Information Notice 2006-18, Significant Loss of Safety-related Electrical Power at Forsmark, Unit 1, in Sweden
| ML071900368 | |
| Person / Time | |
|---|---|
| Issue date: | 08/10/2007 |
| From: | Michael Case NRC/NRR/ADRO |
| To: | |
| Brett Rini, NRR/DIRS/IOEB, 301-415-3931 | |
| References | |
| IN-06-018, Suppl 1 | |
| Download: ML071900368 (4) | |
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, DC 20555-0001
August 10, 2007
NRC INFORMATION NOTICE 2006-18, SUPPLEMENT 1: SIGNIFICANT LOSS OF
SAFETY-RELATED ELECTRICAL
POWER AT FORSMARK UNIT 1 IN
SWEDEN
ADDRESSEES
All holders of operating licenses for nuclear power reactors, except those who have
permanently ceased operations and have certified that fuel has been permanently removed
from the reactor vessel.
PURPOSE
The U.S. Nuclear Regulatory Commission (NRC) is issuing this supplement to Information
Notice (IN) 2006-18, Significant Loss of Safety-Related Electrical Power at Forsmark Unit 1 in
Sweden, to provide additional information regarding the incident that occurred at the Forsmark
Nuclear Power Station, Unit 1 (Forsmark-1), involving the loss of several safety-related
electrical busses. It is expected that addressees will review the information for applicability to
their facilities and consider actions, as appropriate, to avoid similar problems. However, suggestions contained in this IN are not NRC requirements; therefore, no specific action or
written response is required.
DESCRIPTION OF CIRCUMSTANCES
On July 25, 2006, while the plant was operating at full power, a significant event occurred at
Forsmark-1, a 1020 Megawatt electric boiling-water reactor designed by ASEA-Atom. The
event began in the offsite 400 kilovolts (kV) switchyard, which consisted of two main buses and
one transfer bus, during a bus transfer operation being conducted to support maintenance work.
However, due to inadequate administrative procedures, the transfer and connection activities
were not properly implemented. A disconnect switch that was carrying load was opened which
resulted in arcing and a two-phase short circuit at the disconnect switch. The fault was isolated
after approximately 400 milliseconds by the remote circuit breakers on two of the outgoing
transmission lines. The high-voltage fast-acting bus protection was ineffective during the bus
transfer operation.
When the short circuit occurred in the switchyard, the generator bus voltage dipped to
approximately 50 percent of nominal voltage for approximately 300 milliseconds. The breakers
on the high-voltage side of the main transformers tripped on low voltage. This resulted in a loss
of load, and a generator bus voltage surge to approximately 120 percent of nominal voltage for
approximately one second. The loss of offsite electrical load caused an automatic partial scram
of the reactor, a transition to steam dumping, and house load operation by the turbine
generators.
IN 2006-16, Sup 1 After disconnection from the 400 kV grid, the plant electrical system continued to be connected
to the generator buses (house load operation). The voltage surge at the generator buses
caused tripping of the inverters of the battery-backed uninterruptible power supply (UPS) Subs
A and B in the plant auxiliary electrical system. [Subs are similar to the trains/divisions in U.S.
nuclear plants]. As a consequence, the rectifier and inverter of Subs A and B were bypassed, as designed, by the fast-acting electronic/static switch. The voltage transient at UPS buses due
to the electronic switch transfer resulted in tripping of the recirculation pumps of Sub B. Reactor
water level remained within acceptable limits.
The UPS Subs C and D were not impacted by the generator bus voltage surge due to the
slightly lower voltage surge seen by the related rectifiers and inverters because of slight
difference in the impedance path from the generators to the rectifiers. Subsequent tests of the
UPS showed that the rectifier in the UPS could not reliably block steep voltage transients larger
than 25 percent within the 80-130 percent range of nominal voltage. During such a voltage
transient, the inverter voltage surge protection could trip before the rectifier protection if the
rectifier and inverter direct current voltage protection settings are very close to each other. As
result of this lesson learned, Forsmark revised the rectifier and the inverter voltage protection
settings.
One turbine tripped due to low oil pressure caused by 50 percent voltage drop in the switchyard, the other turbine tripped due to high pressure in condensers; this lead to low frequency
operation by the generators. However, the low frequency protection for the generators did not
actuate due to an incorrect phase connection of frequency relays. With the turbines tripped, the
generators continued to supply house loads, and the voltage and frequency continued to drop.
When the voltage at the UPS Subs A and B decreased to 90 percent, the UPS Buses A and B
automatically transferred to the alternate parallel path through the isolating transformer. During
this transfer, UPS Subs A and B lost power for approximately 2 seconds (as per design), which
caused the reactor to trip on two-out-of-four connection logic.
When the frequency at the 6 kV buses dropped below 47 hertz for 3 seconds, the feeders from
the 6 kV buses to the 500 volt diesel buses tripped due to the underfrequency protection
provided at the 6 kV buses. Also, the UPS buses of Subs A and B (fed through isolating
transformers) lost power. However, the UPS buses of Subs C and D continued to be powered
by battery-backed inverters.
Due to the loss of two trains of UPS, some instrumentation and control equipment was
impacted. The major impacts were:
The network between the automatic processors and the operator stations, and the
process computer, was lost.
The control rod in indication in the control rooms core map for all control rods
belonging to Subs A and B was lost.
The average power range monitor and wide range neutron monitor indications that were
powered from Subs A and B were not available.
IN 2006-16, Sup 1 The 500 volt safety buses lost power due to the tripping of feeder breakers between 6 kV buses
and 500 volt safety buses. Each emergency diesel generator (EDG) of Subs A, B, C, and D
received its startup signal due to low voltage. EDGs C and D successfully connected to the
safety buses. However, EDGs A and B tripped due to a long startup time since the EDG
speed measurement signal, powered from its respective UPS bus, was not available.
The delayed tripping of main generator breakers occurred (approximately 38-45 seconds) when
the power supplied by each generator became less than 5 Megawatts in conjunction with the
previous turbine trip signal. Due to this, the 6 kV buses lost power and the automatic
switchover (dead bus transfer with 2 second delay) to the 70 kV alternate offsite occurred per
design. After approximately 22 minutes, voltage was restored to 500 volt diesel buses A and B
by manually closing the 6 kV ties between the 6 kV buses and the 500 volt diesel buses.
DISCUSSION
The lessons learned from the Forsmark-1 event that can be applicable to U.S. plants are as
follows:
(1)
The voltage transient (due to the delayed fault clearing in the switchyard) can impact the
plant electrical system up to the UPS buses.
(2)
The protection relays, if dependent on proper phase connections, can malfunction if not
properly connected.
(3)
The failure of UPS can impact important equipment/systems such as the reactor
recirculation pump control system and important control room indications.
CONTACT
This IN requires no specific action or written response. Please direct any questions about this
matter to the technical contacts listed below or the appropriate Office of Nuclear Reactor
Regulation project manager.
/RA by TQuay for/
Michael J. Case, Director
Division of Policy and Rulemaking
Office of Nuclear Reactor Regulation
Technical Contacts:
Vijay Goel, NRR/DE
Brett Rini, NRR/DIRS
301-415-3730
301-415-3931 E-mail: vkg@nrc.gov
E-mail: bar3@nrc.gov
Note: NRC generic communications may be found on the NRC public Website, http://www.nrc.gov, under Electronic Reading Room/Document Collections.
IN 2006-16, Sup 1 The 500 volt safety buses lost power due to the tripping of feeder breakers between 6 kV buses
and 500 volt safety buses. Each emergency diesel generator (EDG) of Subs A, B, C, and D
received its startup signal due to low voltage. EDGs C and D successfully connected to the
safety buses. However, EDGs A and B tripped due to a long startup time since the EDG
speed measurement signal, powered from its respective UPS bus, was not available.
The delayed tripping of main generator breakers occurred (approximately 38-45 seconds) when
the power supplied by each generator became less than 5 Megawatts in conjunction with the
previous turbine trip signal. Due to this, the 6 kV buses lost power and the automatic
switchover (dead bus transfer with 2 second delay) to the 70 kV alternate offsite occurred per
design. After approximately 22 minutes, voltage was restored to 500 volt diesel buses A and B
by manually closing the 6 kV ties between the 6 kV buses and the 500 volt diesel buses.
DISCUSSION
The lessons learned from the Forsmark-1 event that can be applicable to U.S. plants are as
follows:
(1)
The voltage transient (due to the delayed fault clearing in the switchyard) can impact the
plant electrical system up to the UPS buses.
(2)
The protection relays, if dependent on proper phase connections, can malfunction if not
properly connected.
(3)
The failure of UPS can impact important equipment/systems such as the reactor
recirculation pump control system and important control room indications.
CONTACT
This IN requires no specific action or written response. Please direct any questions about this
matter to the technical contacts listed below or the appropriate Office of Nuclear Reactor
Regulation project manager.
/RA by TQuay for/
Michael J. Case, Director
Division of Policy and Rulemaking
Office of Nuclear Reactor Regulation
Technical Contacts:
Vijay Goel, NRR/DE
Brett Rini, NRR/DIRS
301-415-3730
301-415-3931 E-mail: vkg@nrc.gov
E-mail: bar3@nrc.gov
Note: NRC generic communications may be found on the NRC public Website, http://www.nrc.gov, under Electronic Reading Room/Document Collections.
Distribution: IN Reading File
ADAMS Accession Number: ML071900368 OFFICE
DIRS:IOEB
TECH EDITOR
EEEB:DE
BC:IOEB:DIRS
BC:EEEB:DE
NAME
BRini
LCulp by e-mail
VGoel
MJRoss-Lee
GWilson
DATE
7/10/07
7/2/07
7/10/07
07/25/07
7/12/07 OFFICE
D:DE
LA:PGCB
PGCB:DPR
BC:PGCB:DPR
D:PGCB:DPR
NAME
PHiland
CHawes
DBeaulieu
MMurphy
TQuay for MCase
DATE
07/25/07
08/01/2007
08/07/2007
08/09/2007
08/10/2007 OFFICIAL RECORD COPY