Information Notice 2006-04, Design Deficiency in Pressurizer Heaters for PWRs

From kanterella
Jump to navigation Jump to search
Design Deficiency in Pressurizer Heaters for PWRs
ML060100450
Person / Time
Site: Palo Verde, Waterford  Entergy icon.png
Issue date: 02/13/2006
From: Charemagne Grimes
NRC/NRR/ADRA/DPR
To:
Omid Tabatabai
References
IN-06-004
Download: ML060100450 (4)


UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

WASHINGTON, D.C. 20555 February 13, 2006 NRC INFORMATION NOTICE 2006-04: DESIGN DEFICIENCY IN PRESSURIZER

HEATERS FOR PRESSURIZED-WATER

REACTORS

ADDRESSEES

All holders of operating licenses for pressurized-water reactors, except those who have

permanently ceased operations and have certified that fuel has been permanently removed

from the reactor.

PURPOSE

The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice to inform

addressees about pressurizer heaters that failed following replacement because the heater

elements provided by the vendor did not match the licensees' design specification. It is

expected that recipients will review the information for applicability to their facilities and consider

actions, as appropriate, to avoid similar problems. However, suggestions contained in this

information notice are not NRC requirements; therefore, no specific action or written response is

required.

DESCRIPTION OF CIRCUMSTANCES

During the Fall 2004 refueling outage, the licensee at Palo Verde Generating Station, Unit 3, replaced all 36 pressurizer heaters with replacements supplied by Framatome that had heater

internals manufactured by Thermocoax. From December 2004 through February 2005, four of

the replaced heaters in the proportional heater banks failed. On May 23, 2005, with Palo Verde

Unit 3 in Mode 5 (cold shutdown), the licensee replaced nine Framatome/Thermocoax heaters

with General Electric (GE) heaters. During the subsequent reactor heatup, five

Framatome/Thermocoax heaters in the backup heater banks failed. As a result of the continued

heater failures, the licensee returned to Mode 5 to replace all remaining

Framatome/Thermocoax pressurizer heaters with GE heaters. When the

Framatome/Thermocoax heaters failed, all were grounded, and all but one tripped a circuit

breaker to clear a ground fault. The licensee discovered one heater grounded while

maintenance was being performed during the outage. There was no damage to any other

equipment such as power cables as a result of the heater failures.

During the Spring 2005 refueling outage, Waterford Steam Electric Station, Unit 3, replaced

29 pressurizer heaters with replacements supplied by Framatome that had the heater internals

manufactured by Thermocoax. During plant heatup but prior to reactor startup, two of the

replaced heaters experienced partial ejection of the epoxy in the receptacle area due to heat

transfer to electrical connections in the receptacle area, six experienced failure due to

grounding, and several experienced partial melting of the silicon-type material used to seal the

bottom end of the receptacles. The licensee replaced 23 Framatome/Thermocoax heaters with

Watlow heaters and abandoned the remaining 6 Framatome/Thermocoax heaters in place by

electrically disconnecting them. There was no damage to any other equipment such as power

cables as a result of the heater failures.

The vendor subsequently inspected the failed heaters from the Palo Verde and Waterford plants

and determined that the heaters had been incorrectly fabricated with a

longer heating element than the licensees' design specification. The longer heating elements

extended down into the heater sleeves and pressurizer shell thereby changing the location of

the transition joint that separates the heated and unheated portion of the heater assembly. This

resulted in a reduced ability to transfer that heat away from the heater and also allowed more

heat transfer to electrical connections in the receptacle area.

DISCUSSION

Technical specifications for PWRs specify a minimum required available capacity of pressurizer

heaters to ensure that the RCS pressure can be controlled to maintain subcooled conditions in

the RCS. Plant operation with failed pressurizer heaters can affect a facilitys ability to control

reactor pressure. Following a reactor trip, unnecessary safety injection actuations could occur

due to inability to maintain RCS system pressure above the actuation set point.

Additionally, the longer heating elements extended down into the heater sleeves and

pressurizer shell resulted the potential to exceed the allowable temperature limits by the

American Society of Mechanical Engineers Boiler and Pressure Vessel Code.

The Palo Verde and Waterford licensees had each supplied Framatome the correct design

specification regarding the location of the transition joint between the heated and unheated

portions of the heater assembly. However, Framatome supplied pressurizer heater assemblies

that did not match the design specification. The licensees did not obtain vendor specifications

and drawings that were sufficiently detailed to allow them to identify that the replacement

pressurizer heaters were not consistent with the licensees' design specification.

At Palo Verde Generating Station, Unit 3, one heater was discovered grounded while

maintenance was being performed during the outage. Sensitive ground-fault protection on low

voltage circuits such as 480 V pressurizer heater circuits, can help in the detection of a ground

fault.

Additional information on this subject is available in a Title 10 of the Code of Federal

Regulations Part 21 (10 CFR Part 21) report from Framatome dated July 28, 2005, which is

accessible using NRCs document control system (Agencywide Documents Access and

Management System (ADAMS), Accession No. ML052140277).

CONTACT

S

This information notice requires no specific action or written response. Please direct any

questions about this matter to the technical contacts listed below or the appropriate Office of

Nuclear Reactor Regulation (NRR) project manager.

/RA/

Christopher I. Grimes, Director

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation

Technical Contacts:

David N. Graves, R-IV/DRP/RPB-E Troy W. Pruett, R-IV/DRP/RPB-D

817-860-8147 817-860-8173 E-mail: DNG@nrc.gov E-mail: TWP@nrc.gov

Vijay K. Goel, NRR/DE/EEEB

301-415-3730

E-mail: VKG@nrc.gov

NRR Project Manager:

Omid Tabatabai, NRR/DIRS/IOEB

301-415-6616 E-mail: OTY@nrc.gov

Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov, under Electronic Reading Room/Document Collections.

CONTACT

S

This information notice requires no specific action or written response. Please direct any

questions about this matter to the technical contacts listed below or the appropriate Office of

Nuclear Reactor Regulation (NRR) project manager.

/RA/

Christopher I. Grimes, Director

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation

Technical Contacts:

David N. Graves, R-IV/DRP/RPB-E Troy W. Pruett, R-IV/DRP/RPB-D

817-860-8147 817-860-8173 E-mail: DNG@nrc.gov E-mail: TWP@nrc.gov

Vijay K. Goel, NRR/DE/EEEB

301-415-3730

E-mail: VKG@nrc.gov

NRR Project Manager:

Omid Tabatabai, NRR/DIRS/IOEB

301-415-6616 E-mail: OTY@nrc.gov

Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov, under Electronic Reading Room/Document Collections.

DISTRIBUTION:

IN File

ADAMS ACCESSION NO: ML060100450

OFFICE BC: R-IV/DRP/RPB-E BC: R-IV/DRP/RPB-D TECH EDITOR D:R-IV/DRP NRR/DE/EEEB

NAME DNGraves TWPruett HChang ATHowell VKGoel

DATE 1/24/2006 1/24/2006 1/17/2006 1/24/2006 2/13/2006 OFFICE BC:NRR/DE/EEEB NRR/DIRS/IOEB TL:NRR/DIRS/IOEB LA:PGCG/DPR PM:PGCB/DPR

NAME RVJenkins OTabatabai EJBenner CMHawes DBeaulieu

DATE 1/23/2006 1/19/2006 1/3/2006 1/19/2006 2/13/2006 OFFICE BC:NRR/DPR/PGCB D:NRR/DPR/PGCB

NAME CJackson CIGrimes

DATE 2/13/2006 2/14 /2006