ML062640096

From kanterella
Jump to navigation Jump to search
July 14, 2006, Letter, 05-ON-002, Rev. 1. Re Third Ten Year Inservice Inspection Interval Request for Relief No. 05-ON-002
ML062640096
Person / Time
Site: Oconee Duke Energy icon.png
Issue date: 07/14/2006
From: Brandi Hamilton
Duke Energy Corp
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Olshan L N, NRR/DORL, 415-1419
References
05-ON-002, Rev 1
Download: ML062640096 (34)


Text

BRUCE H HAMILTON P&Duke Vice President Oconee Nuclear Station rEnergye Duke Energy Corporation ONO VP / 7800 Rochester Highway Seneca. SC 29672 864 885 3487 864 885 4208 fax bhhamilton@duke-energy.com July 14, 2006 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555

Subject:

Duke Power Company LLC Oconee Nuclear Station, Unit 3 Docket Nos. 50-287 Third Ten Year Inservice Inspection Interval Request for Relief No. 05-ON-002, Rev 1 By letter dated June 24, 2005, Duke Power Company (Duke),

now Duke Power Company LLC d/b/a Duke Energy Carolinas, LLC, submitted Request for Relief 05-ON-002, seeking relief from the requirement to examine 100% of the volume specified by the ASME Boiler and Pressure Vessel Code,Section XI, 1989 Edition with no Addenda (as modified by Code Case N-460).

During the NRC review of this request, the reviewer communicated a Request for Additional Information to Duke via the NRC Project Manager assigned to Oconee.

Enclosed is a copy of that request, followed by the Duke response to each question. This response should satisfy the reviewer's request.

In addition, following submittal of 05-ON-002, Duke noted that the request included a statement which continued to credit the reactor building gaseous radiation monitor for leak detection. Industry experience has discovered that current fuel performance has reduced the level of failed fuel, such that these monitors are not sufficiently sensitive to detect leakage promptly. Therefore the statement in the relief was inappropriate. Paragraph I of the original relief request has been revised to correct the statement.

www.duke-energy. corn

U. S. Nuclear Regulatory Commission July 14, 2006 Page 2 As a result of the above, Revision 1 to the original request is also enclosed. Revision 1 includes changes to incorporate both the additional information requested, including updates to Enclosures B and C, and a correction to Paragraph I.

Please refer any additional questions regarding either the relief request or this response to Randy Todd - ONS Regulatory Compliance at (864) 885-3418.

Sincerely, Bruce H. Hamilton, Vice President Oconee Nuclear Site Enclosures (2) xc w/enc: Mr. William D. Travers Administrator, Region II U.S. Nuclear Regulatory Commission Atlanta Federal Center 61 Forsyth St., SWW, Suite 23T85 Atlanta, GA 30303 L. N. Olshan, Project Manager, Section 1 Project Directorate II.

Division of Licensing Project Management Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, DC 20555-0001 xc(w/o enc):

D. W. Rich Senior NRC Resident Inspector Oconee Nuclear Station Mr. Henry Porter Division of Radioactive Waste Management Bureau of Land and Waste Management SC Dept. of Health & Environmental Control 2600 Bull St.

Columbia, SC 29201

Enclosure 1 Request for Additional Information With Response Re:

Request for Relief 05-ON-002 Limited Examinations on Reactor Vessel 3EOC 21

TECHNICAL LETTER REPORT REQUEST FOR ADDITIONAL INFORMATION ON THIRD 10-YEAR INSERVICE INSPECTION INTERVAL REQUEST FOR RELIEF 05-ON-002 FOR DUKE POWER COMPANY OCONEE NUCLEAR STATION, UNIT 3 DOCKET NUMBER 50-287

1. SCOPE By letter dated June 24, 2005, the licensee, Duke Power Company, submitted Request for Relief 05-ON-002 from the requirements of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section XI, for Oconee Nuclear Station, Unit 3 (Oconee 3). The requests for relief are for the third 10 year inservice inspection (ISI) interval, in which Oconee 3 adopted the 1989 Edition of ASME Section XI as the code of record.

In accordance with 10CFR50.55a(g) (5) (iii), the licensee has submitted Relief Request 05-ON-002 for certain reactor pressure vessel weld examinations. The ASME Code requires that 100% of the examination volumes described in Tables IWB-2500-1 be completed. The licensee has claimed that 100% of the ASME Code required volumes are impractical to obtain at Oconee 3.

10 CFR 50.55a(g) (5)(iii) states that when licensees determine that conformance with ASME Code requirements is impractical at their facility, they shall submit information to support this determination. The NRC will evaluate such requests based on impracticality, and may impose alternatives, giving due consideration to public safety and the burden imposed on the licensee.

Pacific Northwest National Laboratory (PNNL) reviewed the information submitted by the licensee, and based on this review, determined the following information is required to complete the evaluation.

2. REQUEST FOR ADDITIONAL INFORMATION 2.1 General Information The licensee's submittal stated that this request is for Oconee 3, however, the transmittal letter shows docket number 50-270.

Confirm that Request for Relief 05-ON-002 is applicable only to Oconee Nuclear Station, Unit 3, and that the correct docket number is 50-287.

RAI Response RFR 05-ON-002 Page 2 of 4 Duke Power (DUKE) response:

05-ON-002 is for Unit 3 only and 50-287 is the correct docket number.

2.2 Examination Category B-A, Pressure Retaining Welds 3-RPV-WR34, -WR35, and -WRl9, on the Reactor Pressure Vessel (RPV) 2.2(a) For RPV shell-to-lower head Weld 3-RPV-WR34, the licensee stated that core support/guide lugs caused restrictions to the scanning access for these welds. Please be more specific as to how the RPV appurtenances restrict scanning access. Describe the remote UT fixture, including the transducer sled dimensions, and how the guide lugs prevented placing the transducer sled in a proper position for performing the examinations. Provide similar information for lower head ring Weld 3-RPV-WR35.

Duke response:

For weld 3-RPV-WR34:

Pages 2 of 4 and 4 of 4 were added to attachment B that should help to answer the question.

(note: Page 2 of 4 should have been sent with the original request for relief but may have been lost during the transmittal process. Page 4 of 4 is a new page.)

For weld 3-RPV-WR35:

Pages 2 of 5, 3 of 5, 4 of 5 and 5 of 5 were added to attachment C that should help to answer the question.

(note: Pages 2 of 5 and 3 of 5 should have been sent with the original request for relief but may have been lost during the transmittal process. Pages 4 of 5 and 5 of 5 are new pages.)

2.2(b) The licensee stated that ultrasonic examination of Welds 3-RPV-WR34, -WR35, and -WRl9 were conducted using personnel, equipment and procedures qualified in accordance with ASME Section XI, Appendix VIII, Supplements 4 and 6, 1995 Edition with the 1996 Addenda, as administered by the industry's Performance Demonstration Initiative. This is appropriate for Welds 3-RPV-WR34 and -WR35, because they are both RPV shell and head welds, and are required by CFR to be inspected by these type of performance-demonstrated methods.

RAI Response RFR 05-ON-002 Page 3 of 4 However, Weld 3-RPV-WR19 is a shell-to-flange weld, and is specifically excluded, by Article 1-2000, from the requirements of Appendix VIII. This weld must be examined using the procedures, personnel and equipment requirements listed in ASME Code Section V, Article 4, as supplemented by ASME Code Section XI, Article I.

While the NRC would like to encourage the use of performance-demonstrated UT methods for components not currently within the scope of Appendix VIII, the actual ASME Code requirement for Weld 3-RPV-WR19 at Oconee 3 is to use Article 4 of ASME Section V, supplemented by Article I of ASME Section XI. The licensee has not met this requirement, and therefore, must propose an alternative, in accordance with 10 CFR 50.55a(a) (3) (I), to use personnel, equipment and procedures qualified in accordance with ASME Section XI, Appendix VIII, Supplements 4 and 6, 1995 Edition with the 1996 Addenda, for Weld 3-RPV-WRI9.

Duke response:

Duke submitted Relief 04-GO-002 on 7-14-2004, which was approved by the NRC by letter of 10-20-2004. This was a proposed alternative to use personnel, equipment and procedures qualified in accordance with ASME Section XI, Appendix VIII, Supplements 4 and 6, 1995 Edition with the 1996 Addenda, for several welds, including Weld 3-RPV-WRI9.

2.3 Examination Category B-D, Item B3.90, Nozzle-to-Vessel Welds 3-RPV-WR54 and-WR54A on the Reactor Pressure Vessel (RPV) 2.3(a) These nozzle-to-vessel welds are on core flood nozzles located at 0 and 180 degrees on the RPV. The licensee stated that these examinations were performed during December 2004, and that examination of nozzle-to-vessel Welds 3-RPV-WR54 and -WR45A were conducted using personnel, procedures and equipment qualified in accordance with ASME Section XI, Appendix I, 1989 Edition, with no Addenda.

However, 10 CFR 50.55a(g)(6)(ii) (C) requires licensees to implement the 1995 Edition, with 1996 Addenda, of ASME Section XI, Appendix VIII, Supplements 5 and 7, for RPV nozzle-to-vessel welds examined after November 22, 2002.

These Supplements list the requirements for performance demonstration of procedures, personnel and equipment. The licensee should clarify whether the stated UT qualifications

RAI Response RFR 05-ON-002 Page 4 of 4 were mistakenly identified or explain why the examination of Welds 3-RPV-WR54 and -WR54A were not performed using personnel, procedures and equipment qualified under Supplements 5 and 7, as required by CFR.

Duke response:

The wrong reference was used. Paragraph H of the Original Relief Request will be revised to read as shown below:

Paragraph H:

Ultrasonic examination of areas/welds for item numbers B03.090 were conducted using personnel, equipment and procedures qualified in accordance with ASME Section XI, Appendix VIII, Supplements 4, 6, & 7, 1995 Edition with the 1996 Addenda. Although limited scanning prevented 100% coverage of the examination volume, the amount of coverage obtained for these examinations provides an acceptable level of quality and integrity.

(See Paragraph I for additional justification.)

Note: Supplement 5 was not used to examine the nozzle inside radius because an enhanced visual examination was performed in lieu of UT examination per Code Case N-648-1.

Enclosure 2 Request for Relief 05-ON-002 Revision 1 Limited Examinations on Reactor Vessel 3EOC 21

Relief Request 05-ON-002 Rev. 1 Page 1 of 6 Proposed Relief in Accordance with 10 CFR 50.55a(g)(5)(iii)

Inservice Inspection Impracticality Duke Energy Corporation Oconee Nuclear Station - Unit 3 (EOC-21)

Third 10-Year Interval - Inservice Inspection Plan Interval Start Date = 12-16-1994 Interval End Date = 1-2-2005 ASME Section XI Code - 1989 Edition with No Addenda Code Case N-460 is applicable

!. II. iII. IV. &V. VI. VII. VIII.

List Limited System/ Code Requirement from Impracticality/ Proposed Alternate Implementation Justification for Number Area/Weld I.D. Component for Which Which Relief is Requested: Burden Caused by Examinations or Schedule and Granting Relief Number Relief is Requested: 100% Exam Volume Coverage Compliance Testing Duration Area or Weld to be Exam Category Examined Item No.

Fig. No.

Limitation Percentage

1. 3-RPV-WR34 NC System Exam Category B-A See Paragraph "A" See Paragraph "E" See Paragraph "F" See Paragraph "G" Reactor Vessel Item No. BO 1.011.004 Lower Shell to Lower Fig. IWB-2500-1 Head Ring 44.5% Volume Coverage Circumferential Weld
2. 3-RPV-WR35 NC System Exam Category B-A See Paragraph "B" See Paragraph "E" See Paragraph "F" See Paragraph "G" Reactor Vessel Item No. B01.021.003 Lower Head Cap to Fig. IWB-2500-3 Lower Head Ring 50% Volume Coverage Circumferential Weld 3 3-RPV-WR19 NC System Exam Category B-A See Paragraph "C" See Paragraph "E" See Paragraph "F' See Paragraph "G" Reactor Vessel Item No. B01.030.001 Upper Shell to Flange Fig. IWB-2500-4 Circumferential Weld 85.8% Volume Coverage
4. 3-RPV-WR54 NC System Exam Category B-D See Paragraph "D" See Paragraph "E" See Paragraph "F" See Paragraph "H" Reactor Vessel Item No. B03.090.007 Core Flood (UT from vessel I.D.)

Nozzle-to-Vessel Weld Fig. 'WB-2500-7(a)

@ 00 84.2% Volume Coverage

Relief Request 05-ON-002 Rev. 1

_Page 2 of 6

. I. III. IV. &V. VI. VII. VIII.

List Limited System / Code Requirement from Impracticality/ Proposed Alternate Implementation Justification for Number Area/Weld I.D. Component for Which Which Relief is Requested: Burden Caused by Examinations or Schedule and Granting Relief Number Relief is Requested: 100% Exam Volume Coverage Compliance Testing Duration Area or Weld to be Exam Category Examined Item No.

Fig. No.

Limitation Percentage

5. 3-RPV-WR54 NC System Exam Category B-D See Paragraph "D" See Paragraph "E" See Paragraph "F" See Paragraph "H" Reactor Vessel Item No. B03.090.007A Core Flood (UT from nozzle bore.)

Nozzle-to-Vessel Weld Fig. IWB-2500-7(a)

@ 00 84.2% Volume Coverage

6. 3-RPV-WR54A NC System Exam Category B-D See Paragraph "D" See Paragraph "E" See Paragraph "F" See Paragraph "H" Reactor Vessel Item No. B03.090.008 Core Flood (UT from vessel ID)

Nozzle-to-Vessel Weld Fig. IWB-2500-7(a)

@ 1800 84.2% Volume Coverage

7. 3-RPPV-WR54A NC System Exam Category B-D See Paragraph "D" See Paragraph "E" See Paragraph "F" See Paragraph "H" Reactor Vessel Item No. B03.090.008A Core Flood (UT from nozzle bore)

Nozzle-to-Vessel Weld Fig. IWB-2500-7(a)

@ 1800 84.2% Volume Coverage See Attachment A for area/weld locations.

Note: The welds listed in the table above were inspected in December of 2004.

Relief Request 05-ON-002 Rev. 1 Page 3 of 6 IV. & V. Impracticality/ Burden Caused by Code Compliance Paragraph A: (The Lower Shell and Lower Head Ring material is SA508 CL2. This weld has a diameter of 170.250 inches and a wall thickness of 5.5 inches.)

During ultrasonic examination, 100% coverage of the required examination volume could not be obtained. Twelve core guide lugs restrict the scanning surface, as shown on the Attachment B drawing, causing limitations that resulted in 44.5% coverage. The percentage of coverage reported represents the aggregate coverage from all scans parallel and perpendicular to the weld. The weld and adjacent base material were examined using 450 refracted shear waves and 450 refracted longitudinal waves. Examination volumes directly below the core guide lugs received no coverage when scanned parallel to the weld. Additionally no scans were performed perpendicular to the weld directly below the core guide lugs. Scans parallel to the weld were restricted to 7.6 inches on either side of each core guide lug and scans perpendicular to the weld were restricted to 4.7 inches on either side of each core guide lug. In order to achieve more coverage, the core guide lugs would have to be moved to allow greater access, which is impractical.

There were no recordable indications found in the areas that were examined.

54% of the weld and base material volume received coverage in two directions perpendicular to the weld.

35% of the weld and base material volume received coverage in two directions parallel to the weld.

55.50% of the weld and base material volume received no coverage.

(See Attachment B for exam information)

Paragraph B: (The Lower Head Cap material is SA533 CLI GRB and Lower Head Ring material is SA508 CL2.

This weld has a diameter of 143.00 inches and a wall thickness of 5.375 inches.)

During ultrasonic examination, 100% coverage of the required examination volume could not be obtained. The examination coverage was limited to 50%. The percentage of coverage reported represents the aggregate coverage from all scans parallel and perpendicular to the weld. The flow stabilizers, core guide lugs and in-core nozzles that restrict the scanning surface, as shown on the Attachment C drawing, caused the limitations. The weld and adjacent base material were examined using 450 refracted shear waves and 450 refracted longitudinal waves. There were no recordable indications found in the areas that were examined. In order to achieve more coverage the flow stabilizers, core guide lugs and in-core nozzles would have to be moved to allow greater access for scanning, which is impractical.

53.33% of the weld and base material volume received coverage in two directions perpendicular to the weld.

46.66% of the weld and base material volume received coverage in two directions parallel to the weld.

50% of the weld and base material received no coverage.

(See Attachment C for exam information)

Paragraph C: (The Upper Shell and Flange material is SA508 CL2. This weld has a diameter of 167.630 inches and a wall thickness of 12.00 inches.)

During ultrasonic examination, 100% coverage of the required examination volume could not be obtained. The examination coverage was limited to 85.8%. The percentage of coverage reported represents the aggregate coverage from all scans parallel and perpendicular to the weld. Limitations were caused by inside surface taper and the ledge shown in Attachment D. The percentage of coverage reported represents the aggregate coverage from all scans. The weld and adjacent base material were examined using 450 refracted shear waves and 450 refracted longitudinal waves. There were no recordable indications found in the areas that were examined. In order to achieve more coverage, the weld would have to be redesigned which is impractical.

(See Attachment D for exam information)

Relief Request 05-ON-002 Rev. I Page 4 of 6 Paragraph D: (The Upper Shell and Core Flood Nozzle material is SA508 CL2. This weld has a diameter of 25.00 inches and a wall thickness of 12.00 inches.)

During ultrasonic examination, 100% coverage of the required examination volume could not be obtained. The examination coverage was limited to 84.2% of the required volume. The Core Flood Nozzles of a B&W 177 plant have several obstructions which limit ultrasonic examination coverage. In order of significance these are:

  • The flow restrictor which is welded to the inner bore of the nozzle;

" The inlet nozzles located 300 on either side of each core flood nozzle;

" The taper above the core flood nozzles associated with the Core Support Ledge.

The percentage of exam volume coverage reported represents the aggregate coverage as follows:

Weld and adjacent base material = 87.6% scanned parallel to the weld in two opposite directions and 72.9%

scanned perpendicular to the weld centerline from the nozzle bore and the vessel inside surface.

There were no recordable indications found in the areas that were examined for either of these welds. In order to achieve more coverage, the inlet nozzles would have to be moved, and the taper on the flange would have to be redesigned to allow greater access for scanning, which is impractical. In addition, because of the proximity of the flow restrictors limited scanning was performed from the nozzle I.D. as shown in Attachment E. In order to achieve more coverage, the flow restrictor would have to be moved to allow access for scanning, which is impractical.

(See Attachment E for exam information)

VI. Proposed Alternate Examinations or Testing Paragraph E:

The scheduled 10-year code examination was performed on the referenced area/weld and it resulted in the noted limited scanning and coverage of the required ultrasonic volume. No additional examinations are planned for the area/weld during the current inspection interval.

VII. Implementation Schedule and Duration Paragraph F The scheduled third 10-year interval plan code examination was performed on the referenced area/weld resulting in limited scanning and volumetric coverage. No additional examinations are planned for the area/weld during the current inspection interval. The same area/weld may be examined again as part of the next (fourth) 10-year interval plan, depending on the applicable code year edition and addenda requirements adopted in the future.

VIIi. Justification for Granting Relief Paragraph G:

Ultrasonic examination of welds for item numbers B01.011, B101.021 and B101.30 were conducted using personnel, equipment and procedures qualified in accordance with ASME Section XI, Appendix VIII, Supplements 4 and 6, 1995 Edition with the 1996 Addenda as administered through the Performance Demonstration Initiative (PDI)

Program. Although limited scanning prevented 100% coverage of the examination volume, the amount of coverage obtained for these examinations along with the additional volumetric and visual examinations (listed in the next paragraph) provides an acceptable level of quality and integrity. (See Paragraph I for additional justification.)

Relief Request 05-ON-002 Rev. 1 Page 5 of 6 In addition to the Category B-A welds that relief is being sought for, there were 3 circumferential Category B-A welds that were inspected and all obtained greater than 90 % coverage and there were no reportable indications found during the inspections. Visual examinations were also performed as part of the reactor vessel inspections (item number B 13.010.001 and B 13.050.001) and were found to be without any reportable indications.

Paragraph H:

Ultrasonic examination of areas/welds for item numbers B03.090 were conducted using personnel, equipment and procedures qualified in accordance with ASME Section XI, Appendix VIII, Supplements 4, 6, & 7, 1995 Edition with the 1996 Addenda. Although limited scanning prevented 100% coverage of the examination volume, the amount of coverage obtained for these examinations provides an acceptable level of quality and integrity.

(See Paragraph I for additional justification.)

Paragraph I:

Duke Energy will use the Code required pressure testing and VT-2 visual examination to compliment the limited examination coverage. The Code requires (reference Table IWB-2500-1, item numbers B 15.010 and B15.050) that a system leakage test be performed after each refueling outage for Class 1. Additionally a system hydrostatic test (reference Table IWB-2500-1, item numbers B 15.011 and B 15.051) is required once during each 10-year inspection interval; however, Code Case N-498-1 was invoked in lieu of performing the hydrostatic test. These tests require a VT-2 visual examination for evidence of leakage. This testing provides adequate additional assurance of pressure boundary integrity.

Duke Energy will use VT-3 visual examination to compliment the limited examination coverage. The Code requires (reference Table IWB-2500-1, item number B 13.010) that a VT-3 examination be performed after the first refueling outage and subsequent refueling outages at approximately 3 year periods. During the first and second periods of an interval a VT-3 examination is performed on areas above and below the reactor core that are made accessible for examination by removal of components during normal refueling outages. During the third period of an interval the VT-3 examination is performed on all of the reactor vessel interior surfaces at the same time that the automated UT exams are performed on the reactor vessel welds. These examinations provide adequate additional assurance of pressure boundary integrity.

In addition to the above Code required examinations (volumetric, pressure test, and VT-3), there are other activities which provide a high level of confidence that, in the unlikely case that leakage did occur through these welds, it would be detected and the Unit shutdown for repairs. Specifically, Technical Specification 3.4.13, "Reactor Coolant System Leakage" requires evaluation of Reactor Coolant System (RCS) leakage every 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. This requirement is met using procedure PT/3/A10600/10, "RCS Leakage," which is performed daily. In addition, Technical Specification 3.4.15, "RCS Leakage Detection Instrumentation" requires that a Reactor Building normal sump level indicator and a containment atmosphere radioactivity monitor be operable for RCS leakage detection. This requirement is met using the normal sump level indicator and the Reactor Building air particulate monitor (3RIA 47). An unexpected loss of level in the Letdown Storage Tank is another indication of potential RCS leakage.

Duke Energy Corporation has examined the welds/components referenced in this request to the maximum extent possible utilizing the latest in examination techniques and equipment. These welds were rigorously inspected by volumetric NDE methods during construction and verified to be free from unacceptable fabrication defects. Based on the coverage and results of the required volumetric and visual examinations performed during this outage, it is Duke's belief that this combination of elements provides a reasonable assurance of component integrity.

J 4 Relief Request 05-ON-002 Rev. 1 Page 6 of 6 IX. Other Information The following individuals contributed to the development of this relief request:

James I. McArdle (Principal NDE Level III Inspector) provided Sections III through V and part of Section VIII.

B. W. Carney, Jr. (Oconee Engineering) provided part of Section VIII.

Larry C. Keith (Oconee ISI Plan Manager) compiled the remaining sections.

Sponsored By: *7M% C. , Date 6'; 8- 0 6 Approved By: Date ~'2fl24

Reclassified as Westinghouse Non-Proprietary Class 3 on 8/7/06 Westinghouse Proprietary Class 2C 150" 180' 210" 270' 330' 360'

-~ ____ I ____ _____ 292'0 10

__ _ _ _ _ _.0 _I N 0

_ _ _ _~~~~_

-- 7.00 W17 W21 V23 3-RPV-WR12C 3-RPV-VR12A 3-RPV-R2B 3-RPV-VR13A (B090.006)

(D03,090.004) (003.090,005) (03.090.00),

, , I I - 3035.19

.I I I ,. I i .... 9., 8 SCALED TO THE ID SURFACE OCONEE 3 BOCf3 VWesDyne International T Vessel RoLtout EXAMINATION PROGRAM PLAN 2004 Page 29 of 52 UNL=0mw0 .Nn HI*1 ET 1 O2 P

Reclassified as Westinghouse Non-Proprietary Class 3 on 817106 Westinghouse Proprietary Clams 2C 0"

Wd15 3RPV-WR13 B03.090501 270" 90, OCONEE 3 BOC03 o

WesDyne InternationaL ag1 T Nozzle Orientation EXAMINATION PROGRAM PLAN 2004 Page 31 of 52 ALL DDOONS I N ONARLOWMI SHEET 3 OF 2 2

Aj 7T ACA r^ -eoJT r.

R.V. COVERAGE ESTIMATE BREAKDOWNS PLANT NAME Oconee WesDyne WELD NO. W4 (3-RPV-WR34)

International COMPONENT Transition to Lower Shell Circ. Weld BEAM ANGLE BREAK DOWN BEAM DIRECTION 45 Shear 45 L Single 45 L Dual WELD VOLUME WELD VOLUME WELD IVOLUME WELD VOLUME Perpendicular 54.00 54.00 54.00 54.00 54.00 54.00 Parallel 35.00 1 35.00 35.00 35.00 35.00 AVERAGE 44.50 44.50 44.50 Comments:

Combined Perp. 54.00 Combined Para. 35.00 Combined Average 44.50 Analyst A-. A-d# Date

Reclassified as Westinghouse Non-Proprietary Class 3 on 817106 Westinghouse Pi*oprietary Class 2C

/

000o CI

- 291.94 1' 1 *Working Point 8.56

,13\(85.19*) Top Perp (82.56") 303.10 301.39 (83.69") Top Poaraltel N

(79.13") 308.43 309.50 313.06 (75.97') Bottom Paratlet (77.09") 312.64 313.35 (75.76) Bottom Perp

_,- R87.06

.19 5.38 (WO4) 3-RPV-W/R34 B01.011.004 Scan Inrrement = 0.329" (0.5') for Pu'ratkel Scans

= 0.329" (0,50') for Perp ScQns OCONEE 3 BOC03 Par'QUet Scan Limits +/- 4.6' Either Side of Core Guide Lugs WesDyne InternationaQ Perp Scan Limits */- 3,1" Either Side of Corve Guide Lugs C"" Trcins$tion*, to Lower Shell Circ Weld No Scans Performed Below Core Guide Lugs EXAMINATION PROGRAM PLAN 2004 D*A OM rnsI¶SuE 8I0 22 Amwl ty~~nJSf bcmfl Sr I M 8 OF 2- 2

%,J 36 of 52

AkItdCh cr, Qj T- f3 P',. ~

5 r-3+l,*L Zone of partial coveraige typical 12 locations COkAe 'e ONS-3 3-RPV-VIR34

Reclassified as Westinghouse Non-Proprietary Class 3 on 817/06 Westinghotme Proprietary Clam 2C

'V TOP of Vessel

.1%

0 for Axiat Scans 0

-u 0

4+ 0 o-

3 0J U o 0 (C

C5

-~

4 0

I-0 U L Qj C-, C" L C O+*O

- oP n

P APPENDIX VIII SHELL EXAM CONFIGURATION U' Note, USI-8 = Upper Robot W[TH EXTRA COVERAGE DUCERS LS1-8 = Lower Robot VIEW, FROM VESSEL CENTERLINE 06+/-

OCONEE 3 B]CO3 QIB(D1I~

V/esDyne International I Appendix'VIII Shell Sled EXAMINATION PROGRAM PLAN I1mnf

" _wimg req A WI ubi vDwmTQVI ImgmI I I- IQ i4c ý2

F. A-r'rACh m'-esdT C.~

paTe 4 -S I I IIIIIEl P[__

R.V. COVERAGE ESTIMATE BREAKDOWNS PLANT NAME Oconee WesDyne WELD NO. W5 (3-RPV-WR35)

International COMPONENT Lower Head to Transition Circ. Weld BEAM ANGLE BREAK DOWN BEAM DIRECTION1 45 Shear 45 L Single 45 L Dual WELD j VOLUME I WELD VOLUME WELD VOLUME jWELD JVOLUME Perpendicular 53.33 53.33 53.33 53.33 53.33 53.33 Parallel 46.66 46.66 46.66 46.66 46.66 46.66 _

AVERAGE 50.00 50.00 50.00 Comments:

COMBINED AVERAGE 50.00 Analyst Date 2ý//-//,Oorzy

Reclassified as Westinghouse Non-Proprietary Class 3 on 8/7106 Westinghouse Proprietary Clima 2C

/

Thr~ent (working point)

Efevation I

58.53' ParatieL Top Perp Top Perp Bottom Parallel Bottom (W5) 3-RPV-WR35 B01.021.003 OCONEE 3 BOC03 i

WesDyne

  • iI International i

Scan Increment = 0.329' (0,5') For ParIateL Scans a,-Lower Hea~d to Transition Circ Weld

= 0.3290 (0.50') f or Perp Scans EXAMINATION PROGRAM PLAN 2004

%" 1* 4q AUDUMIS rv A tJflen iv,'ibivfln NHEEj~rT 9 OF 22 J~*S V'

A7-74ch 14ei C Reclassified as Westinghouse Non-Proprietary Class 3 on 8/7/06 Westinghouse Proprietary Claw 2C TOP of Vessel -- I 0

for AxIaL Scans U 0

0 4r+

0

3

%.0 U,

<,I-- In U

-C +,

d 4-- LC5 0 In (4-0

( -5 APPENDIX VIII SHELL EXAM CONFIGURATION Note, USI-8 = Upper Robot WITH EXTRA COVERAGE DUCERS LSI-8 = Lower Robot Cw ROTATION. SHELL EXAMSiam TAN SCANS VIEW, FROM VESSEL CENTERLINE OCONEE 3 BOC03 ErLWdJ W/esDyne I nternaQtionat r Appendix' VIII Shell Sled EXAMINATION PROGRAM PLAN AM DO OS D1 MeS I

.1 - -- I UnEM OTMWM NOTM I

Reclassified as Westinghouse Non-Proprietary Class 3 on 817106 Westinghouse Proprietary Class 2C LOWER HEAD VR 34 ý ORIEN TATION TY(P.

30.0 -7" FLOW STABILIZER TYP, QUANTITY 12 I

EXAM

-V 0LUR~E-R87.06 SCANS AROUND OBSTRUCTIONS TYP, 5,38 00 90C OCONEE 3 BUC[3 WesDyne International T LOWER HEAD WELD WR35 FLOW STABILIZER LIMITATION AUL DIBM ONS IN INCHESI RFR RAI SUPPLEMTAL UNLS OTH'WISE NOTEDI JUNE 20o6

6: . .. _ - ,

A TtAC-k IM,'t" 72 ,o /4 x R.V. COVERAGE ESTIMATE BREAKDOWNS PLANT NAME OCONEE WesDyne WELD NO. WI (3-RPV-WR19)

International COMPONENT Shell to Flange Weld BEAM ANGLE BREAK DOWN BEAM DIRECTION 45 Shear 45 L Single 45 L Dual WELD jVOLUME WELD VOLUMEI WELD JVOLUMEI WELD VOLUME Perpendicular 86.66 86.66 86.66 86.66 86.66 86.66 Parallel 85.00 85.00 85.00 85.00 85.00 85.00 _

AVERAGE 85.83 85.83 85.83 Comments:

Combined Perp. 86.66 7* , Combined Para. 85.00 Combined Average 85.83 Analyst Date

'-I

RseftdtW SO WOSPN@IOw. FftM4VVupddarY Mean 3 On WOT v~"M PNVMWYu m PC 3e0.44R to Clod 1821 Top Perp 22A036 Tupwr 2425 24.90 Top Parvitel 27D058 T&We 32.00 - 17.4' 39.75

=41-460 bottom PurWIWe 4823 Dottom Perp l-- 4.OR to Clad 3-RPV-WR19 L1o2!20.o OCONEE 3 BJC03 seen krnrve a OZ" tor PareIr# Scans a 0.341 for sc," VesDvrxe InterfltionaO

....il II III . .. . .

IN Omer Sheti to rtanQe qWin*T r Pi PWLN

" oo4 I II I II l _

L- 12 f12 V. RI* 4OF1

- a I A 7Thc1ýc-h I

R.V. COVERAGE ESTIMATE BREAKDOWNS PLANT NAME Oconee WesDyne WELD NO. WI 1 (3-RPV-WR54)

International COMPONENT Core Flood Nozzle to Shell @ 0° BEAM ANGLE BREAK DOWN BEAM DIRECTION 45 Shear 45 L Single 45 L Dual Combined Bore/Star WELD VOLUME J WELD VOLUME WELD VOLUME WELD VOLUME J TAN Scan ___,,

Parallel 94.22 80.95 100.00 98.71 100.00 100.00 Combined Bore&Star _ _ _iiii Perpendicular 1 74.75 71.01 AVERAGE 87.59 99.35 100.00 72.88 Comments: Coverage calculation is based on the Bore and.Star scan (combined) as perpendicular, and the Tan Scan (parallel). Limitation Is due to vessel saddle effect at 90° &2700 and the flow restrictor located in the inside of the nozzle.

nA A* A ....

Combined Perp. 72.88 Combined Para. 95.65 Combined Average 84.26 Analyst 4ý Date/? /d

. I t .

R.V. COVERAGE ESTIMATE BREAKDOWNS PLANT NAME Oconee WesDyne WELD NO. W19 (3-RPV-WR54A)

International COMPONENT Core Flood Nozzle to Shell @ 180D BEAM ANGLE BREAK DOWN BEAM DIRECTION 45 Shear 45 L Single 45 L Dual Combined Bore/Star WELD VOLUME WELD VOLUME WELD VOLUME WELD VOLUME TAN Scan Parallel 94.22 80.95 100.00 98.71 100.00 100.00 Combined Bore&Star Perpendicular 74.75, 71.01 AVERAGE 87.59 99.35 100.00 72.88 Comments: Coverage calculation is based on the Bore and Star scan.(combined) as perpendicular, and the Tan Scan (parallel). Limitation is due to vessel saddle effect at 90_ &270° and the flow restrictor located in the Inside of the nozzle.

Combined Perp. 72.88 Combined Para. 95.65 Combined Average 84.26 Analyst Date 9*/ Y

Reclassified as Westinghouse Non-Proprietary Class 3 on 9/12/2006 Westinghouse Proprietary Class 2C 9 84.OR to CLad LL L4 PA co U

C C 0

U C C 0 CI 60,0 Ref.

14 VI U U

" 0 to Top of Vessel U U Core Flood Nozzle to ShelL 3RPV-W/R54 (B03.090.007A)

Core Flood Nozzle to Shell 180" - 3RPV-WR54A (D03.090.008A)

Core Flood Nozzle Safe End @ 0' - 3RPV-WR53 (B05.010.OO1A, B05.010.OOIB)

Core Flood Nozzle Safe End @ 180" - 3RPV-VR53A (B05.010.002A, B05.010.002B)

OCONEE 3 BOC03 WesDyrne International Co.-e Ftood Nozzte to Shelt I SoF. Lrmd Veldg EXAMINATION PROGRAM PLAN 2004 AMMAM ISHEET 19 OF 22 47 of 52

Reclassified as Westinghouse Non-Proprietary Class 3 on 817106 Westinghouse Proprietary Class 2C

/ 84.0R to Ctld

.19

.19l 12-00 Lin CP CC a o I

,4 ,4 u4 60.0 Ref.

to Top of Vessel U

Core Flood Nozzle Safe End 10 i 3RPV-WR53 (B05.010.OO1A, B05.010.001B) 180" - 3RPV-WR53A (B05.010,002A, B05.010.002B)

Core Flood Nozzle Saofe End Core Flood Nozzle Safe End 0" (OD Alternative) - 3RPV-WR53 (B05.010,001)

Core Flood Nozzle SaFe End 180" (OD Alternative) - 3RPV-VR53A (B05010,002)

Scaxn Increment: AxiaI Scans = 0.125" (1.17°) OICONEE 3 BOC03 Circ Scoans = 0.080' W/esDlyne Internationtia

'mCor*flod We. End V,, ds Srig I. CD Atrra,6ve EXAMINATION PROGRAM PLAN 2004 if,,*Om = SHEET I 20 OF 22 48 of 52

Reclassified as Westinghouse Non-Proprietary Class 3 on 8/7/06 Westinghouse Proprietary Class 2C 12.00 -.- 84.OR to CMaXd 26.79, Star Scan Max i'

21.0 4- 15.00 Tan Scan Max R6.00 9.00 Tan Scan Min 7.56 Star Scan Max 3.00 166 7

Inner Ro*dEnhanced Visual Eaon Surface for Core Flood Nozzles Core Ftood Nozzle to She(( 0" Inner Radius VT-- 3RPV-WR54 (B03.100007)

Core Flood Nozzle to Shell 180" Inner Radius VT- 3RPV-WR54A (B03,100.008)

Core Flood Nozzle to Shell O" - 3RPV-WR54 (B03.090.007)

Core Flood Nozzle to Shell 2 180" - 3RPV-WR54A (B03.090.008)

OCONEE 3 BOC03 Scan Increment- Star Scans = 2.29' (0.50' @ Nozzle to Shelk Weld V/esDy ne Internationat STan Scans 0'50" =4 Core rlood Nozzle to Shell TAN. Star IR Exams EXAMINATION PROGRAM PLAN 2004 I-- 49 of 52 umm M W ISHEET 21 OF 22

ATThak mt4t E Pa~~-z&+

START OF CORE SUPPORT LEDGE TAPER @ Z = 27'

I1A a I7 IIs

.0167500 AS CLAD (R83.75) friTPvChr~v~,jY ~

-~ ii

.CORE FLOOD NOZZLE U

I-I 11 I to 10 I U

" I a I 7 I