IE Insp Repts 50-546/79-17 & 50-547/79-17 on 790828-31.No Noncompliance Noted.Major Areas Inspected:Auxiliary Bldg, Containment Storage Areas & Compliance w/790807 Stop Work Order
ML19254F319
Person / Time
Site: Marble Hill
Issue date: 09/26/1979
From: Clint Jones, Williams C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19254F316 List:
References
50-546-79-17, 50-547-79-17, NUDOCS 7911090033
Download: ML19254F319 (2)


Text

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

.

Report No. 50-546/79-17; 50-547/79-17 Docket No. 50-546; 50-547 License No. CPPR-170; CPPR-171 Licensee:

Public Service of Indiana 1000 East Main Street Plainfield, IN 46168 Facility Name: Marble Hill Generating Station, Units 1 and 2 Inspection At: Marble Hill Site (Jefferson County, Indiana)

Inspection Conducted: August 28-31, 1979

_,g,/.

> r tu. ~ ~

Af b / /h,'

Inspector:[v.C.E. Jones --

o

~

.

y (-(, q,M C s %~-

Approved By:

C. C. Williams, Chief

? / c /7 0 Projects Section 2

/'

/

Inspection Suavaary Inspection on August 28-31, 19i9 (Report No. 50-546/79-17; 50-547/79-17)

Areas Inspected:

Surveillance of the Auxiliary Building, Unit 1 and Unit 2 containments, storage areas and miscellaneous areas to rify that activities in progress complied with the stop work order issued August 7, 1979. This inspection involved a total of 26 inspector-hours on site by one NRC inspector.

3esults: No items of noncompliance or deviations were identified.

1303 358

.

I 7911090 O b

.

DETAILS

Persons Contacted

.

Public Service of Indiana (PSI)

S. W. Shields, Vice President Electrical Systems R. M. Brown, Construction Project Superintendent L. A. Crews, Vice President Construction

  • R. Wooley, Assistant Site Manager F. R. Hodges, QA Manager
  • T. L. McLarty, QA Construction Supervisor S. K. Farlow, Construction Engineer W. G. Minick, QC Inspector D. L. Sutter, QC Engineer, Civil Hartford Steam Boiler and Insurance Company W. C. Rice, AI for PSI W. Burden, AI for Cherne Contracting Corporation
  • Denotes those persons present at the exit meeting.

Functional or Program Areas Inspected 1.

Construction Activities Surveillance of construction activities indicated that work in all Category 1 areas i.e., safety related work, had been terminated except for the protection of installed or in place components.

Work in other portions of the plant such as the turbine building and cooling towers is continuing but at a reduced rate.

Exit Meeting The inspector met with those persons (denoted in the Persons Contacted paragraph) at the conclusion of the inspection on August 31, 1979. The inspector summarized the scope and findings of the inspection.