TOCUME NRSC, FO TRM VERMONT YANKEE CONTROLLED DOCUMENT TRANSMITTAL FORM SECTION 1 DOCUMENT TITLE: IMPLEMENTING PROCEDURES TO THE E-PLAN COPY NUMBER:

CHANGE NUMBER: #200 Aoril 1 7. 2002 ISSUE DATE:

And 1 17 2002 INSTRUCTIONS:

a. Attached is an authorized controlled copy to the above listed document for retention as your assigned copy.
b. Review the revised material.
c. Incorporate new change into the controlled document by document issue date, if applicable.
d. Ensure that those who use the document are aware of the change.
e. Destroy all superseded pages.
f. Destroy obsolete forms and insert new forms into the files.
g. Sign and date this form and return to the Executive Secretary (ES) or Document Control Center (DCC).
h. Complete appropriate change information on VY Controlled Document Record of Changes.

TRANSMITTED BY: Q(, .,-- 1 ES or DCC signature AFTER COMPLYING WITH THE ABOVE INSTRUCTIONS, PLEASE RETURN TO THE ES OR DCC WITHIN 10 DAYS OF THE ISSUE DATE.

SECTION 2 The undersigned acknowledges completion of the preceding instructions.

Signature of Recipient:. Date:

Epa leme][

Imp1F1U I~Il nt in!

To: Eplan Implementing Procedure Controlled Set Holders From: Diane McCt*A ,.r'O Date: 04/17/02 Re: VY EPlan Implementing Procedure Change #200, Instruction Sheet A new Table of Contents is included.

REVISIONS: Please replace the following procedures:

Proc/Rev # Procedure Title OP 3524/18 Emergency Actions to Ensure Initial Accountability/Security Response OP 3533/5 Post Accident Sampling of Reactor Coolant

Vermont Yankee Emergency Plan Implementing Procedures Table of Contents April 24, 2002 Emergency Plan Classification and Action Level Scheme AP 3125 Rev. 18 "R" Emergency Communications OP 3504 Rev. 34 "R" OP 3505 Rev. 23 ?fi Emergency Preparedness Exercises and Drills Emergency Equipment Readiness Check OP 3506 Rev. 40 "R" Emergency Radiation Exposure Control OP 3507 Rev. 29 "R" On-Site Medical Emergency Procedure OP 3508 Rev. 22 "R" Environmental Sample Collection During an Emergency OP 3509 Rev. 17 "R" Off-Site and Site Boundary Monitoring OP 3510 Rev. 25 "R" Off-Site Protective Action Recommendations OP 3511 Rev. 11 "R" Evaluation of Off-Site Radiological Conditions OP 3513 Rev. 20 "R" Emergency Actions to Ensure Accountability and Security Response OP 3524 Rev. 18 "R" Radiological Coordination OP 3525 Rev. 9 "R" Emergency Call-In Method OP 3531 Rev. 14 "R" AP 3532 Rev. 10 "TI Emergency Preparedness Organization OP 3533 Rev. 5 "C" Post Accident Sampling of Reactor Coolant OP 3534 Rev. 3 "C" Post Accident Sampling of Plant Stack Gaseous Releases OP 3535 Rev. 3 "C" Post Accident Sampling and Analysis of Primary Containment OP 3536 Rev. 1 "C" In Plant Air Sample Analysis with Abnormal Condition Control Room Actions During an Emergency OP 3540 Rev. 0 "R" Activation of the Technical Support Center OP 3541 Rev. 0 "R" Operation of the Technical Support Center OP 3542 Rev. 0 "R" Operation of the Operations Support Center OP 3544 Rev. 1 "R" Activation of the Emergency Operations Facility/Recovery Center OP 3545 Rev. 0 "R" Operation of the Emergency Operations Facility/Recovery Center OP 3546 Rev. 0 "R" Security Actions During an Emergency OP 3547 Rev. 0 "R" OP 3712 Rev. 16 "I" Emergency Plan Training

VERMONT YANKEE NUCLEAR POWER STATION OPERATING PROCEDURE OP 3524 REVISION 18 EMERGENCY ACTIONS TO ENSURE INITIAL ACCOUNTABILITY AND SECURITY RESPONSE USE CLASSIFICATION: REFERENCE LPC Effective No. Date Affected Pages 1 1 Implementation Statement: N/A I I

Issue Date: 04/24/2002 OP 3524 Rev. 18 Page 1 of 17

TABLE OF CONTENTS PURPOSE PU.RPOSE ........... ° ..... ° .. .... ..................................................................... 3 3..

DISCUSSION ......................................................... 3 ATTACHMENTS ....................................................... 3 REFERENCES ......................................................... 3 DEFINITIONS ......................................................... 4 PROCEDURE ......................................................... 4 I. Personnel Evacuation in the Event of an Alert ......................... 4 II. Initial Personnel Accountability in the Event of an Alert ................................... 6 III. Additional Security Force Functions in the Event of an Alert .......................... 11 IV. Personnel Evacuation in the Event of a Site Area Emergency or General Emergency Which Has Not Been Preceded by the Declaration of an Alert ......... 13 V. Personnel Accountability in the Event of a Site Area Emergency or General Emergency, Not Preceded by the Declaration of an Alert ................................ 14 VI. Additional Security Force Functions in the Event of a Site Area Emergency or General Emergency Not Preceded by the Declaration of an Alert ................... 15 VII. Other Security Force Functions in the Event of an Emergency (Alert, Site Area or Gen eral) ................................................................................................................. 16 VIII. Criteria for Evacuation of Gatehouse 2 ............................. 17 FIN AL C ON D ITIO N S .................................................................................................................. 17 OP 3524 Rev. 18 Page 2 of 17

PURPOSE To define necessary actions by members of the security force, in conjunction with plant personnel, during emergency conditions at Vermont Yankee Nuclear Power Station.

DISCUSSION Under emergency conditions, the security force functions are to aid the Plant Emergency Director (Operations Shift Supervisor) and the Technical Support Center (TSC) Coordinator by providing supplemental security staff, providing pertinent information, regulating access to the site, and performing security functions as deemed necessary. Plant personnel are responsible for reporting to appropriate areas and aiding security in the accountability process.

Vermont Yankee personnel and contractors working within the Plant Support Building and Gate 3, located in the Owner Controlled Area (OCA), are required to attend OCA training and are exempt from having to wear a Vermont Yankee OCA Unescorted Access Badge.

Visitors to the Plant Support Building or Gate 3 require escort by an individual with current training for OCA unescorted access and are not required to wear an OCA Visitor's Badge.

In cases of an Emergency Plan drill or actual event, individuals within the Plant Support Building and Gate 3 shall follow the procedures presented during OCA training.

ATTACHMENTS

1. VYOPF 3524.01 Initial Accountability Report Form
2. VYOPF 3524.02 Initial Accountability Check-In Form
3. Figure 1 Hallway Outside Control Room Map
4. Figure 2 Technical Support Center (TSC) Layout
5. Figure 3 Operations Support Center (OSC) Layout
6. Figure 4 Condenser Bay - Ground Floor REFERENCES
1. Technical Specifications and Site Documents
a. None
2. Codes, Standards, and Regulations
a. None
3. Commitments
a. None OP 3524 Rev. 18 Page 3 of 17
4. Supplemental References
a. OP 3510, Off-Site and Site Boundary Monitoring
b. OP 3540, Control Room Actions During an Emergency C. OP 3541, Activation of the Technical Support Center
d. OP 3542, Operation of the Technical Support Center
e. OP 3544, Operation of the Operations Support Center
f. OP 3545, Activation of the Emergency Operations Facility/Recovery Center
g. OP 3546, Operation of the Emergency Operations Facility/Recovery Center
h. OP 3547, Security Actions During an Emergency
i. AP 6807, Collection, Temporary Storage and Retrieval of QA Records DEFINITIONS
1. Normal Hours: Periods of time when sufficient personnel are on-site to activate the Technical Support Center (TSC) within a short period of time.
2. Off-Normal Hours: Periods of time when personnel needed to activate the TSC will be responding from off-site.

PROCEDURE I. Personnel Evacuation in the Event of an Alert On notification of an Alert condition by alarm or verbal report, the following actions shall be taken to ensure personnel (including contractors and visitors) site evacuation:

A. Plant emergency response personnel shall:

1. without delay, proceed to the plant Administration Building and report, as required, to the TSC or OSC,
2. upon arrival, promptly check in using VYOPF 3524.02 where indicated,
3. take actions as required by their duty assignment.

OP 3524 Rev. 18 Page 4 of 17

NOTES Plant workers and contractors should hang their Dositec (if any) along with their TLD on the dosimetry rack in Gatehouse 2.

Visitors should turn in Dositecs (if any), clipped together with their visitor's badge and TLD, to the Access Control Officer (ACO) or as directed.

During emergency evacuation periods due to a declared event, the portal monitor at Gatehouse 2 may be bypassed per DP 4532.

B. All personnel assigned to the EOF shall:

1. without delay, proceed to Gatehouse 2 and leave the Protected Area (PA) as normal,
2. travel to the EOF and, upon arrival, promptly check in at the front desk of the Training Center.

C. All unassigned individuals (plant personnel, contractors, and visitors) shall:

1. without delay, proceed to Gatehouse 2 and leave the Protected Area (PA) as normal,
2. walk to the Governor Hunt House (GHH) and await further instructions.

D. Security Shift Supervisor(s) (SSS) shall, as necessary:

1. supplement security shift staffing,
2. request local law enforcement support.

OP 3524 Rev. 18 Page 5 of 17

II. Initial Personnel Accountability in the Event of an Alert On notification of an Alert condition by alarm or verbal report, actions shall be taken to ensure personnel (including contractors and visitors) accountability. The accountability process to be used will be determined by activation of the TSC during normal or off-normal hours.

A. During normal hours:

1. The Access Control Officer (ACO) shall direct security personnel to:
a. ensure that all evacuating personnel deposit their identification badges and card keys in the proper collection slots and promptly exit the Gatehouse,
b. immediately return all identification badges and card keys to their proper slots in the badge rack,
c. obtain an On-Site report from the security computer when personnel have evacuated the Protected Area (PA), inventory the Owner Controlled Area (OCA) badge rack, as well as the Visitor's Log,
d. initiate VYOPF 3524.01.

NOTE The ACO shall contact the TSC to ascertain the status of the VYOPF 3524.02 forms (check-in sheets) if they are not delivered following the evacuation of personnel.

2. The TSC Coordinator shall designate Accountability Coordinators to:
a. ensure all personnel reporting to the TSC and OSC check in on VYOPF 3524.02,
b. promptly deliver completed VYOPF 3524.02 forms to the ACO at Gatehouse 2,
c. activate accountability posts to monitor all personnel entering/exiting the emergency response facilities located in the Administration Building, using VYOPF 3542.01.

OP 3524 Rev. 18 Page 6 of 17

3. The ACO shall:
a. assign an individual to read off the gatehouse slot number and name, in that order, from the VYOPF 3524.02's, the OCA badge rack and the Visitor's Log, if applicable,
b. check off the corresponding gatehouse slot number and name on the On-Site computer report,
c. when complete, verify that badges assigned to those personnel not checked-off on the On-Site computer report are not in the badge and OCA rack, or in the deposit slots, NOTE Should an individual incorrectly note their slot number or a printed name is illegible, a cross-reference may be obtained using the current Employee Card Key Inventory List maintained at the ACO's desk.
d. list personnel not checked off on the On-Site computer report as unaccounted for on VYOPF 3524.01,
e. report the status of the accountability process to the TSC and the name(s) of any unaccounted for personnel, within 30 minutes of the announcement of the emergency classification, NOTE If the process is not complete at the time of this report another notification to the TSC is required upon completion.
f. place colored pegs in the badge rack slots indicating those personnel unaccounted for.
4. When an On-Site computer report is not available, the ACO shall:
a. ensure that all personnel deposit their identification badges and card keys in the proper collection slots and promptly exit the Gatehouse,
b. immediately return all identification badges and card keys to their proper slots in the badge rack,
c. initiate VYOPF 3524.01, OP 3524 Rev. 18 Page 7 of 17

NOTE The ACO shall contact the TSC to ascertain the status of the VYOPF 3524.02's (check-in sheets) if they are not delivered following the evacuation of personnel.

d. following site evacuation numerically inventory by slot number the empty slots in the identification badge rack, the OCA badge rack and the Visitor's Log, if applicable, NOTE During the time after the inventory list is compiled and before the process is complete, individuals who leave site must be deleted from the list in order to avoid appearing unaccounted for.
e. assign an individual to read off the gatehouse slot number and name from the VYOPF 3524.02's, the OCA badge rack, as well as the Visitor's Log, if applicable,
f. check-off the corresponding gatehouse slot number on the inventory list compiled in step 4.d.,
g. when complete, verify that badges assigned to those personnel not checked off on the inventory list are not in the badge and OCA rack or in the deposit slots, NOTE Should an individual incorrectly note their slot number or a printed name is illegible, a cross-reference may be obtained using the current Employee Card Key Inventory List maintained at the ACO's desk.
h. list personnel not checked off as unaccounted for on VYOPF 3524.01,
i. report the status of the accountability process to the TSC, and the name(s) of any unaccounted for personnel, within 30 minutes of the announcement of the emergency classification.

OP 3524 Rev. 18 Page 8 of 17

NOTE If the process is not complete at the time of this report another notification to the TSC is required upon completion.

5. The TSC, on notification of unaccounted for personnel, shall designate personnel to:
a. page the unaccounted for individual(s) in an attempt to locate them, NOTE Whenever possible an Armed Security Officer should be assigned as a member of the search and rescue team.
b. as necessary, dispatch an on-site search and rescue team to locate the individual(s),
c. inform the ACO when the individual is located.
6. The ACO shall:
a. delete the individual from VYOPF 3524.01 as appropriate,
b. remove the colored peg from the individual's badge rack slot.

B. During off-normal hours:

I1. the ACO shall direct security personnel to:

a. ensure that all evacuating personnel deposit their identification badges and card keys in the proper collection slots and promptly exit the Gatehouse,
b. immediately return all identification badges and card keys to their proper slots in the badge rack,
c. obtain an On-Site report from the security computer when personnel have evacuated the PA, inventory the OCA badge rack and Visitor's Log, if applicable, OP 3524 Rev. 18 Page 9 of 17

NOTE If an On-Site report from the security computer is unavailable, perform accountability in accordance with step A.4.

d. initiate VYOPF 3524.01,
e. verify the well-being and accountability of each individual listed on the On-Site report, by contacting the senior supervisor for each department currently on site, NOTE If there is someone listed as on-site who cannot be accounted for by a supervisor, they will need to be located individually via Gai-Tronics or other means.
f. check off the corresponding name and slot number on the On-Site report,
g. note on the On-Site report the name(s) of the supervisors verifying well-being,
h. when complete, verify that badges assigned to those personnel not checked off on the On-Site report are not in the badge and OCA rack or in the deposit slots,
i. list them as unaccounted for on VYOPF 3524.01,
j. report the status of the accountability process to the Operations Shift Supervisor (OSS), and the name(s) of any unaccounted for personnel, within 30 minutes of the announcement of the emergency classification,
k. place colored pegs in the badge rack slots indicating those personnel unaccounted for.

OP 3524 Rev. 18 Page 10 of 17

2. The OSS, on notification of unaccounted for personnel, shall designate personnel to:
a. page the unaccounted for individual(s) in an attempt to locate them, NOTE Whenever possible an Armed Security Officer should be assigned as a member of the search and rescue team.
b. as necessary, dispatch an on-site search and rescue team to locate the individual(s),
c. inform the ACO when the individual is located.
3. The ACO shall:
a. delete the individual from VYOPF 3524.01 as appropriate,
b. remove the colored peg from the individual's badge rack slot.

III. Additional Security Force Functions in the Event of an Alert On notification of an Alert condition by alarm or verbal report, the following actions shall be taken by the security force:

A. Site Access Control

1. The Gatehouse 1 security officer(s) shall:
a. as necessary, direct personnel to the GHH, NOTE Personnel responding to the Emergency Operations Facility (EOF) at Brattleboro will be allowed to leave site.
b. control access to the plant site to ensure that only those persons and vehicles authorized by the TSC Coordinator, OSC Coordinator or Plant Emergency Director (OSS) are allowed to enter the plant site (the ACO will be the point of contact),
c. direct any emergency response vehicles to proceed to the Gatehouse 2 parking lot, OP 3524 Rev. 18 Page 11 of 17
d. direct all other incoming vehicles as normal unless otherwise directed by the TSC Coordinator or Plant Emergency Director,
e. ensure that the site access road is not obstructed to prevent personnel evacuation or passage of emergency equipment.
2. The Gatehouse 2 Access Control Officer shall:
a. ensure that all personnel entering the PA have been authorized by the TSC Coordinator,
b. ensure that all personnel entering the site enter through the Administration Building main west entry (lobby entry).

B. Posting of Signs at the Emergency Response Facility

1. The Security Shift Supervisor (SSS) shall dispatch a security officer(s) to post "Accountability Control" signs on doors which form the boundary of the facility.
2. The security officer(s) shall post signs on all doors shown on Figures 1, 2, and 3.

C. Posting of CO 2 Hazard Signs

1. When directed by the Fire Brigade Commander, the SSS shall dispatch a security officer(s) to post "CO 2 Hazard" signs on the doors indicated in Figures 1 through 4.
2. The security officer(s) shall post the signs on the doors indicated on Figures 1 through 4.

OP 3524 Rev. 18 Page 12 of 17

IV. Personnel Evacuation in the Event of a Site Area Emergency or General Emergency Which Has Not Been Preceded by the Declaration of an Alert The following actions shall be taken to ensure personnel (including contractors and visitors) site evacuation:

A. Any personnel exiting a known contamination area shall report to the Radiation Protection Control Point to be monitored and receive further instructions from Radiation Protection personnel.

B. Plant emergency response personnel shall take actions as previously described in the Alert notification and required by their duty assignment.

C. All other plant personnel shall evacuate the site as follows:

1. Without delay, proceed to Gatehouse 2 (PA gatehouse), place dosimetry (to include Dositec, if any) in the appropriate slot in the dosimetry rack, and leave the PA as normal.
2. Exchange their VY identification badge (and card key) for a VY "EMPLOYEE EXIT PASS." A security officer will be stationed at the gatehouse exit turnstiles to ensure badges are placed in the proper collection slots and exit passes issued.
3. Proceed to Gatehouse 1 (OCA gatehouse) and hand the "EXIT PASS" to the security officer at the gatehouse.
4. Proceed to the Emergency Operations Facility/Recovery Center (EOF/RC) unless assigned for duty at the Governor Hunt House.

OP 3524 Rev. 18 Page 13 of 17

D. Contractor employees and visitors shall evacuate the site as follows:

NOTE If a visitor has been issued dosimetry, he/she will be instructed to clip the badge and dosimetry together and hand it to the security officer stationed at the gatehouse exit turnstiles.

1. Without delay, proceed to Gatehouse 2 (PA gatehouse), place dosimetry (to include Dositec, if any) in the appropriate slot in the dosimetry rack, and leave the PA as normal.

NOTE Any contractor or visitor who is found to be contaminated shall be directed by the Governor Hunt House monitoring team to proceed to the EOF/RC.

2. Walk to the Governor Hunt House to be frisked by the Governor Hunt House monitoring team. After being frisked, each contractor or visitor shall be given a "CONTRACTOR EXIT PASS."
3. Retrieve their vehicle from the parking lot, hand their "EXIT PASS" to the security officer at Gatehouse 1 and leave site.

V. Personnel Accountability in the Event of a Site Area Emergency or General Emergency, Not Preceded by the Declaration of an Alert (See Section I - Shall be the same as in the Alert notification.)

OP 3524 Rev. 18 Page 14 of 17

VI. Additional Security Force Functions in the Event of a Site Area Emergency or General Emergency Not Preceded by the Declaration of an Alert The following actions shall be taken by the security force.

A. Site Access Control

1. The Gatehouse 1 Security Officer(s) shall:
a. as necessary, direct personnel to the GHH such that no contractor personnel or visitors leave without first being frisked by the Governor Hunt House monitoring team,
b. control access to the plant site to ensure that only those persons and vehicles authorized by the TSC Coordinator, OSC Coordinator or Plant Emergency Director (OSS) are allowed to enter the plant site, (the ACO will be the point of contact),
c. direct any emergency response vehicles to proceed to the Gatehouse 2 parking lot,
d. direct all other incoming vehicles as normal unless otherwise directed by the TSC Coordinator or Plant Emergency Director,
e. ensure that the site access road is not obstructed to prevent personnel evacuation or passage of emergency equipment.
2. The ACO shall:
a. ensure that all personnel entering the plant Protected Area have been authorized by the TSC Coordinator,
b. ensure that all personnel entering the site enter through the Administration Building main west entry (lobby entry).

B. Posting of Signs at the Emergency Response Facilities

1. The SSS shall dispatch a security officer(s) to post "Accountability Control" signs on doors which form the boundary of the facility.
2. The security officer(s) shall post signs in all doors shown on Figures 1, 2, and 3.

OP 3524 Rev. 18 Page 15 of 17

VII. Other Security Force Functions in the Event of an Emergency (Alert, Site Area or General)

The following additional actions shall be taken by the security force:

A. Site Boundary Radiological Survey. If the SSS is notified of the need to perform a site radiological survey:

1. contact the Control Room and request the following information:
a. Downwind direction.
b. Type of release (elevated or ground).
2. dispatch a Security Survey Team to the requested location. The Security Survey Team shall:
a. obtain equipment in accordance with OP 3510,
b. report to the assigned location,
c. perform a survey in accordance with the provisions of OP 3510,
d. report the results of the survey to the TSC (if it is manned) or the Control Room.

B. Issue of Controlled Keys. The SSS shall:

1. issue keys from the emergency key repository as requested by the Operations Support Center Coordinator. This could include issue of Emergency Key Rings which contain the master keys for Vital Areas, Protected Areas and Radiation Areas,
2. log the issue and return of the keys on the SSS key control log.

C. Evacuation Assistance: As requested, security force members shall provide directions to Gatehouse 1, the Governor Hunt House, or EOF/RC at Brattleboro.

D. Protected Area Access Control: The security force shall adhere to all normal PA access control requirements (search, authorization, etc.) except Plant personnel dispatched by the TSC or OSC to work in the OCA shall retain their dosimetry.

OP 3524 Rev. 18 Page 16 of 17

E. Status of Security Systems and Security Force. The SSS shall:

1. report the status of plant security, perimeter integrity, location of security personnel, number of persons on-site, etc., as requested by the TSC Coordinator or Plant Emergency Director,
2. ensure that all required security force emergency functions are completed,
3. notify the Security Operations Supervisor and Security Manager in the event of an emergency situation.

VIII. Criteria for Evacuation of Gatehouse 2 A. During a Site Area Emergency or General Emergency it may become necessary to evacuate Gatehouse 2 due to habitability concerns.

B. On notification by the TSC Coordinator of the need to evacuate Gatehouse 2, the Security Manager shall:

1. assess relocation alternatives with the TSC Coordinator,
2. develop a plan for the relocation of security personnel and equipment,
3. determine necessary compensatory measures and actions as a result of the relocation.

FINAL CONDITIONS

1. Return emergency equipment to normal location at Gatehouse 2.
2. Return all completed forms to the Emergency Plan Coordinator who will ensure proper filing in accordance with AP 6807.

OP 3524 Rev. 18 Page 17 of 17

INITIAL ACCOUNTABILITY REPORT FORM I. Date: II. Time Event Initiated:

III. Names of Individuals Unaccounted For: (if none, leave blank)

_____________________________________________________________________ I ___________________________________________________________________

1-4-

1-4.

4.

1*

+

4-4.

4.

1-4.

IV. Time Completed:

Time TSC or CR Contacted:

Access Control Officer (Print/Sign)

VYOPF 3524.01 OP 3524 Rev. 18 Page 1 of 1

INITIAL SITE ACCOUNTABILITY CHECK-IN FORM FOR TECHNICAL SUPPORT CENTER RESPONSE PERSONNEL DATE:

GATEHOUSE POSITION SLOT NO. PLEASE PRINT NAME CLEARLY DEPT.

TECHNICAL SUPPORT CENTER COORDINATOR SECURITY COORDINATOR MAINTENANCE COORDINATOR ENGINEERING COORDINATOR REACTOR ENGINEERING COORDINATOR OPERATIONS COORDINATOR RADIATION PROTECTION COORDINATOR CHEMISTRY COORDINATOR TECHNICAL SUPPORT SERVICES COORDINATOR G.E. ENGINEER (WHEN AVAILABLE)

DOC. & ADMIN. SERVICES COORDINATOR DECISION MAKER VYOPF 3524.02 OP 3524 Rev. 18 Page 1 of 3

INITIAL SITE ACCOUNTABILITY CHECK-IN FORM (Continued)

FOR TECHNICAL SUPPORT CENTER AND OPERATIONS SUPPORT CENTER RESPONSE PERSONNEL DATE:

GATEHOUSE SLOT NO. PLEASE PRINT NAME CLEARLY DEPT./POSITION "VYOPF3524.02 OP 3524 Rev. 18 Page 2 of 3

INITIAL SITE ACCOUNTABILITY CHECK-IN FORM (Continued)

FOR EMERGENCY RESPONSE PERSONNEL DATE:

GATEHOUSE SLOT NO. PLEASE PRINT NAME CLEARLY DEPT./POSITION VYOPF 3524.02 OP 3524 Rev. 18 Page 3 of 3

(

FIGURE 1 HALLWAY OUTSIDE CONTROL ROOM MAP I

CONTROL ROOM w U U 0 Ill iiiiiiiiiiiiiiiiiiiiiillillilliiiiiiiiiiill11111 x.Lx 4<

I "0JL (yV 7-.> IK, STAIR-:0 I&C SHOP WELL I I.

x x"

l r-l x4 x TURBINE DECK SIGN 0 OBSERVER CO 2 HAZARD DOOR ARROW INDICATES LOCATION OF SIGN I

Figure 1 OP 3524 Rev. 18 Page 1 of I

I FIGURE 2 TECHNICAL SUPPORT CENTER LAYOUT X SIGN SC0O2 HAZARD DOOR ARROW INDICATES LOCATION OF SIGN I SWING GATE Figure 2 OP 3524 Rev. 18 Page 1 of 1

FIGURE 3 OPERATIONS SUPPORT CENTER LAYOUT CLEAN CHEM LAB L x

CO2 HAZARD DOOR ARROW INDICATES LOCATION OF SIGN Figure 3 OP 3524 Rev. 18 Page 1 of 1

FIGURE 4 CONDENSER BAY - GROUND FLOOR ELEVATION 248' -6" NOTE: PRIMARY 1E IN REPORTED FIRE AREA, IF TENABLE. IF UNTENABLE, KP AT DI IN TURBINE HALL 0D- ALONG NORTH WALL.

0D- SCO 2 HAZARD DOOR ARROW INDICATES LOCATION OF SIGN Ns APPENDIX R WALL CPPRIMARY COMMAND POST "FC-pAT SECONDARY 0D- FD COMMAND POST 3HOUR FIRE DAMPER E VENTILATION Figure 4 OP 3524 Rev. 18 Page 1 of 1

VERMONT YANKEE NUCLEAR POWER STATION OPERATING PROCEDURE OP 3533 REVISION 5 POST ACCIDENT SAMPLING OF REACTOR COOLANT USE CLASSIFICATION: CONTINUOUS LPC Effective Affected Pages No. Date 4 .4

__ _ _I __ _ _ _ _I Implementation Statement: N/A Issue Date: 04/24/2002 OP 3533 Rev. 5 Page 1 of 6

TABLE OF CONTENTS PURPOSE ................................................................. 3 DISCUSSION ............................................................... 3 ATTACHMENTS ............................................................ 4 REFERENCES AND COMMITMENTS 4 PRECAUTIONS/LIMITATIONS ................................................. 5 P RE R EQ U ISITE S ...................................................................................................................................... 5 PROCEDURE 6 FINAL CONDITIONS ......................................................... 6 OP 3533 Rev. 5 Page 2 of 6

PURPOSE To outline the special procedures necessary to collect and handle samples, perform analyses and interpret results during post accident conditions.

Primary containment integrity issues are addressed in Technical Specifications section 3.7.

The use classification of this procedure is Continuous Use. However, each Appendix may be used individually and the entire procedure does not need to be in hand.

DISCUSSION Post accident sampling and analysis of reactor coolant is performed to provide information on the nature and extent of fuel damage, boron concentration following SLC injection and damage information on other in-core components such as control rods.

NUTREG-0737 requires a combined time of 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> or less for sampling and selected analyses from the time the decisions is made to collect a sample (TSC).

During post accident conditions, samples of reactor coolant may be highly radioactive.

Because of the high radiation levels, these samples require special handling. This procedure outlines the special handling required. The Chemistry Manager is assigned responsibility for implementation of this procedure.

In addition to the above concerns, conductivity readings of the reactor coolant may be useful during an accident. Readings can be obtained in the Control Room up to 10 Itmho/cm; if exceeded, conductivity readings may be taken at a later date at the discretion of the Chemistry Manager.

During certain postulated accidents, the availability of on-site counting equipment may be compromised. In these instances, post accident samples may be counted at alternative laboratories. A determination will be made by the Operations Support Center Coordinator's Assistant, in conjunction with the Radiological Assistant at the Emergency Operations Facility/Recovery Center, as to the most appropriate alternative laboratory facility to be used, based on existing conditions.

Tables 1, 2, 3 and 4 are provided for use by the OSC Coordinator's Assistant and the sampling and analysis teams in their evaluation of sampling conditions prior to obtaining the isotopic results after analysis. The information contained in these tables is generated from design basis accident assumptions and this fact should be taken into account in the use of these tables.

VYOPF 3533.02, Sample Accountability Log shall be utilized to track the location of emergency samples collected in accordance with this procedure.

OP 3533 Rev. 5 Page 3 of 6

In accordance with AP 6002, Preparing 50.59 Evaluations, the results of an Applicability Determination (AD) has determined that an AD is not required for future changes provided the procedure scope is not changed. The basis for this conclusion is that this document is an Emergency Implementing Procedure and is subject to 10CFR50.54(q) to determine if the changes decrease the effectiveness of the Emergency Plan and if they have the potential to affect our ability to meet the standards of 10CFR50.47(b) and the requirements of IOCFR50 Appendix E.

ATTACHMENTS

1. Figure 1 Post Accident Sampler
2. Figure 2 Post Accident Sampling System
3. VYOPF 3533.01 Reactor Coolant Post Accident Sampling Data/Analysis
4. VYOPF 3533.02 RV PASS Sample Accountability Log
5. Appendix A Reactor Coolant Sampling and Analysis - RB 303' Sample Sink
6. Appendix B Operation of the PASS to Sample Reactor Coolant
7. Appendix C Flushing and Restoring the PASS Following Use
8. Appendix D PASS Sample Analysis
9. Appendix E Deleted
10. Table 1 VY Radioactivity Concentration (ptCi/g) in Reactor Coolant Based on Design Basis Source Term (100/50/1)
11. Table 2 VY Dose Rates (R/hr) at Different Sampling Stations at Different Times After Shutdown
12. Table 3 VY Reactor Coolant and Containment Air Samples Dose Rates (RPhr) at Different Times After Shutdown
13. Table 4 VY Reactor Coolant and Containment Air Samples Dose Rates (R/hr) at Different Times after Shutdown REFERENCES AND COMMITMENTS
1. Technical Specifications and Site Documents
a. TS 3.7
b. UFSAR, Section 10.20
2. Codes, Standards, and Regulations
a. NUREG 0737, Sec. II.B.3
3. Commitments
a. None OP 3533 Rev. 5 Page 4 of 6
4. Supplemental References
a. EDCR 97-407 on FCV-39 and FCV-40
b. OP 0630, Water Chemistry
c. OP 0634, Operation of the Dionex Ion Chromatograph
d. DP 2630, Analytical Instrumentation
e. DP 2631, Radiochemical Instrumentation
f. OP 3506, Emergency Equipment Readiness Check
g. OP 4612, Sampling and Treatment of the Reactor Water System
h. AP 6807, Collection, Temporary Storage and Retrieval of QA Records PRECAUTIONS/LIMITATIONS
1. During sampling, communications should be maintained using either a portable radio or a Gai-Tronics.
2. High levels of Kr 88 may cause an interference with 113 identification. If this is suspected, purge sample if possible or count sample again at a later time.
3. Be aware of the radiological concerns and RWP requirements. Dose rates during sampling could increase rapidly.

PREREQUISITES

1. Post accident sampling equipment and tools, as needed.
2. Dose rate meter.
3. Evaluate with RP whether or not respiratory protection should be worn during sampling.
4. Evaluate with RP whether or not extremity dosimetry and high range pocket dosimeters should be worn during sampling.
5. Maximum Dose Rate and Dose commitment limits have been established, if needed, and should be adhered to for all Post Accident Sampling. Consult with the OSC Coordinator for specific instructions. Tables 3 and 4 should be consulted by the OSC Coordinator and sample team members for information concerning expected dose rates.

OP 3533 Rev. 5 Page 5 of 6

PROCEDURE A. Reactor Coolant Sampling and Analysis - RB 303' Sample Sink NOTE Sampling the reactor coolant at the RB 303' sample sink is only allowed if the Reactor Building is accessible with acceptable dose rates. If the RB is not accessible, sample the Reactor Coolant at the PASS panel per Appendix B of this procedure.

1. Utilize Appendix A to sample and analyze the Reactor Coolant via the RB 303' sample sink.

B. Operation of the PASS to Sample Reactor Coolant NOTE Chemistry Emergency Equipment Readiness Check is maintained per VYOPF 3506.05.

1. Utilize Appendix B to sample the Reactor Coolant via the PASS Panel.

C. Flushing and Restoring the PASS Following Use

1. Utilize Appendix C to flush and restore the PASS Panel following use.

D. PASS Sample Analysis I. Utilize Appendix D to analyze the PASS liquid and gas samples.

2. Make a copy of VYOPF 3533.01 and any printouts and retain for filing.
3. Submit original VYOPF 3533.01 and printouts to the OSC Coordinator or OSC Assistant.

FINAL CONDITIONS

1. Submit all forms for review and filing as per AP 6807.
2. Report all results to the OSC Coordinator or Assistant.
3. If any portion of the PASS Panel is found to be inoperable, submit a high priority Work Request.

OP 3533 Rev. 5 Page 6 of 6

(

FIGURE 1 POST ACCIDENT SAMPLER LIQUID SEPTUM NOTE: Broken line Indicales lubing on operaiing panel side.

Figure 1 OP 3533 Rev. 5 Page 1 of I

0 Ln C) cn C/)

( w 11 o w D£ om eN wm v ma nN

-C LAi

REACTOR COOLANT PASS DATA/ANALYSIS (For Use with Appendix B and D)

SAMPLE DATA: Date Time By DILUTION WATER VOL: ml GAS: High (Cyl B and C) OR Low Activity (Cyl B) (CIRCLE ONE)

I. GASEOUS Analyses from PASS RV System:

A. Gas Sample correction factor when diluting with carrier gas (CIRCLE ONE):

1. If App. B. Step F.3.a.l) is performed (high activity, Cyl B and C) CF=29 OR
2. If App. B. Step F.3.a.2) is performed (low activity, Cyl B only) CF=7.2 BASIS: Vol, + Volc Vol1 = 329 cc MassA = CF Volc = 1005 cc MassA = 46 g B. Hydrogen Concentration Input Needed: 1) Hydrogen concentration H2 conc (from analysis as decimal)
2) Gas Sample CF (from I.A) CF
1. Calculate H2 concentration in Reactor Coolant:

14* X H2conc X CF = Coolant Hydrogen Concentration in Coolant

"*14 = volume of offgas vial in cc X X = cc H2 per g. Rx Coolant

2. Attach chromatograph to this form.

C. Oxygen Concentration Input Needed: 1) Oxygen concentration 02conc (from analysis as decimal)

2) Gas Sample CF (from I.A) CF
1. Calculate 02 concentration in Reactor Coolant:

14* X 0 2 conc X CF = Coolant Oxygen Concentration in Coolant

"*14 = volume of offgas vial in cc X X _ = cc 02 per g. Rx Coolant

2. Attach chromatograph to this form.

VYOPF 3533.01 OP 3533 Rev. 5 Page 1 of 3

REACTOR COOLANT PASS DATA/ANALYSIS (Continued)

D. GASEOUS Isotopic Analysis Input Needed: 1) Gas Sample CF (from I.A) CF

1. Calculate volume of gas to be analyzed on MCA:

1 CF x 14 = cc (enter as MCA sample volume)

2. Attach isotopic printout to this form. Results are JtCi/cc of gas per gram of Rx coolant.

II. LIQUID Analyses from PASS RV System:

A. Calculate sample PASS Dilution factor (DFpass):

Input Needed: PASS Dilution Water volume VDIL ml VDIL DFPass 0.5 ml 0.5 DFpass B. Chloride Concentration NOTE A lab dilution may be required for this analysis due to the small initial sample size.

1. Calculate lab dilution factor (DFLab):

Final Volume (ml) (ml)

DFLab Aliquot (ml) (ml) DFLab

2. Analyze sample with IC.
3. Calculate chloride concentration in coolant:

Input needed: DFpass from II.A. and analysis result.

Analysis (ppb) X DFpass X DFL, = Coolant Cl- (ppb) ppb X X = ppb coolant C!

(analysis)

4. Attach any chromatograph to this form.

C. Boron Concentration NOTE A lab dilution may be required for this analysis due to the small initial sample size.

1. Calculate lab dilution factor (DFLab):

Final Volume (ml) (ml)

DFLab Aliquot (ml) (ml) DFLa

2. Analyze sample with ICP or Titration (circle one).

VYOPF 3533.01 OP 3533 Rev. 5 Page 2 of 3

REACTOR COOLANT PASS DATA/ANALYSIS (Continued)

3. Calculate BORON concentration in coolant:

Input needed: DFpass from II.A. and analysis result.

Analysis (ppb) X DFPass X DFLab = Coolant Boron (ppb) ppb X X = ppb coolant Boron (analysis)

4. Attach any printout to this form.

D. LIQUID Isotopic Analysis

1. Calculate corrected sample volume for MCA analysis entry:

Input needed: DFpass from II.A.

Aliquot (ml) - Corrected sample vol. for MCA entry DFpass (ml)

DFpass ml (corrected vol)

2. Attach any printout to this form.

Reviewed By:

OSC Coordinator's Assistant VYOPF 3533.01 OP 3533 Rev. 5 Page 3 of 3

RV PASS SAMPLE ACCOUNTABILITY LOG Sample Location Identification (Update after each movement) Date Time Initials VYOPF 3533.02 OP 3533 Rev. 5 Page 1 of 1

APPENDIX A REACTOR COOLANT SAMPLING AND ANALYSIS - RB 303' SAMPLE SINK NOTES

  • The following procedure assumes the Reactor Building is accessible, otherwise utilize Appendix B to operate the PASS panel.

Samples can be obtained from one of three points depending on what systems are in service. All sample points are at the Reactor Building sample sink. Refer to OP 4612 as necessary when sampling the Reactor Cleanup System. The sample points are:

Reactor Cleanup System Reactor Recirc Loop A RHR System CAUTION A maximum dose rate and dose commitment (review Tables 2 and

3) will be established for this sample prior to it being taken. Dose rates will be monitored during sampling and if it appears the dose commitment will be exceeded, the sampling will be terminated until further evaluation.

A. Sampling of the Reactor Water System (Recirc Loop)

1. Request the OSC to CLOSE/VERIFY CLOSED V10-199A & B.
2. Request the OSC to:
a. OPEN FCV-39 and FCV-40 isolation valves.
b. Notify Chemistry when valves are OPEN.

Appendix A OP 3533 Rev. 5 Page 1 of 4

APPENDIX A (Continued)

NOTE Monitor area dose rates with a dose rate meter occasionally during sampling. Be aware of changes due to sampling and valve manipulation.

3. OPERATE RSS-44B and RSS-60 to draw samples from the Reactor Building sample panel per Steps C, D and E below.

B. Sampling of the RHR System (RB 303' Sample Sink)

1. Request the OSC to OPEN V1O-198A or B.
2. OPERATE RSS-160/161 (common switch at sample panel) and RSS-96 to draw samples from the RHR System per Steps C, D and E below.

WARNING EXPECT THAT RADIATION LEVELS WILL INCREASE AT THE SAMPLE SINK DURING THE SAMPLE PURGING AND SAMPLING. DO NOT STAY AT THE SAMPLE SINK TO WAIT FOR THE SAMPLE LINES TO PURGE. SEEK A LOW RADIATION AREA IN WHICH TO WAIT.

C. Sample lines must be purged prior to sampling to ensure a representative sample is taken.

If the sample lines have not been running, they must be purged for 30 minutes at a rate of about 500 ml/minute prior to obtaining the sample.

D. After the sample line is flushed, if a dissolved oxygen analysis is requested to be run, use a CIIEMET or Orbisphere analyzer and run the analysis at the sample panel.

E. As dose rates permit, obtain about a 50 ml sample or less for further analysis in the Chemistry Lab.

Appendix A OP 3533 Rev. 5 Page 2 of 4

APPENDIX A (Continued)

F. If RHR or Reactor Cleanup System samples were taken, secure the sample point. If a Reactor Recirc Loop A sample was taken proceed as follows:

1. Request the OSC to CLOSE FCV-39.
2. Secure the sample flow path from recirc loop A as follows:
a. CLOSE RSS-60.
b. CLOSE RSS-44A.
3. Re-establish the RWCU influent sample point flow by THROTTLING OPEN RSS-44 as required.

G. Place the sample bottle in a plastic bag on carrier to maintain distance between you and the sample. Proceed promptly to the Chemistry Lab.

H. Once at the Chemistry Lab, place the sample behind a shield, as necessary, to reduce exposure.

I. If a RHR System sample was taken, notify the OSC that sampling is complete and to CLOSE root valve V10-198A(B) which ever was opened in Step B.

J. CLOSE FCV-160, FCV-161 and RSS-96 if opened in Step B.1.

K. If a chloride analysis is required, use OP 0634 with a 1 ml sample volume diluted to 30 ml.

L. If a pH analysis is required, insert the probe into the sample bottle while the bottle is still behind the shield and read the pH.

M. If an isotopic analysis is required, perform serial dilutions on 1 ml of the sample until standard counting techniques can be used. Do not exceed 20% dead time.

N. If a boron analysis is required, refer to OP 0630. Use a small sample volume, preferably 1 milliliter with dilutions as needed. Use ICP if available.

Appendix A OP 3533 Rev. 5 Page 3 of 4

APPENDIX A (Continued)

0. Report all results to the OSC Coordinator.

P. Log all samples on VYOPF 3533.02 for accountability.

Appendix A OP 3533 Rev. 5 Page 4 of 4

APPENDIX B OPERATION OF THE PASS TO SAMPLE REACTOR COOLANT WARNING FAILURE TO FOLLOW THESE PROCEDURES VERBATIM COULD RESULT IN DAMAGE TO THE SYSTEM OR PERSONNEL INJURY.

A. If the Gai-Tronics is unavailable, obtain a portable radio from the OSC.

B. Obtain the RV Post Accident Sample Kit from the Chemistry Lab.

C. Obtain a dose commitment from the OSC Coordinator for this sample prior to the start of sampling.

CAUTION Do not exceed 900 ml of dilution water.

D. Obtain the following from Chemistry supervision:

1. Dilution water volume (Enter here and on VYOPF 3533.01) ml
2. Information as to whether high noble gas activity is present.

HIGH / LOW (circle one here and on VYOPF 3533.01)

3. Request if a gas sample or gas stripping of the liquid sample is required.
4. PASS Diluted Liquid Sample volume desired:

ml Appendix B OP 3533 Rev. 5 Page 1 of 14

APPENDIX B (Continued)

E. Prerequisites for Sample Panel Set-Up

1. Perform the following:
a. Evacuate and label three off-gas vials, obtain one 2-dram vial, place in lead shield brick.
b. Obtain 2 11/2" syringes, 2 rubber septa, tongs, a flashlight, graduated cylinder and other sample containers as needed. (These items can be found in the RV Pass Sample Kit.)

CAUTION Breaker 11 on AC-DP-5 affects primary containment isolation (PCIV) valves PAS-102/104 (PASS SW-1) and valves PAS-101/103 (PASS SW-2). Failure to maintain positive control of the breaker while primary containment integrity is required by Technical Specifications (plant other than in cold shutdown) could violate LCO 3.7.A.2.

c. Request the OSC to:
1) CLOSE Breaker 11 on AC-DP-5 located in Turbine Building Switchgear Room.
2) POST an Operator at Breaker 11 while the breaker is closed.
3) Notify the OSC that PASS panel operation may affect calibrated jet pump flow indicator FI-2-3-87A/C at CRP 9-4 (jet pumps 1 and
11) from transmitter FT-2-3-63A/C.

Appendix B OP 3533 Rev. 5 Page 2 of 14

APPENDIX B (Continued)

d. Notify the OSC when you are ready to leave for sampling.
1) Verify with the OSC that the breaker is closed.

CAUTION If it appears maximum dose rate or dose commitment will be exceeded, leave high dose rate area and contact OSC Coordinator for further instructions.

2. Argon bottle is >500 psi with tank valve open.
3. Valves PAS-17 and PAS-18 (3-way valves) are positioned with the arrow pointing to the left.
4. CLOSE PAS-27.

WARNING PAS-112 MUST BE LEFT OPEN EXCEPT WHEN SPECIFIED HEREIN TO PRECLUDE CROSS-CONNECTION OF THE DEMIN WATER SYSTEM WITH THE REACTOR VESSEL.

a. Verify at the panel front, all other valves, with the exception of PAS-32 and PAS-1 12, are in the CLOSED position.
5. Install new rubber septa on sample valves PAS-39 and PAS-40.

Appendix B OP 3533 Rev. 5 Page 3 of 14

APPENDIX B (Continued)

CAUTION Do not exceed 900 ml of dilution water.

6. Place graduated cylinder under PAS-1 12 and OPERATE PAS-1 10 to obtain dilution water.
a. Fill the dilution water funnel with the recommended volume of demineralized water.

F. Sample Panel Operation Instruction

1. Evacuate cylinders B and C and gas septum.
a. START vacuum pump SW-5.
b. OPEN valves PAS-12, PAS-13, PAS-14 and PAS-15.
c. Run vacuum pump until approximately 0 psia reads on PI-2.
d. CLOSE valve PAS-13.
e. STOP vacuum pump SW-5.
f. Check PI-2 is stable to ensure no leaks.
g. CLOSE PAS-12 and PAS-14.

Appendix B OP 3533 Rev. 5 Page 4 of 14

APPENDIX B (Continued)

2. Obtaining a coolant sample in Cylinder A.

NOTES Obtain sample from Reactor Vessel by following instructions in Section a. below unless otherwise instructed.

To obtain sample from HP Heater (training use), go to Section b.

below.

a. Reactor Vessel Sampling (From JP-1 unless otherwise directed to sample JP-11)
1) OPEN SW-1 to open PAS-102/104 (inboard sample valves).
2) OPEN SW-2 to open PAS-101/103 (outboard sample valves).
3) OPEN SW-4 to open PAS-105/106 (purge valves).

CAUTION If there is no pressure indication on PI-1 when sampling, it's possible the line may be plugged. Obtain sample from other reactor sample point and observe pressure indication on PI-1.

4) OPEN valve PAS-2 (for JP-1) or valve PAS-3 (for JP- 11) and valves PAS-5, PAS-6 and PAS-8 on panel.

Appendix B OP 3533 Rev. 5 Page 5 of 14

APPENDIX B (Continued)

5) THROTTLE valve PAS-7 on panel to initiate flow to approximately 20 gph. Monitor pressure on PI-1 and flow on FI-109-36. Sample lines are now purging.

a) Record FI-109-36 flow:

gph CAUTION Retreat to low dose area during sample purge.

6) Perform the following calculation to determine purge time.

60 min 12 gallons (Purgetime in minutes) hr gal/hr(Flowrate on FI - 109 - 36)

7) After the line is purged:

a) CLOSE valves PAS-6 and PAS-5 to isolate sample cylinder A.

b) Record sample isolation time.

Time:

c) CLOSE SW-2, SW-1 and SW-4.

d) CLOSE valves PAS-2 or PAS-3.

e) CLOSE PAS-8.

Appendix B OP 3533 Rev. 5 Page 6 of 14

APPENDIX B (Continued)

8) Fill bath tank with cooling water via bath water funnel (takes approximately 6 liters):

a) Place cylinder under PAS- 112 and, b) OPERATE PAS-1 10 to obtain demin water.

c) Add -6 liters of water to the water bath funnel.

9) Proceed to section F.3 ("Gas Strip the Liquid Sample").
b. High Pressure Feedwater Sampling CAUTION Sampling of the high pressure feedwater via the pass panel will probably cause solids to make flow indicator FI-109-36 inoperable.

Permission of Chemistry supervision is required to proceed with feedwater sampling.

1) OPEN SW-4 (purge valves).
2) OPEN valves PAS-1, PAS-5, PAS-6 and PAS-8.
3) THROTTLE valve PAS-7 on panel to initiate flow, monitor pressure on PI-1 and flow on FI-109-36. Sample lines are now purging.

a) Record FI-109-36 flow:

gph Appendix B OP 3533 Rev. 5 Page 7 of 14

APPENDIX B (Continued)

CAUTION Retreat to low dose area during purge.

4) Perform the following calculation to determine purge time.

60 min 12 gallons (Purge time in minutes) hr gal/hr(Flowrate on Fl - 109 - 36)

5) After the line is purged:

a) CLOSE valves PAS-6 and PAS-5 to isolate sample Cylinder A.

b) Record sample isolation time.

Time:

c) CLOSE SW-4.

d) CLOSE valves PAS-1 and PAS-8.

6) Fill bath tank with approximately 6 liters of demin cooling water via the bath water funnel:

a) Place graduated cylinder under PAS-1 12 and, b) OPERATE PAS- 110 to obtain demin water.

c) Add -6 liters of water to the water bath funnel.

Appendix B OP 3533 Rev. 5 Page 8 of 14

APPENDIX B (Continued)

3. Gas Strip the Liquid Sample NOTE Gas stripping may be omitted if gas stripping or sampling is not required. If Step 3. is omitted, proceed to Step 4. to fill liquid grab sample assembly.
a. OPEN Valves PAS-10 and PAS-1 1 and observe pressure change on PI-2.

NOTE If pressure is >14.7 psi or if a high concentration of noble gases are assumed present, perform Step a. 1) to use cylinders B and C; if pressure is <14.7 psi perform Step a.2) to use cylinder B. If cylinders used are a change from initial instructions from supervision, be sure to change VYOPF 3533.01 data to reflect the change.

1) If high concentration of noble gas is assumed present, or if PI-2 shows a positive pressure (>14.7 psi), then:

a) OPEN valve PAS-16.

CAUTION The following step requires Argon gas to be purged very slowly through the liquid sample.

b) While observing PI-2, operate valve PAS-26 to bring PI-2 to approximately 64 psia.

c) CLOSE PAS-16.

Appendix B OP 3533 Rev. 5 Page 9 of 14

APPENDIX B (Continued)

NOTE This action will ensure good mixing of the internal volumes and will return the system to approximately one atmosphere (14.7 psia).

d) Open PAS-12 to re-expand Cylinder A and B into Cylinder C.

e) If the system is not at 14.7 psia, then OPEN PAS-16.

f) OPERATE PAS-26 and add argon until 14.7 psia is achieved.

g) CLOSE valves PAS-26 and PAS-16 and proceed to Step F.3.a.3) on page 10.

2) If noble gas concentration is not significant or PI-2 remains in vacuum (<14.7 psi), then:

a) OPEN PAS-16.

b) OPERATE PAS-26 to very slowly purge argon gas through the sample and bring PI-2 up to one atmosphere (14.7 psia).

c) CLOSE PAS-16.

3) Perform the following:

a) OPEN valve PAS-14 and PAS-39 and extract 1 ml gas samples with a 1'" syringe at the gas septum.

b) Inject each 1 ml sample into three separate pre-labeled 14 ml vials (e.g., #1, 2, 3) and place vials in shielded container.

Appendix B OP 3533 Rev. 5 Page 10 of 14

APPENDIX B (Continued)

4) CLOSE valves PAS-14, PAS-39, PAS-15, PAS-I 1 and PAS-10.
5) If sample was gas stripped (Step 3.a.1)), CLOSE PAS-12.
6) Return to Chemistry Lab with gas sample or continue with sampling.
7) Enter sample data on VYOPF 3533.02 for accountability of samples.
4. Fill liquid grab sample assembly.
a. OPEN/CHECK OPEN PAS- 11, PAS-10 and PAS-15.
b. OPEN PAS-16.
c. OPERATE PAS-26 to achieve 64 psi on pressure gauge PI-2.
d. CLOSE PAS-16.
e. OPEN PAS-21.
f. POSITION PAS-18 with the arrow to the RIGHT.
g. After 30 seconds, POSITION PAS-18 with the arrow to the LEFT.
h. CLOSE PAS-21.
i. OPEN PAS-19 and PAS-16. Note slight pressure drop on PI-2.

Appendix B OP 3533 Rev. 5 Page 11 of 14

APPENDIX B (Continued)

j. Allow one minute before proceeding for the grab sample assembly to fill.
k. POSITION PAS-17 and PAS-18 to their mid positions (ARROW DOWN).
1. POSITION the grab sample assembly valves PAS-17 and PAS-18 to the RIGHT.
m. OPEN SW-4 and PAS-8.
n. OPEN PAS-6, PAS-7 and PAS-12 to vent the pressure in Cylinders A, B, and C to the Torus.
o. When the pressure has equalized as indicated on PI-2, CLOSE PAS-6, PAS-7, PAS-8, PAS-10, PAS-1 1, PAS-12, PAS-16, PAS-19, and PAS-15.
p. CLOSE SW-4.
q. Request the OSC to OPEN Breaker 11.

Appendix B OP 3533 Rev. 5 Page 12 of 14

APPENDIX B (Continued)

5. Dilute sample and remove for analysis.

CAUTION The following drain-down step requires approximately 5 minutes to occur. During this evolution, retreat to a low dose area to reduce exposure.

a. OPEN valves PAS-21 and PAS-24. Allow the dilution water funnel to drain for 1 minute after water is no longer visible in the funnel.
b. CLOSE valve PAS-24.

NOTE This action will blow argon gas into the line and push all the water into Cylinder D. Read Steps 5.c through 5.f BEFORE PROCEEDING.

c. CRACK OPEN valve PAS-25 approximately 1/4 turn.
d. Allow the argon gas to bubble slowly through Cylinder D for approximately 30 seconds.
e. SLOWLY CLOSE valve PAS-21 and pressurize Cylinder D with argon to approximately 5 psig on PI-3.

AND IMMEDIATELY

f. CLOSE valve PAS-25.
g. OPEN valves PAS-8, PAS-22 and PAS-20.

Appendix B OP 3533 Rev. 5 Page 13 of 14

APPENDIX B (Continued)

CAUTION

  • In the following step PAS-23 should be opened only long enough to verify sample flow and ensure that sample is at the sample valves. If the inside edge of tygon tubing is not visible, then it has water in it. Do not allow sample to run out.

This action will allow the diluted sample to flow from Cylinder D through the liquid septum.

Be aware of area dose rate changes.

h. OPEN valve PAS-23 and observe sample flow at liquid septum/sightglass.

Use flashlight if needed.

i. As soon as flow has been observed, CLOSE PAS-23.
j. OPEN valve PAS-21 to release any remaining argon overpressure on PI-3.

CAUTION When using liquid sample valves, tongs should be used to hold sample container. Monitor dose rates on sample vial during filling.

k. To obtain a sample:
1) OPERATE sample valve PAS-40 to extract a liquid sample with a syringe (<5 ml) or,
2) OPERATE valve PAS-35 for larger volumes.
1. Place appropriate samples in lead shielding and transport to the Chemistry Lab for analysis.
1) Enter sample information on VYOPF 3533.02 to ensure accountability.

Appendix B OP 3533 Rev. 5 Page 14 of 14

APPENDIX C FLUSHING AND RESTORING THE PASS FOLLOWING USE CAUTION Breaker 11 on AC-DP-5 affects primary containment isolation (PCIV) valves PAS-102/104 (PASS SW-1) and valves PAS-101/103 (PASS SW-2). Failure to maintain positive control of the breaker while primary containment integrity is required by Technical Specifications (plant other than in cold shutdown) could violate LCO 3.7.A.2.

A. Request the OSC to:

1. CLOSE Breaker 11 on AC-DP-5 located in the Switchgear Room.
2. POST an Operator at Breaker 11 while the breaker is energized.

B. CLOSE or check closed valves PAS-21, PAS-22, and PAS-35 or PAS-40.

C. To repressurize and drain Cylinder D, perform the following:

1. OPEN SW-4.
2. OPERATE valve PAS-25 until PI-3 reads approximately 25 psig.
3. OPEN valves PAS-23 and PAS-22.
4. When flow has ceased through the sightglass, then CLOSE valves PAS-23 and PAS-22.
5. Repeat Steps 2 through 4 until no more liquid remains in Cylinder D.

Appendix C OP 3533 Rev. 5 Page 1 of 5

APPENDIX C (Continued)

D. OPERATE PAS-1 10 to obtain water from PAS-1 12.

E. Refill the dilution water funnel with 900 ml of water.

F. OPEN valves PAS-21 and PAS-24.

G. Allow the flush water in the funnel to gravity drain into Cylinder D for 1 minute after it is no longer visible in the funnel.

H. CLOSE valves PAS-24 and PAS-21.

I. CRACK OPEN valve PAS-25 to allow Cylinder D to pressurize to 25 psig on PI-3.

J. CLOSE valve PAS-25.

K. OPEN valve PAS-23 and PAS-22 to allow Cylinder D to drain.

L. CLOSE valves PAS-22 and PAS-23.

M. Repeat Steps I through L as necessary to ensure that no liquid remains in Cylinder D.

N. CYCLE PAS-21 open and closed to bleed off any residual pressure indicated on PI-3.

0. POSITION grab sample valves PAS-17 and PAS-18 so that the arrow points to the LEFT.

Appendix C OP 3533 Rev. 5 Page 2 of 5

APPENDIX C (Continued)

P. OPEN SW-2 and SW-3 (outboard sample and flush valves).

Q. CLOSE valves PAS-112 and PAS-20.

R. OPEN valves PAS-110, PAS-111, PAS-2 (JP-1) or PAS-3 (JP-11), PAS-5, PAS-6 and THROTTLE PAS-7 while MONITORING FI-109-36 (do not exceed 25 gph).

S. After 5 minutes, CLOSE valves PAS-2 or PAS-3 and PAS- 111.

T. CLOSE SW-3 and SW-2.

CAUTION For steps U. and AA. below, throttle PAS-7 so as not to exceed 25 gph on FI-109-36.

U. CLOSE PAS-7.

V. OPEN valves PAS-4, PAS-16 and PAS-19.

W. THROTTLE PAS-20 to achieve 15 gph on FI-109-36.

X. THROTTLE PAS-7 to achieve 25 gph on FI-109-36.

Y. After 1 minute, CLOSE valve PAS-16.

Appendix C OP 3533 Rev. 5 Page 3 of 5

APPENDIX C (Continued)

Z. FULLY OPEN PAS-20 and THROTTLE PAS-7 as needed to maintain 25 gph on FI-109-36.

AA. After 5 minutes, CLOSE valves PAS-4, PAS-5, PAS-6 and PAS-7.

BB. OPEN PAS-26 to blow water out of the grab sample assembly.

CC. After approximately 30 seconds, CLOSE valves PAS-26, PAS-19, PAS-20 and PAS-8.

DD. CLOSE SW-4.

EE. OPEN valves PAS-11, PAS-12, PAS-13, PAS-14 and PAS-15.

FF. Turn SW-5 ON to start vacuum pump to evacuate Cylinders B and C.

GG. Remove gas septum port, OPEN valve PAS-39 and allow air to enter the evacuated systems for 1 minute as vacuum pump is running.

HH. Turn SW-5 OFF to stop vacuum pump.

II. CLOSE valve PAS-39 and reinstall gas septum cover.

JJ. CLOSE valves PAS-1 1, PAS-12, PAS-13, PAS-14 and PAS-15.

KK. OPEN valve PAS-27 to allow bath water to gravity drain.

LL. CLOSE PAS-110.

MM. OPEN PAS-112.

Appendix C OP 3533 Rev. 5 Page 4 of 5

APPENDIX C (Continued)

NOTE The Reactor Coolant Sampling Panel is now lined up to repeat sampling procedure as necessary.

WARNING ENSURE THAT RADIATION LEVELS ALLOW FOR PERSONNEL ACCESS BEHIND THE PASS PANEL AND LIQUID RADIATION LEVELS ALLOW FOR PERFORMING THE NEXT STEP. MONITOR DOSE RATES DURING MOISTURE SEPARATOR DRAINING.

NN. OPEN valve PAS-38 and drain water from the vacuum pump moisture separator into a suitable container.

00. CLOSE PAS-38.

PP. Request the OSC to OPEN Breaker 11 on AC-DP-5.

QQ. CLOSE argon tank valve.

Appendix C OP 3533 Rev. 5 Page 5 of 5

APPENDIX D PASS SAMPLE ANALYSIS A. Gas samples NOTE Perform hydrogen and oxygen analysis on the gas chromatograph according to DP 2630. Be aware of carrier gas requirements for specific analysis.

1. Adjust vial pressure to zero by injecting approximately 13 ml of the appropriate GC carrier gas into each vial collected. Indicate gas used on vial.
2. Hydrogen and oxygen analyses will be performed as requested by following the gas chromatograph procedure in DP 2630.
a. Complete VYOPF 3533.01,Section I.B and I.C.
3. Isotopic analysis
a. Obtain 1 ml of sample from a gas sample vial and inject into an evacuated 14 ml vial.
b. Analyze gas vial as a general sample using DP 2631 or steps outlined in Section C (High Activity) using sample volume from VYOPF 3533.01, Step I.D. Up to 20% dead time is allowed.

Appendix D OP 3533 Rev. 5 Page 1 of 5

APPENDIX D (Continued)

B. Liquid samples

1. Chloride analysis
a. Analyze sample for chloride content per OP 0634.
b. Complete VYOPF 3533.01,Section II.B.
2. Boron analysis
a. Analyze sample for Boron using the Lab ICP using the "50B" method file or by titration per DP 2630.
b. Complete VYOPF 3533.01,Section II.C.
3. Isotopic analysis
a. Using a syringe (shielded if high dose rates exist), obtain 1 ml of sample (more may be used if dose rates allow) and inject into a known geometry container. Fill container with DI water. Record aliquot volume on VYOPF 3533.01,Section II.
b. Analyze liquid sample as a general sample per DP 2631 or steps outlined in Section C to obtain activity in ýtCi/ml using corrected sample volume from VYOPF 3533.01, Step II.D. Up to 20% dead time is allowed.
c. Complete VYOPF 3533.01,Section II.D.

Appendix D OP 3533 Rev. 5 Page 2 of 5

APPENDIX D (Continued)

C. Counting Techniques for Highly Radioactive Samples NOTE If sample size or dilutions can be used to permit a sample to be counted by conventional techniques, this should be done. If this is not possible, the following techniques can be used.

1. Use of the MCA at extended distances.

NOTE If general area dose rate in the Counting Room exceeds 5 mR/hr, the use of the MCA at extended distance with shield top removed is prohibited (LAI-417B).

a. Open the shield top from the 10% germanium detector.
b. Using rod and holder, suspend the sample above the detector at a distance that will give a dead time of <20% (must be >1 ft.).
c. Measure the distance from the sample to the top of the detector.
d. Count the sample using a 2" filter paper geometry efficiency.

Appendix D OP 3533 Rev. 5 Page 3 of 5

APPENDIX D (Continued)

NOTE Step e. or f. below may be used to calculate elevated sample activity.

e. Analyze the sample using the MCA selection for "PASS Elevated Samples" OR
f. Calculate the sample activity as follows:

,Ci/ml = (X) (d&) (17)

NOTE The below correction factor must be re-evaluated if the detector geometry for the filter paper with a 2" shelf is modified at the time the efficiency calibration (DP 2631) is performed.

where: X = ýtCi/ml from isotopic printout d = distance in ft. measured in B.l.c above 17 = correction factor pCi/ml Verified by:

2. Use of portable instruments.

NOTE If neither conventional methods or those in Step C. 1 can be used, a portable gamma survey meter can be used to determine sample activities.

a. If the MCA is available, it can be used to give a qualitative measure of major isotopes. If it is not available, an assumption must be made based on what is known about the sample at the time.
b. Measure the radiation level of the sample at 1 meter.

Appendix D OP 3533 Rev. 5 Page 4 of 5

APPENDIX D (Continued)

c. Calculate the sample activity as follows:

_m (R/hr at 1 meter)(10 6) p'.Ci/ml = (T) (V)

Verified by:

where: 106 = [tCi/Ci V = sample volume (milliliters)

T = R/hr @ 1 meter/Ci Values for T (R/hr @ I meter/Ci)

Time Degassed Liquid* Containment Air**

1 hr 0.60 0.41 4 hr 0.43 0.28 8 hr 0.35 0.22 12 hr 0.31 0.18 24 hr 0.26 0.14 Assumed mix of 0% of core noble gas inventory, 50% of core halogen inventory and 1% of core solids inventory. For convenience, the mix ratio is expressed as 00/50/1 (% NOBLE GAS/% HALOGENS/%

SOLIDS)

    • Assumed mix of 100/50/1.

Appendix D OP 3533 Rev. 5 Page 5 of 5

TABLE 1 VY - RADIOACTIVITY CONCENTRATION (RCi/g) IN REACTOR COOLANT BASED ON DESIGN BASIS SOURCE TERM (100/50/1)

Nuclide 1 Hour 8 Hours 24 Hours Kr-85m 6. 5E+04 2 .2E+04 1 .8E+03 Kr-85 2 . 5E+03 2 .5E+03 2 .5E+03 Kr-87 8. 5E+04 1. 9E+03 3. E-01 Kr-88 1. 6E+05 2. 9E+04 5. 8E+02 Xe-133 5. 3E+05 5. 3E+05 5 . 1E+05 Xe-135m 7. 5E+04 3. 5E+04 6 .6E+03 Xe-135 1. 9E+05 2. 4E+05 1 .3E+05 1-131 1.3E+05 1.3E+05 1 .2E+05 1-132 1. 9E+05 1. 8E+05 1. 6E+05 1-133 2. 7E+05 2 1E+05 1. 3E+05 1-134 2 IE+05 1. 8E+03 6. 9E-03 1-135 2. 3E+05 1. 1E+05 2 .E+04 Sr-90 1. 9E+02 1. 9E+02 1. 9E+02 Sr-91 3. 2E+03 1. 9E+03 5 .9E+02 Sr-92 2. 8E+03 4. 7E+02 7. 9E+00 Y-91 3. 5E+03 3. 5E+03 3 .5E+03 Y-93 4. OE+03 2. 5E+03 8. 2E+02 Zr-95 4. 6E+03 4. 5E+03 4.5E+03 Nb-97 4. 5E+03 3 . 5E+03 1.7E+03 Ru-103 3. 9E+03 3 .8E+03 3 .8E+03 Cs-134 2. 6E+02 2. 6E+02 2.6E+02 Cs-136 9 .3E+01 9 1E+01 8.8E+01 Cs-137 2. 6E+02 2. 6E+02 2.6E+02 Ba- 14 0 4. 7E+03 4. 7E+03 4.5E+03 La-140 4. 9E+03 4. 9E+03 4.8E+03 Ce-141 4. 5E+03 4. 5E+03 4.4E+03 Ce-143 4. 1E+03 3 .6E+03 2 .6E+03 Eu-156 2. 4E+02 2 .4E+02 2 . 3E+02 Np -238 4. 1E+02 3. 7E+02 3 . OE+02 Np-239 5. 1E+04 4. 7E+04 3 . 9E+04 TOTAL (above) 2. 2E+06 1 6E+06 1. 1E+06 TOTAL (including others) 2.4E+06 1. 6E+06 1 .2E+06 Table 1 OP 3533 Rev. 5 Page 1 of 2

TABLE 1 (Continued)

Assumptions and

References:

1. Design Basis Source Term 100% NG, 50% Iodines and 1% Solids.
2. ORIGEN2 Calculation (VY Core Damage Assessment Methodology).
3. NSSS isolated liquid mass = 1.615E+08 g (VY Core Damage Assessment Methodology).

Table 1 OP 3533 Rev. 5 Page 2 of 2

TABLE 2 VY - RADIOACTIVITY CONCENTRATION ([tCi/cm3 ) IN CONTAINMENT ATMOSPHERE AFTER SHUTDOWN BASED ON DESIGN BASIS SOURCE TERM (100/25/0)

Nuclide 1 Hour 8 Hours 24 Hours Kr-85m 1. 6E+03 5 .3E+02 4. 4E+01 Kr-85 5. 9E+01 5. 9E+01 5. 9E+01 Kr-87 2 . OE+03 4. 5E+01 7 .3E-03 Kr-88 3 .8E+03 6. 9E+02 1. 4E+01 Xe-133 1.3E+04 1. 3E+04 1. 2E+04 Xe-135m 1. 8E+03 8. 4E+02 1. 6E+02 Xe-135 4. 5E+03 5. 7E+03 3 .2E+03 1-131 1. 6E+03 1. 5E+03 1. 5E+03 1-132 2 .3E+03 2 .2E+03 1. 9E+03 1-133 3 .2E+03 2. 6E+03 1. 5E+03 1-134 2 .5E+03 2 .2E+01 8 .2E-05 1-135 2 . 7E+03 1. 3E+03 2 .5E+02 TOTAL (above) 3. 9E+04 2. 8E+04 2 .lE+04 Assumptions and

References:

1. ORIGEN2 Calculation (Core Damage Assessment Methodology).
2. Containment Air Volume = 6.742E+09cm3 (Core Damage Assessment Methodology).
3. Design Basis Source Term: 100% NG and 25% Iodines.

Table 2 OP 3533 Rev. 5 Page 1 of 1

TABLE 3 VY - DOSE RATES (R/hr) AT DIFFERENT SAMPLING STATIONS AT DIFFERENT TIMES AFTER SHUTDOWNc Post-Accident Containment Air Vent Stack Time (hr) Sampling Station Sampling Station Sampling Room 1 4. 5E-Ia 6. 0E+0a 1.0E+Ob 3 1. 9E-1 2 .6E+O 5.lE-1 8 5. 4E-02 1. IE+O 2.2E-1 24 6. 8E-03 4.7E-1 5.8E-02 72 4. IE-03 3. 1E-1 1.8E-02 NOTES:

a Per Calculation VYC-70.

b Per Calculation VYC-83, Vent Stack Only.

C Dose Rates at other decay times are based on Table 11 of EDS Nuclear, Report No. 02-0180-1126, December 29, 1979.

Table 3 OP 3533 Rev. 5 Page 1 of 1

TABLE 4 VY - REACTOR COOLANT AND CONTAINMENT AIR SAMPLES DOSE RATES (R/hr) AT DIFFERENT TIMES AFTER SHUTDOWNa 1cm3 Undiluted Degassed icm 3 Dissolved Gas From 1cm 1cm3 Undiluted Time (hr) Reactor Coolant Pressurized Reactor Coolant Containment Air Sample 1 2.OE+Ob 8. 9Elb 1.6E-02b 3 1.2E+O 3 .9E-1 7. OE-03 8 6.4E-1 1.6E-1 2 . 9E-03 24 3.2E-1 6. 9E-02 1.3E-03 72 1.5E-1 4. 6E-02 8. 3E-04 NOTES:

a All dose rates are calculated at 1m away from the source. Dose rates at other decay times are based on Table 11 of EDS Nuclear, Report No.

02-0180-1026, December 29, 1979.

Per VYC-70, no shielding, no dilution.

Table 4 OP 3533 Rev. 5 Page 1 of 1