IR 05000528/2025002

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000528/2025002 and 05000529/2025002 and 05000530/2025002
ML25209A466
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 07/29/2025
From: John Dixon
NRC/RGN-IV/DORS/PBD
To: Heflin A
Arizona Public Service Co
References
IR 2025002
Download: ML25209A466 (1)


Text

July 29, 2025

SUBJECT:

PALO VERDE NUCLEAR GENERATING STATION - INTEGRATED INSPECTION REPORT 05000528/2025002 AND 05000529/2025002 AND 05000530/2025002

Dear Adam Heflin:

On June 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Palo Verde Nuclear Generating Station. On July 8, 2025, the NRC inspectors discussed the results of this inspection with Mike DiLorenzo, Acting Director, Nuclear Regulatory Affairs, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, John L. Dixon, Jr., Chief Reactor Projects Branch D Division of Operating Reactor Safety Docket Nos. 05000528; 05000529; and 05000530 License Nos. NPF-41; NPF-51; and NPF-74

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000528; 05000529; and 05000530

License Numbers:

NPF-41; NPF-51; and NPF-74

Report Numbers:

05000528/2025002; 05000529/2025002; and 05000530/2025002

Enterprise Identifier:

I-2025-002-0000

Licensee:

Arizona Public Service Company

Facility:

Palo Verde Nuclear Generating Station

Location:

Tonopah, Arzona

Inspection Dates:

April 1, 2025, to June 30, 2025

Inspectors:

C. Alldredge, Health Physicist

N. Armstrong, Project Engineer

L. Carson, Senior Health Physicist

N. Cuevas, Resident Inspector

J. Hickey, Senior Project Engineer

E. Lantz, Senior Resident Inspector

A. Sanchez, Senior Project Engineer

A. Tran, Resident Inspector

Approved By:

John L. Dixon, Jr., Chief

Reactor Projects Branch D

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Palo Verde Nuclear Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000530/2024-003-00 LER 2024-003-00 for Palo Verde Nuclear Generating Station, Unit 3, Violation of Technical Specifications 3.9.2 and 3.3.12 71153 Closed

PLANT STATUS

Unit 1 entered the inspection period shut down for refueling outage 1R25. On May 9, 2025, the reactor was made critical following completion of the refueling outage and returned to full power on May 14, 2025, where it remained for the remainder of the inspection period.

Unit 2 operated at or near full power for the duration of the inspection period.

Unit 3 entered the inspection period at full power. On April 25, 2025, the reactor was down powered to approximately 12 percent power to perform repairs to a switchyard breaker due to a hot spot. On April 27, 2025, the reactor returned to full power following repairs, where it remained for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1, shutdown cooling train A during the 1R25 outage, on April 2, 2025
(2) Unit 1, spent fuel pool cooling trains A and B during the 1R25 outage, on April 7, 2025
(3) Unit 2, Cardox fire protection system following maintenance, on May 8, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 1, 100-foot elevation auxiliary building rooms, fire zones 42C and 42D, essential cooling water heat exchangers A and B rooms, fire zone 43, on April 30, 2025
(2) Unit 3, 100-foot elevation auxiliary building rooms, fire zones 42C and 42D, essential cooling water heat exchangers A and B rooms, fire zone 43, on April 30, 2025
(3) Unit 1, containment during 1R25 outage, fire zones 63A, 63B, 66A, 66B, 67A, and 67B, on May 2, 2025
(4) Unit 2, main control room, fire zone 17, on June 18, 2025

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated internal flooding mitigation protections in the Units 1, 2, and 3 essential pipe density tunnels, on May 29, 2025.

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Unit 1 essential cooling water train B heat exchanger, on April 6, 2025

===71111.08P - Inservice Inspection Activities (PWR) The inspectors verified that the reactor coolant system boundary, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities in Unit 1 during refueling outage 1R25 from April 7 to 18, 2025, on site and completion of the inspection on May 30, 2025, via in office review.

PWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding Activities (IP Section 03.01)===

The inspectors verified that the following nondestructive examination and welding activities were performed appropriately:

(1) Ultrasonic Examination
  • charging line, weld 37-33, reducer to pipe
  • charging line, weld 37-34, pipe to elbow
  • pressurizer spray 1B, weld 28-41, pipe to elbow
  • pressurizer spray 1B, weld 28-42, pipe to elbow
  • pressurizer spray 1B, weld 28-45, safe-end to pipe
  • safety injection B, weld 75-27, pipe to elbow Dye Penetrant Examination
  • safety injection, part SI-119-H-014-W
  • charging system, part CH-005-H-019-W Visual VT-1 Examination
  • pressurizer manway studs and nuts, component 1MRCEX02 Welding Activities

pressurizer instrument half-nozzle repair PWR Inservice Inspection Activities Sample - Vessel Upper Head Penetration Inspection Activities (IP Section 03.02)

The inspectors verified that no upper reactor vessel head penetration inspections were required this outage.

PWR Inservice Inspection Activities Sample - Boric Acid Corrosion Control Inspection Activities (IP Section 03.03) (1 Sample)

The inspectors verified the licensee is managing the boric acid corrosion control program through a review of the following evaluations:

(1)

  • CR-25-2585 1PSIAVA07
  • CR 25-2586 1JSICUV0653
  • CR 25-2663 1PRCEV242
  • CR 25-2665 1JSIAPSV0469
  • CR-25-2666 1JSIBUV0616
  • CR-25-2668 1JSIBUV0614
  • CR 25-2675 1JSIBUV0638 PWR Inservice Inspection Activities Sample - Steam Generator Tube Inspection Activities (Section 03.04) (1 Sample)

The inspectors verified that the licensee is monitoring the steam generator tube integrity appropriately through a review of the following examinations:

(1)

  • one-hundred percent of the tubes in steam generator SG11 and SG12 were inspected via eddy current methods
  • high pressure feedwater heaters 5A and 6A were visually inspected and tubes inspected via eddy current methods

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (2 Samples)

The inspectors observed and evaluated licensed operator performance in the control room during the following activities:

(1) Unit 3, down power to repair a switchyard motor operated disconnect, on April 28, 2025
(2) Unit 1, startup activities following completion of refueling outage 1R25, on May 9, 2025

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Unit 1, class 1E 480 Vdc load center train B, on May 23, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 3, planned maintenance on emergency diesel generator train B, on June 10, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 1, class 1E 125 Vdc battery PK-C functionality assessment due to discharge test results showing lower capacity than expected, on April 3, 2025
(2) Unit 1, emergency diesel generator train A operability determination due to automatic voltage regulator swap following failure to control voltage, on April 22, 2025
(3) Unit 1, steam generator atmospheric dump valves, SGB-HV-178 and SGB-HV-185, operability determination due to excessive leakage during inservice testing, on April 7, 2025
(4) Unit 1 containment spray train A operability determination due to voids discovered during surveillance testing, on May 21, 2025

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Unit 1, permanent modification to upgrade the balance of plant engineered safety features actuation system channel B to address component obsolescence and equipment failure issues, on May 13, 2025

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated the Unit 1 refueling outage 1R25 activities from March 28 to May 14, 2025.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (9 Samples)

(1) Unit 2, coolant charging pump E seal lube pump replacement, on April 4, 2025
(2) Unit 1, refueling water tank level transmitter channel A post-maintenance testing following transmitter replacement, on April 30, 2025
(3) Unit 1, low-pressure safety injection pump B post-maintenance testing following mechanical seal replacement, on April 30, 2025
(4) Unit 1, shutdown cooling suction from containment recirculation sump valve SIB-UV-675 post-maintenance test following seat ring replacement, on April 30, 2025
(5) Unit 1, essential chiller B post-maintenance testing following eddy current testing and repairs, on May 6, 2025
(6) Unit 1, safety injection tank B to reactor coolant loop check valve SIE-V-247 post-maintenance test following repairs, on May 15, 2025
(7) Unit 3, emergency diesel generator train A post-maintenance testing following maintenance outage, on May 16, 2025
(8) Unit 1, engineered safety features train B post-maintenance testing following balance of plant engineered safety features actuation system upgrade, on May 20, 2025
(9) Unit 1, reactor coolant pump 2A post-maintenance testing following mechanical seal replacement, on June 17, 2025

Surveillance Testing (IP Section 03.01) (2 Samples)

(1) Unit 1, remote input system voltage testing, on April 30, 2025
(2) Unit 2, turbine-driven auxiliary feedwater pump testing, on June 5, 2025

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) Unit 1, low-pressure safety injection pump B inservice testing, on May 14, 2025

Containment Isolation Valve (CIV) Testing (IP Section 03.01) (1 Sample)

(1) Unit 1, pressurizer steam space sample header containment isolation valve SSA-UV-205 testing, on May 27, 2025

Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)

(1) Units 1, 2, and 3, FLEX spent fuel pool make up pumps, on May 6,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (3 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1)surveys of potentially contaminated packages/equipment from the radiologically controlled area and workers exiting potentially contaminated areas (2)labeling for several nonexempt radioactive sources listed in the licensee's source inventory in Unit 2 and Unit 3, including the following specific Unit 1 RP sources13-011, 24-001, and RP-179 (3)physical and programmatic controls for highly activated and contaminated non-fuel materials stored within the spent fuel pool including radwaste filter canisters

Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following radiological work:

(1)medium and high risk radiological work and job coverage for reactor inboard loop discharge check valve disassembly, inspection, lapping in-body seats for low-pressure safety injection and repair of safety injection valves SIE-V-245 and 247 (RWPs 1-3125 and 3321 tasks 30 and 50)

(2)medium and high risk radiological work and job coverage for primary side steam generator (SG-1) maintenance and eddy current (ET) testing activities for Unit 1 reactor (RWP 1-3306-R25, all tasks)

(3)high risk radiological work and job coverage for pressurizer nozzle work (RWP 1-3425-R25)

(4) Unit 1 in-core instrumentation area chase inspections (RWP 1-3325-R25)

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (4 Samples)

The inspectors evaluated licensee controls of the following high radiation areas (HRAs) and very high radiation areas (VHRAs):

(1)

(VHRA) Unit 1 under vessel access on the 80-foot containment elevation (2)

(HRA) Unit 1 regenerative heat exchanger room on the 111-foot containment elevation (3)

(HRA) Unit 1 reactor vessel head stand on the 140-foot containment elevation (4)

(LHRAs) Units 1, 2, & 3 high level storage area on the 120-foot elevation of the radwaste building Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)

(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.04 - Occupational Dose Assessment

Source Term Characterization (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated licensee performance as it pertains to radioactive source term characterization.

External Dosimetry (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee processes, stores, and uses external dosimetry.

Internal Dosimetry (IP Section 03.03) (3 Samples)

The inspectors evaluated the following internal dose assessments:

(1) CR-1-23-11265, Dose Assessment, dated July 23, 2024
(2) PCE 2-24-0005, Dose Assessment, dated November 26, 2024
(3) CR-1-23-11087, Dose Assessment, dated April 28, 2024

Special Dosimetric Situations (IP Section 03.04) (2 Samples)

The inspectors evaluated the following special dosimetric situations:

(1) use of multi-pack dosimetry and dose assignment on activities related to work orders

===5405544, 5419142, and 5456945 (2)monitoring of three declared pregnant workers and their associated NRC Form 5s

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 1 (April 1, 2024, through March 31, 2025)
(2) Unit 2 (April 1, 2024, through March 31, 2025)
(3) Unit 3 (April 1, 2024, through March 31, 2025)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) Units 1, 2, and 3 (October 1, 2024, through March 31, 2025)

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)

(1) Units 1, 2, and 3 (October 1, 2024, through March 31, 2025)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issue:

(1) Accidental discharge during a dry fire exercise inside of the security training building on February 11, 2025. This included the site level one evaluation 25-01522-002 completed on March 27, 2025.

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000530/2024-003-00, PVNGS Unit 3 Violation of Technical Specifications 3.9.2 and 3.3.12, Agencywide Documents Access and Management System (ADAMS) Accession No. ML24347A138. The inspection conclusions associated with this LER are documented in inspection report 050000530/2024003. This LER is closed.

Personnel Performance (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the loss of Unit 1 emergency diesel generator A resulting in a declaration of unusual event CU2.1, Loss of all but one AC Power source to emergency buses for 15 minutes or longer and the licensee response on April 10,

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 14, 2025, the inspectors presented the occupational radiation safety inspection results to Jennifer Spina, Vice President, Nuclear Regulatory & Oversight, and other members of the licensee staff.
  • On June 27, 2025, the inspectors presented the Unit 1 inservice inspection results to Jennifer Spina, Vice President, Nuclear Regulatory & Oversight, and other members of the licensee staff.
  • On July 8, 2025, the inspectors presented the integrated inspection results to Mike DiLorenzo, Acting Director, Nuclear Regulatory Affairs, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Corrective Action

Documents

25-02122

71111.04

Drawings

01-M-NCP-002

Piping & Instrumentation Diagram Nuclear Cooling Water

System

71111.04

Drawings

01-M-PCP-001

Piping & Instrumentation Diagram Fuel Pool Cooling &

Cleanup System

71111.04

Drawings

03-M-CHP-002

Piping & Instrumentation Diagram Chemical and Volume

Control System

71111.04

Drawings

03-M-FPP-004

P & I diagram fire protection system (CO2 system)

71111.04

Drawings

03-M-SIP-001

Piping & Instrumentation Diagram Safety Injection &

Shutdown Cooling System

71111.04

Drawings

03-M-SIP-002

Piping & Instrumentation Diagram Safety Injection &

Shutdown Cooling System

71111.04

Engineering

Evaluations

4758718

Engineering Evaluation

71111.04

Procedures

14OP-9FP02

CO2 fire protection (CARDOX)

71111.04

Procedures

40AO-9ZZ23

Loss of [spent fuel pool] SFP Level or Cooling

71111.04

Procedures

40DP-9ZZ30

Reduced Inventory Operations

71111.04

Procedures

40MG-9ZZ07-002

FLEX Support Guidelines Mode 5, 6, or Defueled

71111.04

Procedures

40OP-9PC01

Fuel Pool Cooling

71111.04

Procedures

40OP-9SI01

Shutdown Cooling Initiation

71111.04

Procedures

40OP-9ZZ16

Reactor Coolant System Drain Operations

71111.04

Procedures

40OP-9ZZ23

Outage General Operating Procedure (GOP)

71111.05

Calculations

13-MC-FP-0803

Combustible Loads - Control Building

71111.05

Corrective Action

Documents

25-05151, 19-06334, 23-10795, 23-05322, 25-06454,

FSCCR 5729570, CRDR 2960716, CRDR 2960717

71111.05

Drawings

M650-00410

Auxiliary Building 100 Northeast Corridor

71111.05

Miscellaneous

Palo Verde Generating Station Pre-Fire Strategies Manual

71111.05

Miscellaneous

Pre-Fire Strategies Manual

71111.05

Procedures

14DP-0FP02-02

Fire Point Inactivation and Activation Administrative

Guidance

71111.06

Calculations

13-MC-ZA-0809

As Built Auxiliary Building Flooding Calculation

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.06

Calculations

13-MC-ZY-0599

Essential Pipe Density Tunnel Flooding

71111.06

Calculations

13-MC-ZY-0599

Essential Pipe Density Tunnel Flooding

71111.06

Corrective Action

Documents

23-07148

71111.07A

Corrective Action

Documents

25-04112, 25-03985

71111.07A

Miscellaneous

25-0360

Eddy Current Examination Report

71111.07A

Miscellaneous

AN449-A00029

Belzona 1111 Super Metal Product Data and Application

Instructions

71111.07A

Miscellaneous

AN449-A00030

Belzona 1321 Super Metal Product Data and Application

Instructions

71111.07A

Miscellaneous

VTM-S445-00001

Struthers Wells Corporation Turbine, Nuclear, Fuel Pool and

Essential Cooling Water Heat Exchangers

71111.07A

Procedures

30DP-9MP03

Mechanical System Cleanliness

71111.07A

Procedures

31MT-9EW02

Tube Plugging of the Essential Cooling Water Heat

Exchanger

71111.07A

Procedures

31MT-9EW02

Tube Plugging of the Essential Cooling Water Heat

Exchanger

71111.07A

Procedures

38DP-0MI01

Control of Painting and Coating Operations

71111.07A

Procedures

73DP-9ZZ21

Heat Exchanger Visual Inspection

71111.07A

Procedures

73TI-9ZZ28

Eddy Current Examination of Tubing

71111.07A

Work Orders

5591895, 5592316, 5574324

71111.08P

Corrective Action

Documents

25-04561

71111.08P

Engineering

Changes

23-10254-025

RC-1911 Unit 1 Pressurizer Upper and Lower Head

Instrument Nozzle Replacement

04/14/2025

71111.08P

Engineering

Evaluations

25-03798-002

Lever 3 Evaluation Report

04/20/2025

71111.08P

Engineering

Evaluations

MN725-A02143

Palo Verde Generating Station U1R25 Steam Generator

Condition Monitoring Evaluation

05/05/2025

71111.11Q

Miscellaneous

Standard Maneuver Plan: Unit 3 Cycle 25, 350 EFPD 100%

to 12%

71111.11Q

Procedures

40OP-9ZZ02

Initial Reactor Startup Following Refuelings

71111.11Q

Procedures

40OP-9ZZ05

Power Operations

153

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.12

Miscellaneous

VTD-A915-00165

ABB Installation/Maintenance instructions for I-T-E low

voltage AC metal-enclosed power switchgear K-Line

71111.12

Miscellaneous

VTD-A915-00169

ABB Installation & Maintenance instructions for low-voltage

power circuit breakers type K-225 thru 2000& K-6000s thru

2000s

71111.12

Miscellaneous

VTD-A915-00175

ABB Maintenance and Surveillance for low-voltage

switchgear equipment K-Line

71111.12

Procedures

2MT-9ZZ92

Inspection/Cleaning of 1E and Non-1E 480 Volt Load

Centers

71111.12

Work Orders

5591598

71111.15

Corrective Action

Documents

25-03388, 25-04140, 25-00893, 25-00893-002, 24-00699,

25-00978, 25-00980, 25-02049, 25-02086, 25-05395

71111.15

Drawings

13-M01-01239

Regulator Chassis Schematic

71111.15

Engineering

Evaluations

25-00893-001

Minor Leaks Identified Per CMWO 5596546

71111.15

Miscellaneous

13-MS-B067

Containment Spray System Evaluation for Minor Amounts of

Air Remaining in Piping Following Normal Venting Activities

71111.15

Miscellaneous

13-MS-B092

Development of ECCS Discharge Side Piping Arc Lengths

Associated with Calculated Max Void Volumes

71111.15

Miscellaneous

VTD-E940-0003

Engine System Company Installation Operating And

Maintenance Manual For Dual Automatic Voltage Regulator

System Upgrades

71111.15

Procedures

30DP-9MP01

Conduct of Maintenance

71111.15

Procedures

30DP-9MP27

Toolpouch and Minor Maintenance Process

71111.15

Procedures

40DP-9OP26

Operations Operability Determination Process

71111.15

Procedures

40DP-9OP26-01

Operations Operability Determination Process Administrative

Guideline

71111.15

Procedures

40OP-9DG01

Emergency Diesel Generator A

71111.15

Procedures

40ST-9SI13

Train A LPSI and CS System Alignment Verification

71111.15

Procedures

73DP-9ZZ14

Surveillance Testing

71111.15

Procedures

73ST-9XI20

[Atmospheric dump valves] ADVs - Inservice Test

71111.18

Corrective Action

Documents

25-01352, 25-04326, 25-04144, 25-04396, 25-04748, 25-

04748

71111.18

Miscellaneous

CFR 50.59 Screening/Evaluation for EC 2589411

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.18

Miscellaneous

EC 2589411

BOP-ESFAS Replacement

71111.18

Miscellaneous

Specification 13-

JM-0104

Balance of Plant Engineered Safety Feature Actuation

System

71111.18

Procedures

40OP-9SA01

BOP ESFAS Modules Operation

71111.18

Work Orders

5600334, 5232544

71111.20

Miscellaneous

Specific Maneuvering Plan 500 EFPD 100 To 26.7% For

EOC Shutdown Unit 1 Cycle 25

71111.20

Miscellaneous

Specific Maneuver Plan: EOC Shutdown 90% to 20% Unit 2

Cycle 24

71111.20

Miscellaneous

Reactor Coolant System Pressure And Temperature Limits

Report (PTLR), Technical Requirements Manual Appendix

TA

71111.20

Miscellaneous

TRM APPX TA Reactor Coolant System Pressure and

Temperature Limits Report

71111.20

Procedures

30DP-9MP11

Field Use Of Rigging

71111.20

Procedures

31MT-9RC30

Reactor Vessel Head Removal And Installation, Multiple

Pass Multi-Stud Tensioner

71111.20

Procedures

31MT-9ZC07

Miscellaneous Containment Building Heavy Loads

71111.20

Procedures

40DP-9AP19

Lower Mode Functional Recovery Technical Guideline

71111.20

Procedures

40EP-9E01

Standard post trip actions

71111.20

Procedures

40EP-9EO11

Lower Mode Functional Recovery

71111.20

Procedures

40OP-9RC01

Reactor Coolant Pump Operation

71111.20

Procedures

40OP-9SG01

Main steam isolation valves

71111.20

Procedures

40OP-9SI01

Shutdown Cooling Initiation

71111.20

Procedures

40OP-9ZZ23

Outage general operating procedure (GOP)

71111.20

Procedures

40ST-9RC01

Reactor Coolant System (RCS) and Pressurizer Heatup and

Cooldown Rates

71111.20

Procedures

40ST-9ZZ09

Containment Cleanliness Inspection

71111.20

Procedures

2ST-9RX14

Shutdown Margin - Modes 3, 4, and 5

71111.24

Calculations

2011-00315

Incorporated Essential Chiller Tubing Minimum Allowable

Wall Calculations

71111.24

Calculations

73TI-9ZZ28

Eddy Current Examination Of Tubing

71111.24

Corrective Action

25-04471, 25-04298, 25-03122, 21-07136, 25-05929

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

71111.24

Corrective Action

Documents

Resulting from

Inspection

25-06490

71111.24

Drawings

01-M-ECP-0001

Piping & Instrumentation Diagram Essential Chilled Water

System

71111.24

Drawings

N001-0902-

00039

Sectional Assembly (LPSI pumps) DMWO 00739596

71111.24

Drawings

N001-0902-

00040

Sectional Assembly (LPSI pumps) DMWO 00739596

71111.24

Drawings

N001-0902-

00042

Mechanical Seal Drawing (LPSI pump)

71111.24

Engineering

Evaluations

24-04772-001

Commercial Grade Item Dedication Technical Evaluation For

Item 50001406

71111.24

Miscellaneous

PVGS Diverse and Flexible Coping Strategies (FLEX)

Program

71111.24

Procedures

14MT-9BD61

FLEX SFP Makeup Pump Inspections and Tests

71111.24

Procedures

31MT-9RC23

Reactor Coolant Pump Sulzer Bingham Seal Replacement

71111.24

Procedures

31MT-9SI01

Low Pressure Safety Injection Pump Maintenance

71111.24

Procedures

2MT-9PE01

Cleaning, Inspection, and Testing of the Class 1E Diesel

Generator

71111.24

Procedures

36ST-9SB32

PPS Input Loop Calibration for Parameter 20, LO RWT

LEVEL

71111.24

Procedures

36ST-9SB51

PPS Transmitter Response Time Test Outside Containment

71111.24

Procedures

39MT-9ZZ06

Disassembly/Assembly of Limitorque Type SMB/SB-00

Actuators

71111.24

Procedures

40MG-9ZZ07

FLEX Support Guidelines

71111.24

Procedures

40OP-9CH01

CVCS Normal Operations

71111.24

Procedures

73DP-9CL02

Containment Leakage Rate Testing Program

71111.24

Procedures

73ST-9CL01

Containment Leakage Type B and C Testing

71111.24

Procedures

73ST-9DG08

Class 1E Diesel Generator Load Rejection, 24 Hour Rated

Load and Hot Start Test Train B

71111.24

Procedures

73ST-9SI11

Low Pressure Safety Injection Pumps Miniflow - Inservice

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Test

71111.24

Procedures

73ST-9SI14

LPSI Pumps Full Flow - Inservice Test

71111.24

Procedures

73ST-9XI43

Containment Recirculation Sump Isolation Valve Leak

Testing

71111.24

Procedures

2DP-0PP01

Out of Tolerance Program Controls

71111.24

Work Orders

5707412, 5692288, 5584954, 5589654, 5585313, 5605691,

5589705. 5585313, 5578080, 5582630, 5582692, 5582721,

5582631, 5582652, 5362206, 5585266, 5585309, 5600216,

5592425, 5592040, 5392331

71124.01

ALARA Plans

ALARA 5-Year Plan 2021 - 2025

2/16/2023

71124.01

ALARA Plans

RWP-3002

Reactor Destack and Restack

71124.01

ALARA Plans

RWP-3306

Steam Generator Maintenance and Support

71124.01

ALARA Plans

RWP-3411

Repairs on Pressurizer Nozzles

71124.01

ALARA Plans

RWP-3502

Valve, Flange, and Pump Maintenance and Inspection

71124.01

ALARA Plans

RWP-3521

High Risk - Inboard Loop Discharge Check Valve Work

71124.01

Corrective Action

Documents

24-11031, 24-11601, 24-11695, 25-00057, 25-00238,

25-00437, 25-00536, 25-00872, 25-02109, 25-02190,

25-03348

71124.01

Corrective Action

Documents

Resulting from

Inspection

25-03726, 25-03980, 25-4016, 25-4021, 25-04083,

71124.01

Procedures

2DP-9NF01

Control of SNM Configuration, Inventory & Reporting

71124.01

Procedures

75DP-0RP01

Radiological Posting and Labeling

71124.01

Procedures

75DP-9RP01

Radiation Exposure and Access Control

71124.01

Procedures

75RP-9OP02

Control of High Radiation Areas, Locked High Radiation

Areas, and Very High Radiation Areas

71124.01

Procedures

75RP-9RP04

Personnel Contamination Monitoring

71124.01

Procedures

75RP-9RP05

Contamination Dose Evaluation

71124.01

Procedures

75RP-9RP07

Radiation and Contamination Surveys

71124.01

Procedures

75RP-9RP10

Conduct of R.P. Operations

71124.01

Procedures

75RP-9RP16

Special Dosimetry

71124.01

Radiation

Surveys

0-M-20240826-1

Low-Level Radioactive Material Storage Facility (LLRMSF)

08/26/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.01

Radiation

Surveys

1-M-20230919-5

U1R24 Containment Power Entry

09/22/2023

71124.01

Radiation

Surveys

1-M-20231102-10

1R24 55' and 100' Incore Chase

11/04/2023

71124.01

Radiation

Surveys

1-M-20240628-1

AD08 - Equipment Drain Tank

06/28/2024

71124.01

Radiation

Surveys

1-M-20240816-3

R124 Resin Transfer Gallery

09/11/2024

71124.01

Radiation

Surveys

1-M-20240816-4

R101 High Level Storage Area

09/24/2024

71124.01

Radiation Work

Permits (RWPs)

1-3002-R25

Reactor Head Destack/Restack (High Risk)

71124.01

Radiation Work

Permits (RWPs)

1-3306-R25

Steam Generator Maintenance (High Risk)

71124.01

Radiation Work

Permits (RWPs)

1-3502-R25

Valve, Flange, and Pump Maintenance (Medium Risk)

71124.01

Radiation Work

Permits (RWPs)

1-3521-R25

Inboard Loop Discharge Check Valve (High Risk)

71124.01

Radiation Work

Permits (RWPs)

RWP-9-1021

L..R. Evaporator and Boric Acid Concentrator System

Maintenance

71124.01

Self-Assessments

Integrated Performance Assessment -Radiation Protection

01/31/2025

71124.01

Self-Assessments 202502

Radiological Safety Trends

2/28/2025

71124.01

Self-Assessments24-002

Offsite Safety Review Committee Meeting

10/09/2024

71124.04

Calculations

Intake Dose Assessment - HPID 25371 PCE 2-24-0005

11/26/2024

71124.04

Calculations

Intake Dose Assessment - HPID 31511 CR 1-23-11087

04/28/2024

71124.04

Calculations

Intake Dose Assessment - HPID 20995

2/21/2023

71124.04

Calculations

Intake Dose Assessment - HPID25801

07/23/2024

71124.04

Corrective Action

Documents

23-04285, 23-05711, 23-07340, 23-07524, 23-07659,

23-07738, 23-09984, 23-11516, 23-11679, 24-04309,

24-06677, 24-08113, 24-10135, 24-12058, 24-12127,

25-00306, 25-01640

71124.04

Miscellaneous

National Voluntary Laboratory Accreditation Program On-

Site Assessment

05/24/2024

71124.04

Miscellaneous

1-23-0050

Air Sample

10/29/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.04

Miscellaneous

1-23-00548

Air Sample

10/26/2023

71124.04

Miscellaneous

1-23-00549

Air Sample

10/29/2023

71124.04

Miscellaneous

1-23-00694

Air Sample

11/2/2023

71124.04

Procedures

75DP-0RP02

Radioactive Contamination Control

71124.04

Procedures

75DP-9RP01

Radiation Exposure and Access Control

71124.04

Procedures

75RP-9ME21

DLR Issue, Exchange, and Termination

71124.04

Procedures

75RP-9ME24

Dosimetry Processing, Evaluation, and Documentation

71124.04

Procedures

75RP-9ME29

Operation of the Whole Body Counters with APEX-InVivo

Software

71124.04

Procedures

75RP-9RP03

Bioassay Analysis

71124.04

Procedures

75RP-9RP04

Personnel Contamination Monitoring

71124.04

Procedures

75RP-9RP16

Special Dosimetry

71124.04

Self-Assessments

Palo Verde Generating Station Dosimetry Program 2022

NVLAP Internal Audit

05/11/2023

71151

Miscellaneous

SSFF 1 April 2024 - 31 March 2025 PIC Data

71151

Miscellaneous

Unit 1 OR/PR01

Performance Indicator Occupational/Public Radiation Safety

Cornerstone Summary Report - Unit 1

03/18/2025

71151

Miscellaneous

Unit 2 OR/PR02

Performance Indicator Occupational/Public Radiation Safety

Cornerstone Summary Report - Unit 2

03/18/2025

71151

Miscellaneous

Unit 3 OR/PR03

Performance Indicator Occupational/Public Radiation Safety

Cornerstone Summary Report - Unit 3

03/18/2025

71151

Procedures

75RP-0LC02

Performance Indicator Public Radiation Safety Cornerstone

71151

Procedures

93DP-0LC09

NRC ROP PI Data Collection, Verification, and Submittal

71151

Procedures

93DP-0LC10

SSFF Mitigating Systems Performance Indicator

71152A

Corrective Action

Documents

25-01522

71152A

Corrective Action

Documents

Resulting from

Inspection

25-05964

71153

Corrective Action

Documents

25-004142, 24-03849, 22-06446

71153

Miscellaneous

Formal Troubleshooting Game Plan: Troubleshoot

1JDGAB02 Bridge 2 Components

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71153

Procedures

36ST-9SE13

Excore Startup Channel and Boron Dilution Alarm System

Calibration

71153

Procedures

40DP-9OP26

Operations Operability Determination Process,

71153

Procedures

40ST-9ZZ24

Boron Dilution System Inoperable

71153

Work Orders

5503044, 5617375