Report 22, Surry Inspection/Activity Plan for 03/01/2009 - 06/30/2010ML090630529 |
Person / Time |
---|
Site: |
Surry |
---|
Issue date: |
03/04/2009 |
---|
From: |
NRC/RGN-II |
---|
To: |
|
---|
References |
---|
IR-09-001 |
Download: ML090630529 (2) |
|
Similar Documents at Surry |
---|
Category:Inspection Plan
MONTHYEARIR 05000280/20230052023-08-23023 August 2023 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2023005 and 05000281/2023005) IR 05000280/20220062023-03-0101 March 2023 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2022006 and 05000281/2022006 ML22339A1582022-11-30030 November 2022 Requalification Inspection Notification Letter IR 05000280/20220052022-08-24024 August 2022 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Reports 05000280/2022005 and 05000281/2022005) ML22223A1192022-08-14014 August 2022 RP Inspection Document Request Letter Final ML22168A0272022-06-15015 June 2022 Information Request for the Cyber-Security Baseline Security Inspection, Notification to Perform Inspection 05000280/2022404; 05000281/202240 IR 05000280/20210062022-03-0202 March 2022 Annual Assessment Letter for Surry Power Station, Units 1 and 2 (Reports No. 05000280/2021006 and 05000281/2021006) ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections IR 05000280/20210052021-08-31031 August 2021 Mid-Cycle Letter Revised Updated Inspection Plan for Surry Power Station, Units 1 and 2 (05000280/2021005 and 05000281/2021005) IR 05000280/20210012021-08-26026 August 2021 Updated Inspection Plan for Surry Power Station, Units 1 and 2 -(05000280/2021001 and 05000281/2021001) ML21239A0052021-08-26026 August 2021 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 - (Report 05000280/2021001 and 05000281/2021001) IR 05000280/20200062021-03-0303 March 2021 Annual Assessment Letter for Surry Power Station, Units 1 and 2 NRC Inspection Reports 05000280/2020006 and 05000281/2020006 ML21061A0292021-03-0101 March 2021 2021 Sur - POV Inspection Information Request ML21050A0352021-02-18018 February 2021 Radiation Safety Baseline Inspection Information Request ML20315A2492020-11-0909 November 2020 Requal Inspection Notification Letter W Materials List IR 05000280/20200052020-08-24024 August 2020 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2020005 and 05000281/2020005) ML20175A7802020-06-23023 June 2020 Heat Sink RFI ML20092J5002020-04-0101 April 2020 Radiation Safety Baseline Inspection Information Request IR 05000280/20190062020-03-0303 March 2020 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2019006 and 05000281/2019006 IR 05000280/20190052019-08-27027 August 2019 Updated Inspection Plan for Surry Power Station, Units 1 and 2, NRC Report 05000280/2019005 and 05000281/2019005 IR 05000280/20180062019-03-0404 March 2019 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Report 05000280/2018006 and 05000281/2018006 ML19057A1052019-02-26026 February 2019 License Renewal Phase 4 2019003 RFI - SD ML18283A7332018-10-0101 October 2018 Rad Safety Inspection RFI IR 05000280/20180052018-08-23023 August 2018 Updated Inspection Plan for Surry Power Station Units 1 and 2, NRC Report 05000280/2018005 and 05000281/2018005 ML18215A1252018-08-0303 August 2018 U2 ISI SGI 2018004 - Notification of Inspection and RFI (Public) IR 05000280/20170062018-02-28028 February 2018 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2017006 and 05000281/2017006, 05000280/2017402 and 05000281/2017402, 05000280/2017501 and 05000281/2017501 ML18037B1092018-02-0505 February 2018 Emergency Preparedness Inspection and Request for Information ML17290A0592017-10-13013 October 2017 Radiation Safety Inspection Document Request IR 05000280/20170052017-08-21021 August 2017 Updated Inspection Plan for Surry Power Station, Units 1 and 2 - Report 05000280/2017005 and 05000281/2017005 IR 05000280/20160062017-03-0101 March 2017 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - Report 05000280/2016006 and 05000281/2016006 ML16307A1972016-11-0202 November 2016 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML16244A1262016-08-31031 August 2016 Mid-Cycle Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Report 05000280,281/2016005 ML16062A2732016-03-0202 March 2016 Annual Assessment Letter IR 05000280/20150052015-09-0101 September 2015 Mid-Cycle Letter for Surry Power Station Units 1 and 2 - NRC Assessment Report 05000280/2015005 and 05000281/2015005 ML15140A4142015-05-20020 May 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000280/20140012015-03-0404 March 2015 Annual Assessment Letter for Surry Power Station, Units 1 and 2 Report 05000280/2014001 and 05000281/2014001 IR 05000280/20140062014-09-0202 September 2014 Mid-Cycle Letter for Surry, Units 1 & 2, NRC Assessment Report 05000280/2014006, 05000281/2014006 IR 05000280/20130012014-03-0404 March 2014 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - Report 05000280/2013001 and 05000281/2013001 ML13262A1812013-09-17017 September 2013 Notification of Inspection and Request for Information ML13246A1352013-09-0303 September 2013 Mid Cycle Assessment Letter ML13123A3552013-05-0202 May 2013 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000280/20120012013-03-0404 March 2013 Annual Assessment Letter, Surry Power Station, Units 1 and 2, 05000280/2012001 and 05000281/2012001 ML12248A1232012-09-0404 September 2012 Mid Cycle Assessment Letter Surry 2012 ML1206506182012-03-0505 March 2012 EOC Report 22 ML1124401072011-09-0101 September 2011 Report 22 - Surry Inspection/Activity Plan, 09/01/2011 - 12/31/2012 ML1106303102011-03-0404 March 2011 Inspection / Activity Plan 03/01/2011 - 06/30/2012, EOC Report 22 ML1024402372010-09-0101 September 2010 Report 22 - 2010 Mid-Cycle Inspection/Activity Plan ML1006209142010-03-0303 March 2010 Report 22 - 2010001 Inspection/Activity Plan ML0924405052009-09-0101 September 2009 Inspection/Activity Plan 09/01/2009 - 12/31/2010 ML0906305292009-03-0404 March 2009 Report 22, Surry Inspection/Activity Plan for 03/01/2009 - 06/30/2010 2023-08-23
[Table view] |
Text
Page 1 of 2 Surry 03/04/2009 07:35:31 Inspection / Activity Plan Report 22 03/01/2009 - 06/30/2010 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EB3ISI - UNIT 1 INSERVICE INSPECTION 1 1 04/27/2009 05/01/2009 IP 7111108P Inservice Inspection Activities - PWR EB3SGISI - UNIT 1 STEAM GENERATOR INSERVICE INSP 2 1 05/04/2009 05/08/2009 IP 7111108P Inservice Inspection Activities - PWR TFPI - TRIENNIAL FIRE PROTECTION 5 1, 2 06/08/2009 06/12/2009 IP 7111105T Fire Protection [Triennial]
1, 2 06/22/2009 06/26/2009 IP 7111105T Fire Protection [Triennial]
ISFSI - ISFSI OPERATIONAL INSPECTION 2 1, 2 06/01/2009 09/15/2009 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants OL EXAM - INITIAL EXAM PREP 3 1 06/29/2009 07/02/2009 V23314 SURRY/NOVEMBER 2009 EXAM AT POWER FACILITIES OL EXAM - INITIAL EXAM WEEK 3 1 07/20/2009 07/24/2009 V23314 SURRY/NOVEMBER 2009 EXAM AT POWER FACILITIES PSB1EP - EMERGENCY PREPAREDNESS EXERCISE 3 1, 2 08/03/2009 08/07/2009 IP 7111401 Exercise Evaluation 1, 2 08/03/2009 08/07/2009 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 08/03/2009 08/07/2009 IP 71151 Performance Indicator Verification PSB1-RP - RP OCCUPATIONAL INSPECTION WK 1 (OUTAGE) 2 1, 2 11/02/2009 11/06/2009 IP 7112101 Access Control to Radiologically Significant Areas 1, 2 11/02/2009 11/06/2009 IP 7112102 ALARA Planning and Controls 1, 2 11/02/2009 11/06/2009 IP 7112202 Radioactive Material Processing and Transportation 1, 2 11/02/2009 11/06/2009 IP 71151 Performance Indicator Verification PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 6 1 11/30/2009 12/04/2009 IP 71152B Identification and Resolution of Problems 1 12/14/2009 12/18/2009 IP 71152B Identification and Resolution of Problems EB3ISI - UNIT 2 INSERVICE INSPECTION 1 2 11/09/2009 11/13/2009 IP 7111108P Inservice Inspection Activities - PWR EB3SGISI - UNIT 2 SG INSERVICE INSPECTION 1 2 11/16/2009 11/20/2009 IP 7111108P Inservice Inspection Activities - PWR PSB1-RP - RP OCCUPATIONAL INSPECTION WK2 (OUTAGE) 2 1, 2 11/16/2009 11/20/2009 IP 7112101 Access Control to Radiologically Significant Areas 1, 2 11/16/2009 11/20/2009 IP 7112102 ALARA Planning and Controls 1, 2 11/16/2009 11/20/2009 IP 7112202 Radioactive Material Processing and Transportation INSP - MODS/50.59 INSPECTION 4 1, 2 01/11/2010 01/15/2010 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
Page 2 of 2 Surry 03/04/2009 07:35:31 Inspection / Activity Plan Report 22 03/01/2009 - 06/30/2010 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site INSP - MODS/50.59 INSPECTION 4 1, 2 01/25/2010 01/29/2010 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications OL EXAM - INITIAL EXAM PREP 4 1 06/28/2010 07/02/2010 V23336 SURRY/JULY 2010 EXAM AT POWER FACILITIES This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure