Information Notice 2006-08, Secondary Piping Rupture at Mihama Power Station in Japan

From kanterella
Jump to navigation Jump to search
Secondary Piping Rupture at Mihama Power Station in Japan
ML052910008
Person / Time
Issue date: 03/16/2006
From: Charemagne Grimes
NRC/NRR/ADRA/DPR
To:
Hodge, CV, NRR/DIPM/IROB, 415-1861
References
IN-06-008 IN-02-008
Download: ML052910008 (5)


UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

WASHINGTON, D.C. 20555 March 16, 2006 NRC INFORMATION NOTICE 2006-08: SECONDARY PIPING RUPTURE AT THE

MIHAMA POWER STATION IN JAPAN

ADDRESSEES

All holders of operating licenses, except those who have permanently ceased operations and

have certified that fuel has been permanently removed from the reactor vessel.

PURPOSE

The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice (IN) involving

foreign operating experience to alert addressees of the root causes and lessons learned from a

secondary piping rupture at the Mihama Power Station, Unit 3 (Mihama 3) in Japan. It is

expected that recipients will review the information for applicability to their facilities and consider

actions, as appropriate, to avoid similar problems. However, suggestions contained in this

information notice are not NRC requirements; therefore, no specific action or written response

is required.

DESCRIPTION OF CIRCUMSTANCES

The Mihama 3, is an 826 Megawatts electric, 3-loop Westinghouse type pressurized-water

reactor (PWR) owned by Kansai Electric Power Company, Inc., and licensed by the Japanese

government. This unit has been in service since 1976.

On August 9, 2004, a fire alarm annunciated in the central control room at Mihama 3. Upon

investigation, operators discovered the area covered by the alarm was filled with steam.

Suspecting that steam or high temperature water was leaking from the secondary piping, the

operators began an emergency load reduction. While they were doing this, the reactor tripped

automatically based on the steam flow from the 3A steam generator exceeding the feedwater

flow to that steam generator.

The rupture occurred in a 55.9 centimeter (cm) (22 inch) outside diameter pipe in the A loop

condensate system between the fourth feedwater heater and the deaerator, downstream of an

orifice for measuring single-phase water flow. At the time of the secondary piping rupture,

105 workers were preparing for the periodic inspections to commence. The accident resulted in

five deaths and six injuries.

A review of plant parameters did not uncover any precursor indicators before the accident nor

were there any special operations that could have caused the pipe rupture. An investigation

concluded that water quality had been maintained since the commissioning of the plant.

The rupture opening measured 51.5 cm (20.3 inches) in the axial direction and 93.0 cm

(36.6 inches) in the circumferential direction of the carbon steel pipe. The nominal wall

thickness of the pipe at the time of initial plant service was 10 millimeters (mm) (0.39 inches).

The thinnest section of the pipe wall was 0.4 mm (0.02 inches). The same section of piping in

the B loop was 1.8 mm (0.07 inches) at its thinnest place. The pipe was designed for a

maximum service temperature of 195 ECentigrade (EC) (383 EFahrenheit (EF)) and a maximum

service pressure of 1.27 megapascal (MPa) (184 pounds per square inch (psi)). At the time of

the pipe rupture, the flow rate through the pipe was 1700 cubic meters per hour (7485 gallons

per minute) with a temperature of 140 EC (284 EF) and a pressure 0.93 MPa (135 psi).

A microscopic inspection of the inside surface of the ruptured pipe revealed a fish scale-like

pattern over almost the entire inner surface of the pipe downstream of the orifice, except at the

bottom of the pipe. The thickness along the bottom of the pipe was found to be the nominal

wall thickness. The inside surface of the bottom of the pipe was covered with a thick surface

film. These conditions are characteristic of flow-accelerated corrosion (FAC).

BACKGROUND

The condensate system and main feedwater system, as well as other power conversion

systems, are important to safe plant operation. Failures in these systems may challenge plant

safety systems required for safe shutdown and accident mitigation. All U.S. licensees have

committed to adhere to criteria, codes and standards for high-energy piping systems described

in licensing documents. Part of this commitment is keeping pipes within the allowable thickness

values. The NRC has issued numerous generic communications, including IN 2001-09, "Main

Feedwater System Degradation in Safety-Related [American Society of Mechanical Engineers]

ASME Code Class 2 Piping Inside the Containment of a Pressurized-Water Reactor," on

various pipe wall thinning issues and events.

DISCUSSION

In May 1990, the operators of PWRs in Japan established "Guidelines for Secondary Piping

Wall Thickness Control at Nuclear Facilities (PWR)," (abbreviated PWR Management

Guidelines, hereafter) which were implemented at Mihama 3. These guidelines are based on

the known wall thinning rate of secondary system piping at various plants and describe the

methods for managing pipe wall thinning. The guidelines cover carbon steel piping in the

secondary system, where flow makes the walls susceptible to wall thinning. Approximately

25 percent of the piping within the scope of the guide is inspected within a 10-year period. The

frequency of inspection is determined by the calculated residual life before the minimum pipe

wall thickness is reached. Repeated inspections ensure that either the calculated residual life is

greater than 2 years or that the pipe is replaced with a pipe made of corrosion-resistant

material.

An investigation of the accident by the Nuclear and Industrial Safety Agency (NISA) found no

reviews of the PWR Management Guidelines after 1990 to reflect new data. In addition, NISA

concluded that the direct cause of the pipe failure was wall thinning but that the omission of this

pipe from the initial inspection plan, ineffective management, ineffective quality management

systems, and insufficient penetration of safety culture were contributing factors. As a result, the

plant owner and the owners contractors developed preventive measures to address quality assurance and maintenance management, inspection plans, and assessment of management

programs. After reviewing the owners preventive measures, NISA concluded that the actions

described were appropriate.

The Japanese regulatory authority has asked the Japanese Society of Mechanical Engineers to

develop new guidelines to replace the existing industrial guidelines on FAC. In its investigation

report, NISA noted the importance of periodically examining program management and

reviewing industry operating experience. NISA also emphasized that the success of these

programs depends on owner corporate commitment to foster a strong safety culture.

FAC is managed differently in Japan than in the U.S. Most U.S. licensees manage FAC by

implementing the Electric Power Research Institute (EPRI) guidelines described in NSAC-202L,

"Recommendations for an Effective Flow Accelerated Corrosion Program." Nevertheless, successful implementation of the EPRI guidelines relies on several of the factors addressed by

the NISA investigation report. For example, a successful FAC program depends upon periodic

review and re-evaluation of the program in the light of new information and operating

experience, application of sound engineering judgement, evaluation of the effect of design

changes with respect to FAC, a strong safety culture, and management support. This and

previous INs point to the continuing need for attention to the potential effects of FAC on piping

system integrity and to the elements of an effective degradation management program.

REFERENCES

"Interim Summary on Secondary Piping Rupture Accident at Mihama Power Station, Unit 3 of

the Kansai Electric Power Co., Inc.", (translated by Japan Nuclear Energy Safety Organization

(JNES)), September 27, 2004, The Nuclear and Industrial Safety Agency.

"Secondary Piping Rupture Accident at Mihama Power Station, Unit 3 of the Kansai Electric

Power Co., Inc. (Final Report)", Revision 1 (translated by Japan Nuclear Energy Safety

Organization (JNES)), May 14, 2005, The Nuclear and Industrial Safety Agency.

CONTACT

This information notice does not require any specific action or written response. Please direct

any questions about this matter to the technical contact listed below.

/RA/

Christopher I. Grimes, Director

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation

Technical Contact:

Carolyn Lauron, NRR

301-415-2736 E-mail: cll@nrc.gov

Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov, under Electronic Reading Room/Document Collections. assurance and maintenance management, inspection plans, and assessment of management programs. After

reviewing the owners preventive measures, NISA concluded that the actions described were appropriate.

The Japanese regulatory authority has asked the Japanese Society of Mechanical Engineers to develop new

guidelines to replace the existing industrial guidelines on FAC. In its investigation report, NISA noted the

importance of periodically examining program management and reviewing industry operating experience. NISA

also emphasized that the success of these programs depends on owner corporate commitment to foster a strong

safety culture.

FAC is managed differently in Japan than in the U.S. Most U.S. licensees manage FAC by implementing the

Electric Power Research Institute (EPRI) guidelines described in NSAC-202L, "Recommendations for an Effective

Flow Accelerated Corrosion Program." Nevertheless, successful implementation of the EPRI guidelines relies on

several of the factors addressed by the NISA investigation report. For example, a successful FAC program depends

upon periodic review and re-evaluation of the program in the light of new information and operating experience, application of sound engineering judgement, evaluation of the effect of design changes with respect to FAC, a

strong safety culture, and management support. This and previous INs point to the continuing need for attention to

the potential effects of FAC on piping system integrity and to the elements of an effective degradation management

program.

REFERENCES

"Interim Summary on Secondary Piping Rupture Accident at Mihama Power Station, Unit 3 of the Kansai Electric

Power Co., Inc.", (translated by Japan Nuclear Energy Safety Organization (JNES)), September 27, 2004, The

Nuclear and Industrial Safety Agency.

"Secondary Piping Rupture Accident at Mihama Power Station, Unit 3 of the Kansai Electric Power Co., Inc. (Final

Report)", Revision 1 (translated by Japan Nuclear Energy Safety Organization (JNES)), May 14, 2005, The Nuclear

and Industrial Safety Agency.

CONTACT

This information notice does not require any specific action or written response. Please direct any questions about

this matter to the technical contact listed below.

/RA/

Christopher I. Grimes, Director

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation

Technical Contact:

Carolyn Lauron, NRR

301-415-2736 E-mail: cll@nrc.gov

Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov, under

Electronic Reading Room/Document Collections.

DISTRIBUTION:

IN File

The Japanese have confirmed the accuracy of the notice.

ADAMS ACCESSION NUMBER: ML052910008 (TAC #MC8529)

OFFICE OES:IROB:DIP TECH EDITOR EMCB:DE C:EMCB:DE TL:OES:IROB:DIPM

M

NAME CVHodge PKleene CLLauron WHBateman ICJung

DATE 12/15/2005 10/21/2005 01/03/2005 01/ 03/2005 01/ 09/2005 OFFICE NRR LA:PGCG:DPR PGCG:DPR BC:PGCB:DP D:PGCB:DPR

R

NAME MCCullingford CHawes DBeaulieu CJackson CIGrimes DATE 01/ 04/2005 03/07/06 03/07/2006 03/14/2006 03/16/2006 OFFICIAL RECORD COPY