|
---|
Category:Meeting Summary
MONTHYEARML24292A1832024-10-30030 October 2024 Summary of Meeting with Tennessee Valley Authority, October 16, 2024, to Discuss Proposed License Amendment Regarding Implementation of an Online Monitoring Methodology ML24269A0062024-10-0303 October 2024 Correction to Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the TVA Nuclear Quality Assurance Plan ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24228A2652024-08-20020 August 2024 Summary of Public Pre-Submittal Meeting with Tennessee Valley Authority Regarding a Future Sequoyah Nuclear Plant and Watts Bar Nuclear Plant LAR Related to TS 3.5.2. ECCS - Operating ML24221A0132024-08-19019 August 2024 July 10, 2024, Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24173A2122024-06-27027 June 2024 Summary of Public Meeting with Tennessee Valley Authority to Discuss a Proposed License Amendment Request Regarding Adoption of TSTF-276-A, Revision 2 to Clarify Requirements for Diesel Generator Testing ML24158A3002024-06-11011 June 2024 Summary of May 6, 2024, Public Meeting with Tennessee Valley Authority to Discuss the Potential for a License Amendment Request Regarding the Control Room Envelope and Selective Use of an Alternative Source Term ML24089A0712024-04-0101 April 2024 3/20/24 & 3/27/24 2023 TVA Public Annual Assessment Meeting Summary ML24057A0582024-02-27027 February 2024 Summary of February 15, 2024, Public Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML24008A1592024-01-18018 January 2024 Summary of December 13, 2023, Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML23304A0682023-11-0606 November 2023 Summary of October 24, 2023, Public Mtg W/Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2, and Sequoyah Nuclear Plant, Units 1 and 2 to Revise Function 5, Turbine Trip and F ML23265A1512023-09-28028 September 2023 Summary of September 12, 2023, Partially Closed Meeting with Tennessee Valley Authority to Discuss Proposed License Amendment Request ML23198A3102023-07-20020 July 2023 July 10, 2023, Summary of Public Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML23142A2132023-05-22022 May 2023 Public Meeting Summary - 2022 Annual Assessment Meetings for Browns Ferry, Sequoyah and Watts Bar Nuclear Plants ML23068A1532023-03-16016 March 2023 Summary of February 22, 2023, Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request to Increase Allowable Number of Tritium Producing Burnable Absorber Rods at Watts Bar Nuclear Plant, Units 1 and 2 ML23055A4562023-03-0909 March 2023 Summary of February 15, 2023, Public Meeting with Tennessee Valley Authority Regarding Proposed Expedited License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML22329A1382022-12-0505 December 2022 Summary of Meeting with Tennessee Valley Authority Related to Planned Alternative Request WBN-2-ISI-01 for Watts Bar Nuclear Plant, Unit 2 ML22168A1642022-06-27027 June 2022 Summary of June 9, 2022, Meeting with TVA Regarding a Proposed License Amendment Request Related to Low Temperature Overpressure System and Cold Overpressure Mitigation System for Sequoyah and Watts Bar Nuclear Plants ML22104A2252022-04-20020 April 2022 Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Exemption Request for Watts Bar Nuclear Plant, Unit 2 ML22109A0042022-04-20020 April 2022 Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Alternative Request Related to Testing of the Motor-Driven Auxiliary Feedwater Pumps at Sequoyah and Watts Bar Nuclear Plants ML22108A1842022-04-18018 April 2022 TVA 2021 Annual Assessment Public Meeting Summary ML22042B3262022-02-14014 February 2022 Summary of February 8, 2022, Meeting with Tennessee Valley Authority Regarding a Proposed License Amendment Request to Revise the Allowable Value for Trip of Turbine-Driven Main Feedwater Pump at Watts Bar Nuclear Plant, Unit 1 ML22025A3112022-02-0909 February 2022 Summary of January 19, 2022, Meeting with Tennessee Valley Authority Regarding a Proposed Schedule for Development of a License Amendment Request for Increased Tritium Production ML21349A3642022-01-0404 January 2022 Summary of December 14, 2021, Teleconference with Tennessee Valley Authority Regarding a Proposed Change to the Capsule Withdrawal Schedule for Watts Bar Nuclear Plant, Unit 2 ML21279A0902021-11-0303 November 2021 Summary of Conference Calls Regarding the Fall 2021, Mid-Cycle Steam Generator Tube Inspections ML21291A0092021-11-0303 November 2021 Tennessee Valley Authority Fleet - Summary of October 13, 2021, Teleconference with Tennessee Valley Authority to Discuss Planned License Amendment Requests Related to the Emergency Action Level Scheme ML21253A0872021-09-15015 September 2021 Summary of August 19, 2021, Partially Closed Meeting with Tennessee Valley Authority to Discuss Mid-Cycle Outage Contingencies for Watts Bar Nuclear Plant, Unit 2 ML21245A4252021-09-15015 September 2021 Summary of August 19, 2021, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request Related to the Watts Bar Nuclear Plant, Units 1 and 2 ML21165A1482021-06-30030 June 2021 Summary of Closed Meeting with Tennessee Valley Authority to Discuss Planned Requests for Exemption from Certain Requirements of 10 CFR Part 37 ML21137A0022021-05-17017 May 2021 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plants, Docket Nos. 50-259, 50-260, 50-296, 50-327, 50-328, 50-390, and 50-391, Meeting Number 20210392 ML21120A2192021-05-0404 May 2021 April 28,2021, Summary of Meeting with Tennessee Valley Authority Related to a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2, to Remove from Technical Specifications Redundant Units of Measurement for Control ML21099A2072021-04-13013 April 2021 Summary of April 7, 2021, Meeting with Tennessee Valley Authority Related to a Planned Relief Request from ASME Code Testing Requirements ML21060B0532021-03-0303 March 2021 Summary of February 11, 2021, Meeting with Tennessee Valley Authority Related to a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 2, to Apply a Temperature Adjusted Steam Generator Tube Flaw Growth Rate Methodology ML21033A5952021-02-23023 February 2021 Summary of Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Requests Related to the Watts Bar Nuclear Plant, Unit 2 Steam Generator Replacement ML20351A4212021-01-19019 January 2021 Summary of Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Requests Related to the Watts Bar, Unit 2, Steam Generator Replacement ML20357A0092021-01-19019 January 2021 Summary of December 17, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request Related to Use of Alternate Probability of Detection at Watts Bar Nuclear Plant, Unit 2 ML20351A2192021-01-11011 January 2021 Summary of Conference Calls Regarding the Fall 2020 Steam Generator Tube Inspections ML20337A0402020-12-15015 December 2020 Summary of November 17, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request for Technical Specification 5.9.9, Steam Generator Tube Inspection Report ML20323A0662020-11-27027 November 2020 Summary of October 28, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request for Technical Specification Surveillance Requirement 3.6.15.4, Shield Building ML20244A1892020-09-11011 September 2020 Summary of Teleconference Call with Tennessee Valley Authority Regarding a Proposed Change to the Containment Leakage Rate Testing Program ML20233A8352020-08-25025 August 2020 Summary of August 11, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML20213C7112020-08-25025 August 2020 Summary of July 28, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned Alternative Request for Watts Bar Nuclear Plant, Unit 1 ML20175A8012020-08-11011 August 2020 Summary of June 23, 2020, Public Meeting with Tennessee Valley Authority to Discuss a Planned License Amendment ML20211L8222020-08-10010 August 2020 Summary of Teleconference Call with the Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 1 ML20150A4162020-06-24024 June 2020 Summary of May 28, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 1 ML20153A3622020-06-22022 June 2020 Summary of May 27, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML20135H2702020-05-28028 May 2020 Summary of May 5, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML20143A1692020-05-28028 May 2020 Summary of May 14, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 2 ML20127H8412020-05-0606 May 2020 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plant, Meeting No. 20200384 ML20034F5232020-02-12012 February 2020 Summary of Meeting with Tennessee Valley Authority Regarding Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 2024-09-23
[Table view] |
Text
March 22, 2007 APPLICANT: TENNESSEE VALLEY AUTHORITY FACILITY: WATTS BAR NUCLEAR PLANT UNIT 2
SUBJECT:
SUMMARY
OF MARCH 12, 2007, MEETING WITH THE TENNESSEE VALLEY AUTHORITY REGARDING THE POSSIBLE RESUMPTION OF CONSTRUCTION AND LICENSING FOR THE WATTS BAR NUCLEAR PLANT UNIT 2 On March 12, 2007, a Category 1 public meeting was held between representatives of the U.S. Nuclear Regulatory Commission (NRC, or the Commission) staff and the Tennessee Valley Authority (TVA). The purpose of this meeting was to discuss TVAs ongoing study of the feasibility of resuming construction and licensing of the Watts Bar Nuclear Plant (WBN) Unit 2, as described in TVAs letter of November 14, 2006 (Agencywide Documents Access and Management System (ADAMS) Accession Number ML063200135). A list of meeting attendees is enclosed. Handouts provided by TVA may be found at ADAMS Accession Number ML070740440.
TVA and its contractors are conducting a Detailed Scoping, Estimating, and Planning (DSEP) study of the feasibility of completing WBN Unit 2 by 2013. The planned product of the DSEP is a detailed cost estimate and schedule for presentation to the TVA Board of Directors in August 2007. The study is also intended to identify and quantify project risks, including licensing risks. If the Board of Directors approves proceeding with the project, TVA will notify the NRC 120 days in advance of resuming construction in accordance with the Commission Policy on Deferred Plants. TVA is also preparing a Supplemental Environmental Impact Statement addressing impacts of resuming construction and future operation of WBN Unit 2.
Onsite activity supporting DSEP began in early January 2007, with walkdowns and inspections being conducted to assess the plant material condition. For example, TVA has conducted limited steam generator inspections, and believes those components can operate for 10 to 12 years before requiring replacement. TVA is also identifying equipment that will be replaced or overhauled. Additional walkdowns will be needed to support engineering design if construction resumes.
WBN Units 1 and 2 share some common areas, including the control room, so TVA is assessing how construction activities can be safely segregated from the operating unit.
TVA stated that WBN Unit 2 will be completed using the same licensing basis and design criteria as Unit 1. However, TVA recognizes that there will be some licensing and design differences between the units due to changes in regulatory requirements and criteria. Topics that will be addressed include application of Corrective Action Programs and Special Programs developed to address issues identified in the Nuclear Performance Plan (NPP). The NPP was written to respond to a September 17, 1985, NRC letter requesting information from TVA regarding significant problems at all TVA sites. TVA also plans to incorporate upgrades to WBN Unit 1 into Unit 2, including capital projects planned over the next 5 years. TVA intends to
keep the units as similar as possible. The regulatory standard to be applied to WBN Unit 2 are current rules and review criteria, such as the current Standard Review Plan. An evaluation to address severe accidents will also be needed.
The NRC staff and TVA discussed the timing and content of TVA submittals, particularly the "120-day" letter per the Commission Policy Statement on Deferred Plants. The staff stressed the need for early interaction to identify regulatory issues. During discussion of the WBN Unit 2 milestone schedule, the NRC staff emphasized the need for TVA to provide details regarding its proposed regulatory framework. The NRC staff also noted that construction activities conducted before regulatory reviews are completed will proceed at TVAs risk. TVA personnel indicated they understood these issues, and that they will review their milestones to determine if information can be provided sooner than originally envisioned.
Additional meetings and communications prior to the presentation to the TVA Board of Directors in August 2007 are expected. As discussed above, the staff expressed particular interest in early identification of potential regulatory issues. The staff is also interested in the material condition of the facility, so a meeting may be held at or near the WBN site. The staff also suggested that a closed meeting be planned to discuss security topics.
TVA has taken notice of the Commissioners' discussion of WBN Unit 2 licensing and inspection during the March 8, 2007, Commission briefing on NRR programs and is evaluating potential implications.
Members of the public were in attendance. Public Meeting Feedback forms were not received.
Questions regarding this meeting can be directed to me at 301-415-1470 or at jfw1@nrc.gov.
/RA/
Joseph F. Williams, Senior Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391
Enclosure:
As stated cc w/encl: See next page
ML070780080 OFFICE LPL2-2/PM LPL2-2/LA LP3-1/BC NAME JWilliams CSola LRaghavan DATE 3/22/07 3/22/07 3/22/07 Attendees NRC Meeting With TVA Possible Reactivation of Watts Bar Nuclear Plant Unit 2 March 12, 2007 Name Affiliation Pedro Salas AREVA Tom Harrison McGraw-Hill Eric Benner NRC Scott Burnell NRC Cathy Haney NRC Doug Huyck NRC Mark Lesser NRC John Lubinski NRC Charles Moulton NRC L. Raghavan NRC Will Smith NRC Sherwin Turk NRC Joe Williams NRC Jack Bailey TVA Raul Baron TVA Joe McCarthy TVA Jim Gresham Westinghouse Enclosure
Tennessee Valley Authority WATTS BAR NUCLEAR PLANT cc:
Mr. Karl W. Singer Ms. Beth A. Wetzel, Manager Chief Nuclear Officer and Corporate Nuclear Licensing and Executive Vice President Industry Affairs Tennessee Valley Authority Tennessee Valley Authority 6A Lookout Place 4X Blue Ridge 1101 Market Street 1101 Market Street Chattanooga, TN 37401-2801 Chattanooga, TN 37402-2801 Mr. Ashok S. Bhatnagar, Senior Vice President Mr. James D. Smith, Acting Manager Nuclear Operations Licensing and Industry Affairs Tennessee Valley Authority Watts Bar Nuclear Plant 6A Lookout Place Tennessee Valley Authority 1101 Market Street P.O. Box 2000 Chattanooga, TN 37402-2801 Spring City, TN 37381 Mr. Preston D. Swafford, Senior Vice President Mr. Michael J. Lorek, Plant Manager Nuclear Support Watts Bar Nuclear Plant Tennessee Valley Authority Tennessee Valley Authority 6A Lookout Place P.O. Box 2000 1101 Market Street Spring City, TN 37381 Chattanooga, TN 37402-2801 Senior Resident Inspector Mr. Larry S. Bryant, Vice President Watts Bar Nuclear Plant Nuclear Engineering & Technical Services U.S. Nuclear Regulatory Commission Tennessee Valley Authority 1260 Nuclear Plant Road 6A Lookout Place Spring City, TN 37381 1101 Market Street Chattanooga, TN 37402-2801 County Executive 375 Church Street Mr. Michael D. Skaggs, Site Vice President Suite 215 Watts Bar Nuclear Plant Dayton, TN 37321 Tennessee Valley Authority P.O. Box 2000 County Mayor Spring City, TN 37381 P. O. Box 156 Decatur, TN 37322 General Counsel Tennessee Valley Authority Mr. Lawrence E. Nanney, Director 6A West Tower Division of Radiological Health 400 West Summit Hill Drive Dept. of Environment & Conservation Knoxville, TN 37902 Third Floor, L and C Annex 401 Church Street Mr. John C. Fornicola, Manager Nashville, TN 37243-1532 Nuclear Assurance Tennessee Valley Authority Ms. Ann P. Harris 6A Lookout Place 341 Swing Loop Road 1101 Market Street Rockwood, TN 37854 Chattanooga, TN 37402-2801 Mr. Robert H. Bryan, Jr., General Manager Licensing and Industry Affairs Tennessee Valley Authority 4X Blue Ridge 1101 Market Street Chattanooga, TN 37402-2801