Notice of Meeting with Exelon Generation Company, SlidesML051370424 |
Person / Time |
---|
Site: |
Limerick |
---|
Issue date: |
04/14/2005 |
---|
From: |
NRC Region 1 |
---|
To: |
|
---|
References |
---|
Download: ML051370424 (24) |
|
|
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML24137A1882024-05-16016 May 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML24100A7672024-04-11011 April 2024 Meeting Slides - Preapplication with Constellation on Planned Fleet Alternative Request to Adopt OMN-2 ML24089A2612024-04-0909 April 2024 Slides - Constellation - Pre-Application Regarding Hooded Masks 4/9/2024 Meeting Slides (L-2024-LLM-0041) ML24029A1742024-01-30030 January 2024 Constellation Pre-Application January 30, 2024, Meeting Slides - Proposed Alternative to Utilize Code Case N-932, Alternative Requirements for Acceptance of Containment Base Metal Corrosion or Erosion ML23317A0712023-11-14014 November 2023 NRC Pre-Submittal Meeting on November 14th, 2023 - TSTF-591 and Selected 50.69 License Condition Updates (EPID L-2023-LLM-0098) (Slides) ML23255A1042023-08-11011 August 2023 Slides - Constellation - Pre-Application EP 9/18/2023 Draft CEG Presubmittal SG Performance Monitoring Plan Meeting Handout ML23157A0352023-06-0606 June 2023 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML23053A1562023-02-23023 February 2023 NRC Presentation Slides for Public Meeting on February 23, 2023 - 10 CFR 50.69 Alternate Processes License Amendment Request Preliminary Partial Denial ML23076A2812023-02-23023 February 2023 Licensee Presentation on Pressure Boundary Process ML23076A2822023-02-23023 February 2023 Licensee Presentation on Defense-in-Depth Process ML23006A2572023-01-10010 January 2023 Digital Modernization Project Installation Support License Amendment Request and Exemption Request Presentation - January 10, 2023 (EPID L-2022-LRM-0099) (Slides) ML22347A1532022-12-13013 December 2022 Public Meeting Presentation, December 15, 2022 Di&C License Amendment Request ML22319A0012022-11-14014 November 2022 Constellation Energy Generation, Llc'S Presentation for November 10, 2022 Public Meeting with NRC ML22312A4402022-11-10010 November 2022 Public Meeting with Constellation About Acceptance Review: Status of NRC Staff'S Acceptance Review of the Limerick Digital Instrumentation and Controls License Amendment Request ML22249A0972022-09-0808 September 2022 Constellation'S Open Presentation for September 8, 2022 Partially Closed Public Meeting ML22250A4372022-09-0808 September 2022 NRC Staff'S Presentation for September 8, 2022 Partially Closed Public Meeting with Constellation - Review Planning and Tentative Review Timeline ML22249A2202022-09-0606 September 2022 Constellation'S Non-Proprietary Presentation for Limerick Generating Station Digital Modernization Project LAR Pre-submittal Meeting September 8, 2022 ML22164A8082022-06-13013 June 2022 Westinghouse, Presentation GLIMM-RPS-PM-L1-000008, Revision 0 ML22153A3602022-06-0909 June 2022 Constellation'S Presentation for June 9, 2022 Public Meeting About Limerick Generating Station Digital Modernization Project ML22187A0652022-06-0808 June 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - NRC Presentation Slides ML22103A2542022-04-19019 April 2022 Draft Request for Additional Information ML22076A1942022-03-23023 March 2022 Constellation Presentation March 23, 2022 NRC Di_C Workshop ML22080A1522022-03-21021 March 2022 Non-Proprietary Presentation for March 31, 2022 Pre-Submittal Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 ML22010A0692022-01-10010 January 2022 Jan 11 2022 LGS Digital Modernization Pre-submittal Meeting Slides ML21335A0772021-12-0707 December 2021 Dec 07 2021 LGS Digital Modernization Pre-submittal Meeting Slides ML21294A3692021-11-15015 November 2021 Summary of October 6, 2021, Public Observation Meeting with Exelon Generation Company, LLC Proposed License Amendment Request to Modify Emergency Diesel Generator and Emregency Core Cooling System Surveillance Requirements ML21314A4472021-11-10010 November 2021 Slides for Presubmittial Meeting for Proposed Alternative to Adopt ASME Code Case N-921 to Extend the Inservice Inspection Interval ML21278A5452021-10-20020 October 2021 Digital Modernization Project LAR Pre-submittal Meeting Presentation Slides October 20, 2021 ML21174A0852021-06-23023 June 2021 Digital Modernization Project LAR Pre-submittal Meeting ML21165A1942021-06-16016 June 2021 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation ML21165A2882021-06-16016 June 2021 Joint Annual Assessment for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation (Updated) ML21063A1192021-03-0404 March 2021 Digital Modernization Project LAR Pre-submittal Meeting - March 16, 2021 (EPID L-2020-LRM-0041) (Slides) ML21049A3102021-02-19019 February 2021 CFR 50.69 Alternative Categorization LAR ML21034A6032021-02-0303 February 2021 External Presentation Am Connelly_ISG-6 Workshop Presentation ML20261G7322020-09-16016 September 2020 Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a ML20178A4202020-06-30030 June 2020 NEI Slides for June 30, 2020, Public Meeting on COVID-19 Response ML20175A8722020-06-23023 June 2020 Risk-Informed Inservice Inspection - U.S Nuclear Regulatory Commission (NRC) - Four Element Risk-Informed Approach ML20170B0212020-06-23023 June 2020 NRC Pre-Submittal Meeting Byron Unit 2 One-Time Deferral of Reactor Pressure Vessel Head Penetration Nozzle (Rpvhpn) Inspections ML20169A5592020-06-16016 June 2020 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections (Rev 1) ML20163A6552020-06-16016 June 2020 6-16-20 Byron Unit 2 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections ML20168A3192020-06-15015 June 2020 Joint Annual Assessment Meeting for Pa/Md Power Plants - Webinar Presentation ML20162A0192020-06-10010 June 2020 NRC Staff Presentation for June 12, 2020, Public Pre-Application Meeting: ISG-06 Alternate Review Process Lessons Learned from Pre-Application Meetings ML20160A0532020-06-0808 June 2020 Digital Modernization Project LAR - Presubmittal Meeting - NRC Presubmittal Meeting Telecon June 12, 2020 ML19318F9512019-11-20020 November 2019 Presentation Slides for November 20, 2019, Pre-Application Meeting - Request for Revision to Quality Assurance Program Internal Audit Frequency ML19317C9952019-11-12012 November 2019 In-Service Testing Supplemental Position Indication Relief Request NRC Pre-Application Meeting November 18, 2019 ML19157A0542019-06-0606 June 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - NRC Presentation Slides ML19161A2572019-06-0404 June 2019 BWR Fleet Msv/Srv - Testing Frequency Relief Request NRC Pre-Application Meeting June 4, 2019 ML19151A6602019-05-31031 May 2019 BWR Fleet Mssv/Srv Testing Frequency Relief Request NRC Pre-Application Meeting June 4, 2019 ML19022A2002019-01-23023 January 2019 Request for Use of ASME Code Case N-879 for Exelon Nuclear Power Plants ML18347B3142018-12-19019 December 2018 Bwrvip/Asme Relief Request Discussion December 19, 2018 2024-05-16
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24249A3092024-09-0606 September 2024 September 6, 2024, Public Meeting Related to Digital Instrumentation and Control Amendment Slides ML24137A1882024-05-16016 May 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML24100A7672024-04-11011 April 2024 Meeting Slides - Preapplication with Constellation on Planned Fleet Alternative Request to Adopt OMN-2 ML24089A2612024-04-0909 April 2024 Slides - Constellation - Pre-Application Regarding Hooded Masks 4/9/2024 Meeting Slides (L-2024-LLM-0041) ML24029A1742024-01-30030 January 2024 Constellation Pre-Application January 30, 2024, Meeting Slides - Proposed Alternative to Utilize Code Case N-932, Alternative Requirements for Acceptance of Containment Base Metal Corrosion or Erosion ML23317A0712023-11-14014 November 2023 NRC Pre-Submittal Meeting on November 14th, 2023 - TSTF-591 and Selected 50.69 License Condition Updates (EPID L-2023-LLM-0098) (Slides) ML23255A1042023-08-11011 August 2023 Slides - Constellation - Pre-Application EP 9/18/2023 Draft CEG Presubmittal SG Performance Monitoring Plan Meeting Handout ML23157A0352023-06-0606 June 2023 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML23053A1562023-02-23023 February 2023 NRC Presentation Slides for Public Meeting on February 23, 2023 - 10 CFR 50.69 Alternate Processes License Amendment Request Preliminary Partial Denial ML23076A2812023-02-23023 February 2023 Licensee Presentation on Pressure Boundary Process ML23076A2822023-02-23023 February 2023 Licensee Presentation on Defense-in-Depth Process NEI 99-01, Slides - Constellation - Pre-Application EP 2/23/2023 Meeting Slides2023-02-21021 February 2023 Slides - Constellation - Pre-Application EP 2/23/2023 Meeting Slides ML23006A2572023-01-10010 January 2023 Digital Modernization Project Installation Support License Amendment Request and Exemption Request Presentation - January 10, 2023 (EPID L-2022-LRM-0099) (Slides) ML22347A1532022-12-13013 December 2022 Public Meeting Presentation, December 15, 2022 Di&C License Amendment Request ML22319A0012022-11-14014 November 2022 Constellation Energy Generation, Llc'S Presentation for November 10, 2022 Public Meeting with NRC ML22250A4372022-09-0808 September 2022 NRC Staff'S Presentation for September 8, 2022 Partially Closed Public Meeting with Constellation - Review Planning and Tentative Review Timeline ML22249A0972022-09-0808 September 2022 Constellation'S Open Presentation for September 8, 2022 Partially Closed Public Meeting ML22249A2202022-09-0606 September 2022 Constellation'S Non-Proprietary Presentation for Limerick Generating Station Digital Modernization Project LAR Pre-submittal Meeting September 8, 2022 ML22195A2172022-07-12012 July 2022 D3 Audit Open Items List (Non-Proprietary) (07-12-22)_redacted ML22164A8082022-06-13013 June 2022 Westinghouse, Presentation GLIMM-RPS-PM-L1-000008, Revision 0 ML22153A3602022-06-0909 June 2022 Constellation'S Presentation for June 9, 2022 Public Meeting About Limerick Generating Station Digital Modernization Project ML22187A0652022-06-0808 June 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - NRC Presentation Slides ML22076A1942022-03-23023 March 2022 Constellation Presentation March 23, 2022 NRC Di_C Workshop ML22080A1522022-03-21021 March 2022 Non-Proprietary Presentation for March 31, 2022 Pre-Submittal Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 ML22010A0692022-01-10010 January 2022 Jan 11 2022 LGS Digital Modernization Pre-submittal Meeting Slides ML21335A0772021-12-0707 December 2021 Dec 07 2021 LGS Digital Modernization Pre-submittal Meeting Slides ML21294A3692021-11-15015 November 2021 Summary of October 6, 2021, Public Observation Meeting with Exelon Generation Company, LLC Proposed License Amendment Request to Modify Emergency Diesel Generator and Emregency Core Cooling System Surveillance Requirements ML21314A4472021-11-10010 November 2021 Slides for Presubmittial Meeting for Proposed Alternative to Adopt ASME Code Case N-921 to Extend the Inservice Inspection Interval ML21278A5452021-10-20020 October 2021 Digital Modernization Project LAR Pre-submittal Meeting Presentation Slides October 20, 2021 ML21294A3792021-10-0606 October 2021 WCAP-17308 Implementation Licensing Amendment Request Pre-Submittal Meeting Presentation, October 6, 2021 ML21175A1732021-06-29029 June 2021 Digital Modernization Project LAR Pre-submittal Meeting ML21174A0852021-06-23023 June 2021 Digital Modernization Project LAR Pre-submittal Meeting ML21165A2882021-06-16016 June 2021 Joint Annual Assessment for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation (Updated) ML21165A1942021-06-16016 June 2021 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation ML21162A3322021-06-11011 June 2021 BWR Fleet Relief Request Associated with RPV Instrument Nozzle Repairs ML21063A1192021-03-0404 March 2021 Digital Modernization Project LAR Pre-submittal Meeting - March 16, 2021 (EPID L-2020-LRM-0041) (Slides) ML21049A3102021-02-19019 February 2021 CFR 50.69 Alternative Categorization LAR ML21034A6032021-02-0303 February 2021 External Presentation Am Connelly_ISG-6 Workshop Presentation ML20261G7322020-09-16016 September 2020 Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a ML20178A4202020-06-30030 June 2020 NEI Slides for June 30, 2020, Public Meeting on COVID-19 Response ML20170B0212020-06-23023 June 2020 NRC Pre-Submittal Meeting Byron Unit 2 One-Time Deferral of Reactor Pressure Vessel Head Penetration Nozzle (Rpvhpn) Inspections ML20175A8722020-06-23023 June 2020 Risk-Informed Inservice Inspection - U.S Nuclear Regulatory Commission (NRC) - Four Element Risk-Informed Approach ML20163A6542020-06-18018 June 2020 2020 NRC Annual Assessment Webinar Presentation - Pennsylvania and Maryland Facilities (Beaver Valley, Calvert Cliffs, Limerick, Peach Bottom, Susquehanna) ML20163A6552020-06-16016 June 2020 6-16-20 Byron Unit 2 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections ML20169A5592020-06-16016 June 2020 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections (Rev 1) ML20168A3192020-06-15015 June 2020 Joint Annual Assessment Meeting for Pa/Md Power Plants - Webinar Presentation ML20162A0192020-06-10010 June 2020 NRC Staff Presentation for June 12, 2020, Public Pre-Application Meeting: ISG-06 Alternate Review Process Lessons Learned from Pre-Application Meetings ML20160A0532020-06-0808 June 2020 Digital Modernization Project LAR - Presubmittal Meeting - NRC Presubmittal Meeting Telecon June 12, 2020 ML19304A8752019-11-0505 November 2019 Presentation Slides for Limerick/Nrc Pre-Submittal Meeting (Technical Specification 4.05 License Amendment Request) - November 5, 2019 ML19157A0542019-06-0606 June 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - NRC Presentation Slides 2024-09-06
[Table view] |
Text
Limerick Annual Assessment Meeting Reactor Oversight Program - CY 2004 Nuclear Regulatory Commission - Region I King of Prussia, PA April 14, 2005
Agenda z Introduction z Review of Reactor Oversight Process z National Summary of Plant Performance z Discussion of Plant Performance Results z Licensee Response and Remarks z NRC Closing Remarks z Break z NRC available to address public questions
Purpose of Todays Meeting z A public forum for discussion of the licensees performance z NRC will address the licensee performance issues identified in the annual assessment letter z Licensee will respond to the information in the letter and inform the NRC of new or existing programs to maintain or improve their performance
NRC Representatives z Mohamed Shanbaky, Branch Chief, Division of Reactor Projects z (610) 337-5209 z Samuel Hansell, Senior Resident Inspector z (610) 327-1344 z Greg Bowman, Resident Inspector z (610) 327-1344 z Carey Colantoni, Resident Inspector z (610) 327-1344 z Travis Tate, Project Manager, NRR z (301) 415-8474
Region 1 Organization Samuel Collins Regional Administrator James Wiggins Deputy Regional Administrator A. Randolph Blough Wayne Lanning Director Division of Reactor Projects Director Division of Reactor Safety Brian Holian John Lubinski Deputy Director Acting Deputy Director Mohamed Shanbaky Regional Specialists Branch Chief Limerick Project Engineers Resident Inspectors Arthur Burritt Samuel Hansell Dante Johnson Carey Colantoni Lauren Casey Greg Bowman Geoffrey Ottenberg
NRC Performance Goals z Safety: Ensure protection of the public health and safety and the environment z Security: Ensure the secure use and management of radioactive materials z Openness: Ensure openness in our regulatory process z Effectiveness: Ensure that NRC actions are effective, efficient, realistic, and timely z Management: Ensure excellence in agency management to carry out the NRCs strategic objective
Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Baseline Inspection Performance Indicator Results Results Significance Significance Threshold Threshold Action Matrix Regulatory Response
Examples of Baseline Inspections z Equipment Alignment ~92 hrs/yr z Triennial Fire Protection ~200 hrs every 3 yrs z Operator Response ~125 hrs/yr z Emergency Preparedness ~80 hrs/yr z Rad Release Controls ~100 hrs every 2 yrs z Worker Radiation Protection ~100 hrs/yr z Corrective Action Program ~200 hrs every 2 yrs z Corrective Action Case Reviews ~60 hrs/yr z Safety System Design ~420 hrs every 2 yrs
Significance Threshold Performance Indicators Green: Only Baseline Inspection White: May increase NRC oversight Yellow: Requires more NRC oversight Red: Requires more NRC oversight Inspection Findings Green: Very Low safety issue White: Low to moderate safety issue Yellow: Substantial safety issue Red: High safety issue
Action Matrix Concept Licensee Regulatory Degraded Multiple/Rep. Unacceptable Response Response Cornerstone Degraded Performance Cornerstone Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions
National Summary of Plant Performance Status at End of CY 2004 Licensee Response 78 Regulatory Response 21 Degraded Cornerstone 0 Multiple/Repetitive Degraded Cornerstone 3 Unacceptable 0 Total 102*
National Summary z Performance Indicator Results (at end of CY 2004)
Green 1834 White 6 Yellow 0 Red 0 z Total Inspection Findings (CY 2004)
Green 778 White 11 Yellow 0 Red 0
Limerick Performance Indicators Limerick Inspection Activities (Jan 1 - Dec 31, 2004) z 5660 hours0.0655 days <br />1.572 hours <br />0.00936 weeks <br />0.00215 months <br /> of inspection related activities z 2 resident inspectors assigned to the site z 9 regional inspections z 4 team inspections z Inspection findings z 8 findings of very low safety significance (Green)
Limerick Inspection Results Reactor Safety y Initiating Events (No findings) y Mitigating Systems (6 Green findings) y Barrier Integrity (2 Green findings) y Emergency Preparedness (No findings)
Radiation Safety y Occupational Radiation Safety (No findings) y Public Radiation Safety (No findings)
Limerick Assessment Results (Jan 1 - Dec 31, 2004) z Operated safely z Licensee response column of the Action Matrix for all four quarters of 2004 (cornerstone objectives fully met) z NRC will conduct baseline inspections during the next cycle
Limerick Inspection Activities (Jan 1 - Dec 31, 2005) z 7 regional inspector visits scheduled z 2 team inspections scheduled
NRC Security Program Update z NRC has issued Orders (February 2002):
z Increased Patrols z Augmented Security Capabilities z Added Barriers and Posts z Enhanced Personnel Screening for Access z Enhanced Security Awareness z Office of Nuclear Security and Incident Response Formed (April 2002) z Established Threat Advisory and Protective Measure System (August 2002)
NRC Security Program Update (continued) z Access Authorization Order (January 2003) z Training Order (April 2003) z Fatigue Order (April 2003) z Design Basis Threat (April 2003) z Changes to Site Security plans to incorporate the requirements of the orders (April 2004)
NRC Security Program Update (continued) z Expanded Force-on-Force Exercises z New NRC Baseline Inspection Program initiated (February 2004) z All Security Upgrades were required to be completed by October 29, 2004, and are currently being inspected through the baseline inspection program
Reference Sources z Reactor Oversight Process http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html z Public Electronic Reading Room http://www.nrc.gov/reading-rm.html z Public Document Room 1-800-397-4209 (Toll Free)
Ways for the Public To Become Informed
& Involved in the Regulatory Process Participate in NRC Public Meetings Sign up to be on our mailing list Visit the NRC website on a regular basis Publicly comment on proposed licensing actions or file a Petition for Rulemaking 10 CFR 2.206 petition process Contact the NRC via e-mail, mail, or phone to address questions or areas of concern Participate in open NRC/industry symposiums Freedom of Information Act (FOIA) requests
Contacting the NRC z Report an emergency z (301) 816-5100 (call collect) z Report a safety concern:
z (800) 695-7403 z Allegation@nrc.gov z General information or questions z www.nrc.gov z Select What We Do for Public Affairs
Licensee Response and Remarks Limerick Generating Station Exelon