Digital Modernization Project LAR Pre-submittal Meeting - March 16, 2021 (EPID L-2020-LRM-0041) (Slides)
ML21063A119
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 03/04/2021
From:
Exelon Generation Co, Exelon Nuclear
To: Marshall M
NRC/NRR/DORL/LPL1
Marshall, M., NRR/DORL/LPLI
References
EPID L-2020-LRM-0041
Download: ML21063A119 (56)


Text

Westinghouse Non-Proprietary Class 3 @ 2021 Westinghouse Electric Company LLC. All Rights Reserved Limerick Generating Station Digital Modernization Project LAR Pre-submittal Meeting NRC Pre-submittal Meeting March 16, 2021 WMP-1197~NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Agenda / Opening Remarks Open / Public Session

  • Introductions
  • Expected outcome for meeting
  • Project overview
  • Vendor Oversight Plan (VOP)

Closed Session

  • Architecture and Fundamental Design Principles
  • Applicability of Regulatory Precedent
  • Defense-in-Depth and Diversity (D3) Approach
  • NRC & Exelon Closing Remarks 1 WAAP-11979-NP
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)
' Exelon.

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Introductions - Exelon Project Team

  • Licensing
  • Shannon Rafferty-Czincila, Licensing Director
  • Dave Helker, Licensing Manager
  • Frank Mascitelli, Licensing Lead
  • Laura Lynch, LGS Regulatory Assurance Manager
  • Pareez Golub, Digital Licensing SME
  • Engineering
  • John Connelly, Central Design Organization (CDO) Manager
  • Mark Samselski, CDO - Lead Responsible Engineer
  • George Bonanni, CDO - Senior Staff Engineer
  • Mike Foote, CDO - Senior Staff Engineer
  • Scott Schumacher, Systems Engineering 2 WAAP-11979-NP
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)
' Exelon.

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Introductions - Exelon Project Team

  • Project Management
  • Steve Hesse, Project Director
  • Dave Molteni, Senior Manager and Station Lead
  • Jerry Segner, Principal Project Manager
  • Kayla Marriner, Project Manager
  • Operations
  • Paul Krueger, Operations
  • Craig Myers, Operations Support
  • Nuclear Oversight
  • Dave Peiffer, Performance and Assessment Lead 3 WAAP-11979-NP
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)
' Exelon.

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Introductions - Westinghouse Project Team

  • Project Management
  • Chris Crefeld, Project Director
  • Stefan Levine, Senior Manager
  • Bill Bennett, Project Manager
  • Tom Pietryka, Project Manager
  • Engineering
  • Terry Tuite, Lead - Engineering
  • Warren Odess-Gillett, Lead - Licensing
  • Steve Merkiel, System Design Engineer
  • Cal Tang, BWR Technical Advisor 4 WAAP-11979-NP
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)
' Exelon.

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Expected Outcome of Meeting Provide the NRC a more detailed view of the Limerick Modernization Project and gain staff feedback on core concepts that underlie the project:

  • Project scope/schedule/milestones
  • LAR contents and proposed use of ARP
  • Approach to addressing defense-in-depth and diversity
  • Architecture and approach to fundamental design principles
  • Applicability of previous generic licensing approvals
  • Migration of Redundant Reactivity Control System (ATWS) to a DCS Platform 5 WAAP-11979-NP
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Project Overview 6 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)
' Exelon.

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Project Scope

  • Upgrade analog, Safety-Related, protection systems to Westinghouse Common QTM digital platform integrated into PPS:
  • Nuclear Steam Supply Shutoff System (NSSSS)
  • Upgrade analog Redundant Reactivity Control System (RRCS) to OvationTM DCS platform and reclassify to non-safety in accordance with the ATWS Rule (10 CFR 50.62)
  • Install Data Display System (DDS) to display sources of information in an environment that improves the ability to synthesize plant data 7 WAAP-11979-NP
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)
' Exelon.

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Current Main Control Room Configuration 8 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)
' Exelon.

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved General Arrangement for Main Control Room 9 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)
' Exelon.

Westinghouse Non-Proprietary Class 3 @ 2021 Westinghouse Electric Company LLC. All Rights Reserved Potential Arrangement with Monitor Visuals 10 WMP-1197~NP ,,=, Exelon.

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 @ 2021 Westinghouse Electric Company LLC. All Rights Reserved Potential Arrangement with View from RO Console a

  • I * * -' W 11 WMP-1197~NP ,,=, Exelon.
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 @ 2021 Westinghouse Electric Company LLC. All Rights Reserved Potential Arrangement with View from SRO Station 12 WMP-1197~NP ,,=, Exelon.

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved LAR Overview 13 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved LAR Scope and Attachments LAR will include the following:

  • Required information per ISG-06 Enclosure B Alternate Review Process
  • Licensing Technical Report (LTR)
  • Technical Specification changes
  • System Requirements Specification (SyRS)
  • System Design Specification (SyDS)
  • FMEA to support TS SR eliminations
  • Equipment Qualification Summary Report (EQSR)
  • Human Factors Summary
  • VOP Summary
  • Regulatory commitments
  • Conceptual FSAR Mark-ups (Info Only) 14 WAAP-11979-NP
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Licensing Technical Report

  • Will address:
  • DI&C-ISG-06 Sections D.1 - D.8
  • TS surveillance elimination
  • Common Cause Failure analysis summary
  • Plant Specific Action Items (PSAI)
  • Common Q platform changes subsequent to generic NRC approval
  • Similar structure to Waterford LTR 16 WAAP-11979-NP
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Vendor Oversight Plan 17 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved VOP Scope The VOP is a critical part of the Project Quality Management Plan (QMP):

  • Leverages existing Exelon Quality Assurance, Engineering, and Project Management processes for oversight of Westinghouse Common Q development
  • Ensures high quality vendor products through QA program implementing procedures
  • Includes NRC acceptance criteria provided to industry, adapted for project use (ML19087A230)
  • Performs vendor audits as part of oversight activities
  • Ensures vendor is complying with NRC approved Common Q Software Program Manual (WCAP-16096-P-A, Rev. 5)
  • Validate PSAIs have been properly addressed 18 WAAP-11979-NP
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Closed Portion 19 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Architecture and Fundamental Design Principles 20 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Integrated Architecture a,c 21 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved PPS High-Level System Design Concept a,c 23 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved PPS High-Level System Design Concept (cont.)

Bistable Processing Logic (BPL) - Level 1 a,c 25 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved PPS High-Level System Design Concept (cont.)

Local Coincidence Logic (LCL) - Level 2 a,c 26 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved PPS High-Level System Design Concept (cont.)

Integrated Logic Processor (ILP) - Level 3 a,c 27 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved PPS High-Level System Design Concept (cont.)

RT Matrix/RPS TU Scram a,c 28 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved PPS High-Level System Design Concept (cont.)

Interface and Test Processor (ITP) a,c 29 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved PPS High-Level System Design Concept (cont.)

Flat Panel Display System - Safety Displays a,c 30 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved PPS High-Level System Design Concept (cont.)

Flat Panel Display System - MTP a,c 31 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved High-Level System Design Concept (cont.) a,c 32 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Fundamental Design Principles a,c 33 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Fundamental Design Principles (cont.) a,c 34 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Fundamental Design Principles (cont.) a,c 35 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Fundamental Design Principles (cont.) a,c 36 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Fundamental Design Principles (cont.) a,c 37 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Fundamental Design Principles (cont.) a,c 38 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Fundamental Design Principles (cont.)

Defense-in-depth and Diversity (D3)

D3 coping analysis - SECY 93-087 Position 1 - 3 a,c 39 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Fundamental Design Principles (cont.) - split content over two slides Defense-in-depth and Diversity (D3)

D3 coping analysis - SECY 93-087 Position 1 - 3 (cont.)

a,c SECY 93-087 Position 4 Displays and Controls a,c 40 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Fundamental Design Principles (cont.) - split content over two slides Defense-in-depth and Diversity (D3)

D3 coping analysis - SECY 93-087 Position 1 - 3 (cont.) a,c 41 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved CCF Approach (cont.)

SRM-SECY 93-087 Position 4 Displays and Controls a,c 42 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Priority Module a,c 44 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Priority Module (Cont.) a,c 45 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Prior NRC Review of the CIM

  • The CIM was reviewed as part of the AP1000 PMS
  • The CIM technical report, WCAP 17179, Revision 2 was docketed July 2010 (ML102170259)
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Prior NRC Review of the CIM (cont.)

  • ITAAC 2.5.02.14 covers the complete CIM development life cycle.
  • The following ADAMS Accession Numbers are the NRC ITAAC inspection reports:
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Applicability of previous NRC Approvals 48 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Applicability of Other Previous NRC Approvals The LAR will reference the following approved topical reports:

Platform topical report, WCAP-16097-P-A, Common Qualified Platform a,c 49 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Applicability of Other Previous NRC Approvals (cont.)

Application development topical report, WCAP-16096-P-A, Software Program Manual a,c 50 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Applicability of Previous NRC Approvals (cont.)

Surveillance reduction topical report, WCAP-18461-P-A, Common Q Platform and Component Interface Module Elimination of Technical Specification Surveillance Requirements a,c 51 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Scope for Non-safety related DCS Changes 52 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Redundant Reactivity Control System (RRCS)

  • The LAR will request downgrading the existing safety-related Redundant Reactivity Control System (RRCS) to non-safety and enhanced reliability, since its purpose is to meet the ATWS Rule (10 CFR 50.62)
  • It will be replaced with a separate and diverse non-safety Westinghouse Ovation product
  • Use redundant Ovation controllers as a dedicated drop from DCS a,c
  • Sensors (RPV water level, RPV pressure, Reactor power status) to be hardwired from PPS prior to connecting into PPS analog input modules (i.e., signal share w/ isolation) 53 WAAP-11979-NP
      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Closing Comments 54 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)

Westinghouse Non-Proprietary Class 3 © 2021 Westinghouse Electric Company LLC. All Rights Reserved Acronyms ADS Automatic Depressurization System LCL Local Coincidence Logic AER Auxiliary Equipment Room LGS Limerick Generating Station ARP Alternate Review Process LRA Licensee Required Action ASAI Application Specific Action Item LTR Licensing Technical Report ATWS Anticipated Transient Without Scram MCR Main Control Room BPL Bistable Protection Logic MPB Manual Partial Bypass BWR Boiling Water Reactor MPT Manual Partial Trip CCF Common Cause Failure MSFIS Main Steam and Feedwater Isolation System CDO Central Design Organization NSSSS Nuclear Steam Supply Shutoff System CIM Component Interface Module PC Personal Computer CPU Central Processing Unit PMS Protection and Monitoring System CS Core Spray PSAI Plant Specific Action Items D3 Defense-in-Depth and Diversity QMP Quality Management Plan DCS Distributed Control System RCIC Reactor Core Isolation Cooling DDS Data Display System RHR Residual Heat Removal ECCS Emergency Core Cooling System RPS Reactor Protection System EDG Emergency Diesel Generator RPV Reactor Pressure Vessel EOP Emergency Operating Procedures RRCS Redundant Reactivity Control System EQSR Equipment Qualification Summary Report SDV Scram discharge volume FMEA Failure Modes and Effects Analysis SPDS Safety Parameter Display System FMEDA Failure Modes, Diagnostics, and Effects Analysis SPM Software Program Manual FPGA Field Programmable Gate Array SRNC Safety Remote Node Controller FSAR Final Safety Analysis Report SyDS System Design Specification HPCI High Pressure Core Injection SyRS System Requirements Specification HSL High Speed Link TS Technical Specifications IBR Incorporated by Reference TU Trip Unit ILP Integrated Logic Processor UFSAR Updated Final Safety Analysis Report ITAAC Inspection, Test, Analysis, and Acceptance Criteria VOP Vendor Oversight Plan LAR License Amendment Request 55 WAAP-11979-NP

      • This record was final approved on 3/2/2021 1:59:11 PM. (This statement was added by the PRIME system upon its validation)