IR 05000528/2025003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000528/2025003, 05000529/2025003 and 05000530/2025003
ML25350C236
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 12/16/2025
From: John Dixon
NRC/RGN-IV/DORS/PBD
To: Heflin A
Arizona Public Service Co
Sanchez A
References
IR 2025003
Download: ML25350C236 (0)


Text

December 16, 2025

SUBJECT:

PALO VERDE NUCLEAR GENERATING STATION - INTEGRATED INSPECTION REPORT 05000528/2025003 AND 05000529/2025003 AND 05000530/2025003

Dear Adam Heflin:

On September 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Palo Verde Nuclear Generating Station. On December 9, 2025, the NRC inspectors discussed the results of this inspection with Cary Harbor, Senior Vice President, Site Operations and other members of your staff. The results of this inspection are documented in the enclosed report.

Due to the temporary cessation of government operations, which commenced on October 1, 2025, the NRC began operating under its Office of Management and Budget-approved plan for operations during a lapse in appropriations. Consistent with that plan, the NRC operated at reduced staffing levels throughout the duration of the shutdown. However, the NRC continued to perform critical health and safety functions and make progress on other high-priority activities associated with the ADVANCE Act and Executive Order 14300. On November 13, 2025, following the passage of a continuing resolution, the NRC resumed normal operations.

However, due to the 43-day lapse in normal operations, the Office of Nuclear Reactor Regulation granted the Regional Offices an extension on the issuance of the calendar year 2025 inspection reports that should have been issued by November 13, 2025, to December 31, 2025. The NRC resumed the routine cycle of issuing inspection reports on November 13, 2025.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

A licensee-identified violation which was determined to be of very low safety significance is also documented in this report. We are treating this violation as a non-cited violation (NCV)

consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Palo Verde Nuclear Generating Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at Palo Verde Nuclear Generating Station.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, John L. Dixon, Jr., Chief Reactor Projects Branch D Division of Operating Reactor Safety Docket Nos: 05000528 and 05000529 and 05000530 License Nos: NPF-41 and NPF-51 and NPF-74

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000528, 05000529 and 05000530

License Numbers:

NPF-41, NPF-51 and NPF-74

Report Numbers:

05000528/2025003, 05000529/2025003 and 05000530/2025003

Enterprise Identifier:

I-2025-003-0000

Licensee:

Arizona Public Service

Facility:

Palo Verde Nuclear Generating Station

Location:

Tonopah, AZ

Inspection Dates:

July 1, 2025 to September 30, 2025

Inspectors:

N. Armstrong, Resident Inspector

B. Baca, Health Physicist

N. Greene, Senior Health Physicist

E. Lantz, Sr Resident Inspector

J. Miller, Health Physicist

J. O'Donnell, Senior Health Physicist

Approved By:

John L. Dixon, Jr., Chief

Reactor Projects Branch D

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Palo Verde Nuclear Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation is documented in report section: 71111.1

List of Findings and Violations

Partial Loss of Offsite Power and Loss of Spent Fuel Pool Cooling due to Inadequate Procedure Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000528/2025003-01 Open/Closed

[H.12] - Avoid Complacency 71153 A self-revealed Green finding and associated Non-cited Violation (NCV) of Technical Specification 5.4.1.a was identified when the licensee failed to adequately establish and perform maintenance procedures appropriate to the circumstances, as required in Regulatory Guide 1.33, Quality Assurance Program Requirements, revision 2. Specifically, procedure 40OP-9SA02, De-Energization of BOP-ESFAS, revision 27, did not adequately ensure that the required step of lifting load shed relays K202 and K204 would be completed, resulting in a subsequent partial loss of offsite power and loos of spent fuel pool augmented cooling.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000528/2025-003-00 LER 2025-003-00 for Palo Verde Nuclear Generating Station (PVNGS), Unit 1,

Specified System Actuation due to Loss of Power (LOP)/Load Shed (LS)

Signal 71153 Closed

PLANT STATUS

Unit 1 operated at or near full power for the duration of the inspection period.

Unit 2 entered the inspection period at full power. On September 16, 2025, the reactor was down powered to approximately 94 percent power to perform repairs to a circulating water pump due to increased vibrations and bearing temperatures. On September 20, 2025, the reactor returned to full power following repairs, where it remained for the remainder of the inspection period.

Unit 3 operated at or near full power for the duration of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk significant systems from impending monsoon thunderstorms, on August 28, 2025.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 2, containment spray train B due to overall system risk, on July 25, 2025
(2) Unit 3, high-pressure safety injection train A during high-pressure safety injection train B maintenance, on August 22, 2025
(3) Unit 2, turbine-driven auxiliary feedwater train A following inservice testing, on September 2, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 3, class 1E 4kV switchgear B room and class 1E battery channel B and D rooms, fire zones 5B, 8B, and 9B, on July 15, 2025
(2) Units 1, 2, and 3, electrical penetration rooms, fire zones 42A and 42B, on July 23, 2025
(3) Unit 2, lower cable spreading room, fire zones 11A, 11B, 12, 13 and 14, on August 20, 2025
(4) Unit 2, turbine-driven and motor-driven auxiliary feedwater pump rooms, fire zones 72 and 73, on August 22, 2025
(5) Unit 3, remote shutdown room fire zones, 10A and 10B, on August 26, 2025
(6) Unit 2, essential switchgear train A and B rooms and emergency diesel generator train A and B rooms, fire zones 22A, 22B, 5A, and 5B, during emergency diesel generator A super outage, on September 24, 2025

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator requalification simulator exam activities, on August 28, 2025.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Units 1, 2, and 3, review of the 10 CFR 50.65(a)(3) periodic evaluation, on July 9, 2025
(2) Units 1, 2, and 3, charging pump pulsation dampener train B, on September 5, 2025
(3) Unit 2, emergency diesel generator train A, on September 26, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Units 1, 2, and 3, 4.16 kV FLEX diesel generator A nonfunctional due to failed functional testing, on August 8, 2025
(2) Unit 1, planned work on the number one station blackout generator after surveillance test failure, on September 2, 2025
(3) Unit 2, high risk for emergent work on train B circulating water pump requiring unit down power, on September 18, 2025
(4) Unit 2, emergent work on normal chiller containment isolation valve WCB-UV-61, on September 19, 2025
(5) Unit 2, high risk for planned emergency diesel generator A outage, on September 27, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (7 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 2, containment power access purge isolation valve, CPA-UV-4B, operability determination due to unexpectedly closing during containment venting, on July 15, 2025
(2) Unit 3, emergency diesel generator train B operability determination due to master rod stud stretch measurements outside of specification, on July 22, 2025
(3) Unit 1, main steam system operability determination due to failure of the support hanger 1SG042H011, on August 20, 2025
(4) Unit 3, emergency diesel generator train A operability determination due to control board indication discrepancy, on August 20, 2025
(5) Unit 1, control room essential air temperature controller system train B operability determination due to failed calibration, on September 5, 2025
(6) Units 1, 2, and 3 essential cooling water trains A and B operability determination due to connection to non-seismically qualified piping during alarm response, on September 9, 2025
(7) Unit 1, primary reactor coolant radiation monitor train B, SQB-RU-151, operability determination due to loss of communication with radiation monitoring system, on September 15, 2025

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (2 Samples)

(1) Unit 3, high-pressure safety injection pump B post-maintenance testing following failed breaker replacement, on August 20, 2025
(2) Unit 2, emergency diesel generator A after super outage, on September 30, 2025

Surveillance Testing (IP Section 03.01) (4 Samples)

(1) Unit 1, emergency diesel generator train B, 24-hour rated load, load rejection, and hot start testing, on July 21, 2025
(2) Unit 1, plant protection system bistable trip units functional surveillance testing, on August 6, 2025
(3) Unit 3, low-pressure safety injection pump surveillance testing, on August 07, 2025
(4) Unit 3, train B remote shutdown disconnect switch control circuit operability test, on September 19, 2025

71114.06 - Drill Evaluation

Required Emergency Preparedness Drill (1 Partial)

(1)

(Partial)

The inspectors evaluated an emergency preparedness drill, on August 5, 2025. The inspectors completed the inspection procedure sections 03.01 through 03.02.

Additional Drill and/or Training Evolution (2 Partials)

The inspectors evaluated:

(1)

(Partial)

The inspectors evaluated an emergency preparedness drill, on August 19, 2025. The inspectors completed the inspection procedure sections 03.01 through 03.02.

(2)

(Partial)

The inspectors evaluated an emergency preparedness drill, on September 3, 2025.

The inspectors completed the inspection procedure sections 03.01 through

RADIATION SAFETY

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (5 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1)area radiation monitors in Unit 3 auxiliary building and radwaste building (2)portable survey instruments located in Unit 3 buildings and in the 'ready for use' shelving in Unit 3 (3)stationary radiation monitors in Units 1 and 3, including small article monitors, personnel contamination monitors, and portal monitors (4)laboratory instruments in Unit 2 count room, including a gamma spectroscopy system and a liquid scintillation counter (5)process radiation monitors in Unit 3 auxiliary building and radwaste building

Calibration and Testing Program (IP Section 03.02) (10 Samples)

(1) Thermo-Scientific Model RO-20 ion chamber survey meter S/N 1411, September 10, 2025
(2) Ludlum Model 26-1 frisker, S/N 18522, March 14, 2025
(3) Mirion Amp-100 high range survey meter, S/N 5021191, January 15, 2025
(4) Thermo Fischer Scientific SAM-12 small articles monitor, S/N 6710, November 6, 2024
(5) Thermo Scientific iPCM12 contamination monitor, S/N 12024, January 30, 2025
(6) Thermo Fischer Scientific PM12 portal monitor, S/N 1216, December 4, 2024
(7) KAMAN 'B' Train containment high range monitor, SQBRU0149, April 16, 2025 (8)waste gas decay tank process radiation monitor, Unit 1, RU-12, August 20, 2025 (9)gamma spectroscopy system calibration verification, Unit 2, detector 2, S/N 11447, particulate filter on shelf 1, January 3, 2025
(10) Beckman Coulter liquid scintillation counter, Unit 2, S/N 7070530. May 28, 2020 Effluent Monitoring Calibration and Testing Program Sample (IP Section 03.03) (2 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1) Unit 3, plant vent effluent low range, RU-143, October 30, 2024
(2) Unit 1, fuel handling building B vent exhaust monitor low, RU-145, May 21, 2025

71124.06 - Radioactive Gaseous and Liquid Effluent Treatment

Walkdowns and Observations (IP Section 03.01) (4 Samples)

The inspectors evaluated the following radioactive effluent systems during walkdowns:

(1) Units 2 and 3, plant vent exhaust system
(2) Unit 1, radwaste building ventilation system
(3) Units 1 and 3, fuel building exhaust system
(4) Units 1 and 3, auxiliary building ventilation system

Sampling and Analysis (IP Section 03.02) (4 Samples)

Inspectors evaluated the following effluent samples, sampling processes and compensatory samples:

(1) Unit 3, filter changeout for fuel building exhaust radiation monitoring system (RU-145)
(2) Unit 2, grab sampling for primary to secondary leak rate (RU-141B) and liquid sampling for condensate demineralizer influent
(3) Unit 1, auxiliary feed pump A steam release (AFA-P01)
(4) Unit 3, plant vent exhaust grab sample (RU-143)

Dose Calculations (IP Section 03.03) (2 Samples)

The inspectors evaluated the following dose calculations:

(1)2025 annual dose evaluation for gaseous effluents for Unit 1 (January 1 to September 19, 2025)

(2)2024 annual dose evaluations for gaseous effluents for Unit 3 (January 1 to December 31, 2024)

Abnormal Discharges (IP Section 03.04)

There were no abnormal discharges for the inspectors to evaluate.

71124.07 - Radiological Environmental Monitoring Program

Environmental Monitoring Equipment and Sampling (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated environmental monitoring equipment and observed collection of environmental samples.

Radiological Environmental Monitoring Program (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the implementation of the licensees radiological environmental monitoring program.

GPI Implementation (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees implementation of the Groundwater Protection Initiative program to identify incomplete or discontinued program elements.

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &

Transportation

Radioactive Material Storage (IP Section 03.01)

The inspectors evaluated the licensees performance in controlling, labeling and securing the following radioactive materials:

(1)within the dry active waste processing and storage facility (2)within Units 1 and 3 radwaste truck bays

Radioactive Waste System Walkdown (IP Section 03.02) (1 Sample)

The inspectors walked down the following accessible portions of the solid radioactive waste systems and evaluated system configuration and functionality:

(1) Unit 3 solid radwaste system, specifically the resin processing and transfer system

Waste Characterization and Classification (IP Section 03.03) (2 Samples)

The inspectors evaluated the following characterization and classification of radioactive waste: (1)concentrates (2)dry active wastes

Shipment Preparation (IP Section 03.04) (1 Sample)

(1) The inspectors observed the preparation and shipment of package 25-SH-050 containing radioactive material sent for analysis.

Shipping Records (IP Section 03.05) (3 Samples)

The inspectors evaluated the following non-accepted radioactive material shipments through a record review:

(1)shipment package 23-RW-019 containing low specific activity, LSA-II, metal oxides (2)shipment package 24-RW-046 containing type A dry active waste (3)shipment package 25-RW-010 containing low specific activity, LSA-I, metal oxides

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS06: Emergency AC Power Systems (IP Section 02.05)===

(1) Unit 1 (July 1, 2024, through June 30, 2025)
(2) Unit 2 (July 1, 2024, through June 30, 2025)
(3) Unit 3 (July 1, 2024, through June 30, 2025)

MS07: High Pressure Injection Systems (IP Section 02.06) (3 Samples)

(1) Unit 1 (July 1, 2024, through June 30, 2025)
(2) Unit 2 (July 1, 2024, through June 30, 2025)
(3) Unit 3 (July 1, 2024, through June 30, 2025)

MS08: Heat Removal Systems (IP Section 02.07) (3 Samples)

(1) Unit 1 (July 1, 2024, through June 30, 2025)
(2) Unit 2 (July 1, 2024, through June 30, 2025)
(3) Unit 3 (July 1, 2024, through June 30, 2025)

MS09: Residual Heat Removal Systems (IP Section 02.08) (3 Samples)

(1) Unit 1 (July 1, 2024, through June 30, 2025)
(2) Unit 2 (July 1, 2024, through June 30, 2025)
(3) Unit 3 (July 1, 2024, through June 30, 2025)

MS10: Cooling Water Support Systems (IP Section 02.09) (3 Samples)

(1) Unit 1 (July 1, 2024, through June 30, 2025)
(2) Unit 2 (July 1, 2024, through June 30, 2025)
(3) Unit 3 (July 1, 2024, through June 30, 2025)

71153 - Follow-Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 2025-003-00, Unit 1 Specified System Actuation due to Loss of Power (LOP)/Load Shed (LS) Signal (ADAMS Accession No. ML25156A358)

The inspection conclusions associated with this LER and associated finding are documented in the Inspection Results section 71153. This LER is closed.

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71111.15 This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Title10 CFR Part 50, Appendix B, Criterion III, Design Control, states, in part, that design control measures shall provide for verifying or checking the adequacy of design, such as by the performance of design reviews, by the use of alternate or simplified calculation methods, or by the performance of a suitable testing program.

Contrary to the above, until August 1, 2024, the licensee failed to provide design control measures for verifying or checking the adequacy of seismic qualification of the essential cooling water system, such as by the performance of design reviews or by the performance of a suitable testing program. Specifically, the licensees failure to check the adequacy of the design of the essential cooling water system by the performance of design reviews or engineering evaluation resulted in the inability of the essential cooling water system to maintain adequate water inventory to perform its safety-related function for the duration of its mission time during a seismic event resulting in a pipe break when isolation valves between non-quality related seismic category III piping and quality-class seismic category I piping were open, affecting the reliability of the essential cooling water system to respond to initiating events to prevent undesirable consequences.

Significance/Severity: Green. The inspectors determined the performance deficiency is more than minor because it adversely affected the Configuration Control attribute of the Mitigating Systems Cornerstone. The inspectors assessed the significance of the finding using Inspection Manual Chapter 0609 Appendix A, The Significance Determination Process for Findings At-Power, dated January 1, 2021. The inspectors screened the finding using Exhibit 2 - Mitigating Systems Screening Questions. The inspectors determined that the finding had very low safety significance (Green) because the valves in question have not been open for greater than the allowed technical specification outage time and the finding: 1) is not a deficiency affecting the design or qualification of a mitigating structure, system, or component; 2) does not represent a loss of the probability risk analysis (PRA) function of a single train TS system for greater than its TS allowed outage time; 3) does not represent a loss of the PRA function of one train of a multi-train TS system for greater than its TS allowed outage time; 4) does not represent a loss of the PRA function of two separate TS systems for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />; 5) does not represent a loss of a PRA system and/or function as defined in the plant risk information e-book or the licensee's PRA for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />; and 6) does not represent a loss of the PRA function of one or more non-TS trains of equipment designated as risk-significant in accordance with the licensee's maintenance rule program for greater than 3 days.

Corrective Action References: The licensee has documented the performance deficiency in their corrective action program in Condition Report 24-06486.

Partial Loss of Offsite Power and Loss of Spent Fuel Pool Cooling due to Inadequate Procedure Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000528/2025003-01 Open/Closed

[H.12] - Avoid Complacency 71153 A self-revealed Green finding and associated Non-cited Violation (NCV) of Technical Specification 5.4.1.a was identified when the licensee failed to adequately establish and perform maintenance procedures appropriate to the circumstances, as required in Regulatory Guide 1.33, Quality Assurance Program Requirements, revision 2. Specifically, procedure 40OP-9SA02, De-Energization of BOP-ESFAS, revision 27, did not adequately ensure that the required step of lifting load shed relays K202 and K204 would be completed, resulting in a subsequent partial loss of offsite power and loss of spent fuel pool augmented cooling.

Description:

On April 8, 2025, Unit 1 was defueled for refueling outage 1R25. Balance of Plant Engineered Safety Features Actuation System (BOP-ESFAS) trains A and B (safety-related) were deenergized for maintenance and the installation of a modification on train B using procedure 40OP-9SA02, De-Energization of BOP-ESFAS, revision 27. Unit 1 PBA-S03 Class 1E 4.16kV bus, which is normally powered through engineering safety features transformers, was being supplied by offsite power via the NBN-X04 non-class transformer through its alternate supply breaker PBA-S03K because breaker NBN-X03 was tagged out for planned maintenance. The licensee developed [AS2] [NA3] [AS4] Train A Emergency Diesel Generator (DG) Safety Protection Plan, revision 0 [AS5] to maintain the availability of EDG train A during the BOP-ESFAS de-energization and it was staged prior to the maintenance and operator responsibilities were briefed and logged at the beginning of every shift.

At 7:24 p.m., while BOP-ESFAS train A was being reenergized under procedure 40OP-9SA02, a valid loss of power/load shed signal actuated. This opened the PBA-S03K alternate supply breaker resulting in a loss of power to the PBA-S03 bus. The loss of power to PBA-S03 resulted in the associated train A equipment being de-energized, including the train A containment spray pump, which provided augmented cooling to the spent fuel pool and fuel pool cooling pump A. Operators implemented the Train A Emergency Diesel Generator (DG)

Safety Protection Plan, to manually start EDG A. Electrical power was restored to PBA-S03 bus at 7:34 p.m. from EDG A, and spent fuel pool cooling was restored using abnormal operating procedure 40AO-9ZZ23, Loss of Spent Fuel Pool Level/Cooling, revision 35.

The licensee initiated a condition report and performed a level 2 cause analysis to determine the cause of the event. The licensee determined that procedure 40OP-9SA02, De-Energization of BOP-ESFAS, revision 27, step 6.1.14 identified an action step to be performed by multiple users to notify the instrumentation and controls personnel to perform the steps to lift leads on the C2 terminals of the load shed relays K202 and K204.

However, with no subsequent step for operations personnel to confirm completion that instrumentation and controls had completed this step. This critical step to have instrumentation and control personnel lift the load shed relay leads had been marked N/A because of an assumption that lifting the leads was not required and had already been performed. Consequently, during the pre-job brief on the morning of April 8, 2025, for the re-energization of BOP-ESFAS train A, the unit shift manager and control room supervisor did not take issue or challenge the N/A of the non-conditional step to have the load shed leads lifted. The leads of the load shed relays K202 and K204 not being lifted during the energizing of BOP-ESFAS train A resulted in the valid loss of power/load shed signal, opening of the PBA-S03K breaker, and subsequent loss of power to PBA-S03 bus and spent fuel pool cooling.

Corrective Actions: The licensee entered abnormal operating procedures 40AO-9ZZ12, Degraded Electrical Power, revision 84, and 40AO-9ZZ23, Loss of SFP Level or Cooling, revision 35, to manually start EDG A and restore power to the PBA-S03 bus. This restored power to containment spray pump A which restored augmented spent fuel pool cooling.

Corrective Action References: Condition Report 25-04039

Performance Assessment:

Performance Deficiency: The failure to establish and implement written procedures appropriate to the circumstance for maintenance that can affect the performance of safety-related equipment is a performance deficiency. The cause was reasonably within the licensees ability to foresee and correct because the licensee failed to establish written procedures that would ensure the successful completion of lifting the load shed relay leads.

Specifically, the licensees procedure 40OP-9SA-02, De-Energization of BOP-ESFAS, revision 27, step 6.1.14 only required the notification to instrumentation and controls to perform the lifting of the load shed relay leads K202 and K204 without a requirement for confirmation of the completion of this step, directly resulting in a partial loss of off-site power and subsequent loss of augmented spent fuel pool cooling.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Configuration Control attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. The inspectors determined the performance deficiency was more than minor because it was associated with the Configuration Control attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, the licensees failure to establish the procedure to install cross train jumpers and lift leads for the load shed relays to support de-energizing BOP-ESFAS train A was not written in a way to confirm completion. Not lifting the K202 and K204 relay leads resulted the partial loss of offsite power due to a valid loss of power/load shed signal resulting in the containment spray pump A to be deenergized and a loss of augmented cooling to the spent fuel pool, adversely affecting the spent fuel pools ability to protect the public from radionuclide releases caused by accidents or events.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power.

Cross-Cutting Aspect: H.12 - Avoid Complacency: Individuals recognize and plan for the possibility of mistakes, latent issues, and inherent risk, even while expecting successful outcomes. Individuals implement appropriate error reduction tools. Individuals recognize and plan for the possibility of mistakes, latent issues, and inherent risk, even while expecting successful outcomes. Individuals implement appropriate error reduction tools. Specifically, the licensees procedure 40OP-9SA02, De-Energization of BOP-ESFAS, revision 27, only provided and action step to notify instrumentation and control to install jumpers and lift the load shed relay leads with no subsequent step to confirm completion of their actions.

Enforcement:

Violation: Technical specification 5.4.1.a states in part, that written procedures shall be established, implemented, and maintained coveringthe applicable procedures recommended in Regulatory Guide 1.33, revision 2, Appendix A, section 9, Procedures for Performing Maintenance, which requires, in part, that maintenance that can affect the performance of safety-related equipment should be properly pre-planned and performed in accordance with written procedures, documented instruction, or drawings appropriate to the circumstances. The licensee established operating procedure 40OP-9SA02, De-Energization of BOP-ESFAS, revision 27 to meet this requirement.

Contrary to the above, on April 8, 2025, the licensee failed to adequately pre-plan and perform maintenance that can affect the performance of safety-related equipment in accordance with written procedures and documented instructions. Specifically, operating procedure 40OP-9SA02, De-Energization of BOP-ESFAS, revision 27 failed to include adequate instruction to lift relay leads K202 and K204, which resulted in a valid loss of power/load shed signal causing the loss of power to PBA-S03 bus and subsequent loss of containment spray pump A which was providing augmented cooling to the spent fuel pool.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified that no proprietary information was retained or documented in this report.

  • On September 25, 2025, the inspectors presented the radiation safety inspection results to Cary Harbor, Senior Vice President, Site Operations, and other members of the licensee staff.
  • On December 9, 2025, the inspectors presented the integrated inspection results to Cary Harbor, Senior Vice President, Site Operations and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

01DP-0XX01

Control and Monitoring of Potential Tornado Borne Missiles

71111.01

Procedures

40AO-9ZZ21

Acts of Nature

71111.01

Procedures

40DP-9ZZ17

Control of Doors, Hatches and Floor Plugs

71111.04

Corrective Action

Documents

16-04430, 17-15953, 25-00048, 24-01709, 25-09056, 25-

09057

71111.04

Drawings

01-M-SIP-001

P & I Diagram Safety Injection & Shutdown Cooling System

71111.04

Drawings

2-M-AFP-001

P & I Diagram Auxiliary-Feedwater System

71111.04

Drawings

2-M-SGP-001

P & I Diagram Main Steam System

71111.04

Drawings

2-M-SIP-001

P & I Diagram Safety Injection & Shutdown Cooling System

71111.04

Drawings

03-P-SIF-203

Auxiliary BLDG Isometric Safety Injection System HPSI

Pump DISCH Train A & RWT

71111.04

Miscellaneous

2-9321469-002

Risk-Informed Application Document - Palo Verde

Generating Station 10CFR50.69 System Categorization

Document for Safety Injection

71111.04

Procedures

40ST-9SI14

Train B LPSI and CS System Alignment Verification

71111.04

Procedures

73ST-9AF02

Auxiliary Feedwater A - Inservice Test

71111.04

Work Orders

25370, 5630668, 5610143, 5749401, 5625370, 5630668

71111.05

Corrective Action

Documents

18-09532, FSCCR 5740572, 25-08940, 25-09001

71111.05

Drawings

03-E-FPF-005

Control Wiring Diagram Fire Protection System

71111.05

Drawings

13-A-ZJD-0501

Control Building and Corridor Building Floor Plan at

Elevation 74, 100, 120

71111.05

Drawings

13-M-FPP-006

Auxiliary Building Channel B Cable Trays 100 Level East

Half

71111.05

Drawings

13-M999-00004

Halon Fire Suppression System for Remote Shutdown

Room

71111.05

Drawings

13-P-FPG-300

Schematic Diagram Halon-1301 Fire Protection System for

Remote Shutdown Rooms Train A and Train B @ 100ft

Elev.- Control BLDG.

71111.05

Miscellaneous

Pre-Fire Strategies Manual

71111.05

Procedures

38FT-9QK16

Fire Detection/Protection System Supervised

Circuits/Functional Test - Halon Panels

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.05

Procedures

40DP-9ZZ17

Control of Doors, Hatches and Floor Plugs

71111.05

Work Orders

5748465, 5749206

71111.11Q

Corrective Action

Documents

25-09270

71111.11Q

Miscellaneous

SES-0-04-P-09

Palo Verde Nuclear Generating Station Licensed Operator

Continuing Training Exam Scenario

71111.12

Corrective Action

Documents

25-01315, 25-05599, 25-06225, 25-06227, 25-06328, 24-

07598, 25-01245, 25-01624, 25-02566, 25-02567, 25-

10497, 25-10422

71111.12

Miscellaneous

71111.12

Miscellaneous

5069-CH-01

CFR 50.69 System Categorization Chemical and Volume

Control System (CH)

71111.12

Miscellaneous

5069-CH-01

CFR 50.69 System Categorization Chemical and Volume

Control System (CH)

71111.12

Miscellaneous

MR-A1-EVAL-

25-0015

MR 2.0 - MR (a)(1) Issue Worksheet

71111.12

Miscellaneous

PMB-CH, MR 2.0-

Performance Monitoring Bases Document Worksheet: CH

71111.12

Procedures

01DP-0RS07

CFR 50.69 Program

71111.12

Procedures

01DP-0RS08

CFR 50.69 Active Component Categorization From

Qualitative Assessment and Defense-In-Depth

71111.12

Procedures

31MT-9DG05

Installation and Removal of DG A Temporary Piping

Supports

71111.12

Procedures

2FT-9QD06

Annual Fire Protection Test for QDN-N06

71111.12

Procedures

2MT-9PE01

Cleaning, Inspection, and Testing of the Class 1E Diesel

Generator

71111.12

Procedures

40AO-9ZZ19

Control Room Fire

71111.12

Procedures

40OP-9DF01

Diesel Fuel Oil Storage and Transfer (DF)

71111.12

Procedures

70DP-0MR02

Maintenance Rule Monitoring Process

71111.12

Work Orders

5733844, 5743998, 5635705, 5635582, 5635694, 5635808,

5635581, 5635635, 5631470

71111.13

Corrective Action

Documents

25-08289, 25-08440, 24-12325, 25-10157, 25-08294, 25-

01094, 25-08699

71111.13

Drawings

01-J-HJE-051

Instrument LOOP Wiring Diagram Control Building HVAC

71111.13

Miscellaneous

Integrated Risk Assessment for SURV# 5631303

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.13

Miscellaneous

FME Risk Evaluation MEDDET-DB-ID 11341140

71111.13

Miscellaneous

Site Integrated Risk Assessment Work Task 5744929-0

71111.13

Miscellaneous

Formal Troubleshooting Game Plan-SBOG Overspeed

Troubleshooter Related to CR 25-08440 and WO 57444939-

71111.13

Miscellaneous

PV-E2316

Risk Management and Readiness Plan

71111.13

Miscellaneous

RICT-US-2025-01

Risk Informed Completion Time Summary

71111.13

Procedures

Work Instruction for CM# 5744104 - Task #0

71111.13

Procedures

01DP-9ZZ01

Systematic Troubleshooting

71111.13

Procedures

2DP-0RS01

Online Integrated Risk

71111.13

Procedures

14MT-9BD21

FLEX 2 MW Diesel Generator Inspections and Tests

71111.13

Procedures

2MT-9ZZ74

Molded Case Circuit Breaker Test

71111.13

Procedures

36ST-9SA02

ESFAS Train B Subgroup Relay Functional Test

71111.13

Procedures

37MT-9ZZ01

Vibration Survey

71111.13

Procedures

40MG-9ZZ03-003

TSG-3: Site Capabilities

71111.13

Procedures

40MG-9ZZ07-001

FLEX Support Guidelines MODE 1, 2, 3, or 4

71111.13

Procedures

40MG-9ZZ07-002

FLEX Support Guidelines MODE 5, 6, or Defueled

71111.13

Procedures

40ST-9DG01

Diesel Generator Test

71111.13

Procedures

70DP-0RA05

Assessment and Management of Risk When Performing

Maintenance in Modes 1 and 2

71111.13

Procedures

M008-00032

Pump Cross Section Bottom Half

71111.13

Procedures

M008-00041

Assembly of Shaft and Impeller 1076/PI-49 DWG 80257,

71111.13

Procedures

M008-00049

Assembly of Pump-Top-Half

71111.13

Work Orders

5556503, 5585720, 5554860, 5744939, 5756974, 5744104,

5631303, 5746709

71111.15

Calculations

13-MC-SG-0501

Main Steam Line Inside Containment

71111.15

Corrective Action

Documents

25-07712, 17-13429, 18-14835, 19-03217, 25-01939, 25-

03392, 25-03411, 23-10262, 25-08334, 25-08543, 25-

06563, 25-08699, 24-06486, 24-13966

25-08100, 25-08468

71111.15

Drawings

2-M-CPP-001

P & I Diagram Containment Purge System

71111.15

Miscellaneous

PVNGS Design Basis Manual - Containment Purge System

71111.15

Miscellaneous

EDC# 2005-00359

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.15

Miscellaneous

VTD-C628-00051

Cooper Energy Instruction Manual for KSV Turbocharged

Diesel Generating Unit for Nuclear Power Plant Emergency

Stand-By Service

71111.15

Procedures

01DP-0AP09

Procedure and Work Instruction Use and Adherence

71111.15

Procedures

40DP-9OP26

Operations Operability Determination Process

71111.15

Procedures

40OP-9EW01

Essential Cooling Water System (EW) Train A

71111.15

Procedures

40OP-9EW01

Essential Cooling Water System (EW) Train A

71111.15

Procedures

40OP-9EW01

Essential Cooling Water System (EW) Train A

71111.15

Procedures

40OP-9SG01

Main Steam

71111.15

Procedures

40ST-9DG01

Diesel Generator A Test

71111.15

Procedures

73DP-9ZZ14

Surveillance Testing

71111.15

Procedures

73ST-9XI15

CP (Power Access Purge) Valves - Inservice Test

71111.15

Procedures

74RM-9EF43

Actions for Non-Functional Radiation Monitors: Preplanned

Alternat Sampling Program

71111.15

Procedures

74RM-9EF80

RMS/Effluent Action Documentation

71111.15

Work Orders

5710188, 5570282, 5614092, 5746709

71111.24

Corrective Action

Documents

25-07934, 25-03940, 25-08564, 25-08739, 25-08808, 25-

08809, 25-09178, 25-09866, 25-09940, 24-06468, 25-

10085, 25-10083, 25-01094

71111.24

Drawings

01-E-SBB-00005

E/D Plant Protection System Cabling Block Diagram

71111.24

Drawings

03-M-SIP-0001

P&ID Diagram Safety Injection & Shutdown Cooling System

71111.24

Drawings

N001-1303-00078

Plant Protection System Simplified Functional Diagram

VCE7914

71111.24

Drawings

N001-1303-00805

PPS, Initiation Reset Panel Schematic VCE-31245

71111.24

Procedures

36ST-9SB02

PPS Bistable Trip Units Functional Test

71111.24

Procedures

40DP-9OP08

Diesel Generator Test Record

71111.24

Procedures

40ST-9DG01

Diesel Generator A Test

71111.24

Procedures

40ST-9ZZ25

Remote Shutdown Disconnect Switch and Control Circuit

Operability - All Modes

71111.24

Procedures

73ST-9DG08

Class 1E Diesel Generator Load Rejection, 24 Hour Rated

Load and Hot Start Test Train B

71111.24

Procedures

73ST-9SI10

HPSI Pumps Miniflow - Inservice Test

71111.24

Procedures

73ST-9SI11

Low Pressure Safety Injection Pumps Miniflow - Inservice

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Test

71111.24

Work Orders

5553779, 5613929, 5614096, 5625443, 5625514, 5754304,

5631303

71114.06

Miscellaneous

MESSAGE: 1.1 OPS ADV - SEISMIC EVENT, ATWS,

HPSC LEAK, SURGE TANK OVERFLOW, 148/149 LEVELS

2503 ERO Drill

71114.06

Miscellaneous

2503 Drill Objectives Work Sheet

71114.06

Miscellaneous

2503 Drill General Information

71114.06

Procedures

40AO-9ZZ21

Acts of Nature

71114.06

Procedures

40EP-9EO01

Standard Post Trip Actions

71114.06

Procedures

EP-0900-026

ERO Positions - Operations Manager (TSC)

71114.06

Procedures

EP-0900-09

ERO Positions - Emergency Coordinator (TSC)

71124.05

Calibration

Records

AMS-4 S/N

2930

Certificate of Calibration

10/01/2024

71124.05

Calibration

Records

DRM 2 S/N

2611031

DRM 1/2 Calibration Data Sheet

03/11/2025

71124.05

Calibration

Records

H809V-1 S/N

2888

Air Sampler Calibration Data Sheet

2/13/2025

71124.05

Calibration

Records

Model 30 S/N

25025219

Neutron Detector Calibration Data Sheet

04/19/2025

71124.05

Calibration

Records

Model 89, SN

20

Shepherd Model 89 Verification Sheet

04/17/2025

71124.05

Calibration

Records

SAM-12, S/N

6700

Small Article Monitor Calibration Data Sheet

09/25/2025

71124.05

Calibration

Records

Unit 2, Detector 2

- CCART

MCA HpGE Geometry Calibration - Charcoal Cartridge on

shelf 1

07/21/2023

71124.05

Calibration

Records

Unit 2, Detector 2

- PFIL

MCA HpGE Geometry Calibration - Particulate Filter on shelf

07/21/2023

71124.05

Calibration

Records

W/O 5496234

Radiation Monitor Calibration for Baseline Process Monitors

- B train (1JSQBRU0030)

2/13/2025

71124.05

Calibration

Records

W/O 5509856

Radiation Monitor Calibration for RU-144 (1JSQNRE0144)

05/10/2024

71124.05

Calibration

Records

W/O 5518707

Radiation Monitor Calibration for Baseline Area Monitors - B

train (2JSQBRU0038)

06/11/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.05

Calibration

Records

W/O 5549247

Radiation Monitor Calibration for RU-143 (3JSQNRE0143)

11/04/2024

71124.05

Corrective Action

Documents

15-08740, 21-01090, 21-10318, 22-13251, 23-06829, 23-

2468, 23-12634, 24-00528, 24-00817, 24-01436, 24-

01573, 24-02126, 24-03012, 24-04492, 24-05497, 24-

06992, 24-07132, 24-07327, 24-07541, 24-07720, 24-

07853, 24-08507, 24-09904, 24-10407, 24-10764, 24-

10782, 24-11204, 24-11352, 24-12110, 24-12712, 24-

2760, 24-13064, 25-00119, 25-03847, 25-06279, 25-

08795, 25-08911, 25-08981

71124.05

Corrective Action

Documents

Resulting from

Inspection

25-13728

71124.05

Procedures

74ST-9SQ12

Effluent Flowpath Process Flow Calibration

71124.05

Procedures

74ST-9SQ35

Train B Radiation Monitoring Calibration Test for

Containment New Scope Area Monitors

71124.05

Procedures

75RP-9EQ45

Calibration of the Thermo Eberline Model FH40G-L

71124.05

Procedures

75RP-9EQ66

Calibration of the Thermo Scientific Model RO-20 Ion

Chamber Survey Meter

71124.05

Procedures

ODCM

Offsite Dose Calculation Manual, Palo Verde Nuclear

Generating Station, Units 1,2, and 3

71124.05

Self-Assessments 2025-005

Nuclear Assurance Department Audi Report - Radiation

Safety

08/21/2025

71124.06

Corrective Action

Documents

2-05735, 22-06299, 22-06989, 22-07092, 22-08280, 22-

08417, 22-08516, 22-08606, 22-09286, 22-09697, 22-

09851, 22-10795, 22-11462, 22-12337, 22-12469, 22-

2791, 23-03549, 23-08540, 23-08641, 23-09369, 23-

13094, 24-06225, 24-12924, 24-13086, 24-13186, 25-

04097, 25-05293, 25-07910, 25-07927

71124.06

Corrective Action

Documents

Resulting from

Inspection

25-10387

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.06

Drawings

01-M-HRP-001

P&I Diagram HVAC Radwaste Building

71124.06

Drawings

01-P-ZRC-603

Radwaste Building - Level 3 HVAC Plan Between El. 140'-

0" and Roof

71124.06

Drawings

03-P-ZRC-604

Radwaste Building - Level 4 HVAC Plan at Roof

71124.06

Miscellaneous

Results of Radiochemistry Cross Check Program: Arizona

Public Service Palo Verde 4th Quarter 2022

04/20/2023

71124.06

Miscellaneous

Results of Radiochemistry Cross Check Program: Arizona

Public Service Palo Verde 4th Quarter 2023

03/19/2024

71124.06

Miscellaneous

Results of Radiochemistry Cross Check Program: Arizona

Public Service Palo Verde 4th Quarter 2024

2/25/2025

71124.06

Miscellaneous

PVNGS Radioactive Effluent Release Permit Summary

Report: Units 1, 2, and 3 - Year 2022 (01/01/2022 -

2/31/2022)

22

71124.06

Miscellaneous

PVNGS Radioactive Effluent Release Permit Summary

Report: Units 1, 2, and 3 - Year 2023 (01/01/2023 -

2/31/2023)

23

71124.06

Miscellaneous

PVNGS Radioactive Effluent Release Permit Summary

Report: Units 1, 2, and 3 - Year 2024 (01/01/2024 -

2/31/2024)

24

71124.06

Miscellaneous

PVNGS Radioactive Effluent Release Permit Summary

Report: Units 1, 2, and 3 - Year 2025 (01/01/2025 -

9/15/2025)

25

71124.06

Miscellaneous

Offsite Dose Calculation Manual, Palo Verde Nuclear

Generating Station, Units 1, 2, and 3

71124.06

Miscellaneous

Permit 2025-1-

25

Unit 1, auxiliary feed pump 'A' steam release (AFA-P01)

09/23/2025

71124.06

Miscellaneous

Permit 2025-3-

110

Unit 3, filter changeout for fuel building exhaust radiation

monitoring system (RU-145)

09/23/2025

71124.06

Miscellaneous

Permit 2025-3-

111

Unit 3, plant vent exhaust grab sample (RU-143)

09/23/2025

71124.06

Miscellaneous

RCTSAI 1566

24 Palo Verde Nuclear Generating Station Units 1, 2, and

Annual Radioactive Effluent Release Report

04/17/2025

71124.06

Miscellaneous

RCTSAI 1566

23 Palo Verde Nuclear Generating Station Units 1, 2, and

Annual Radioactive Effluent Release Report

04/17/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.06

Miscellaneous

RCTSAI 1566

22 Palo Verde Nuclear Generating Station Units 1, 2, and

Annual Radioactive Effluent Release Report

04/24/2023

71124.06

Miscellaneous

RCTSAI 1566

Updated 2023 Palo Verde Nuclear Generating Station Units

1, 2, and 3 Annual Radioactive Effluent Release Report

11/05/2024

71124.06

Miscellaneous

RCTSAI 1643

23 Palo Verde Nuclear Generating Station Units 1, 2, and

Annual Radiological Environmental Operating Report

05/10/2024

71124.06

Miscellaneous

RCTSAI 1643

24 Palo Verde Nuclear Generating Station Units 1, 2, and

Annual Radiological Environmental Operating Report

05/09/2025

71124.06

Miscellaneous

Sample G2-25-

0845

Unit 2, grab sampling for primary to secondary leak rate

(RU-141B)

09/24/2025

71124.06

Miscellaneous

Sample L2-25-

0846

Unit 2, liquid sampling for primary to secondary leak rate

with condensate demineralizer influent (CDI)

09/24/2025

71124.06

Procedures

40OP-9GR01

Operation of Gaseous Radwaste System

71124.06

Procedures

74RM-9EF20

Gaseous Radioactive Release Permits and Offsite Dose

Assessment

71124.06

Procedures

74RM-9EF40

Radiation Monitoring System Operations

71124.06

Procedures

74RM-9EF41

Radiation Monitoring System Alarm Response

71124.06

Procedures

74RM-9EF42

Radiation Monitor Alarm Setpoint Determinations

71124.06

Procedures

74RM-9EF60

RMS Sample Collection

71124.06

Procedures

74RM-9EF63

RU-143/RU-144 Sample Operations

71124.06

Procedures

74RM-9EF65

RU-145/146 Sample Operations

71124.06

Procedures

74ST-9SQ04

Effluent Monitor Monthly Source Checks

71124.06

Procedures

74ST-9SQ07

Radiation Monitoring System Shiftly Surveillance Test

71124.06

Procedures

75RM-9EF01

Determination of Primary-To-Secondary Leak Rate

71124.06

Self-Assessments 2023-004

Nuclear Assurance Department (NAD) Audit Report:

Radiation Safety

09/13/2023

71124.06

Self-Assessments 2025-005

Nuclear Assurance Department (NAD) Audit Report:

Radiation Safety

08/21/2025

71124.06

Self-Assessments 302-03922

Offsite Safety Review Committee (OSRC) Meeting 24-001,

Operations, Chemistry, and Radiation Protection

Subcommittee Report

09/21/2023

71124.06

Self-Assessments 302-03938

Offsite Safety Review Committee (OSRC) Meeting 24-001,

Operations, Chemistry, and Radiation Protection

Subcommittee Report

03/29/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.06

Self-Assessments 302-03945

Offsite Safety Review Committee (OSRC) Meeting 24-002,

Operations, Chemistry, and Radiation Protection

Subcommittee Report

10/08/2024

71124.06

Work Orders

WO 5346472, 5397633, 5456538, 5487711, 5540561

71124.07

Calibration

Records

5505031

77ST9RG051 METEOROLOGICAL SYSTEM

CALIBRATION

( REDUNDANT SYSTEM)

04/16/2024

71124.07

Calibration

Records

5505114

77ST9RG041 METEOROLOGICAL SYSTEM

CALIBRATION (PRIMARY

SYSTEM)

04/17/2024

71124.07

Calibration

Records

5550731

77ST9RG051 METEOROLOGICAL SYSTEM

CALIBRATION

( REDUNDANT SYSTEM)

10/28/2024

71124.07

Calibration

Records

5550833

77ST9RG041 METEOROLOGICAL SYSTEM

CALIBRATION (PRIMARY

SYSTEM)

10/29/2024

71124.07

Calibration

Records

5594117

77ST9RG051 METEOROLOGICAL SYSTEM

CALIBRATION

( REDUNDANT SYSTEM)

06/13/2025

71124.07

Calibration

Records

5594490

77ST9RG041 METEOROLOGICAL SYSTEM

CALIBRATION (PRIMARY

SYSTEM)

06/17/2025

71124.07

Corrective Action

Documents

2-05573, 22-05633, 22-05697, 22-06461, 22-06449, 22-

07142, 22-07921, 22-09005, 22-09144, 22-10006, 22-

11598, 22-12655, 22-13436, 22-13455, 23-01724, 23-

03754, 23-04147, 23-04635, 23-04847, 23-05482, 23-

05484, 23-05726, 23-05767, 23-06383, 23-06793, 23-

06794, 23-07026, 23-07088, 23-07256, 23-07460, 23-

07777, 23-08785, 23-09404, 23-12560, 23-12693, 23-

2897, 23-13147, 24-00302, 24-00356, 24-00886, 24-

2928, 24-03327, 24-03662, 24-04075, 24-04464, 24-

06117, 24-06216, 24-06761, 24-06778, 24-07269, 24-

07445, 24-07503, 24-08229, 24-08393, 24-08468, 24-

09818, 24-10327, 24-10864, 24-10891-001, 25-02622, 25-

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2626, 25-02876, 25-03981, 25-05492, 25-06308, 25-

06630, 25-06719, 25-06724, 25-06892, 25-08002, 25-

08530, 25-10425, 25-10425-001

71124.07

Miscellaneous

117-127806-

24001

Pace Analytical Report

APS-Palo Verde Nuclear Generating Stat

Sample Delivery Group: L1835676

03/28/2025

71124.07

Miscellaneous

117-127806-

24001

Pace Analytical Report

APS-Palo Verde Nuclear Generating Stat

Sample Delivery Group: L1851082

05/21/2025

71124.07

Miscellaneous

ACT 4657834

REMP Air Sampling Siting Evaluation

11/14/2017

71124.07

Miscellaneous

Legacy Item

No.036843.01

Annual Radiological Environmental Operating Report 2024

Palo Verde Nuclear Generating Station

RCTSAI 1643

05/09/2025

71124.07

Miscellaneous

Legacy Item

No.036843.01

Annual Radiological Environmental Operating Report 2022

Palo Verde Nuclear Generating Station

RCTSAI 1643

03/30/2023

71124.07

Miscellaneous

Legacy Item

No.036843.01

Annual Radiological Environmental Operating Report 2023

Palo Verde Nuclear Generating Station

RCTSAI 1643

05/09/2024

71124.07

Miscellaneous

ODCM_Rev 33

OFFSITE DOSE CALCULATION MANUAL PALO VERDE

NUCLEAR GENERATING STATION

UNITS 1, 2, AND 3

71124.07

Miscellaneous

PV-3A-0625

Pace Analytical Report

APS-Palo Verde Nuclear Generating Stat

Sample Delivery Group: L1868941

07/14/2025

71124.07

Miscellaneous

Site 4

Trending_Rev3

Particulate Gross Beta in Air and Radioiodine in Air for 2023

71124.07

Miscellaneous

TRM 072

Technical Requirements Manual

71124.07

Miscellaneous

UFSAR REV22B

February 2025

Updated Final Safety Analysis Report

Palo Verde Nuclear Generating Station Units 1, 2, and 3

2B

71124.07

Miscellaneous

USNRC Docket

24 ANNUAL RADIOACTIVE EFFLUENT RELEASE

04/15/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

No. STN 50-

28/529/530

REPORT

PALO VERDE NUCLEAR GENERATING STATION UNITS

1, 2 AND 3

RCTSAI 1566

71124.07

Miscellaneous

USNRC Docket

No. STN 50-

28/529/530

23 ANNUAL RADIOACTIVE EFFLUENT RELEASE

REPORT

PALO VERDE NUCLEAR GENERATING STATION UNITS

1, 2 AND 3

RCTSAI 1566

04/13/2024

71124.07

Miscellaneous

USNRC Docket

No. STN 50-

28/529/530

22 ANNUAL RADIOACTIVE EFFLUENT RELEASE

REPORT

RCTSAI 1566

04/24/2023

71124.07

Operability

Evaluations

218-04808-

MLC/MLC

Decommissioning Records Review and 10CFR50.75(g)(1)

Applicability Review

for 2021

06/16/2022

71124.07

Operability

Evaluations

218-04895

22 Spill/Leak Decommissioning Impact Review

04/28/2023

71124.07

Operability

Evaluations

218-05041

23 Spill/Leak Decommissioning Impact Review

03/19/2025

71124.07

Operability

Evaluations

218-05042

24 Spill/Leak Decommissioning Impact Review

03/25/2025

71124.07

Procedures

218-04808

Decommissioning Records Review and 10CFR50.75(g)(1)

Applicability Review

for 2021

07/16/2022

71124.07

Procedures

218-04895

22 Spill/Leak Decommissioning Impact Review

04/28/2023

71124.07

Procedures

218-04916

Decommissioning Records Review and 10CFR50.75(g)(1)

Applicability Review

for 2022

08/17/2023

71124.07

Procedures

218-05041

23 Spill/Leak Decommissioning Impact Review

03/19/2025

71124.07

Procedures

218-05042

24 Spill/Leak Decommissioning Impact Review

03/25/2025

71124.07

Procedures

218-05050

Decommissioning Records Review and 10CFR 50.75(g)(1)

Applicability Review 2023 and 2024

04/30/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.07

Procedures

74-RM-0EN02

Radiological Environmental Air Sampling

71124.07

Procedures

74CH-9ZZ69

Operation of the Liquid Scintillation Systems

71124.07

Procedures

74RM-0EN03

Radiological Environmental Sampling

71124.07

Procedures

74RM-0EN05

Environmental TLD Exchange/Reporting

71124.07

Procedures

74RM-0EN07

Land Use Census

71124.07

Procedures

74RM-9EN01

Sentinel Well Sampling Instructions

71124.07

Procedures

75DP-9AP01

Groundwater Protection Program

71124.07

Procedures

77ST-9RG04

Meteorological System Instrumentation Replacement and

Verification (Primary System)

71124.07

Procedures

77ST-9RG05

Meteorological System Instrumentation Replacement and

Verification (Redundant System)

71124.07

Self-Assessments Audit 2023-004

Nuclear Assurance Department (NAD) Audit Report

71124.07

Self-Assessments Audit 2025-005

Nuclear Assurance Department (NAD) Audit Report

25-005 Radiation Safety

71124.08

Corrective Action

Documents

23-07436, 23-12134, 23-12205, 24-07632, 24-07632, 25-

07151, 25-07747, 25-07777, 25-07778, 25-07779, 25-

07780, 25-07782, 25-07784, 25-07787, 25-10626

71124.08

Miscellaneous

LLRMSF and SG Mausoleum Quarterly Testing and

Inspection

03/05/2024

71124.08

Miscellaneous

LLRMSF and SG Mausoleum Quarterly Testing and

Inspection

09/25/2024

71124.08

Miscellaneous

LLRMSF and SG Mausoleum Quarterly Testing and

Inspection

2/03/2024

71124.08

Miscellaneous

Radiation Protection Logbook: Low Level Radioactive

Material Storage Facility (Monthly): July 2024 and February

25

71124.08

Miscellaneous

LLRMSF and SG Mausoleum Quarterly Testing and

Inspection and Annual Maintenance

06/06/2024

71124.08

Miscellaneous

ESD 86-35

CFR 37 Security Just in Time Training: Category 2

Radioactive Material

03/12/2014

71124.08

Miscellaneous

ESD 86-44

Nuclear Security Training Lesson Plan: Protected Area

Mobile

08/22/2023

71124.08

Miscellaneous

NBA11C000115

Radiation Protection Technician Training Program:

Packaging Radioactive Material

09/14/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.08

Miscellaneous

NBA19C000213

Radiation Protection Technician Training Program: Shipping

Radioactive Material

05/14/2021

71124.08

Procedures

20DP-0SK37

Palo Verde 10 CFR Part 37 Security Program Overview

71124.08

Procedures

20DP-0SK77

Security Miscellaneous Testing

71124.08

Procedures

75RP-9RP15

Control and Storage of Radioactive Material and Radioactive

Wastes

71124.08

Procedures

75RP-9RP26

Radioactive Source Control

71124.08

Procedures

76DP-0RP01

Radioactive Waste Management Program Overview

71124.08

Procedures

76DP-0RP03

Radwaste Process Control Program

71124.08

Procedures

76RP-0RW03

Waste Stream Sampling and Database Maintenance

71124.08

Procedures

76RP-0RW05

Packaging and Classification of Radioactive Waste

71124.08

Procedures

76RP-0RW06

Packaging of Radioactive Material

71124.08

Procedures

76RP-0RW07

Shipping Radioactive Materials

71124.08

Procedures

76RP-0RW08

High Integrity Container Receipt, Handling, Use, and

Closure

71124.08

Procedures

76RP-0RW14

Radioactive Waste Inventory

71124.08

Procedures

76RP-0RW82

Self-Engaging Rapid Dewatering System (SERDS)

Operation

71124.08

Radiation

Surveys

0-M-20160205-3, 0-M-20170727-4, 0-M-20181126-4, 0-M-

250801-2, 0-M-20250917-3, 1-M-20250302-2, 1-M-

250314-3, 1-M-20250411-19, 1-M-20250702-4, 1-M-

250729-2, 1-M-20250806-2, 1-M-20250909-9, 1-M-

250910-3, 1-M-20250910-5, 2-M-20250320-4, 2-M-

250729-7, 2-M-20250806-1, 2-M-20250807-1, 2-M-

250903-2, 2-M-20250909-2, 2-M-20250909-3, 2-M-

250916-1, 2-M-20250916-2, 2-M-20250917-3, 2-M-

250923-1, 3-M-20250724-2, 3-M-20250724-3, 3-M-

250730-5, 3-M-20250730-8, 3-M-20250825-3, 3-M-

250901-2, 3-M-20250914-1, 3-M-20250917-2, 3-M-

250918-4

71124.08

Radiation

Surveys

Filtered Radioactive Source Inventory, Leak Test, and

10CFR20 Appendix E Evaluation

07/15/2025

71124.08

Radiation

Surveys

0-M-20250827-3

Monthly Survey: Dry Active Waste Processing System

Facility - processing area

08/27/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.08

Radiation

Surveys

3-25-00140

Gamma Isotopic Analysis: Soil sample from U3 Yard Non-

RCA

09/25/2025

71124.08

Radiation

Surveys

3-25-00141

Gamma Isotopic Analysis: Soil sample from U3 Yard Non-

RCA

09/25/2025

71124.08

Radiation

Surveys

3-25-00142

Gamma Isotopic Analysis: Soil sample from U3 Yard Non-

RCA

09/25/2025

71124.08

Radiation

Surveys

3-25-00143

Gamma Isotopic Analysis: Soil sample from U3 Yard Non-

RCA

09/25/2025

71124.08

Radiation

Surveys

3-25-00144

Gamma Isotopic Analysis: Soil sample from U3 Yard Non-

RCA

09/25/2025

71124.08

Radiation

Surveys

3-25-00145

Gamma Isotopic Analysis: Soil sample from U3 Yard Non-

RCA

09/25/2025

71124.08

Radiation

Surveys

3-25-00156

Gamma Isotopic Analysis: Soil sample from U3 Yard Non-

RCA

09/24/2025

71124.08

Self-Assessments 2025-005

Nuclear Assurance Department Audit Report: Radiation

Safety

08/21/2025

71124.08

Self-Assessments 2023-004

Nuclear Assurance Department Audit Report: Radiation

Safety

09/08/2023

71124.08

Self-Assessments 2023-004

Nuclear Assurance Department Audit Report: Radiation

Safety

09/08/2023

71124.08

Self-Assessments 2025-002

Nuclear Assurance Department Audit Report: Nuclear

Security

07/01/2025

71124.08

Self-Assessments 2025-002

Nuclear Assurance Department Audit Report: Nuclear

Security

07/01/2025

71124.08

Self-Assessments 2025-005

Nuclear Assurance Department Audit report: Radiation

Safety

08/21/2025

71151

Miscellaneous

Engage Health Maintenance Rule reports - Unavailability for

January 2022 - 30 June 2025

71151

Miscellaneous

Engage Health Maintenance Rule reports - MSPI Failures

for 1 January 2022 - 30 June 2025

71151

Miscellaneous

NRC Action Matrix PI Data Results for Palo Verde Unit 1

Second Quarter 2025

71151

Miscellaneous

NRC Action Matrix PI Data Results for Palo Verde Unit 2

Second Quarter 2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71151

Miscellaneous

NRC Action Matrix PI Data Results for Palo Verde Unit 3

Second Quarter 2025

71151

Miscellaneous

MSPI Margin Report-U1

07/17/2025

71151

Miscellaneous

MSPI Margin Report-U2

07/17/2025

71151

Miscellaneous

MSPI Margin Report-U3

07/17/2025

71151

Miscellaneous

13-NS-C075

MSPI Bases Document

71151

Procedures

70DP-0PI01

Performance Index Data Mitigating Systems Cornerstone

71151

Procedures

93DP-0LC09

NRC ROP PI Data Collection, Verification, and Submittal

71151

Procedures

NEI-99-02

Regulatory Assessment Performance Indicator Guideline

71153

Corrective Action

Documents

25-04111

71153

Miscellaneous

I&C RT 064561

71153

Miscellaneous

PCR 25-04111-001

71153

Procedures

01DP-0AP09

Procedure And Work Instruction Use and Adherence

71153

Procedures

40AO-9ZZ12

Degraded Electrical Power

71153

Procedures

40AO-9ZZ23

Loss of SFP Level or Cooling

71153

Procedures

40OP-9SA02

De-energiazation of BOP ESFAS

71153

Procedures

40OP-9SA02

De-energiazation of BOP ESFAS

71153

Work Orders

232544, 5596311