Information Notice 1992-85, Potential Failures of Emergency Core Cooling Systems Caused by Foreign Material Blackage
- - UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, D.C. 20555 December 23, 1992 NRC INFORMATION NOTICE 92-85: POTENTIAL FAILURES OF EMERGENCY CORE COOLING
SYSTEMS CAUSED BY FOREIGN MATERIAL BLOCKAGE
Addressees
All holders of operating licenses or construction permits for nuclear power
reactors.
Purpose
The U.S. Nuclear Regulatory Commission (NRC) is issuing this information
notice to alert addressees to the potential failure of emergency core cooling
systems (ECCS) caused by foreign material blockage. It is expected that
recipients will review the information for applicability to their facilities
and consider actions, as appropriate, to avoid similar problems. However, suggestions contained in this information notice are not NRC requirements;
therefore, no specific action or written response is required.
Description of Circumstances
H. B. Robinson Unit 2
On August 23, 1992, while the H. B. Robinson Nuclear Plant was in mode 4, hot
shutdown, plant personnel were performing an operations surveillance test of
the B safety injection (SI) pump. This test found that the recirculation flow
was 20 percent lower than it had been when it was last measured on July 12,
1992. Prompted by the resident inspector, the Carolina Power and Light
Company (the licensee) retested this pump on August 24, 1992, and found no
recirculation flow. The licensee also tested the A SI pump and found the
recirculation flow was 10 percent lower than when it was last measured. The
licensee declared both pumps inoperable and took the unit to cold shutdown.
On August 25, 1992, the licensee opened the B SI pump recirculation line and
removed a single piece of white plastic, about the size of a nickel, from the
inline orifice.
Previously, on July 8, 1992, the licensee had declared the B SI pump
inoperable after a quarterly inservice inspection surveillance test found that
it was producing a recirculation flow of 11.4 Liters [3 gallons] per minute, rather than the required 132.5 Liters [35 gallons] per minute. On July 9,
1992, the licensee shut down the plant to determine the cause of the low flow.
The licensee removed the recirculation line for the B SI pump and found that
debris was obstructing the inline orifice.
9212170209 Pyt I ( /'a
q9A Ac s
e 0C20 28
IN 92-85 December 23, 1992 On July 12, 1992, after flushing the B SI pump and verifying that
recirculation flows for both SI pumps were acceptable, the licensee returned
the unit to service. The licensee also tested all other ECCS pumps that could
have had contact with foreign material. The licensee believed, prior to plant
startup, that all debris had been removed.
Point Beach Unit 2 On September 28, 1992, the Wisconsin Electric Power Company (the licensee)
performed an ASME Section XI quarterly test of containment spray pumps and
valves. During the test, the licensee noted that the discharge pressure for
the A train containment spray pump was zero and that the pump was making an
abnormal noise. The test was stopped and the pump was declared inoperable.
Upon disassembly of the pump, a foam rubber plug was found blocking the
impeller suction. The licensee removed the plug and retested the pump. The
test was successfully completed and the pump was declared operable.
Discussion
The licensee at H. B. Robinson determined that the foreign material found in
the SI system was a plastic material that had been used during a modification
of the Residual Heat Removal (RHR) system performed in March through
June 1992. The plastic material is manufactured by DuPont and the trade name
is Delrin-AF. At the time of the RHR modification, the plastic material had
been cut into-four 23=centimeter [9-inch]-diameter,-circular pieces for use-as
weld purge dams. However, after completing the modification, the licensee did
not account for two of the four pieces. Delrin-AF decomposes at RCS system
conditions because of reaction with the water and thermal degradation. The
licensee suspected that the purge dam pieces broke,. entered the RHR piping
after breaking, and migrated into the refueling water storage tank (RWST) and
SI header during initial cavity draindown.
The licensee sent divers with cameras into the RWST to inspect for the
plastic. The divers found three fragments of Delrin-AF plastic and also other
pieces of miscellaneous debris. The location and size of the recovered
Delrin-AF material agrees with the material migration theory since all of the
pieces were larger than those recovered from the B SI pump in July and August.
The licensee inspected orifices for the SI pump minimum flow recirculation
lines and also visually inspected piping, tanks, and components to find and
remove any foreign material. Also, the licensee evaluated the potential
effect on other ECCS equipment and concluded that the ECCS equipment would
continue to be operable and reliable.
a
IN 92-85 December 23, 1992 The licensee for Point Beach Unit 2 reviewed plant records and determined that
the plug was most likely left in the piping after modifications were made to
install full flow test lines in the RHR, containment spray and safety
injection systems, during the 1991 refueling outage. The NRC reviewed the
event and determined that one train of the safety injection system piping was
rendered inoperable in the recirculation mode because of the presence of the
plug. This condition had continued for about a year and was caused by
inadequate foreign material exclusion controls during the system modifications
made in the previous outage.
The presence of small debris may not be detected by operational or post
modification testing since blockages may not appear immediately. However, small debris may migrate into areas with smaller cross sections where the
debris could collect and cause blockage after extended operation. These
examples illustrate the consequences of failure to ensure accountability of
all materials that are used when safety systems are opened and to perform
cleanliness checks of all affected areas prior to system closure.
Related Generic Communication
On November 21, 1989, the NRC issued Information Notice (IN)89-77, "Debris In
Containment Emergency Sumps and Incorrect Screen Configurations," which
addressed problems that could result from debris in containment emergency
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate Office of Nuclear
Reactor Regulation (NRR) project manager.
rnan K. Grimes, Director
Division of Operating Reactor Support
Office of Nuclear Reactor Regulation
Technical contact: Eric Benner, NRR
(301) 504-1171 Attachment: List of Recently Issued NRC Information Notices
z
C
D --
Attachment
IN 92-85 z-4 December 23, 1992 V Page I of 1
0
a
z
-_ _
11 LIST OF RECENTLY ISSUED
0
NRCINFORMATION NOTICES
>n
V
0-4U Information Vate of
-v Notice No. Subject Issuance Issued to
cmm
z 0 Cfl
U1 92-84 Release of Patients
Treated with Temporary
Implants
12/17/92 All Nuclear Regulatory
Comnission Medical
Licensees.
(
Ca/ 88-23, Potential for Gas 12/18/92 All holders of OLs or CPs
Supp. 4 Binding of High-Pres- for nuclear power reactors
sure Safety Injection
Pumps during A Design
z Basis Accident
92-83 Thrust Limits for 12/17/92 All holders of OLs or CPs
Limitorque Actuators for nuclear power reactors
and Potential Over- stressing of Motor- Operated Valves
92-82 Results of Thermo-Lag 12/15/92 All holders of OLs or CPs
330-1 Combustibility for nuclear power reactors
Testing
92-81 Potential Deficiency 12/11/92 All holders of OLs or CPs
of Electrical Cables for nuclear power reactors.
with Bonded Hypalon
Jackets
92-80 Results of Thermo-Lag 12/07/92 All holders of OLs or CPs
330-1 Combustibility for nuclear power reactors.
Testing
92-79 Non-Power Reactor 12/01/92 All holders of OLs or CPs(
Emergency Event Response for test and research
reactors.
92-78 Piston to Cylinder 11/30/92 All holders of OLs or CPs
Liner Tin Smearing on for nuclear power reactors.
Cooper-Bessemer KSV
Diesel Engines
DL - Operating License
CP- Construction Permit
'U
IN 92-XX
December xx, 1992 The licensee for Point Beach Unit 2 reviewed plant records and determined that
the plug was most likely left in the piping after modifications were made to
install full flow test lines-in the residual heat removal (RHR), containment
spray and safety injection systems, during the 1991 refueling outage. The NRC
reviewed the event and determined that one train of the safety injection
system piping was rendered inoperable in the recirculation mode because of the
presence of the plug. The NRC issued a Notice of Violation and Proposed
Imposition of Civil Penalty in the amount of $75,000. This violation, which
was classified at Severity Level III, continued for about a year and was
caused by inadequate foreign material exclusion controls during the system
modifications made in the previous outage.
The presence of small debris may not be detected by operational or post
modification testing since blockages may not appear immediately. However, small debris may migrate into areas with smaller cross sections where the
debris could collect and cause blockage after extended operation. Whenever
safety systems are opened, it is important to ensure accountability of any
materials that are used and to perform cleanliness checks of all affected
areas prior to system closure.
Related Generic Communication
On November 21, 1989, the NRC issued Information Notice (IN)89-77, "Debris In
Containment Emergency Sumps and Incorrect Screen Configurations," which
addressed problems that could result from debris in containment emergency
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate Office of Nuclear
Reactor Regulation (NRR) project manager.
Brian K. Grimes, Director
Division of Operating Reactor Support
Office of Nuclear Reactor Regulation
Technical contact: Eric Benner, NRR
(301) 504-1171 Attachment: List of Recently Issued NRC Information Notices
- SEE PREVIOUS CONCURRENCE
OEAB:DORS ASC/OEAB:DORS ADM:RPB PM:PD2-1:DRPE
DGarcia* AGautam* JMain* BMozafari*
10/07/92 10/14/92 09/28/92 10/13/92 C/SRXB:DSSA C/OEAB:DORS OGCB:DORS OE C/OGCB:DORS D/DORS
RJones* AChaffee* JBirmingham , Lieberman* GMarcus BGrimes
10/08/92 11/09/92 12////92 ~/' 2/09/92 12/1i/927 12/ /92 DOCUMENT NAME: G:\DMG\INDEBRIS.DMG
' J
4 I K)
IN 92-XX
December xx, 1992 The licensee for Point Beach Unit 2 reviewed plant records and determined that
the plug was most likely left in the piping after modifications were made to
install full flow test lines in the residual heat removal (RHR), containment
spray and safety injection systems, during the 1991 refueling outage. The NRC
reviewed the event and determined that one train of the safety injection
system piping was rendered inoperable in the recirculation mode because of the
presence of the plug. The NRC is issuing a Notice of Violation and Proposed
Imposition of Civil Penalty in the amount of $75,000. This violation, which
has been classified at Severity Level III, continued for about a year and was
caused by inadequate foreign material exclusion controls during the system
modifications made in the previous outage.
The presence of small debris may not be detected by operational or post
modification testing since blockages may not appear immediately. However, small debris may migrate into areas with smaller cross sections where the
debris could collect and cause blockage after extended operation. Whenever
safety systems are opened, it is important to ensure accountability of any
materials that are used and to perform cleanliness checks of all affected
areas prior to system closure.
Related Generic Communication
On November 21, 1989, the NRC issued Information Notice (IN)89-77, "Debris In
Containment Emergency Sumps and Incorrect Screen Configurations," which
addressed problems that could result from debris in containment emergency
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate Office of Nuclear
Reactor Regulation (NRR) project manager.
Brian K. Grimes, Director
Division of Operating Reactor Support
Office of Nuclear Reactor Regulation
Technical contact: Eric Benner, NRR
(301) 504-1171 Attachment: List of Recently Issued NRC Information Notices
- SEE PREVIOUS CONCURRENCE
OEAB:DORS ASC/OEAB:DORS ADM:RPB PM:PD2-1:DRPE
DGarcia* AGautam* JMain* BMozafari*
10/07/92 10/14/92 09/28/92 10/13/92 C/SRXB:DSSA C/OEAB:DORS OGCB:DORS OE AzK C/OGCB:DORS D/DORS
RJones* AChaffee* JBirmingham JLieberman GMarcus BGrimes
10/08/92 11/09/92 12/ /92 12/f /92 12/ /92 12/ /92 DOCUMENT NAME: G:\DMG\INDEBRIS.DMG
I I
IN 92-XX
December xx, 1992 pieces of miscellaneous debris. The location and size of the recovered
Delrin-AF material agrees with the material migration theory since all of the
pieces were larger than those recovered from the B SI pump in July and August.
The licensee inspected orifices for the SI pump minimum flow recirculation
lines, and visually inspected piping, tanks, and components to find and remove
any foreign material. Also, the licensee evaluated the potential effect on
other ECCS equipment and concluded that the ECCS equipment would continue to
be operable and reliable.
7-1- t- The staff notes thatl$resence of small debris may not be detected by
operational or post-modification testing since blockages may not appear
immediately. However, small debris may migrate into areas with smaller cross
sections where the debris can collect and cause blockage after extended
operation. Whenever safety systems are opened, it is important to ensure
accountability of any materials that are used and to perform'cleanliness
checks of all affected areas prior to system closure.
Related Generic Communication
On November 21, 1989, the NRC issued Information Notice (IN)89-77, "Debris In
Containment Emergency Sumps and Incorrect Screen Configurations," which
addressed problems that could result from debris in containment emergency
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate Office of Nuclear
Reactor Regulation (NRR) project manager.
Brian K. Grimes, Director
Division of Operating Reactor Support
Office of Nuclear Reactor Regulation
Technical coritact: Eric Benner, NRR
(301) 504-1171 Attachment: List of Recently Issued NRC Information Notices
- SEE PREVIOUS CONCURRENCE
OEAB:DORS ASC/OEAB:DORS ADM:RPB PM:PD2-1:DRPE
DGarcia* AGautam* JMain* BMozafari*
10/07/92 10/14/92 09/28/92 10/13/92 C/SRXB:DSSA C/OEAB:DORS OGCB:DORS OE C/OGC B:DORS D/DORS
RJones* AChaffee* JBirmingham* JLieberman* GMarc us* BGrimes
10/08/92 11/09/92 12/11/92 12/09/92 12/11 /92 12/ /92 DOCUMENT NAME E: G:\DMG\INDEBRIS.DMG
- SEE PREVIOUS CONCURRENCE
OEAB:DORS ASC/OEAB:DORS ADM:RPB PM:PD2-1:DRPE
DGarcia* AGautam* JMain* BMozafari*
10/07/92 10/14/92 09/28/92 10/13/92 C/SRXB:DSSA C/OEAB:DORS C/OGCB:DORS D/DORS
RJones* AChaffee* GMarcus BGrimes
10/08/92 11/09/92 / /92 / /92 DOCUMENT NAME: G:\DMG\INDEBRIS.DMG
IN 92-XX
November xx, 1992 Related Generic Communication
On November 21, 1989, the NRC issued Information Notice (IN)89-77, 'Debris In
Containment Emergency Sumps and Incorrect Screen Configurations," in which it
discussed problems that could result from debris found in containment
emergency sumps.
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate Office of Nuclear
Reactor Regulation (NRR) project manager.
Brian K. Grimes, Director
Division of Operating Reactor Support
Office of Nuclear Reactor Regulation
Technical contacts: D. Garcia, NRR
(301) 504-1170
Attachment:
List of Recently Issued NRC Information Notices
- SEE PREVIOUS CONCURRENCE
OEAB:DORS ASC/OEAB:DORS ADM:RPB PM:PD2-1:DRPE
DGarcia* AGautam* JMain* BMozafari*
10/07/92 10/14/92 09/28/92 10/13/92 C/SRXB:DSSA C/OE f DORS C/OGCB:DORS D/DORS
RJones* AChaffee GMarcus BGrimes
10/08/92 Il /.ci/92 / /92 I / /92 DOCUMENT NAME: G:\DMG\INDEBRIS.DMC
IN 92-XX
October xx, 1992 Related Generic Communication
On November 21, 1989, the NRC issued Information Notice (IN)89-77, "Debris In
Containment Emergency Sumps and Incorrect Screen Configurations," in which it
discussed problems that could result from debris found in containment
emergency sumps.
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate Office of Nuclear
Reactor Regulation (NRR) project manager.
Brian K. Grimes, Director
Division of Operating Reactor Support
Office of Nuclear Reactor Regulation
Technical contacts: D. Garcia, NRR
(301) 504-1170
Attachment:
List of Recently Issued NRC Information Notices
- SEE PREVIOUS CONCURRENCE
OEAB:DORS ASC/OEAB:DgRS ADM:RPB PM:PD2-1:DRPE
DGarcia* /cLAGautamOC JMain* BMozafari*
10/07/92 /6 //~/92 09/28/92 10/13/92 C/SRXB:DSSA C/OEAB:DORS C/OGCB:DORS D/DORS
RJones* AChaffee GMarcus BGrimes
10/08/92 / /92 / /92 / /92 DOCUMENT NAME: G:\DEBRIS.DMG
IN 92-XX
October xx, 1992 Related Generic Communication
On November 21, 1989, the NRC issued Information Notice (IN)89-77, 'Debris In
Containment Emergency Sumps and Incorrect Screen Configurations,' in which it
discussed problems that could result from debris found in containment
emergency sumps.
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate Office of Nuclear
Reactor Regulation (NRR) project manager.
Brian K. Grimes, Director
Division of Operating Reactor Support
Office of Nuclear Reactor Regulation
Technical contacts: Denise M. Garcia, NRR
(301) 504-1170
Attachment:
List of Recently Issued NRC Information Notices
- SEE PREVIOUS CONCURRENCE
0 : RS ASC/OEAB:DORS ADM:RPB PM:PD2-1 :DRP fl,_fv, AGautam JMain* BMozafari
,92 / /92 09/28/92 /0//13/92 C/ SA C/OEAB:DORS C/OGCB:DORS D/DORS
RJon'es AChaffee GMarcus BGrimes
/0/1(/92 / /92 / /92 / /92 DOCUMENT NAME: G:\DEBRIS.DMG
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate Office of Nuclear
Reactor Regulation (NRR) project manager.
Charles E. Rossi, Director
Division of Operational Events Assessment
Office of Nuclear Reactor Regulation
Technical contacts: Denise M. Garcia, NRR
(301) 504-1171 Attachment:
List of Recently Issued NRC Information Notices
OEAB:DOEA SC/OEAB:DOEA ADM:RPB PM:PD2-1:DRPE
DGarcia AGautam JMain Q h BMozafari
/ /92 / /92 9/ 2J /f2 / /92 C/SRXB:DST C/OEAB:DOEA C/OGCB:DOEA D/DOEA
RJones AChaffee GMarcus CRossi
/ /92 / /92 / /92 / /92 DOCUMENT NAME: G:\DEBRIS.DMG
K-)
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, D.C. 20555 December 23, 1992 NRC INFORMATION NOTICE 92-85: POTENTIAL FAILURES OF EMERGENCY CORE COOLING
SYSTEMS CAUSED BY FOREIGN MATERIAL BLOCKAGE
Addressees
All holders of operating licenses or construction permits for nuclear power
reactors.
Purpose
The U.S. Nuclear Regulatory Commission (NRC) is issuing this information
notice to alert addressees to the potential failure of emergency core cooling
systems (ECCS) caused by foreign material blockage. It is expected that
recipients will review the information for applicability to their facilities
and consider actions, as appropriate, to avoid similar problems. However, suggestions contained in this information notice are not NRC requirements;
therefore, no specific action or written response is required.
Description of Circumstances
H. B. Robinson Unit 2
On August 23, 1992, while the H. B. Robinson Nuclear Plant was in mode 4, hot
shutdown, plant personnel were performing an operations surveillance test of
the B safety injection (SI) pump. This test found that the recirculation flow
was 20 percent lower than it had been when it was last measured on July 12,
1992. Prompted by the resident inspector, the Carolina Power and Light
Company (the licensee) retested this pump on August 24, 1992, and found no
recirculation flow. The licensee also tested the A SI pump and found the
recirculation flow was 10 percent lower than when it was last measured. The
licensee declared both pumps inoperable and took the unit to cold shutdown.
On August 25, 1992, the licensee opened the B SI pump recirculation line and
removed a single piece of white plastic, about the size of a nickel, from the
inline orifice.
Previously, on July 8, 1992, the licensee had declared the B SI pump
inoperable after a quarterly inservice inspection surveillance test found that
it was producing a recirculation flow of 11.4 Liters [3 gallons] per minute, rather than the required 132.5 Liters [35 gallons] per minute. On July 9,
1992, the licensee shut down the plant to determine the cause of the low flow.
The licensee removed the recirculation line for the B SI pump and found that
debris was obstructing the inline orifice.
9212 0209
<-2 <off92-85 December 23, 1992 On July 12, 1992, after flushing the B SI pump and verifying that
recirculation flows for both SI pumps were acceptable, the licensee returned
the unit to service. The licensee also tested all other ECCS pumps that could
have had contact with foreign material. The licensee believed, prior to plant
startup, that all debris had been removed.
Point Beach Unit 2
On September 28, 1992, the Wisconsin Electric Power Company (the licensee)
performed an ASME Section XI quarterly test of containment spray pumps and
valves. During the test, the licensee noted that the discharge pressure for
the A train containment spray pump was zero and that the pump was making an
abnormal noise. The test was stopped and the pump was declared inoperable.
Upon disassembly of the pump, a foam rubber plug was found blocking the
impeller suction. The licensee removed the plug and retested the pump. The
test was successfully completed and the pump was declared operable.
Discussion
The licensee at H. B. Robinson determined that the foreign material found in
the SI system was a plastic material that had been used during a modification
of the Residual Heat Removal (RHR) system performed in March through
June 1992. The plastic material is manufactured by DuPont and the trade name
is Delrin-AF. At the time of the RHR modification, the plastic material had
been cut into four 23-centimeter (9-inch] diameter, circular pieces for use as
weld purge dams. However, after completing the modification, the licensee did
not account for two of the four pieces. Delrin-AF decomposes at RCS system
conditions because of reaction with the water and thermal degradation. The
licensee suspected that the purge dam pieces broke, entered the RHR piping
after breaking, and migrated into the refueling water storage tank (RWST) and
SI header during initial cavity draindown.
The licensee sent divers with cameras into the RWST to inspect for the
plastic. The divers found three fragments of Delrin-AF plastic and also other
pieces of miscellaneous debris. The location and size of the recovered
Delrin-AF material agrees with the material migration theory since all of the
pieces were larger than those recovered from the B SI pump in July and August.
The licensee inspected orifices for the SI pump minimum flow recirculation
lines and also visually inspected piping, tanks, and components to find and
remove any foreign material. Also, the licensee evaluated the potential
effect on other ECCS equipment and concluded that the ECCS equipment would
continue to be operable and reliable.
IN 92-85 December 23, 1992 The licensee for Point Beach Unit 2 reviewed plant records and determined that
the plug was most likely left in the piping after modifications were made to
install full flow test lines in the RHR, containment spray and safety
injection systems, during the 1991 refueling outage. The NRC reviewed the
event and determined that one train of the safety injection system piping was
rendered inoperable in the recirculation mode because of the presence of the
plug. This condition had continued for about a year and was caused by
inadequate foreign material exclusion controls during the system modifications
made in the previous outage.
The presence of small debris may not be detected by operational or post
modification testing since blockages may not appear immediately. However, small debris may migrate into areas with smaller cross sections where the
debris could collect and cause blockage after extended operation. These
examples illustrate the consequences of failure to ensure accountability of
all materials that are used when safety systems are opened and to perform
cleanliness checks of all affected areas prior to system closure.
Related Generic Communication
On November 21, 1989, the NRC issued Information Notice (IN)89-77, "Debris In
Containment Emergency Sumps and Incorrect Screen Configurations," which
addressed problems that could result from debris in containment emergency
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate Office of Nuclear
Reactor Regulation (NRR) project manager.
rnan K. Grimes, Director
Division of Operating Reactor Support
Office of Nuclear Reactor Regulation
Technical contact: Eric Benner, NRR
(301) 504-1171 Attachment: List of Recently Issued NRC Information Notices
l
I 1 K"
I
K-,
Attachment
IN 92-85 December 23, 1992 LIST OF RECENTLY ISSUED
NRC INFORMATION NOTICES
Information Date of
Notice No. Subject Issuance Issued to
92-84 Release of Patients 12/17/92 All Nuclear Regulatory
Treated with Temporary Commission Medical
Implants Licensees.
88-23, Potential for Gas 12/18/92 All holders of OLs or CPs
Supp. 4 Binding of High-Pres- for nuclear power reactors.
sure Safety Injection
Pumps during A Design
Basis Accident
92-83 Thrust Limits for 12/17/92 All holders of OLs or CPs
Limitorque Actuators for nuclear power reactors.
and Potential Over- stressing of Motor- Operated Valves
92-82 Results of Thermo-Lag 12/15/92 All holders of OLs or CPs
330-1 Combustibility for nuclear power reactors.
Testing
92-81 Potential Deficiency 12/11/92 All holders of OLs or CPs
of Electrical Cables for nuclear power reactors.
with Bonded Hypalon
Jackets
92-80 Results of Thermo-Lag 12/07/92 All holders of OLs or CPs
330-1 Combustibility for nuclear power reactors.
Testing
92-79 Non-Power Reactor 12/01/92 All holders of OLs or CPs
Emergency Event Response for test and research
reactors.
92-78 Piston to Cylinder 11/30/92 All holders of OLs or CPs
Liner Tin Smearing on for nuclear power reactors.
Cooper-Bessemer KSV
Diesel Engines
OL = Operating License
CP = Construction Permit