergency Management Agency 2605 Interstate Dr.
Harrisburg, PA 17110-9364 Dr. Judith Johnsrud Environmental Coalition on Nuclear Power Sierra Club 433 Orlando Avenue State College, PA 16803 Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077 Tony Gonyea Onondaga Nation RR#1, Route 11A Box 319B Via Nedrow, NY 13120 Cliff Custer FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Mike Banko FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Julie Firestone FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Sherry White Cultural Preservation Officer Stockbridge-Munsee Band of the Mohican Nation, Wisconsin Route 1, P.O. Box 70 Bowler, WI 54416 Greg Bunker Director Environmental/NEPA Stockbridge-Munsee Band of the Mohican Nation, Wisconsin Route 1, P.O. Box 70 Bowler, WI 54416