Letter Sequence Other |
---|
|
|
MONTHYEARML0527600472005-09-23023 September 2005 Tech Spec Page for Amendments 120 and 120 Containment Spray System Surveillance Requirements for Spray Nozzles Project stage: Other ML0525104872005-09-23023 September 2005 License Amendments 120 and 120 Containment Spray System Surveillance Requirements for Spray Nozzles Project stage: Other ML0527905092005-10-14014 October 2005 Correction of Amendments Containment Spray System Surveillance Requirements for Spray Nozzles Project stage: Other 2005-10-14
[Table View] |
|
---|
Category:Letter
MONTHYEARCP-202400030, License Renewal Application Revision 0 - Supplement 3, Revision 12024-01-31031 January 2024 License Renewal Application Revision 0 - Supplement 3, Revision 1 IR 05000445/20230042024-01-29029 January 2024 Integrated Inspection Report 05000445/2023004 and 05000446/2023004 CP-202400034, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1)2024-01-29029 January 2024 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1) ML24024A2102024-01-29029 January 2024 Summary of Regulatory Audit Regarding a License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML24025A0052024-01-25025 January 2024 Review of the Spring 2023 Steam Generator Tube Inspection Report ML24023A0242024-01-24024 January 2024 Correction to Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident Methodology ML24018A1072024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000445/2024012 and 05000446/2024012) and Request for Information ML23159A2082023-12-20020 December 2023 Request for Withholding Information from Public Disclosure ML23319A3872023-12-20020 December 2023 Issuance of Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident (Fsloca) Methodology ML23348A2392023-12-19019 December 2023 Nonacceptance of License Amendment Request to Relocate Technical Specification 3.9.3, Nuclear Instrumentation, to the Technical Requirements Manual CP-202300575, (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 22023-12-13013 December 2023 (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 2 ML23333A0872023-12-13013 December 2023 Transmittal of Dam Safety Inspection Report - Public CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300494, License Renewal Application Revision 0, Supplement 32023-12-0606 December 2023 License Renewal Application Revision 0, Supplement 3 ML23313A0732023-12-0606 December 2023 Issuance of Amendment Nos. 184 and 184 Regarding Revision to Technical Specifications to Implement WCAP-17661-P-A, Rev. 1, Improved Roac and CAOC Fq Surveillance Technical Specifications ML23291A4382023-11-30030 November 2023 Notice of Availability of the Draft Plant-Specific Supplement 60, to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Comanche Peak Nuclear Power Plant, Unit Numbers 1 and 2, License Renewal Applica ML23325A0182023-11-30030 November 2023 Schedule Revision for the License Renewal Application Review IR 05000445/20234022023-11-30030 November 2023 NRC Security Inspection Report 05000445/2023402 and 05000446/2023402 CP-202300349, License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation2023-11-20020 November 2023 License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation ML23308A0032023-11-17017 November 2023 Letter to R. Nelson, Executive Director; Achp; Re., Comanche Peak Draft Environmental Impact Statement ML23308A0022023-11-17017 November 2023 Letter to M. Wolfe, Executive Director; Shpo; Re., Comanche Peak Draft Environmental Impact Statement ML23317A3002023-11-13013 November 2023 Letter to R. Sylestine, Chairman, Alabama-Coushatta Tribe of Texas Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2972023-11-13013 November 2023 Letter to R. Martin, President, Tonkawa Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2872023-11-13013 November 2023 Letter to J. Garza, Chairman, Kickapoo Traditional Tribe of Texas Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2832023-11-13013 November 2023 Letter to D. Dotson, President, Delaware Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2852023-11-13013 November 2023 Letter to E. Martinez, President, Mescalero Apache Tribe Regarding Comanche Peak Draft Environmental Impact Statement ML23306A0302023-11-13013 November 2023 Letter to J. Cernek, Chairman; Coushatta Tribe of Louisiana Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2902023-11-13013 November 2023 Letter to M. Pierite, Chairman, Tunica Biloxi Tribe of Louisiana Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2982023-11-13013 November 2023 Letter to R. Morrow, Town King, Thlopthlocco Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2842023-11-13013 November 2023 Letter to D. Kaskaske, Chairman, Kickapoo Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2822023-11-13013 November 2023 Letter to D. Cooper, Chairman, Apache Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2962023-11-13013 November 2023 Letter to M. Woommavovah, Chairman, Comanche Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2812023-11-13013 November 2023 Letter to C. Hoskin, Principal Chief, Cherokee Nation; Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2862023-11-13013 November 2023 Letter to J. Bunch, Chief, United Keetoowah Band of Cherokee Indians Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3032023-11-13013 November 2023 Letter to W. Yargee, Chief, Alabama-Quassarte Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2882023-11-13013 November 2023 Letter to L. Johnson, Chief, Seminole Nation of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3012023-11-13013 November 2023 Letter to S. Yahola, Mekko, Kialegee Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2792023-11-13013 November 2023 Letter to B. Gonzalez, Chairman, Caddo Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3022023-11-13013 November 2023 Letter to T. Parton, President, Wichita and Affiliated Tribes Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2892023-11-13013 November 2023 Letter to L. Spottedbird, Chairman, Kiowa Indian Tribe Regarding Comanche Peak Draft Environmental Impact Statement ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23360A6312023-10-26026 October 2023 FEMA, Submittal of Radiological Emergency Preparedness Final Report for the Comanche Peak Nuclear Power Plant Medical Services Drill Evaluated on August 23, 2023 CP-202300416, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-10-12012 October 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300432, Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 42023-10-0404 October 2023 Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 4 ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23263A0242023-09-21021 September 2023 Revision of Schedule for the Environmental Review of the Comanche Peak Nuclear Power Plant Units 1 and 2 License Renewal Application 2024-01-31
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML23319A3872023-12-20020 December 2023 Issuance of Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident (Fsloca) Methodology ML23348A2392023-12-19019 December 2023 Nonacceptance of License Amendment Request to Relocate Technical Specification 3.9.3, Nuclear Instrumentation, to the Technical Requirements Manual ML23313A0732023-12-0606 December 2023 Issuance of Amendment Nos. 184 and 184 Regarding Revision to Technical Specifications to Implement WCAP-17661-P-A, Rev. 1, Improved Roac and CAOC Fq Surveillance Technical Specifications ML23237B4412023-09-29029 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Federal Register Notice, Direct and Indirect License Transfer Issuance Order ML23237B4302023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0000) (Public) ML23237B4282023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 2, Draft Conforming License Amendments ML23136B2962023-05-31031 May 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request Regarding General Design Criteria 5 and Regulatory Guide 1.81 ML22329A0332022-11-29029 November 2022 Notification of NRC Initial Operator Licensing Examination 05000445/2023301 and 05000446/2023301 ML22208A1582022-07-29029 July 2022 Correction to Issuance of Amendment Nos. 156 and 156 Relocation of Surveillance Frequencies from the Technical Specifications to a Licensee-Controlled Document ML21321A3492022-02-24024 February 2022 Issuance of Amendment Nos. 182 and 182 to Revise Technical Specifications to Adopt TSTF-577, Rev. 1, Revised Frequencies for Steam Generator Tube Inspections ML21132A0892021-06-0909 June 2021 Issuance of Amendment Nos. 181 and 181 Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-567, Rev. 1, Add Containment Sump TS to Address GSI - 191 Issues ML21061A2172021-05-19019 May 2021 Issuance of Amendment Nos. 180 and 180 to Authorize Revision of Certain Emergency Action Levels of the Emergency Plan ML21103A0392021-04-23023 April 2021 Issuance of Amendment Nos. 179 and 179 the Adoption of Technical Specifications Task Force Traveler, TSTF-569, Revision 2, Revise Response Time Testing Definition (EPID L-2020-0147) ML21015A2122021-02-12012 February 2021 Issuance of Amendment Nos. 178 and 178 Regarding One-Time Revision to Technical Specifications 3.7.8 Station Service Water System (Ssws) and 3.8.1 AC Sources - Operating ML20346A0192021-02-0101 February 2021 Issuance of Amendment Nos. 177 and 177 Regarding Revision to Technical Specifications 3.8.1, AC Sources - Operating ML20168A9242020-11-16016 November 2020 Issuance of Amendment Nos. 176 and 176 Regarding Revision to Technical Specification 3.4.15, RCS Leakage Detection Instrumentation ML20223A3492020-08-31031 August 2020 Issuance of Amendment Nos. 175 and 175 Regarding One-Time Revision to Technical Specification 3.7.19, Safety Chilled Water ML20167A3182020-07-0606 July 2020 Issuance of Amendment Nos. 174 and 174 Regarding Revision to Technical Specifications to Adopt TSTF-563, Revision 0 ML20108E8782020-04-17017 April 2020 Issuance of Amendment Nos. 173 and 173 Revision to TS 5.5.9, Unit 1 Model D76 and Unit 2 Model D5 Steam Generator (SG) Program (Exigent Circumstances) ML19267A0182019-11-0404 November 2019 Issuance of Amendment Nos. 172 and 172 to Revise Augmentation Times and Emergency Response Organization Staffing for the Emergency Plan ML18304A4872018-11-30030 November 2018 Issuance of Amendments 171 and 171 Regarding Revision to Technical Specifications for Engineered Safety Feature Actuation System Instrumentation ML18267A3842018-10-25025 October 2018 Issuance of Amendment Nos. 170 and 170 Revision to Technical Specification 3.8.4, DC Sources - Operating, Condition B (Exigent Circumstances) ML17129A0242017-06-29029 June 2017 Comanche Peak Nuclear Power Plant, Units 1 and 2 - Issuance of Amendment Nos. 169 and 169 Re: Administrative Change to Licensee Name (CAC Nos. MF8933 and MF8934) ML16266A0052016-10-0303 October 2016 ISFSI - Issuance of Amendment Nos. 167 and 167 Related to Order Approving Direct and Indirect Transfer of Licenses and Conforming License Amendments ML16168A0022016-06-24024 June 2016 Correction of Implementation Date, Issuance of Amendment Nos. 166 and 166, Request to Revise Emergency Action Levels Based on Nuclear Energy Institute (NEI) 99-01, Revision 6 ML16137A0562016-06-14014 June 2016 Issuance of Amendment Nos. 166 and 166, Request to Revise Emergency Action Levels Based on Nuclear Energy Institute (NEI) 99-01, Revision 6 ML16096A2662016-05-0606 May 2016 Redacted Letter, Order, Safety Evaluation, and Draft Conforming Amendments, Application for Order Approving Direct and Indirect Transfer of Licenses and Conforming License Amendments ML16096A2642016-05-0606 May 2016 Draft Conforming Amendments, Application for Order Approving Direct and Indirect Transfer of Licenses and Conforming License Amendments ML15309A0732015-12-30030 December 2015 Issuance of Amendment Nos. 165 and 165, Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, to Increase ILRT Test Interval from 10 to 15 Years and Type C Tests from 60 to 75 Mos ML15008A1332015-02-24024 February 2015 Issuance of Amendment Nos. 164 and 164, Revise Technical Specification 3.8.1 for a 14-Day Completion Time for Offsite Circuits ML14183A3422014-09-0808 September 2014 Issuance of Amendment Nos. 163 and 163 to Revise License Condition Related to Approval of Revised Cyber Security Plan Implementation Schedule ML14160A0352014-07-0101 July 2014 Redacted, Issuance of Amendment No. 162, Revise TS 3.7.16, Fuel Storage Pool Boron Concentration, TS 3.7.17, Spent Fuel Assembly Storage, and TS 5.5, Programs and Manuals ML14042A2232014-02-27027 February 2014 Issuance of Amendment Nos. 161 and 161, Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection, Consolidated Line Item Improvement Process (TAC MF2651-MF2652) ML13232A1432013-09-18018 September 2013 Issuance of Amendment Nos. 160 and 160, Revise Technical Specification 3.8.1, AC Sources - Operating, for Extension of Two 14-Day Completion Times for Offsite Circuits ML13156A2482013-07-11011 July 2013 Issuance of Amendment Nos. 159 and 159, Revise Technical Specification (TS) 5.7, High Rad Area, and TS Table 3.3.3-1, Post Accident Monitoring Instrumentation ML12263A0362012-10-18018 October 2012 Issuance of Amendment Nos. 158 and 158, Revise Technical Specification (TS) 5.5.9 and TS 5.6.9 for a Permanent Alternate Repair Criteria ML12067A2442012-06-29029 June 2012 Issuance of Amendment Nos. 156 and 156, Adoption of TSTF-425-A, Rev. 3, Relocate Surveillance Frequencies to Licensee Control - Risk Informed Technical Specifications Task Force (RITSTF) Initiative 5b ML12156A0682012-06-29029 June 2012 Issuance of Amendment Nos. 157 and 157, Adoption of TSTF-491, Revision 2, Removal of Main Steam and Main Feedwater Valve Isolation Times from Technical Specifications ML1117807452011-07-26026 July 2011 Issuance of Amendment Nos. 155 and 155, Revise License Condition and Approve Cyber Security Plan and Associated Implementation Schedule ML1107703222011-04-0606 April 2011 Issuance of Amendment Nos. 154 and 154, Revise Technical Specifications for U2 Model D5 SG Tube Inspections and Reporting Requirements for Temporary Alternate Repair Criteria ML1000705672010-04-26026 April 2010 Issuance of Amendment Nos. 151 and 151, Revise Technical Specification 3.3.1, Reactor Trip System (RTS) Instrumentation, to Add Surveillance Requirement 3.3.1.16 to Function 3 of Table 3.3.1-1 ML0927400762009-10-0909 October 2009 Issuance of Amendment Nos. 149 and 149, Modify Technical Specifications to Establish Alternate Repair Criteria (ARC) and Include Reporting Requirements Specific to ARC for Steam Generator Program ML0917506632009-08-0707 August 2009 Issuance of Amendment Nos. 148 and 148, Modify Technical Specifications to Adopt TSTF-511, Eliminate Working Hour Restrictions from TS 5.2.2 to Support Compliance with 10 CFR Part 26 ML0818400012008-09-12012 September 2008 Issuance of Amendment Nos. 147 and 147, Revise Technical Specification 3.6.7, Spray Additive System to Comply with GL-2004-02 ML0815101732008-06-27027 June 2008 Issuance of Amendment Nos. 146 and 146, Stretch Power Uprate, Revision to TS 1.0, Use and Application, to Revise Rated Thermal Power from 3458 to 3612 Mwt ML0805800042008-04-0303 April 2008 Issuance of Amendment Nos. 145 and 145 Revise TSs 3.1.4, 3.4.10, and 3.7.1 to Reflect Cycle-Specific Safety Analysis Assumptions Re Adoption of Westinghouse Methodologies ML0805006272008-04-0202 April 2008 Issuance of Amendment Nos. 144 & 144, Changes to Technical Specifications to Allow Use of Westinghouse-developed/NRC-approved Analytical Methods Used to Establish Core Operating Limits ML0802201072008-02-29029 February 2008 Issuance of Amendment Nos. 143 and 143, Technical Requirements Surveillance 13.3.33.2 ML0734000372008-01-25025 January 2008 Issuance of Amendment Nos. 142 & 142, Revision to Technical Specifications 3.7.5, 3.8.1 and 3.8.9 and TS Example 1.3-3 ML0731202522007-12-13013 December 2007 Issuance of Amendment Nos. 141 and 141 Revise TS 5.5.16, Containment Leakage Rate Testing Program for Consistency W/Requirements of 10 CFR 50.55a(g)(4) 2023-09-29
[Table view] Category:Safety Evaluation
MONTHYEARML23319A3872023-12-20020 December 2023 Issuance of Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident (Fsloca) Methodology ML23313A0732023-12-0606 December 2023 Issuance of Amendment Nos. 184 and 184 Regarding Revision to Technical Specifications to Implement WCAP-17661-P-A, Rev. 1, Improved Roac and CAOC Fq Surveillance Technical Specifications ML23237B4282023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 2, Draft Conforming License Amendments ML23237B4302023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0000) (Public) ML23198A3212023-07-27027 July 2023 Authorization and Safety Evaluation for Proposed Alternative RV-1 ML22192A0072022-08-22022 August 2022 Issuance of Amendment Nos. 183 and 183 Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-505, Revision 2 ML22194A0592022-07-14014 July 2022 Correction to Amendment Nos. 182 and 182 to Revise Technical Specifications to Adopt TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML22129A0722022-05-16016 May 2022 Review of Quality Assurance Program Changes ML22077A8412022-03-24024 March 2022 Proposed Alternative SNB-3 for the Snubber Inservice Program Third Interval Extension ML21321A3492022-02-24024 February 2022 Issuance of Amendment Nos. 182 and 182 to Revise Technical Specifications to Adopt TSTF-577, Rev. 1, Revised Frequencies for Steam Generator Tube Inspections ML21322A1032021-12-0707 December 2021 Proposed Alternative for the Continued Use of a Risk-Informed Process for the Selection of Class 1 and 2 Piping Welds for Inservice Inspection ML21132A0892021-06-0909 June 2021 Issuance of Amendment Nos. 181 and 181 Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-567, Rev. 1, Add Containment Sump TS to Address GSI - 191 Issues ML21061A2172021-05-19019 May 2021 Issuance of Amendment Nos. 180 and 180 to Authorize Revision of Certain Emergency Action Levels of the Emergency Plan ML21103A0392021-04-23023 April 2021 Issuance of Amendment Nos. 179 and 179 the Adoption of Technical Specifications Task Force Traveler, TSTF-569, Revision 2, Revise Response Time Testing Definition (EPID L-2020-0147) ML21015A2122021-02-12012 February 2021 Issuance of Amendment Nos. 178 and 178 Regarding One-Time Revision to Technical Specifications 3.7.8 Station Service Water System (Ssws) and 3.8.1 AC Sources - Operating ML21022A1622021-02-0808 February 2021 Proposed Alternative to the Requirements of the ASME OM Code to Extend the Inservice Testing Program Interval for Certain Check and Relief Valves (EPID L-2020-LLR-0096 (COVID-19)) ML20346A0192021-02-0101 February 2021 Issuance of Amendment Nos. 177 and 177 Regarding Revision to Technical Specifications 3.8.1, AC Sources - Operating ML21021A1002021-02-0101 February 2021 Proposed Alternative to the Requirements of the ASME OM Code to Extend the Inservice Testing Program Interval for Certain Snubbers (EPID L-2020-LLR-0095 (Covid 19)) ML21013A1282021-01-28028 January 2021 Approval of Proposed Alternative to the Requirements of the ASME Code to Extend the Third Inservice Inspection Interval (EPID L-2020-LLR-0092 (COVID-19)) ML21021A0022021-01-28028 January 2021 Approval of Proposed Alternatives 1A4-1 and 1A4-2 from Certain Requirements of 10 CFR 50.55a for Inservice Inspection of Nuclear Power Plants ML20282A7092020-11-17017 November 2020 Proposed Alternative to the Requirements of the ASME Omcode to Extend the Inservice Testing Program Interval for Certain Snubbers (EPID L-2020-LLR-0060 (COVID-19)) ML20281A4722020-11-0404 November 2020 Use of Later Code Edition to the Requirements of the ASME OM Code ML20255A1002020-10-0707 October 2020 Proposed Alternative to the Requirements of the ASME OM Code to Extend the Inservice Test Program Interval for Certain Check and Relief Valves (EPID L-2020-LLR-0061 and EPID L-2020-LLR-0062 (COVID-19)) ML20223A3492020-08-31031 August 2020 Issuance of Amendment Nos. 175 and 175 Regarding One-Time Revision to Technical Specification 3.7.19, Safety Chilled Water ML20226A0132020-08-17017 August 2020 Use of Later Code Edition to the Requirements of the ASME Code ML20167A3182020-07-0606 July 2020 Issuance of Amendment Nos. 174 and 174 Regarding Revision to Technical Specifications to Adopt TSTF-563, Revision 0 ML20108E8782020-04-17017 April 2020 Issuance of Amendment Nos. 173 and 173 Revision to TS 5.5.9, Unit 1 Model D76 and Unit 2 Model D5 Steam Generator (SG) Program (Exigent Circumstances) ML20054A2762020-02-27027 February 2020 Approval of Change to the Quality Assurance Program as Described in the Comanche Peak Nuclear Power Plant Final Safety Analysis Report ML19267A0182019-11-0404 November 2019 Issuance of Amendment Nos. 172 and 172 to Revise Augmentation Times and Emergency Response Organization Staffing for the Emergency Plan ML18304A4872018-11-30030 November 2018 Issuance of Amendments 171 and 171 Regarding Revision to Technical Specifications for Engineered Safety Feature Actuation System Instrumentation ML18267A3842018-10-25025 October 2018 Issuance of Amendment Nos. 170 and 170 Revision to Technical Specification 3.8.4, DC Sources - Operating, Condition B (Exigent Circumstances) ML18221A6322018-08-15015 August 2018 Eicb Safety Evaluation - Comanche Peak Nuclear Power Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.3.2 Engineered Safety Feature Actuation System Instrumentation Docket/Epid 000976/05000446/L-2018-LLA-0 ML17129A0242017-06-29029 June 2017 Comanche Peak Nuclear Power Plant, Units 1 and 2 - Issuance of Amendment Nos. 169 and 169 Re: Administrative Change to Licensee Name (CAC Nos. MF8933 and MF8934) ML17074A4942017-04-13013 April 2017 Issuance of Amendment Nos. 168 and 168 Adoption of TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing ML17095A2512017-04-0707 April 2017 Request for Alternative 2B3-1 Re Examination of Reactor Vessel Closure Head Penetration Nozzles ML16334A1732016-12-14014 December 2016 Comanche Peak Nuclear Power Plant, Units 1 And 2; Safety Evaluation Regarding Implementation Of Mitigating Strategies And Reliable Spent Fuel Pool Instrumentation Related To Orders EA-12-049 And EA-12-051 ML16179A4052016-07-11011 July 2016 Relief Request Nos. B-9, B-3, B-10, and B-11 for Piping Welds, Second 10-year Inservice Inspection Interval ML16137A0562016-06-14014 June 2016 Issuance of Amendment Nos. 166 and 166, Request to Revise Emergency Action Levels Based on Nuclear Energy Institute (NEI) 99-01, Revision 6 ML16096A2662016-05-0606 May 2016 Redacted Letter, Order, Safety Evaluation, and Draft Conforming Amendments, Application for Order Approving Direct and Indirect Transfer of Licenses and Conforming License Amendments ML16096A2642016-05-0606 May 2016 Draft Conforming Amendments, Application for Order Approving Direct and Indirect Transfer of Licenses and Conforming License Amendments ML16074A0012016-03-14014 March 2016 Relief Request 1B3-3, Alternative for Reactor Pressure Vessel Cold Leg Weld Inspection Frequency from Not to Exceed 7 Years to 9 Years for the Third 10-Year Inservice Inspection Interval ML16063A0012016-03-11011 March 2016 Relief Request No. B-15, C-2, and C-4 for Welds in the RPV and Containment Spray and Residual Heat Removal Heat Exchanger Shells, Second 10-year Inservice Inspection Interval ML16011A0732016-01-19019 January 2016 Relief Request T-1; Alternative to the ASME OM Code Frequency Specifications for Inservice Testing for the Third 10-Year IST Interval ML15309A0732015-12-30030 December 2015 Issuance of Amendment Nos. 165 and 165, Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, to Increase ILRT Test Interval from 10 to 15 Years and Type C Tests from 60 to 75 Mos ML15259A0042015-10-30030 October 2015 Relief Request 1B3-4, Alternative for Reactor Pressure Vessel Head Penetration Weld Inspection Frequency (from 10 to 15 Years), Third 10-Year Inservice Inspection Interval ML15257A2422015-09-18018 September 2015 Relief Request 2A3-1, from ASME Code Section XI Requirements, Risk-Informed Process for Selection of Class 1 and Class 2 Piping Weld Examinations, Third 10-Year Inservice Inspection Interval ML15257A2402015-09-15015 September 2015 Relief Request 2C3-1, from ASME Code, Section XI Requirements Reactor Pressure Vessel Leak-Off Flange for the Third 10-Year Inservice Inspection Interval ML15090A1042015-04-0303 April 2015 Relief Requests B-7, B-12, and B-13 - Steam Generator Head-to-Tube Sheet Welds for the Second 10-Year Inservice Inspection Interval ML15008A1332015-02-24024 February 2015 Issuance of Amendment Nos. 164 and 164, Revise Technical Specification 3.8.1 for a 14-Day Completion Time for Offsite Circuits ML14183A3422014-09-0808 September 2014 Issuance of Amendment Nos. 163 and 163 to Revise License Condition Related to Approval of Revised Cyber Security Plan Implementation Schedule 2023-09-28
[Table view] |
Text
September 23, 2005 Mr. M. R. Blevins Senior Vice President
& Chief Nuclear Officer TXU Power ATTN: Regulatory Affairs P. O. Box 1002 Glen Rose, TX 76043
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES), UNITS 1 AND 2 -
ISSUANCE OF AMENDMENTS RE: CONTAINMENT SPRAY SYSTEM SURVEILLANCE REQUIREMENTS FOR SPRAY NOZZLES. (TAC NOS.
MC4314 AND MC4315)
Dear Mr. Blevins:
The Commission has issued the enclosed Amendment No. 120 to Facility Operating License No. NPF-87 and Amendment No. 120 to Facility Operating License No. NPF-89 for CPSES, Units 1 and 2, respectively. The amendments consist of changes to the Technical Specifications in response to your application dated September 9, 2004.
The amendments revise the current interval for surveillance requirement SR 3.6.6.8, from the current requirement of verification every 10 years, to require verification that the spray nozzles are unobstructed following a maintenance that could result in a nozzle blockage.
A copy of our related Safety Evaluation is enclosed. The Notice of Issuance will be included in the Commission's next biweekly Federal Register notice.
Sincerely,
/RA/
Mohan C. Thadani, Senior Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446
Enclosures:
- 1. Amendment No. 120 to NPF-87
- 2. Amendment No. 120 to NPF-89
- 3. Safety Evaluation cc w/encls: See next page
September 23, 2005 Mr. M. R. Blevins Senior Vice President & Chief Nuclear Officer TXU Power ATTN: Regulatory Affairs P. O. Box 1002 Glen Rose, TX 76043
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES), UNITS 1 AND 2 -
ISSUANCE OF AMENDMENTS RE: CONTAINMENT SPRAY SYSTEM SURVEILLANCE REQUIREMENTS FOR SPRAY NOZZLES. (TAC NOS.
MC4314 AND MC4315)
Dear Mr. Blevins:
The Commission has issued the enclosed Amendment No. 120 to Facility Operating License No. NPF-87 and Amendment No. 120 to Facility Operating License No. NPF-89 for CPSES, Units 1 and 2, respectively. The amendments consist of changes to the Technical Specifications in response to your application dated September 9, 2004.
The amendments revise the current interval for surveillance requirement SR 3.6.6.8, from the current requirement of verification every 10 years, to require verification that the spray nozzles are unobstructed following a maintenance that could result in a nozzle blockage.
A copy of our related Safety Evaluation is enclosed. The Notice of Issuance will be included in the Commission's next biweekly Federal Register notice.
Sincerely, /RA/
Mohan C. Thadani, Senior Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446
Enclosures:
- 1. Amendment No. 120 to NPF-87
- 2. Amendment No. 120 to NPF-89
- 3. Safety Evaluation cc w/encls: See next page DISTRIBUTION:
PUBLIC RidsOgcRp PDIV-1 Reading RidsAcrsAcnwMailCenter RidsNrrDlpmLpdiv (HBerkow) GHill(4)
RidsNrrDlpmLpdiv1 (DTerao) RidsNrrDipmIrob (TBoyce)
RidsNrrPMMThadani RGoel RidsNrrLADBaxley RidsRgn4MailCenter RidsNrrDlpmDpr Accession No.:ML052510487 OFFICE PDIV-1/PM PDIV-1/LA OGC PDIV-1/SC NAME MThadani DBaxley MSpencer(NLO) DTerao DATE 9/19/05 9/22/05 9/21/05 9/22/05
TXU GENERATION COMPANY LP COMANCHE PEAK STEAM ELECTRIC STATION, UNIT NO. 1 DOCKET NO. 50-445 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 120 License No. NPF-87
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by TXU Generation Company LP dated September 9, 2004, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, as amended, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this license amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
- 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment; and paragraph 2.C.(2) of Facility Operating License No. NPF-87 is hereby amended to read as follows:
(2) Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment No. 120, and the Environmental Protection Plan contained in Appendix B, are hereby incorporated into this license. TXU Generation Company LP shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3. The license amendment is effective as of its date of issuance and shall be implemented within 60 days from the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
David Terao, Chief, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications Date of Issuance: September 23, 2005
TXU GENERATION COMPANY LP COMANCHE PEAK STEAM ELECTRIC STATION, UNIT NO. 2 DOCKET NO. 50-446 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No.120 License No. NPF-89
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by TXU Generation Company LP dated September 9, 2004, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, as amended, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this license amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
- 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment; and paragraph 2.C.(2) of Facility Operating License No. NPF-89 is hereby amended to read as follows:
(2) Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment No. 120, and the Environmental Protection Plan contained in Appendix B, are hereby incorporated into this license. TXU Generation Company LP shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3. This license amendment is effective as of its date of issuance and shall be implemented within 60 days from the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
David Terao, Chief, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications Date of Issuance: September 23, 2005
ATTACHMENT TO LICENSE AMENDMENT NO. 120 TO FACILITY OPERATING LICENSE NO. NPF-87 AND AMENDMENT NO. 120 TO FACILITY OPERATING LICENSE NO. NPF-89 DOCKET NOS. 50-445 AND 50-446 Replace the following page of the Appendix A Technical Specifications with the attached revised page. The revised page is identified by amendment number and contains marginal lines indicating the areas of change.
Remove Insert 3.6-19 3.6-19
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 120 TO FACILITY OPERATING LICENSE NO. NPF-87 AND AMENDMENT NO. 120 TO FACILITY OPERATING LICENSE NO. NPF-89 TXU GENERATION COMPANY LP COMANCHE PEAK STEAM ELECTRIC STATION, UNITS 1 AND 2 DOCKET NOS. 50-445 AND 50-446
1.0 INTRODUCTION
By letter dated September 9, 2004 (Agency Documents Access and Management System Accession No. ML042640018), TXU Generation Company LP (the licensee) requested a revision to the Technical Specifications (TS) for the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2. The requested revision will revise the testing frequency for the containment spray nozzles, as specified in TS Surveillance Requirement 3.6.6.8, from a current requirement, once per 10 years, to a new requirement, following maintenance that could result in nozzle blockage.
2.0 REGULATORY EVALUATION
The containment spray system is designed for conformance with provisions of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix A, General Design Criterion (GDC) 38, Containment heat removal; GDC 39, Inspection of containment heat removal system; and GDC 40, Testing of containment heat removal system. In particular, GDC 40 specifies that the containment heat removal system shall be designed for appropriate periodic pressure and functional testing to assure operability of the system. The proposed revision of the surveillance requirements does not impact conformance with the provisions of these GDCs.
The licensee cited precedent for similar license amendments issued for the South Texas, Perry, North Anna, Calvert Cliffs, Beaver Valley, Braidwood, H. B. Robinson, Palisades, Salem, and Surry plants.
3.0 TECHNICAL EVALUATION
3.1 Introduction The containment spray system consists of two independent trains. Four containment spray pumps are provided for each unit (two per train). These pumps are designed to provide
sufficient flow into containment during accident conditions to both cool the containment atmosphere to maintain pressure within design limits and to remove radioactive iodine. Each train is capable of providing 100 percent of the required water and sodium hydroxide flow to the spray headers that are mounted throughout the containment. Also, each train is capable of providing 100 percent of the required containment sprayed volume coverage.
The two trains of sprays are each divided into four regions in the containment and distributed to different elevations. All nozzles in the four regions are pointed at various angles and directions to ensure containment coverage assuming a single active failure. The spray nozzles are hollow-cone, with a 3/8-inch diameter orifice, and are fabricated of stainless steel. The 3/8-inch nozzle discharge orifice is sufficiently large to preclude clogging by particles that pass through the 0.115-inch mesh of the fine containment sump screens.
The containment spray system nozzles for both units were initially tested at five-year intervals.
The surveillance interval is currently 10 years as approved in License Amendment 64 dated February 26, 1999. Airflow tests were conducted as part of pre-operational testing and for the first five-year interval. The results of each test demonstrated unobstructed flow through each nozzle. These tests confirmed that the nozzles are free from construction debris, and also from obstructions that could have occurred following startup and operations of the units.
The two potential modes of a blockage are by corrosion products and by debris (foreign material) blockage. The evaluation below addresses these blockage modes.
3.2 Testing Experience NUREG-1366, Improvements to Technical Specifications Surveillance Requirements, (May 1992) reported on a U.S. Nuclear Regulatory Commission staff review of industry experience which indicated that containment spray systems of similar design are highly reliable and not subject to plugging after testing following construction. The staff reviewed industry experience and found that, in general, once tested after construction, containment spray systems have not been subject to a blockage. The problems discovered were related to a blockage during construction, and not the result of subsequent normal operation.
The licensee indicated that the containment spray system nozzles for both CPSES units have been tested satisfactorily twice during normal operation after the completion of construction, demonstrating that the construction problems identified in NUREG-1366 do not exist at CPSES.
The containment spray system piping and nozzles are stainless steel, and are not coated and therefore not subject to clogging due to coating material. Cleanliness control and foreign material exclusion practices, including post-work inspections, have ensured that system cleanliness requirements are continuing to be met.
3.3 Materials and Corrosion The containment spray system header and nozzles are passive devices that are not normally exposed to fluids or debris. The system piping and nozzles are fabricated of stainless steel, which is highly resistant to corrosion. Conditions for stainless steel corrosion, i.e., stress,
temperature, and chlorides, are not present. Therefore, the nozzles are unlikely to become obstructed due to corrosion.
3.4 Foreign Materials Exclusion (FME)
The licensee indicated that at CPSES, the FME program is implemented by procedure STA-625, Foreign Material Exclusion. This procedure describes the measures to be taken to ensure foreign material is not introduced into a component or system, and measures to be taken if material or tool accountability is lost. The procedure requires that when closing a system or component, an inspection is to be performed to ensure that all foreign material is removed. This requirement applies to all work and inspection activities performed on safety related systems and components. If the required FME is not maintained, a condition report is initiated requiring assessment of the circumstances and implementation of appropriate corrective actions to ensure that the spray system continues to be operable and to prevent recurrence.
The proposed SR change is supported by the existing requirement to verify system operability after system maintenance or repair. The foreign material introduced as a result of maintenance is the most likely cause of obstruction. Therefore, verification to confirm the nozzles are free of blockage following maintenance activities that could result in nozzle blockage, as in the proposed SR, is sufficient to confirm the nozzles are free of a blocking substance. The current post-maintenance testing procedure provides this verification, which requires testing of the system and components following maintenance activities as necessary to demonstrate operability. Consequently, the potential for unidentified nozzle obstruction or introduction of foreign material following maintenance is low. Also, due to the location and orientation of the spray headers and nozzles, introduction of foreign materials into the system through the nozzles is unlikely.
As a result of reviewing the licensees request to revise the testing frequency for the containment spray nozzles from once per 10 years to following maintenance that could result in nozzle blockage, and reviewing and assessing the information provided by the licensee, the NRC staff concludes that the design of the CPSES containment spray system, and the foreign materials controls instituted by the licensee, provide a reasonable assurance that the potential for nozzle obstruction is acceptably low. The foreign material controls provide protection from introduction of foreign materials into open piping during maintenance, and require post-maintenance verification of system cleanliness and freedom from a blockage. Therefore, the staff finds the proposed changes to be acceptable.
4.0 STATE CONSULTATION
In accordance with the Commission's regulations, the Texas State official was notified of the proposed issuance of the amendment. The State official had no comments.
5.0 ENVIRONMENTAL CONSIDERATION
The amendments change a requirement with respect to installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20. The NRC staff has determined that the amendments involve no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is
no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendments involve no significant hazards consideration, and there has been no public comment on such a finding published October 26, 2004 (69 FR 62478). Accordingly, the amendments meet the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(b) no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendments.
6.0 CONCLUSION
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendments will not be inimical to the common defense and security or to the health and safety of the public.
Principal Contributor: R. Goel Date: September 23, 2005
Comanche Peak Steam Electric Station cc:
Senior Resident Inspector Mr. Brian Almon U.S. Nuclear Regulatory Commission Public Utility Commission P. O. Box 2159 William B. Travis Building Glen Rose, TX 76403-2159 P. O. Box 13326 1701 North Congress Avenue Regional Administrator, Region IV Austin, TX 78701-3326 U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Ms. Susan M. Jablonski Arlington, TX 76011 Office of Permitting, Remediation and Registration Mr. Fred W. Madden, Director Texas Commission on Environmental Regulatory Affairs Quality TXU Generation Company LP MC-122 P. O. Box 1002 P. O. Box 13087 Glen Rose, TX 76043 Austin, TX 78711-3087 George L. Edgar, Esq. Terry Parks, Chief Inspector Morgan Lewis Texas Department of Licensing 1111 Pennsylvania Avenue, NW and Regulation Washington, DC 20004 Boiler Program P. O. Box 12157 County Judge Austin, TX 78711 P. O. Box 851 Glen Rose, TX 76043 Environmental and Natural Resources Policy Director Office of the Governor P. O. Box 12428 Austin, TX 78711-3189 Mr. Richard A. Ratliff, Chief Bureau of Radiation Control Texas Department of Health 1100 West 49th Street Austin, TX 78756-3189 December 2004