ML070510476

From kanterella
Jump to navigation Jump to search

Licensee Slides 2-9-07
ML070510476
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 02/09/2007
From:
ALION Science & Technology Corp, Enercon Services, Entergy Corp
To:
Office of Nuclear Reactor Regulation
Boska J, NRR, 301-415-2901
References
TAC MC4689, TAC MD4690
Download: ML070510476 (45)


Text

1 ENERCON IPEC GSI-191 STATUS AND STRATEGY Presentation to the NRC February 9, 2007

2 ENERCON AGENDA

  • GSI-191 Project Team
  • Sump Strainer Design
  • GSI-191 Modifications
  • Overall Methodology
  • Design Basis and Pool Turnover
  • Alternate Break Methodology
  • Chemical Effects
  • Path Forward
  • License Amendments

3 ENERCON GSI-191 Project Team

  • Entergy Project Team

- Project Management, Engineering, Licensing, Nuclear Engineering Analysis, Construction Services

  • Vendor Support

- Enercon

- Alion

- Transco

- Westinghouse

4 ENERCON IP2/IP3 Sump Layout

  • Two Independent and Redundant Sumps

- Internal Recirculation (IR) Sump - primary means of recirculation

- Vapor Containment (VC) Sump - backup to IR sump in case of loss of flow path

- IR Sump served by two IR pumps

- VC Sump served by two RHR pumps

5 ENERCON Plan View of lower containment IR SUMP VC SUMP

6 ENERCON Simplified ECCS Configuration IR PUMP IR PUMP IR SUMP VC SUMP RHR PUMP RHR PUMP Valve M

7 ENERCON Sump Strainer Design

  • Top Hat Characteristics

- Double Top Hat Strainer Module with Bypass Eliminator

- Perforated plate with 3/32 diameter hole

- Fiber Bypass expected to be less than 1 ft3

8 ENERCON Top Hat Strainer Module

9 ENERCON Debris Bypass Eliminator

10 ENERCON Debris Bypass Eliminator Since most of the fiber is captured near the surface of the wire mesh material, very little fiber is observed at the ends of the mesh material exiting the strainer Top Hat modules

11 ENERCON IP2 GSI-191 Modifications

  • 2R17 Spring 2006 Refueling Outage

- Installation of Sump Strainers

  • ~3200 ft2 Installed in IR Sump (original 48 ft2)
  • ~440 ft2 Installed in VC Sump (original 14 ft2)
  • Maximized surface area in sumps

12 ENERCON IP2 IR Sump Strainer

13 ENERCON IP2 IR Sump Strainer

14 ENERCON IP2 VC Sump Strainer

15 ENERCON IP2 VC Sump Strainer

16 ENERCON IP2 GSI-191 Modifications (Contd)

Installation of Flow Channeling Modifications

  • In-core tunnel
  • Crane wall holes
  • Gates and barriers

17 ENERCON Flow Channeling Concept Debris Transport is Reduced by Flow Channeling Concept

  • Flow Channeling

- Step 1: Water inside the crane wall flows to the Reactor Cavity

- Step 2: Water travels through the Incore Instrumentation Tunnel where a majority of the debris settles

- Step 3: Relatively clean water travels to the sumps

18 ENERCON Flow Channeling Concept

19 ENERCON Flow Channeling Concept IP2 North Incore Tunnel Exit Flow Barrier

20 ENERCON IP3 GSI-191 Planned Modifications

  • 3R14 Spring 2007 Refueling Outage

- Installation of Sump Strainers

  • ~3200 ft2 Installed in IR Sump (original 48 ft2)
  • ~1000 ft2 Installed in VC Sump (original 32 ft2)
  • Maximized surface area in sumps

- Installation of Flow Channeling Modifications

  • In-core tunnel
  • Crane wall holes
  • Gates and barriers

21 ENERCON IP3 IR Sump Strainer IP2 and IP3 IR Sump Strainers are Virtually Identical

22 ENERCON IP3 VC Sump Strainer

23 ENERCON OVERALL METHODOLOGY

- Debris Identification

- Debris Generation

- Debris Transport

- Downstream Effects

- Testing

24 ENERCON Debris Identification

  • Insulation

- Calsil/Asbestos, Temp-Mat, Nukon, Transco blanket, RMI, Mineral Wool, Kaowool

- Epoxy, Inorganic zinc, Enamel, High temperature aluminum, Phenoline

  • Latent Debris

- Tape & Equipment labels, Tie wraps, Fiber board tags, Dirt & Dust, Latent Fiber

25 ENERCON Debris Generation

26 ENERCON Debris Transport Vectors showing pool flow direction on the floor

27 ENERCON Debris Transport Vectors of pool flow direction in the Incore Tunnel

28 ENERCON Debris Transport Determination

  • The turbulence and vertical velocity are compared to the turbulent kinetic energy (TKE) and velocity metrics to suspend each kind of debris
  • 3-D CFD plots show the turbulence and z velocities
  • If TKE or vertical velocities not high enough - the debris would settle in tunnel
  • Results show that most debris settles in the tunnel

29 ENERCON Downstream Effects

  • Evaluation of Components

- Blockage of small flow paths

- Seizure of rotating components

- Wear and abrasion of surfaces

  • Evaluation of Reactor Vessel and Fuel

- Reactor vessel flow paths

- Nuclear fuel

  • No Downstream Effects Concerns Identified to Date

30 ENERCON Testing

  • Dissolution / Erosion Measurement of Cal-Sil
  • Array Head Loss for Debris
  • Fiber Bypass

- Fiber Bypass testing of a prototypical module

- Bypass material characterization

31 ENERCON Current Design Basis

  • Indian Points ECCS configuration is unique in that it has two independent and redundant sumps
  • No single active failure will disable the IR Sump and only a passive failure will require the use of the VC Sump
  • The VC Sump is not in itself single active failure protected, however, once a passive failure has occurred no more active failures would need to be considered

32 ENERCON Current Design Basis No single active failure will disable the IR Sump IR PUMP IR PUMP IR SUMP VC SUMP RHR PUMP RHR PUMP Valve M

33 ENERCON Current Design Basis Only a passive failure will require the use of the VC Sump IR PUMP IR PUMP IR SUMP VC SUMP RHR PUMP RHR PUMP Valve M

34 ENERCON Current Design Basis The VC Sump is not in itself single active failure protected IR PUMP IR PUMP IR SUMP VC SUMP RHR PUMP RHR PUMP Valve M

35 ENERCON Alternate Break

  • The Alternate Break Methodology as accepted by the SER allows no single failure for breaks larger than 14 (Large Break, LBLOCA) but requires design basis rules for breaks smaller than 14 (Alternate Break, ABLOCA)
  • This approach allows the VC Sump design to be limited to ABLOCA debris loads with credit for Pool Turnover

36 ENERCON Pool Turnover Strategy

  • At start of recirculation the IR Sump will be in operation. VC Sump will be in stand-by
  • A passive failure of the IR Sump is postulated to occur no earlier than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after the start of recirculation
  • Greater than 95% of the transportable debris would be collected at the IR Sump strainer
  • The VC sump strainer would be essentially clean at this time and would provide necessary recirculation cooling

37 ENERCON

38 ENERCON Alternate Break Methodology IP2/3 (Without Chemical Effects)

  • LBLOCA (no single failure required to be assumed)

- IR Sump can handle LBLOCA debris load (including a single active failure)

- VC Sump can handle LBLOCA debris load after 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of IR Sump recirculation

  • ABLOCA (single failure required to be assumed)

- IR Sump can handle ABLOCA debris load including a single active failure

- VC Sump can handle ABLOCA debris load following 24 hrs of IR Sump recirculation assuming a passive failure of IR system

39 ENERCON Chemical Effects

  • TSP (IP2 only) and Cal-Sil

- Results in Calcium Phosphate formation

- Results in Sodium Aluminum Silicate formation

40 ENERCON

  • LBLOCA (no single failure required to be assumed)

- IR sump will handle debris + chemical loads for at least 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> (including a single active failure)

- VC sump will handle residual debris + chemical loads following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of IR Sump recirculation

  • ABLOCA (single failure required to be assumed)

- IR Sump will handle debris + chemical loads for at least 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> including a single active failure

- VC sump will handle residual debris + chemical loads following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of IR sump operation with a postulated passive failure of IR system.

- If IR sump cannot survive long term with debris + chemical loads, then VC sump must be utilized.

Chemical Effects with Alternate Break Methodology

41 ENERCON Chemical Effects Options

- Reduce debris amounts such that chemical precipitants may pass through the strainer

- Reduce precipitate formation by PWROG WCAP model refinement

- Reduce Aluminum quantity exposed to spray

- Autoclave Testing to determine precipitate formation as function of time

- Replace buffer

- Batch buffer

42 ENERCON Path Forward

  • Debris Generation

- ZOI Refinements for Nukon, Temp Mat, Mineral Wool

- Coatings fail as chips

- Remove Kaowool (IP3)

  • Chemical Effects Options
  • Extension Requests and License Amendments

43 ENERCON GL 2004-02 Extension Request

  • IP2

- 2R18 Spring 2008 Refueling Modifications

  • Buffer replacement or batching
  • IP3
  • None required (Pending Chemical Refinements)

44 ENERCON License Amendments

  • IP2

- Buffer replacement/batching

- Alternate Break

- 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> delay time for passive failure

  • IP3

- Buffer replacement/batching

- Alternate Break

- 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> delay time for passive failure

- RWST switchover level TS change

45 ENERCON End of Presentation