9 Duke
- ffnergy Oconee Digital RPS/ESPS Upgrade Project EPRI/NEI Workshop March 28-29, 2006 Bob Gill VDunkerg 0Eergy Topics
- 44 Defense in Depth & Diversity Assessment License Amendment Request Going Forward Lessons Learned 2
March 28, 2006 Oconee Digital RPSIES Project I
Dnuke Defense in Depth &
nergy Diversity Assessment
- - NRC BTP - 19, applies
- - Duke/Oconee initial submittal made 03/20/2003 Meetings, RAls and Responses followed
- Oconee committed to add diverse LPI actuation system in lieu of crediting LBB o:o Initial approval requested by 10/2004
- Subsequent staff reviews occurred in 2005 o Human Factor RAIs issued and answered in Fall 2005
- o NRC SER March 28,2006 Oconee Digital RPS/ES Project 3
hD,,ke License Amendment WiEEnergy Request
- - Duke/NRC pre-submittal meetings during 2002,2003 and 2004
- Submittal of LAR 02/14/2005 - based on NRC approved TXS Topical and its Safety Evaluation Report
- Approval initially requested in early 2006
- Initial staff draft RAIs provided 03/31/2005
- - RAIs requested:
>Design and installation documents not yet developed
> Clarification of design aspects
> Background information to aid understanding
2
" Duke License Amendment drEnergy Request
- . Oconee began providing formal submittals in response to RAIs in October 2005 o:o Formal submittals have continued monthly through February 2006
- o NRC conducted a site-visit at FANP Alpharetta offices in November 2005
- - Several issues of concern have been identified and Oconee/FANP have provided responses to each of the issues
- Information provided has been both proprietary and non-proprietary
°:° Frequent communications have occurred with NRC staff and Management March 28, 2006 Oconee Digital RPS/ES Project 1rDuke
ýnergy Going Forward Wfergy
- Installation of first system has been postponed from Unit I in 2006 to Unit 3 in 2007
- . Equipment Qualification and Factory Acceptance Testing will be completed by July 1,2006
- - Certain plant calculations and operational procedures are in the process of being developed and will be completed later in 2006 and in 2007 prior to installation
- Licensing process will continue in order to resolve staff concerns in a timely manner
- . NRC SER expected prior to the Unit 3 installation March 28,2006 Oconee Digital RPS/ES Project 6
3
- Eguke "EP D e
Lessons Learned e rgy
- .:- Findings
- - Regulatory standards
- . Submit high quality, accurate, and timely documents
- o Milestone schedule
-:.-Communications
- - Vendor Topical Reports
- - Bench strength March 28, 2006 Oconee Digital RPS/ES Project 7