IR 05000528/2025001

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000528/2025001 and 05000529/2025001 and 05000530/2025001
ML25128A015
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 05/12/2025
From: John Dixon
NRC/RGN-IV/DORS/PBD
To: Heflin A
Arizona Public Service Co
References
IR 2025001
Download: ML25128A015 (1)


Text

May 12, 2025

SUBJECT:

PALO VERDE NUCLEAR GENERATING STATION - INTEGRATED INSPECTION REPORT 05000528/2025001 AND 05000529/2025001 AND 05000530/2025001

Dear Adam Heflin:

On March 31, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Palo Verde Nuclear Generating Station. On April 22, 2025, the NRC inspectors discussed the results of this inspection with Jenn Spina, Vice President, Nuclear Regulatory and Oversight, and other members of your staff. The results of this inspection are documented in the enclosed report.

No NRC-identified or self-revealing findings were identified during this inspection.

A licensee-identified violation which was determined to be of very low safety significance is documented in this report. We are treating this violation as a non-cited violation (NCV)

consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Palo Verde Nuclear Generating Station. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, John L. Dixon, Jr., Chief Reactor Projects Branch D Division of Operating Reactor Safety Docket Nos. 05000528; 05000529; 05000530 License Nos. NPF-41; NPF-51; NPF-74

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000528; 05000529; 05000530

License Numbers:

NPF-41; NPF-51; NPF-74

Report Numbers:

05000528/2025001; 05000529/2025001; 05000530/2025001

Enterprise Identifier:

I-2025-001-0000

Licensee:

Arizona Public Service

Facility:

Palo Verde Nuclear Generating Station

Location:

Tonopah, Arizona

Inspection Dates:

January 1, 2025 to March 31, 2025

Inspectors:

N. Armstrong, Project Engineer

M. Bloodgood, Senior Project Engineer

N. Cuevas, Resident Inspector

P. Elkmann, Sr Emergency Preparedness Inspector

S. Hedger, Sr Emergency Preparedness Inspector

J. Hickey, Senior Project Engineer

L. Merker, Senior Project Engineer

Approved By:

John L. Dixon, Jr., Chief

Reactor Projects Branch D

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Palo Verde Nuclear Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation is documented in report section: 71111.0

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 was shut down for refueling outage 1R25 on March 29, 2025.

Units 2 and Unit 3 operated at or near full power for the duration of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated the sites readiness for seasonal extreme weather conditions prior to the onset of seasonal low temperatures for Units 1, 2, and 3, on January 21, 2025.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 3, emergency diesel generator train A following maintenance, on March 10, 2024
(2) Unit 3, low-pressure safety injection system train B during unplanned maintenance on low-pressure safety injection system train A, on March 14, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 2, class 1E 4kV switchgear B room, channel D class battery room, and channel B class battery room; fire zones 5B, 8B, and 9B, on March 6, 2025
(2) Unit 3, high-pressure safety injection system trains A and B pump rooms; fire zones 31A and 31B, on March 26, 2025
(3) Unit 3, charging system trains A and B, and standby pump and valve gallery rooms; fire zones 46A, 46B, and 46E, on March 26, 2025

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire department training and performance during an unannounced fire drill, on March 25, 2025

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the main control room during the Unit 1 planned down power and shutdown for refueling outage 1R25, on March 28, 2025.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (2 Samples)

(1) The inspectors observed and evaluated licensed operator continued training simulator activities, on January 21 and 28, 2025.
(2) The inspectors observed and evaluated licensed operator continued training simulator activities, on February 4, 2025.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Unit 3, emergency diesel generator train A, on March 28, 2025

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) Units 1, 2, and 3, 600V silicon controlled rectifier for the class 1E 125Vdc power system, on March 3, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 1, high risk for planned supplementary protection system functional testing, on January 17, 2025
(2) Unit 3, high radiological risk for dry cask loading of transportable storage canister, on January 17, 2025
(3) Unit 2, high risk for emergent maintenance to replace control oil pump A air bleed valve, on February 5, 2025
(4) Unit 3, emergent work on engineered safety features actuation system channel C containment spray actuation signal manual actuation switch, on February 14, 2025
(5) Unit 3, planned maintenance on emergency diesel generator train A, on March 1, 2025
(6) Unit 1, planned maintenance on charging pump B, on February 25, 2025
(7) Unit 3, planned steam bypass control system troubleshooting with multiple reactor control systems in manual control (not in automatic), on March 25, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (7 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 1, containment building atmosphere monitor RU-1 operability determination due to channel spiking, on January 8, 2025
(2) Units 1 and 2, qualified safety parameter display system functionality assessment due to upper head saturation margin differences, on March 18, 2025
(3) Unit 1, emergency diesel generator B operability determination due to jacket water cooler leak, on March 21, 2025
(4) Unit 3, high-pressure safety injection long-term cooling valve, SIA-HV-604, functionality assessment due to circuit breaker issue during surveillance testing, on March 21, 2025
(5) Unit 3, essential chiller A operability determination due to low oil temperature during operator rounds, on March 24, 2025
(6) Unit 3, containment spray system train A operability determination due to air voids in piping, on March 24, 2025
(7) Unit 3, auxiliary feedwater flow indicator, AFB-FI-41A, functionality assessment for reading less than zero in standby, on March 27, 2025

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Unit 1, permanent modification to replace the charging pump B gas-filled discharge pulsation dampener with a bladderless pulsation dampener, on March 14, 2025

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)

(1)

(Partial, Sections 03.01(a) and 03.01(b))

The inspectors evaluated the Unit 1 refueling outage 1R25 activities starting on March 28, 2025.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (6 Samples)

(1) Unit 1, plant protection system channel C post-maintenance testing following resistor replacement, on January 15, 2025
(2) Unit 3, containment spray pump A discharge to shutdown cooling valve SI-HV-684 post-maintenance testing following diagnostic testing and maintenance on January 29, 2025
(3) Unit 2, normal chilled water system water return and containment isolation valve WCB-UV-61 circuit breaker post-maintenance testing following auxiliary contact replacement, on February 25, 2025
(4) Unit 1, coolant charging pump B post-maintenance testing following discharge valve replacement, March 11, 2025
(5) Unit 3, low-pressure safety injection pump A discharge to discharge valve SI-HV-635 post-maintenance testing following breaker maintenance, on March 17, 2025
(6) Unit 2, steam generator 1 line 2 atmospheric dump valve ADV-178 post-maintenance testing following close limit switch arm replacement, on March 26, 2025

Surveillance Testing (IP Section 03.01) (2 Samples)

(1) Unit 1, containment spray train A testing, on January 8, 2025
(2) Unit 1, engineered safety features actuation system train A subgroup relay testing, on January 21, 2025

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) Unit 3, high-pressure safety injection pump A inservice testing, on March 13, 2025

71114.01 - Exercise Evaluation

Inspection Review (IP Section 02.01-02.11) (1 Sample)

(1) The inspectors evaluated the biennial emergency plan exercise conducted on March 4, 2025. The exercise scenario simulated a control rod malfunction with a subsequent anticipated transient without reactor trip. This was followed by fuel clad damage and subsequent safety bus power losses. A steam generator tube rupture occurred, including failures in associated main steam safety valves. This resulted in a simulated radiological release offsite involving response organization evaluation versus protective action guidelines.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the PVNGS Emergency Plan, revision 76, that was submitted to the NRC on January 28, 2025.

Several screenings and evaluations associated with the 10 CFR 50.54(q) emergency plan change process were reviewed. These evaluations do not constitute NRC approval.

71114.08 - Exercise Evaluation - Scenario Review

Inspection Review (IP Section 02.01 - 02.04) (1 Sample)

(1) The inspectors reviewed the licensee's preliminary exercise scenario that was submitted to the NRC on January 3, 2025 (ML25003A176), for the exercise scheduled on March 4, 2025. The inspectors discussed the preliminary scenario comments with Mr. A. Radosevic, Manager, Emergency Preparedness, and other members of the emergency preparedness staff on January 28, 2025. The inspectors' review does not constitute NRC approval of the scenario.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) Unit 1 (January 1, 2024, through December 31, 2024)
(2) Unit 2 (January 1, 2024, through December 31, 2024)
(3) Unit 3 (January 1, 2024, through December 31, 2024)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (3 Samples)

(1) Unit 1 (January 1, 2024, through December 31, 2024)
(2) Unit 2 (January 1, 2024, through December 31, 2024)
(3) Unit 3 (January 1, 2024, through December 31, 2024)

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (3 Samples)

(1) Unit 1 (January 1, 2024, through December 31, 2024)
(2) Unit 2 (January 1, 2024, through December 31, 2024)
(3) Unit 3 (January 1, 2024, through December 31, 2024)

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) Units 1, 2, and 3, January 1, 2024, through December 31, 2024 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) Units 1, 2, and 3, January 1, 2024, through December 31. 2024 EP04: Emergency Response Facility and Equipment Readiness (ERFER) (IP Section 02.14)

This is a new NRC performance indicator, introduced in NEI 99-02, Revision 8 (ML24331A114). Licensees began collecting data for this performance indicator on January 1, 2025. Therefore, at the time of inspection, there was no quarterly data compiled and submitted to the NRC as of yet. Verifications will take place on later inspections.

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Unit 3, effectiveness of corrective actions related to plant protection system channel C indication spiking resulting in voltage setpoint change, on January 30, 2025

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends that might be indicative of a more significant safety issue. The inspectors performed an in-depth review of the licensees ability to identify issues regarding feedwater isolation valves high rod end hydraulic pressures, evaluate each occurrence, and implement corrective actions. No issues of more than minor significance were identified.

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71111.05 This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Technical specification 5.4.1.d requires, in part, that written procedures shall be implemented covering fire protection program implementation.

Contrary to the above, on November 16, 2023, the licensee failed to implement a written procedure covering fire protection program implementation. Specifically, the licensee failed to implement the daily restoration steps in section 6.4 of procedure 14FT-9FP08, CO2 Fire Suppression System Functional Test, revision 21, during fire suppression system testing activities resulting in the carbon dioxide fire suppression system remaining isolated to the Unit 2, class 1E 4.16 kV switchgear B room and class 1E 125 Vdc train B battery rooms for approximately four days without an hourly fire watch.

Significance/Severity: Green. The inspectors assessed the significance of the finding using Inspection Manual Chapter 0609 Appendix F, Fire Protection and Post - Fire Safe Shutdown Significance Determination Process, dated January 1, 2025. The inspectors determined that the finding had very low safety significance (Green) because, while the degraded or non-functional detection or fixed suppression system adversely affected the ability of the system to protect any equipment important to safe shutdown, the plant had a fire probabilistic risk assessment capable of adequately evaluating the risk associated with the finding, as determined by a senior reactor analyst, and the licensees risk-based evaluation for this fire finding indicated a delta-core damage frequency (CDF) of 1.39E-7 (less than 1E-6) that was reviewed and accepted by a senior reactor analyst.

Corrective Action References: Condition report 23-12317

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 16, 2025, the inspectors presented the emergency preparedness exercise inspection results to Jenn Spina, Vice President, Nuclear Regulatory and Oversight, and other members of the licensee staff.
  • On April 22, 2025, the inspectors presented the integrated inspection results to Jenn Spina, Vice President, Nuclear Regulatory and Oversight, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Calculations

CALC 13-MC-DF-

0307

Diesel Fuel Oil Transfer System - Line Sizing, Pressure

Drop and NPSH

PVNGS DBM - Main Steam

PVNGS DBM - Auxiliary Feedwater System

Engineering Evaluation Request 92-QJ-002, Temporary

Freeze Protection

Miscellaneous

PVNGS DBM - Essential Spray Pond System

40AO-9ZZ21

Acts of Nature

71111.01

Procedures

40OP-9ZZ17

Essential Spray Pond System

Corrective Action

Documents

2-06095, 25-00116, 25-02189

03-M-SIP-001

P & I Diagram Safety Injection and Shutdown Cooling

System

Drawings

03-M-SIP-002

P & I Diagram Safety Injection and Shutdown Cooling

System

Miscellaneous

CRAI 3127427

Engineering Evaluation of [Emergency Diesel Generator]

Fluid Lea[k]age and Potential Operability Concerns

40DP-9OPA4

Control Building Watch Station Rounds

133

40OP-9DG01

Emergency Diesel Generator A

40OP-9SP01

Essential Spray Pond (SP) Train A

40ST-9DG01

Diesel Generator A Test

71111.04

Procedures

40ST-9SI13

Train A LPSI and CS System Alignment Verification

Product Characteristics and Installation Instructions: 165F

ETL Electro thermal Link

05/01/2015

13-MC-FP-0803

Combustible Loads - Control Building

Calculations

13-MC-FP-0809

Combustible Loads - Auxiliary Building

Corrective Action

Documents

23-12209, 23-12317, 25-01998, 25-02060, 25-03130

Pre-fire Strategies Manual

Fire Plans

Pre-fire Strategies Manual

71111.05

Miscellaneous

FSCCR 5581849

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Unit 2 C Shift Unannounced Fire Drill, NPL41-1Q3C-25

03/21/2025

01DP-0AP09

Procedure and Work Instruction Use and Adherence

14DP-0FP01

Firewatch Requirements

14DP-0FP02

Fire System Impairments and Notifications

14DP-0FP33

Control of Transient Combustibles

14DP-0FP33

Control of Transient Combustibles

14FT-9FP08

CO2 Fire Suppression System Functional Test

14FT-9FP08

CO2 Fire Suppression System Functional Test

Procedures

38FT-9QK14

Fire Detection/Protection System Supervised Circuits Test

and Functional Test - Carbon Dioxide Panels

Work Orders

5466305

Corrective Action

Documents

25-00973

SES-0-03-T-09

LT-110X Fails Low/Inadvertent AFAS/LOCA/Loss of PBB-

S04/A HPSI FTAS/CSAS FTAA

SES-0-09-AI-10

Dropped CEA/Loss of NC/Loss of PBA-S03/LOOP/Loss of B

EDG/ Blackout

01/30/2024

Miscellaneous

SES-0-09-AR-05

SG #1 DP Transmitter Failure/A TC Pump Trip/Condenser

Tube Rupture/LBLOCA

Specific maneuvering plan 500 EFPD 100 to 26.7% for EOC

shutdown Unit 1 cycle 25

40AO-9ZZ03

Loss of Cooling Water

40AO-9ZZ04

Reactor Coolant Pump Emergencies

40AO-9ZZ11

CEA Malfunctions

40AO-9ZZ17

Inadvertent PPS-ESFAS Actuations

40DP-9OP02

Conduct of Operations

40EP-9EO01

Standard Post Trip Actions

40EP-9EO03

Loss of Coolant Accident

40EP-9EO09

Functional Recovery

40EP-9EO10-107

Appendix 107: Aligning a Containment Spray Pump for

Injection

40OP-9SI01

Shutdown cooling initiation

71111.11Q

Procedures

40OP-9ZZ05

Power Operations

153

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

40OP-9ZZ23

Outage general operating procedure (GOP)

40ST-9RC01

Reactor coolant system (RCS) and pressurizer Heatup and

Cooldown rates

2ST-9RX14

Shutdown margin - modes 3, 4, and 5

EP-0900-010

ERO Positions - Emergency Coordinator (STSC)

EP-0902

Notifications

ODP-14

Operations Department Performance Improvement Program

Corrective Action

Documents

25-01667

201098; Revise Inspection Plans for Various SCRs

107245, 114660, 44840014, and 44840160, as Necessary to

Comply with ITTE 01009

Rev 2,

07/18/2012

ITEM 44840160 QRC 11154-24 600V SCR Commercial

Grade Dedication Test/Inspection Results

2/14/2025

Explanation of Sample A vs 100% According to MEE-1009

03/03/2025

13VTD-C628-

00051

Cooper Energy Instruction Manual for KSV Turbocharged

Diesel Generating Unit for Nuclear Power Plant Emergency

Stand-by Service

DT-01009-

44840160

Commercial Grade Dedication Test: 600V Silicon Controlled

Rectifier

MEE-01009

Material Engineering Evaluation: Commercial Grade Item

Type Technical Evaluation of Diode/Rectifier

Miscellaneous

QRC 11154-24

Quality Receiving Checklist for APN 44840160

01/03/2025

2DP-0MC46

Receipt Inspection

2MT-9PE01

Cleaning, Inspection, and Testing of the Class 1E Diesel

Generator

73ST-9DG08

Class 1E Diesel Generator Load Rejection, 24 Hour Rated

Load and Hot Start Test Train B

77DP-0MC01

Commercial Grade Dedication (CGD) of Parts Process

87DP-0MC09

Item Procurement Specification (IPS) Requirements

Procedures

87DP-0MC39

Commercial Grade Dedication (CGD) Process

71111.12

Work Orders

5578080, 5582630, 5582692, 5582721, 5582631, 5582652

71111.13

Corrective Action

Documents

25-00643, 18-13900, 23-01988, 25-01011, 25-01654, 25-

01579

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PVNGS DBM-Reactor Protection System

Pressurizer Pressure RCA-P-199A, RCA-P-199B, RCA-P-

199C, RCA-P-199D SPS Setpoint and Uncertainty

Calculation

Site Integrated Risk Assessment Work Task 5624670-0

01/03/2025

Risk Management and Readiness Plan for WO 5693555,

2MCONP01A

2/05/2025

Risk Management and Readiness Plan for Unit 2 A Control

Oil Pump Air Bleed Valve Replacement, WO #5693555

2/04/2025

Phoenix Risk Monitor - Unit 1, Plant State as of 02/23/2025

11:00 AM

Protected Equipment for Charging pump B

2/10/2025

Phoenix Risk Monitor - Unit 3, Plant State as of 02/14/2025

11:00 AM

Phoenix Risk Monitor - Unit 3, Plant State as of 03/1/2025

11:00 AM

Protected Equipment for DG, EW, EC, and EW INOP

2/24/2025

PVNGS DBM-Engineered Safety Features Actuation

System

01-E-SBB-001

Elementary Diagram Reactor Protection System Reactor

Trip Breakers Channel A and B

01-E-SBB-002

Elementary Diagram Reactor Protection System Reactor

Trip Breakers Channel C and D

2152

Technical Document: Establish A Control Oil Pump

Clearance

2/04/2025

Miscellaneous

2247

Technical Document: Restore A Control Oil Pump

2/05/2025

01DP-0AP57

Management of Critical Evolutions and Infrequently

Performed Tests or Evolutions

2DP-0RS01

Online Integrated Risk

30DP-0MP13

PVGS Rigging Control

40DP-9AP21

Protected Equipment

40DP-9RS01-02

Revising the Phoenix Profile Administrative Guideline

Procedures

70DP-0RA05

Assessment and Management of Risk When Performing

Maintenance in Modes 1 and 2

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

78OP-9FX03

Spent Fuel Handling Machine

78OP-9ZZ04

MAGNASTOR Cask loading Operations

78OP-9ZZ06

MAGNASTOR Contingency Actions

Work Orders

5569179, 5693555, 5685819, 5697782, 5578080

13-JC-RI-0200

Reactor Vessel Level System Rix-L-000x Setpoint and

Uncertainty Calculation

13-JC-SQ-0232

Time Response of Radiation Monitoring System

Calculations

13-JC-SQ-0243

RU-01 Setpoint Evaluation for Particulate and Gaseous

Channels

Corrective Action

Documents

24-03585, 24-05091, 25-01613, 18-19179, 20-06732, 25-

01986, 25-01987, 25-02049, 24-10056, 24-12000, 25-03046

PV Design Basis Manual - Qualified Safety Parameter

Display System

CRAI 3127427

13-M018-00606

19R CPT Exchanger

13-MS-B067

Containment Spray System Evaluation for Minor Amounts of

Air Remaining in Piping Following Normal Venting Activities

13-MS-B086

Development of ECCS Suction Side Piping Arc Lengths

Associated with Calculated Max Void Volumes

13-MS-B092

Development of ECCS Discharge Side Piping Arc Lengths

Associated with Calculated Max Void Volumes

13-VTD-1981-

000101

ITT Standard Storage, Installation, Operation and

Maintenance of Heat Exchangers

Miscellaneous

N001-1101-

00341

, Investigate the Waterhammer Pressures and Axial Forces

for Different Length High Points

36ST-9SH01

Post Accident Monitoring QSPDS Channel A Calibration

40DP-9OP08

Diesel Generator Test Record

40DP-9OP26

Operations Operability Determination Process

40DP-9OP26-01

Operations Operability Determination Process Administrative

Guideline

40EP-9EO09

Functional Recovery

40EP-9EO10-015

Appendix 15: RCS Void Control

71111.15

Procedures

40ST-9SI13

Train A LPSI and CS System Alignment Verification

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

74AL-9SQ01

Radiation Monitoring System Alarm Validation and

Response

74RM-9EF42

Radiation Monitoring System Alarm Setpoint Determination

74ST-9SQ07

Radiation Monitoring System Shiftly Surveillance Test

Work Orders

21243, 5480101

Corrective Action

Documents

15-02755, 24-06479, 24-06480, 24-06585, 24-13699, 25-

00871, 25-01221, 25-01567, 25-01845, 25-02069, 25-02071,

25-02091

4663700

CH-1671 Replace Charging Pump Pulsation Dampener with

New Design that Prevents Possibility of Gas Intrusion

Engineering

Changes

4663700

CH-1671 Replace Charging Pump Pulsation Dampener with

New Design that Prevents Possibility of Gas Intrusion

13-MN-1020

Procurement Specification for Charging pump Discharge

Pulsation Dampeners for Palo Verde Units 1, 2, and 3

13-MS-A160

Discharge Pulsation Dampener Replacement Feasibility

Design Study

1346-0079-RPT-

003

Bladderless Pulsation Dampener Performance Qualification

Report

FCR-APS-2024-

0898

Modify Pedestal for Pulsation Dampener Implementation

01/15/2025

FCR-APS-2024-

0899

Access Path Interference Relocation

2/20/2024

N001-0701-

00129

Project Specification for Pulsation Dampeners for Arizona

Nuclear Power Project Palo Verde Units 1, 2, and 3

S-24-0020

Replace Existing Charging Pump Bladder-type Discharge

Pulsation Dampeners with New Bladderless-type Pulsation

Dampeners

Miscellaneous

S-24-0020

Replace Existing Charging Pump Bladder-type Discharge

Pulsation Dampeners with New Bladderless-type Pulsation

Dampeners

81DP-0EE02

Design Change Request

81DP-0EE10

Design Change Process

93DP-0LC07

CFR 50.59 and 72.48 Screenings and Evaluations

71111.18

Procedures

93DP-0LC07-01

CFR 50.59 and 72.48 Administrative Guideline

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Work Orders

5616026

Corrective Action

Documents

25-03409, 25-03410, 25-03407, 25-03411

Miscellaneous

Unit 1 Cycle 25 72ST-9RX14, Shutdown Margin, Data

03/29/2025

40OP-9SI01

Shutdown cooling initiation

40OP-9ZZ23

Outage (GOP)

40ST-9RC01

Reactor coolant system (RCS) and Pressurizer Heatup and

Cooldown rates

71111.20

Procedures

2ST-9RX14

Shutdown margin - modes 3, 4, and 5

13-JC-HC-0201

Containment Pressure Narrow Range (PPS Input)

Instrument (HCx-P-351x, x=A,B,C,D) Setpoint and

Uncertainty Calculation

13-JC-SI-0212

HPSI (Cold Leg) Flow Indicators (F-311, F-321, F-331, & F-

341) Decision Points and Total Loop Uncertainty

13-JC-SI-0215

Containment Spray Pump Discharge Flow Indication Loops

(SIA-F-338 & SIB-F-348) Uncertainty Calculation

13-MC-SI-0215

HPSI System Performance Evaluation and Surveillance

Requirement Basis Calculation

Calculations

13-MC-SI-0220

Containment Spray System Hydraulic Analysis and Pump

Surveillance Testing Requirements

Corrective Action

Documents

24-10411, 24-13058, CRDR 9-8-0790, 25-01988, 25-02650

01-E-SIB-009

Elementary Diagram Safety Injection Shutdown CLG System

HPSI 1 Flow Control to Reactor Coolant Valve 1J-SIA-UV-

617

03-E-SIB-025

Elementary Diagram Safety Injection-Shutdown CLG System

Shutdown CLG Heat Exch Iso Valve 3J-SIA-HV-684

Drawings

03-E-SIF-025

Control Wiring Diagram Safety Injection-Shutdown CLG

System Shutdown CLG Heat Exch Iso Valve 3J-SIA-HV-684

24-00405

Update Design Documents for EC 24-10411-003

10/15/2024

Engineering

Changes

24-10411-003

Alt Detail DEC to Support the Use of an Alternate Drop

Resistor Within the Process Protective Cabinet

PVNGS DBM - Safety Injection System

71111.24

Miscellaneous

PVNGS DBM-Engineered Safety Features Actuation

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

System

Vibration Data: Charging Pump Mod for Charging Pump B

2/25/2025

2-E-WCF-UV-61

Control Wiring Diagram Chilled Water System NORM Chilled

WTR RTR and CTMT ISO VALVE 2J-WCB-UV-61

03-E-SIB-008

Control Wiring Diagram Safety Injection-Shutdown CLG

System LPSI Flow Cont to Reactor Coolant Valve 3J-SIA-

UV-635

03-E-SIF-008

Control Wiring Diagram Safety Injection-Shutdown CLG

System LPSI Flow Cont to Reactor Coolant Valve 3J-SIA-

UV-635

13-VTD-L200-

0003-3

Instructions and Maintenance Manual For Limitorque Type

SMB Valve Operators

N001-1303-

2483

Vishay Foil Resistors S Series Data Sheet

2MT-9ZZ74

Molded Case Circuit Breaker Test

2ST-9ZZ74

Molded Case Circuit Breaker Surveillance Test

36ST-9SB28

PPS Input Loop Calibrations for Parameter 13, (HI CNT

PRESS) and Parameter 17, (H H CNT PRESS)

36ST-9SB28

PPS Input Loop Calibrations for Parameter 13, (HI CNT

PRESS) and Parameter 17, (H H CNT PRESS)

18a

40DP-9OP06

Operations Department Repetitive Task Program

131

40DP-9OP06-002

Operations Department Repetitive Task Program Vol. 3,

Tasks WC001 through ZZ059

40ST-9ZZM1

Operations MODE 1 Surveillance Logs

40ST-9ZZM1

Operations MODE 1 Surveillance Logs

75a

73DP-9XI01

Pump and Valve Inservice Testing Program

73DP-9XI05

Check Valve Condition Monitoring Program

73DP-9ZZ12

Motor Operated Valve MOV Program

73DP-9ZZ24

MOV Diagnostic Test Preparation Instructions

73DP-9ZZ26

Motor Operated Valve MOV Testing with Quiklook

73ST-9SI06

Containment Spray Pumps and Check Valves - Inservice

Test

Procedures

73ST-9SI06

Containment Spray Pumps and Check Valves - Inservice

Test

49a

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

73ST-9SI10

HPSI Pumps Miniflow - Inservice Test

73ST-9SI10

HPSI Pumps Miniflow - Inservice Test

56a

73ST-9XI03

SI Train A Valves - Inservice Test

79ST-9CH06

Charging Pump - Inservice Test

Work Orders

5503860, 5662955, 5562442, 5567138, 5577274, 5575878,

21495, 5540888, 5685819, 5573922, 5578082, 5705731,

5707514

Corrective Action

Documents

23-01724, 23-09921, 23-10098, 24-00898, 24-00979, 24-

2109, 24-02747, 24-02789, 24-04557, 24-07378, 24-08486,

24-08488, 24-09439, 24-09590, 24-09496, 24-09597, 24-

09598, 24-09636, 24-09680, 24-10908, 24-11236, 24-12109,

24-13224, 24-13465, 25-00569, 25-00578, 25-00703, 25-

207, 25-02235, 25-02265, 25-02266, 25-02331, 25-03093,

25-03103, 25-03106, 25-03109, 25-03114, 25-03134, 25-

03160, 25-03171

Corrective Action

Documents

Resulting from

Inspection

Condition Reports

25-03490, 25-03491, 25-03995, 25-04089

INPO EMPE Drill Report

01/31/2023

NRC Evaluated Exercise Report

03/07/2023

Emergency Preparedness 2304 Drill Report

08/04/2023

Emergency Preparedness 2305, 2306 Drill Report

9/19/2023,

9/26/2023

Emergency Preparedness 2401 Dress Rehearsal Drill

Report

01/30/2024

Emergency Preparedness 2402 Exercise Report

3/05/2024

Emergency Preparedness 2403, 2404 Drill Report

07/30/2024,

08/13/2024

Emergency Preparedness 2405, 2406 Drill Report

09/04/2024,

09/10/2024

Palo Verde Executive Management Debrief, NRC Evaluated

Full Scale Exercise, March 4, 2025

03/26/2025

71114.01

Miscellaneous

Evaluation Report HU4.2 Fire Alarm in Containment Event Report (Actual

05/03/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

24-03363-01

Event)

Joint Public Information Procedure (JPIP)

EP-0900-006

ERO Positions - Dose Assessment Health Physicist (EOF)

EP-0900-010

ERO Positions - Emergency Coordinator (STSC)

EP-0900-011

ERO Positions - Emergency Operations Director (EOF)

EP-0900-012

ERO Positions - Engineering Director (EOF)

EP-0900-019

ERO Positions - HPN Communicator (EOF)

EP-0900-025

ERO Positions - Operations Advisor (STSC)

EP-0900-029

ERO Positions - Radiation Protection Coordinator (TSC)

EP-0900-030

ERO Positions - Radiation Protection Monitor (STSC)

EP-0900-031

ERO Positions - Radiological Assessment Communicator

(EOF)

EP-0900-032

ERO Positions - Radiological Assessment Coordinator

(EOF)

EP-0900-036

ERO Positions - RP Support Technician (TSC)

EP-0900-037

ERO Positions - Security Director (TSC)

EP-0900-039

ERO Positions - Shift Technical Advisor (STSC)

EP-0900-040

ERO Positions - STSC Communicator (STSC)

EP-0903

Accident Assessment

EP-0904

ERO/ERF Activation and Operation. Appendix B

Procedures

EP-0906

Termination and Recovery

2-08902-

AR/TR

Palo Verde Nuclear Generating Station (PVNGS), Units 1, 2,

and 3 and Independent Spent Fuel Storage Installation;

Docket Nos. 50-528, 50-529, 50-530 and 72-44; License

Nos. NPF-41, NPF-51 and NPF-74; PVNGS Emergency

Plan, Revision 76

1/28/2025

Evaluation

Tracking Number:

24-02E

Revision 76 Emergency Plan

2/19/2024

Miscellaneous

Screening

Tracking Number

24-004S

Revision 76 Emergency Plan

2/13/2024

71114.04

Procedures

16DP-0EP22

Emergency Plan Maintenance

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Dose Assessment User Manual

Miscellaneous

2-08894-

AR/LMW

Palo Verde Nuclear Generation Station (PVNGS), Units 1, 2,

and 3 and Independent Spent Fuel Storage Installation;

Docket Nos. 50-528, 50-529, 50-530 and 72-44; License

Nos. NPF-41, NPF-51 and NPF-74; 2025 PVNGS NRC

Evaluated Exercise Manual

1/3/2025

EP-0901

Classifications

EP-0902

Notifications

EP-0903

Accident Assessment

EP-0904

ERO/ERF Activation and Operation

71114.08

Procedures

EP-0905

Protective Actions

Corrective Action

Documents

24-01358, 24-01480, 24-01889, 24-01894, 24-12643

Units 1, 2, and 3 Power Profile PI Vision, January 1, 2024

through December 31, 2024

Miscellaneous

24 Initiating Events Performance Indicator Data

73DP-9PP01

Thermal Performance Monitoring and Evaluation

Procedures

93DP-0LC09

NRC ROP PI Data Collection, Verification and Submittal

71151

Work Orders

5600793, 5602457

Calculations

2-JC-SE-0201

Excore Safety Channel Log Power Instrument (Sex-J-0001x)

Setpoint and Uncertainty Calculation (x = A,B,C,D)

Corrective Action

Documents

16-05525, 16-07210, 17-00002, 18-11241, 18-11315, 18-

11534, 18-14393, 18-18483, 24-11959

Drawings

03-J-SEE-0057

Engineering

Changes

18-18483-008

13-JS-A093

Excore Log Channel Calibrations

Miscellaneous

VTD-C490-00007

Combustion Engineering Inc. Operation-Maintenance

Instructions for Ex-core Neutron Flux Monitoring System

[Pub. # CENTM-16]

36ST-9SE01

Excore Safety Channel Log Calibration

115

40DP-9OP26

Operations operability determination process administrative

guidance

71152A

Procedures

81DP-0EE02

Design change request

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Work Orders

5034837, 5292278

Corrective Action

Documents

19-10308, 24-05395, 24-05528, 24-05605, 24-05866, 24-

233, 24-06713, 24-06784, 24-07044, 24-07129, 24-12530,

24-13489, 24-13628, 25-01143, 25-01260, 25-02006, 25-

2050

24-002

Operations and Chemistry Audit

05/31/2024

24-004

Maintenance and Modifications Audit

08/29/2024

24-005

Corrective Action Audit

08/23/2024

29530

High Rod End Pressure Engineering Evaluation

07/10/13

Miscellaneous

VTD-A391-00010

Anchor/Darling Instruction Manual for Main Steam Isolation

Valves (MSIV) and Feedwater Isolation Valves (FWIV)

[Pub.#E9023-9]

01DP-0AP12

Condition Reporting Process

01DP-0AP12-01

Condition Reporting Process Administrative Guideline

01DP-0AP59

Conduct of Organizational Effectiveness

01DP-0AP59-07

Trend Analysis Administrative Guideline

01DP-0AP59-10

Self-Assessment and Benchmarking Administrative

Guideline

40AL-9RK6A

Panel B06A Alarm Responses

71152S

Procedures

60DP-0QQ19

Internal Audits

36