Information Notice 2007-29, Temporary Scaffolding Affects Operability of Safety-Related Equipment
ML072150614 | |
Person / Time | |
---|---|
Site: | Beaver Valley, Millstone, Monticello, Oyster Creek, Turkey Point |
Issue date: | 09/17/2007 |
From: | Michael Case NRC/NRR/ADRO/DPR |
To: | |
References | |
IN-07-029 | |
Download: ML072150614 (5) | |
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, DC 20555-0001
September 17, 2007
NRC INFORMATION NOTICE 2007-29:
TEMPORARY SCAFFOLDING AFFECTS
OPERABILITY OF SAFETY-RELATED
EQUIPMENT
ADDRESSEES
All holders of operating licenses for nuclear power reactors, except those who have
permanently ceased operations and have certified that fuel has been permanently removed
from the reactor vessel.
PURPOSE
The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice (IN) to alert
licensees about recent operating experience at nuclear power facilities where temporary
scaffolding installed to support maintenance activity has affected the operability of safety- related equipment. The NRC expects that recipients will review the information for applicability
to their facilities and consider actions, as appropriate, to avoid similar problems. Suggestions
contained in this IN are not NRC requirements; therefore, no specific action or written response
is required.
DESCRIPTION OF CIRCUMSTANCES
Several recent events have occurred at nuclear power facilities where temporary scaffolding
that has affected the operability of safety-related equipment. Specific instances include the
following:
Millstone Power Station Unit 2
Scaffolding was constructed adjacent to a main steam isolation valve (MSIV) to support
replacing the operating cylinder during the upcoming refueling outage. Supplementary
instructions were provided for building the scaffolding close to safety-related equipment, and a
post-installation inspection was performed. Approximately forty days later during a MSIV stroke
time test, the MSIV was determined to be inoperable due to scaffold decking interfering with the
travel of the valve actuator preventing the MSIV from fully closing.
Also at Millstone Unit 2, temporary scaffolding was inadvertently placed on top of a blowout
panel in the turbine-driven auxiliary feedwater pump room ceiling. The impact of this oversight
could have resulted in all three auxiliary feedwater pumps becoming inoperable during
a high energy line break. (NRC Integrated Inspection Report 05000336/2006005 and
05000423/2006005, January 30, 2007, Agencywide Documents Access and Management
System (ADAMS) Accession No. ML070300143)
Beaver Valley Power Station Unit 2
The licensee discovered that scaffolding constructed around the A and B MSIVs two days
earlier had seismic bracing located in the path of MSIV travel. This condition could have
potentially prevented the MSIVs from fully closing. (NRC Integrated Inspection Report 05000334/2006005 and 05000412/2006005, January 24, 2007, ADAMS Accession No.
Oyster Creek Generating Station
NRC inspectors identified a scaffold pole in contact with piping associated with the scram
discharge volume. This condition was not consistent with the licensees scaffold procedure
which states that scaffold shall not be in contact with safety-related piping. During the
subsequent disassembly of this scaffolding, a scaffold coupler (knuckle) fell and damaged an
oiler reservoir for the B core spray booster pump, rendering the pump inoperable for
approximately twelve hours to effect repair. (NRC Integrated Inspection Report 05000219/2006003, July 13, 2006, ADAMS Accession No. ML061950007)
Monticello Nuclear Generating Plant
NRC inspectors identified a scaffold that was in contact with safety-related piping for the
residual heat removal system. This condition was not consistent with the licensees scaffolding
procedure that specifies maintaining a clearance of greater than 2 inches from safety-related
equipment. During the extent of condition review, the licensee found two scaffolds erected in
the intake structure that were less than 2 inches away from fire protection piping. The licensee
determined that all three scaffolds were originally constructed with the required 2-inch
separation, but the separation became less than 2 inches during use of the scaffolds. The
Licensee revised their scaffold control procedure to provide additional guidance on the need for
adequate bracing to prevent scaffolding from moving during use. (NRC Integrated Inspection
Report 05000263/2006002, April 26, 2006, ADAMS Accession No. ML061160574)
Turkey Point Nuclear Plant
NRC inspectors identified two examples where scaffolding was not installed in accordance with
scaffold control procedures. The licensee requires that installed scaffolding be a minimum of 2 inches from fragile items, including but not limited to valves and instrument lines. The first
example involved scaffolding erected within 2 inches of the Unit 3 refueling water storage tank
suction valves. The second example involved scaffolding that was in contact with an
emergency diesel generator starting air system pipe hanger. The licensees corrective actions
included revising their scaffolding procedure to establish a minimum clearance requirement of 2 inches for all plant equipment and to emphasize the requirement to perform an engineering
evaluation when the procedural requirements could not be met. (NRC Problem Identification
and Resolution Inspection Report 050000250/2006007 and 05000251/2006007, March 17,
2006, ADAMS Accession No. ML060760175)
BACKGROUND
Systems and components that are required to be operable by technical specifications or by the
fire protection program can be rendered inoperable by improperly installed scaffolding.
Technical specification administrative requirements and Title 10 of the Code of Federal
Regulations (10 CFR) Part 50, Appendix B, Criterion V, Instructions, Procedures and
Drawings, require procedural controls for certain activities that would include scaffolding
controls.
In addition, NRC Regulatory Guide 1.187, Guidance for Implementation of 10 CFR 50.59, Changes, Tests, and Experiments, endorses the Nuclear Energy Institute (NEI) document NEI
96-07, Guidelines for 10 CFR 50.59 Evaluations, Revision 1. NEI 96-07 states that:
temporary changes to the facility such as the installation of scaffolding that are not associated
with maintenance are subject to 10 CFR 50.59 in the same manner as permanent changes, to
determine if prior NRC approval is required; the risk impacts of temporary changes associated
with maintenance activities (i.e., temporary alterations) should be assessed and managed in
accordance with 10 CFR 50.65(a)(4), and associated guidance; and applying 10 CFR 50.59 to
such activities is not required provided that temporary alterations are not in effect longer than
90 days at power, and affected structure, system or components are restored to their normal, as-designed condition at the conclusion of the maintenance activity.
DISCUSSION
The above events highlight the need to adequately establish and implement procedural controls
so that scaffolding does not adversely affect safety-related equipment. It is important that
scaffolding: does not interfere with the operation of equipment such as valves and ventilation
dampers; is properly braced to prevent displacement or sliding during use or during a seismic
event; is not directly attached to instrument racks or piping supports; does not block access to
fire protection equipment such as hose reels, fire extinguishers, and fire doors; and materials
that are non-fire retardant are accounted for as transient combustibles. At some facilities, structures such as floor grating and scaffolding are required to be maintained greater than
some minimum distance from the containment wall to ensure that the integrity of the
containment is maintained during a design basis or seismic event.
CONTACT
This information notice does not require any specific action or written response. Please direct
any questions about this matter to the technical contacts listed below or to the appropriate
Office of Nuclear Reactor Regulation (NRR) project manager.
/RA by TQuay for/
Michael J. Case, Director
Division of Policy and Rulemaking
Office of Nuclear Reactor Regulation
Technical Contacts: Stephen Pannier, NRR
Heather Jones, Region I
(301) 415-4083
(610) 337-5390
E-mail: sjp@nrc.gov
E-mail: hmj@nrc.gov
Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov, under Electronic Reading Room/Document Collections.
CONTACT
This information notice does not require any specific action or written response. Please direct
any questions about this matter to the technical contacts listed below or to the appropriate
Office of Nuclear Reactor Regulation (NRR) project manager.
/RA by TQuay for/
Michael J. Case, Director
Division of Policy and Rulemaking
Office of Nuclear Reactor Regulation
Technical Contacts: Stephen Pannier, NRR
Heather Jones, Region I
(301) 415-4083
(610) 337-5390
E-mail: sjp@nrc.gov
E-mail: hmj@nrc.gov
Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov, under Electronic Reading Room/Document Collections.
Distribution: IN Reading File
ADAMS Accession Number: ML072150614 OFFICE
IOEB:DIRS
IOEB:DIRS
TECH EDITOR
TL:IOEB:DIRS
BC:IOEB:DIRS
NAME
HJones
SPannier
LCulp by email
JThorp
MRoss-Lee
DATE
8/17/2007
8/27/2007
8/10/2007
8/24/2007
8/28/2007 OFFICE
D:DIRS
PGCB:DPR
PGCB:DPR
BC:PGCB:DPR
D:DPR
NAME
FBrown
CHawes
DBeaulieu
MMurphy
MCase
DATE
8/29/07
09/12/07
09/12/07
09/17/07
09/17/07 OFFICIAL RECORD COPY