l-joatn
ýIRowley-.
telecon summary for review From:.
Jonathan Rowley To:
mhamer@entergy.com Date:
11/01/2006 8:55:57 AM
Subject:
telecon summary for review Attached is the call summary for our Oct. 10 call. Please provide comments if applicable.
Jonathan Rowley, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission (301) 415-4053
ýqmp\\W)O00083MP ag6 1j Mail Envelope Properties (4548A76D.5D8 :12 : 35182)
Subject:
Creation Date From:
Created By:
telecon summary for review 11/01/2006 8:55:57 AM Jonathan Rowley JGR@nrc.gov Recipients entergy.com AM mhamer (mhamer@entergy.com)
Action Transferred Date & Time 11/01/2006 8:56:18 Post Office Delivered Route entergy.com Files Size Date & Time MESSAGE 789 11/01/2006 8:55:57 AM Summary of Telephone Conference - October 10, 2006 (VY).wpd 20870 11/01/2006 8:54:02 AM Options Auto Delete:
No Expiration Date:
None Notify Recipients:
Yes Priority:
Standard ReplyRequested:
No Return Notification:
Send Notification when Opened Concealed
Subject:
No Security:
Standard To Be Delivered:
Status Tracking:
Immediate Delivered & Opened
iJonathan Rowley -Summary of Telephone Conference-October 10, 2006 (VY).wpd
_Pagejl LICENSEE:
Entergy Nuclear Operations, Inc.
FACILITY:
Vermont Yankee Nuclear Power Station
SUBJECT:
SUMMARY
OF A TELEPHONE CONFERENCE CALL HELD ON OCTOBER 10, 2006, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING INFORMATION PERTAINING TO THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Entergy Nuclear Operations, Inc., held a telephone conference call on October 10, 2006, to discuss and clarify the staff's requests for additional information concerning the Vermont Yankee Nuclear Station license renewal application. The conference call was useful in clarifying the staff's questions. provides a listing of the conference call participants. Enclosure 2 contains a listing of the issues discussed with the applicant, including a brief discussion of the items' status.
The applicant had an opportunity to comment on this summary.
Jonathan Rowley, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-271
Enclosures:
As stated cc w/encls: See next page
jgo::ný(f fi"a7nfý_
ofTýýle-h----C-Onf-ere'-n'c-e'--'--O-c't-o'b-er-1 0--,2-00-ý-(-V--Y).w`pd--
Pag--e-!ý I If'Jbnathan~~~~~~
~~~~~~
Role..Sum.y.f.e.pon.Cnfrece..ctbe.0,206..Y.w..ag LIST OF PARTICIPANTS FOR TELEPHONE CONFERENCE CALL TO DISCUSS THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION October 10, 2006 PARTICIPANTS Jonathan Rowley Michael Morgan Dan Hoang Kenneth Chang Kaihwa Hsu Greg Galletti John Dreyfuss Lori Potts Alan Cox Dave Lach Jim DeVincentis Mike Hamer Mike Metel Ted Ivey AFFILIATIONS U.S. Nuclear Regulatory Commission (NRC)
NRC NRC NRC NRC NRC Entergy Nuclear Operations, Inc. (ENO)
Ionatha On Rowley - SummaryofTelephone Conference - October 10, 2006 (VY).wpd
__ag__
VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION October 10, 2006 The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Entergy Nuclear Operations, Inc., held a telephone conference call on October 10, 2006, to discuss and clarify the staff's requests for additional information (RAIs) and other issues concerning the Vermont Yankee Nuclear Power Station (VYNPS) license renewal application (LRA). The following issues were discussed during the telephone conference call:
RAI 3.6.2.2-N-08-1 The applicant responded to the staff's Request for Additional Information (RAI) 3.6.2.2-N-08 in a letter dated July 14, 2006, "License Renewal Application, Amendment 4". In the letter the applicant stated:
"Entergy, consistent with the Peach Bottom precedent, credited the [Federal Energy Regulatory Commission] FERC dam inspection program to manage the effects of aging on civil and structural elements of the [Vernon Hydroelectric Station] VHS."
A FERC letter to the previous owner of the VHS, New England Power Company (currently owned by TransCanada Hydro Northeast Inc.), dated August 6, 1997 states: "By letter dated June 26, 1997, you requested an exemption from filing an Independent Consultant's Safety Inspection Report under Part 12, Subpart D, of the Commission's Regulations..." and "...I am granting your request for an exemption from the Part 12, Subpart D requirement for submittal of an Independent Consultant's Safety Inspection Report."
As the exemption is only on the filing of an Independent Consultant's Safety Inspection Report under Part 12, Subpart D, describe specific Vermont Yankee Nuclear Power Station aging management activities, provide inspection reports, and describe any corrective actions that have been take as a result of the inspection reports - as they pertain to the VHS in accordance with 10 CFR 54.21 (a)(3) - since the exemption was granted.
Discussion: Prior to submitting its response to this RAI, the applicant wanted to inform the staff of new and significant information pertaining to the VHS. The applicant directed the staff to the Federal Energy Regulation Commission (FERC), where some operation reports containing information to be used in the applicant's response reside. Due to non-disclosure agreements with the hydro stations owner, the applicant was unable to provide the information directly. The staff was informed of the appropriate report numbers and will obtain them for FERC. The applicant will reference these reports in the RAI response.