IR 05000456/2020002

From kanterella
(Redirected from IR 05000457/2020002)
Jump to navigation Jump to search
Integrated Inspection Report 05000456/2020002 and 05000457/2020002
ML20211L708
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 07/28/2020
From: Hironori Peterson
Region 3 Branch 3
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2020002
Preceding documents:
Download: ML20211L708 (22)


Text

July 28, 2020

SUBJECT:

BRAIDWOOD STATION - INTEGRATED INSPECTION REPORT 05000456/2020002 AND 05000457/2020002

Dear Mr. Hanson:

On June 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Braidwood Station. On July 13, 2020, the NRC inspectors discussed the results of this inspection with Mr. J. Keenan, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Hironori Peterson, Chief Branch 3 Division of Reactor Projects

Docket Nos. 05000456 and 05000457 License Nos. NPF-72 and NPF-77

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000456 and 05000457

License Numbers:

NPF-72 and NPF-77

Report Numbers:

05000456/2020002 and 05000457/2020002

Enterprise Identifier: I-2020-002-0023

Licensee:

Exelon Generation Company, LLC

Facility:

Braidwood Station

Location:

Braceville, IL

Inspection Dates:

April 01, 2020 to June 30, 2020

Inspectors:

R. Bowen, Illinois Emergency Management Agency

J. Bozga, Senior Reactor Inspector

M. Domke, Reactor Inspector

G. Edwards, Health Physicist

M. Holmberg, Senior Reactor Inspector

D. Kimble, Senior Resident Inspector

P. Smagacz, Resident Inspector

Approved By:

Hironori Peterson, Chief

Branch 3

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Braidwood Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period operating at full power. With the exception of minor reductions in power to support scheduled testing activities and load changes requested by the transmission system dispatcher, the unit remained operating at or near full power for the entire inspection period.

Unit 2 began the inspection period operating at full power. On April 6, 2020, the unit reached the end of the fuel cycle and power coast down operations commenced. On April 20, 2020, the unit was shut down for its planned 21st refueling outage (A2R21). Following completion of refueling and other maintenance activities, the reactor was restarted and taken critical on May 5, 2020, and the main electrical generator was synchronized to the power grid the following day. The unit reached full power operation on May 9, 2020, and with the exception of minor reductions in power to support scheduled testing activities and load changes requested by the transmission system dispatcher, the unit remained operating at or near full power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week and during that time conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities, and completed on-site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated summer readiness of offsite and alternate alternating current (AC) power systems during the weeks ending June 20 through June 27, 2020.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial physical alignment verification of the following components and trains:

(1) The 2B Emergency Diesel Generator (EDG) with the 2A EDG inoperable for testing during the week ending May 2, 2020.
(2) The 2A EDG with the 2B EDG inoperable for testing during the week ending May 2, 2020.
(3) The 2A Auxiliary Feedwater (AF) train with the 2B AF train out of service for maintenance during the week ending May 16, 2020.
(4) The 1B Safety Injection (SI) train with the 1A SI train out of service for maintenance during the week ending May 30, 2020.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting physical inspections and performing reviews to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) The Unit 2 Containment, Fire Zone 1.1-2, during the week ending April 25, 2020.
(2) The Unit 2 Containment, Fire Zone 1.2-2, during the week ending April 25, 2020.
(3) The Unit 2 Containment, Fire Zone 1.3-2, during the week ending May 9, 2020.
(4) The Unit 1 Auxiliary Building, 383 feet elevation, General Area - North, Fire Zone 11.4-0 North, during the week ending June 13, 2020.
(5) The Unit 1 Auxiliary Building, 346 feet elevation, 1A Containment Spray Pump Room, Fire Zone 11.2B-1, during the week ending June 20, 2020.
(6) The 1B EDG and Day Tank Room, 401 feet elevation, Fire Zones 9.1-1 and 9.4-1, during the week ending June 27, 2020.

71111.07A - Heat Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated the readiness and performance of the following elements of the station's heat sink features:

(1) The 2A EDG lube oil coolers during planned periodic inspections as documented in work orders (WOs) 4794446 and 4794447 during the week ending June 13, 2020.

71111.08P - Inservice Inspection Activities (PWR) PWR Inservice Inspection Activities Sample (IP Section 03.01)

(1) The inspectors verified the reactor coolant system boundary, steam generator tubes, reactor vessel internals, risk-significant piping system boundaries, and containment boundary were appropriately monitored for degradation and repairs and replacements were appropriately fabricated, examined and accepted by reviewing the documentation for the following activities from April 20, 2020 to May 1, 2020:

03.01.a - Nondestructive Examination and Welding Activities.

  • There were no examination records with relevant indications accepted for continued service.
  • Pressure boundary welds 3-1 and 6-1 from work order no. 4871866, 2SI16BB Remove Minimum Flow Orifice for Internal Inspection.

03.01.b - Pressurized-Water Reactor Vessel Upper Head Penetration Examination Activities.

There were no volumetric or other non-visual exams performed on the upper head.

  • There were no reactor head penetration examinations with indications accepted for continued service.
  • There were no reactor head penetrations with welded repairs.

03.01.c - Pressurized-Water Reactor Boric Acid Corrosion Control Activities.

  • Boric acid corrective action reports for Boric Acid on 2PS9355B, on 2PS9357B, 2RC014, 2RC001A, and 2RC8042A.
  • Boric acid evaluations for 2CV066B, 2SI051, and 2SI8810A.

03.01.d - Pressurized-Water Reactor Steam Generator Tube Examination Activities.

  • There were no steam generator examinations performed during this inspection on the primary or secondary side.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed various on-watch Operations shift crew activities, including startup and shutdown activities associated with Unit 2 Refueling Outage A2R21, during the weeks ending April 25 through May 9, 2020.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated the performance of a complex casualty graded scenario by a crew of licensed plant operators in the facility's simulator on June 23, 2020.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance during the following activities to ensure that structures, systems, and components (SSCs) remain capable of performing their intended functions:

(1) Review of the maintenance effectiveness and performance history for main feedwater check valves 1/2FW079A-D during the weeks ending June 6 through June 20, 2020.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's assessment of risk associated with the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Emergent repairs to Unit 2 Control Rod Drive Mechanism (CRDM) Penetration 39 guide tube alignment funnel as specified in WO 5033582 during the weeks ending April 25, through May 2, 2020.
(2) Emergent repairs to the 2A EDG as specified in WO 5036351 during the weeks ending May 9 through May 30, 2020.
(3) Emergent repairs to the 2B EDG as specified in WO 5036665 during the weeks ending May 9 through May 30, 2020.
(4) Controller tuning for the 1B and 1C Turbine-Driven Main Feedwater Pumps while operating at high power as specified in WO 5044768 during the weeks ending June 20 through June 27, 2020.
(5) Emergent repairs to the 2A EDG jacket water circulating pump as specified in WO 5055032 during the week ending June 27, 2020.

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (7 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Evaluation of 2B SI Train operability and functionality following failure to meet all acceptance criteria during full flow testing as documented in Issue Report (IR)

===4337719 during the weeks ending April 25 through May 9, 2020.

(2) Evaluation of 2SI8853B operability and functionality after failing pressure testing as documented in IR 4338921 during the weeks ending May 2 through May 23, 2020.
(3) Evaluation of Unit 2 Containment Emergency Sump Suction Valve (2RH01SB)operability and functionality following excessive leakage testing results as documented in IRs 4338522 and 4338772 during the weeks ending May 2 through May 23, 2020.
(4) Evaluation of 2A EDG operability and functionality associated with the loss of Direct Current Circuit No. 1 as documented in IR 4340079 during the weeks ending May 9 through May 30, 2020.
(5) Evaluation of main steam safety valve (MSSV) 2MS016A operability following setpoint testing failure as documented in IR 4335846 during the weeks ending May 2 through June 30, 2020.
(6) Evaluation of MSSV 2MS014B operability following setpoint testing failure as documented in IR 4335997 during the weeks ending May 2 through June 30, 2020.
(7) Evaluation of MSSV 2MS016C operability following setpoint testing failure as documented in IR 4336005 during the weeks ending May 2 through June 30, 2020.

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

=

The inspectors reviewed and evaluated the following permanent changes to the facility that were enacted on Unit 2:

(1) Engineering Change (EC) 400436: Westinghouse Ovation' digital upgrade for 7300 Nuclear Steam Supply System (NSSS) Cabinets 2PA05J, 2PA06J, 2PA07J, and 2PA08J during the weeks ending April 11 through May 30, 2020.
(2) EC 400362: Westinghouse Ovation' Digital Upgrade for Balance of Plant (BOP)

Cabinets 2PA20JA and 2PA20JB during the weeks ending April 11 through May 30, 2020.

(3) EC 626998: Rod Control (RD) Ovation' Upgrade Multiplexing Logic and Step Counter Logic Adjustment (Unit 2) during the weeks ending April 11 through May 30, 2020.
(4) EC 405410: Replacement of the 2B Essential Service Water Pump during the weeks ending April 18 through May 30, 2020.

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (9 Samples)

The inspectors evaluated the following post maintenance testing activities to verify system operability and functionality:

(1) Functional testing of MSSV 2MS017A following setpoint adjustments as set forth in WO 4867041 during the weeks ending April 18 through May 23, 2020.
(2) Functional testing of MSSV 2MS017B following setpoint adjustments as set forth in WO 4867041 during the weeks ending April 18 through May 23, 2020.
(3) Functional testing of MSSV 2MS013B following setpoint adjustments as set forth in WO 4867041 during the weeks ending April 18 through May 23, 2020.
(4) Functional testing of 2B EDG after emergent maintenance as set forth in WO 4836047 during the week ending May 2, 2020.
(5) Leakage testing of various reactor coolant system high-to-low pressure isolation valves (PIVs) at 800 to 1000 psig as set forth in WO 4861076 during the week ending May 9, 2020.
(6) Review of modification acceptance testing (MAT) for Westinghouse Ovation' digital upgrade for 7300 NSSS, BOP, and Turbine-Driven Feedwater Pump (TDFWP)cabinets per ECs 400436, 404362, and 404363 (MAT Test - 400436/404362/404363)during the weeks ending May 9 through May 30, 2020.
(7) Review of power ascension testing for Westinghouse Ovation' digital upgrade for 7300 NSSS, BOP, and TDFWP cabinets per ECs 400436, 404362, and 404363 (SPP-20-002: Unit 2 Ovation Startup Test) during the weeks ending May 9 through May 30, 2020.
(8) Unit 2 core alignment verification activities following refueling as set forth in WO 4847014-11 during the week ending May 15, 2020.
(9) Operability and functionality testing for the 1B Containment Spray (CS) Train following completion of a planned maintenance work window as set forth in WO 5032462 during the weeks ending June 20 through June 27, 2020.

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors reviewed licensee activities and evaluated licensee performance associated with Unit 2 refueling outage A2R21 during the weeks ending April 25 through May 9, 2020.

71111.22 - Surveillance Testing

The inspectors reviewed and evaluated the following surveillance tests or changes to surveillance testing frequency:

Surveillance Tests (other) (IP Section 03.01) (4 Samples)

(1)2BwOSR 3.8.1.2-1: 2A EDG operability surveillance during the week ending April 11, 2020.

(2)1BwOSR 3.6.6.2: Reactor containment fan cooler surveillance during the week ending April 11, 2020.

(3) A frequency extension for radiation monitor operational surveillance testing during the week ending April 11, 2020.

(4)1BwOSR 3.7.5.4-2: 1B AF Pump surveillance test during the weeks ending May 16 through May 30, 2020.

RCS Leakage Detection Testing (IP Section 03.01) (1 Sample)

(1) Assessment of unidentified reactor coolant system (RCS) leakage rate on Unit 1 as documented in IRs 4344110, 4344858, 4345453, and 4345579 during the weeks ending May 30 through June 20, 2020.

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1)2BwOSR 3.6.3.7-1(2): Primary containment Type C local leakage rate tests of containment purge supply and exhaust isolation valves during the weeks ending April 25 through May 2, 2020.

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) The inspectors conducted a review of the implementation of the site's emergency plan by a crew of licensed operators during an evaluated emergency scenario in the facility's simulator on June 23,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Instructions to Workers (IP Section 03.02) (1 Partial)

(1)

(Partial) The inspectors evaluated radiological protection-related instructions to plant workers.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 1 (April 1, 2019 - March 31, 2020)
(2) Unit 2 (April 1, 2019 - March 31, 2020)

MS06: Emergency AC Power Systems (IP Section 02.05) (2 Samples)

(1) Unit 1 (April 1, 2019 - March 31, 2020)
(2) Unit 2 (April 1, 2019 - March 31, 2020)

MS07: High Pressure Injection Systems (IP Section 02.06) (2 Samples)

(1) Unit 1 (April 1, 2019 - March 31, 2020)
(2) Unit 2 (April 1, 2019 - March 31, 2020)

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in human performance that might be indicative of a more significant safety issue during the weeks ending June 27 through July 4, 2020.

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of their corrective action program related to the following issue:

(1) The inspectors performed a detailed review of Issue Report (IR) 4304787; Part 21-Westinghouse Thermal Sleeves and IR 4320102, WEC NSAL-20-1, RVH CRDM Penetration Thermal Sleeve Failure during the weeks ending May 2 through May 9, 2020.

71153 - Followup of Events and Notices of Enforcement Discretion Event Followup (IP Section 03.01)

The inspectors assessed licensee performance related to the following events:

(1) Review and tracking of licensee actions during the COVID-19 National Emergency declaration, as set forth by the President of the United States during the weeks ending April 11 through June 27,

INSPECTION RESULTS

Observation: Thermal Sleeves 71152 The sample selected was associated with a 10 CFR Part 21 notification to the NRC (Westinghouse LTR-NRC-19-79, dated December 12, 2019; ADAMS Accession No.

ML19346H873) and additional information on the 10 CFR Part 21 in Nuclear Safety Advisory Letter (NSAL) NSAL-20-1, Reactor Vessel Head Control Rod Drive Mechanism Penetration Thermal Sleeve Cross-Sectional Failure, dated February 14, 2020 (ADAMS Accession No.

ML20063J583). The specific issue was associated with mechanical fatigue and fracture that leads to flange separation of thermal sleeves in the control rod drive mechanism penetration tubes, which could have a safety consequence that was not previously considered. The review for this sample was conducted to evaluate the licensees use of operating experience and ensure that this issue was adequately evaluated for applicability, and applicable lessons learned communicated to appropriate organizations and implemented.

The licensee performed an evaluation of the most recent thermal sleeve wear measurements taken at thermal sleeve penetrations for Braidwood Units 1 and 2 versus the NSAL-20-1 lowering criteria. The largest thermal wear measurement for Braidwood Units 1 and 2 was less than the NSAL 20-1 lowering criteria, and therefore presently considered acceptable for continued operation. No findings or violations were identified.

Observation: Trend in Human Performance Issues 71152 The inspectors performed a review of plant issues, particularly those entered into the licensees corrective action program (CAP), associated with human performance errors over the past six months. During their review, the inspectors noted that there had been several recent issues at the station that had as their predominant cause errors in human performance. These included, but were not limited to:

  • Damage caused to the 2B Rod Drive Motor-Generator set when a foreign material exclusion (FME) cover over a vent on the machine was inadvertently left in place during a test run on April 28, 2020, and the cover was subsequently drawn into the machine. This was entered into the licensees CAP as IR 4339238.
  • The valve handle for 2CC9493B, the 2B Reactor Coolant Pump Upper Motor Bearing Component Cooling Water Outlet Isolation, was sheared off when the component was inadvertently struck during the Unit 2 A2R21 refuel outage as personnel inside containment were moving other equipment in the area on April 28, 2020. This was entered into the licensees CAP as IR 4339260.
  • On May 9,2020, a ventilation fan for the Division 12 Engineered Safety Features (ESF) Electrical Switchgear Room, 1VX01C, was inadvertently tripped during a planned temperature loop controller calibration for another fan in the area, 1VX03C, when the instrument technicians began work on the wrong component. This was entered into the licensees CAP as IR 4342165.

While none of these issues individually rose to the level of being documented as a finding, taken in aggregate the inspectors concluded that they could suggest a generic level of distraction within the licensees workforce. Licensee management also noted this, as well as several similar issues at the licensees other nuclear facilities, and a targeted human performance intervention was undertaken.

The inspectors did not identify any findings or violations of NRC requirements in the course of their review.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 13, 2020, the inspectors presented the integrated inspection results to Mr. J. Keenan, Site Vice President and other members of the licensee staff.
  • On April 29, 2020, the inspectors presented the Radiation Protection inspection results to Mr. J. Cady, Radiation Protection Manager and other members of the licensee staff.
  • On May 1, 2020, the inspectors presented the Inservice Inspection inspection results to Mr. G. Gugle, Plant Manager and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

OP-AA-108-107-1001

Station Response to Grid Capacity Conditions

71111.04

Procedures

BwOP AF-E2

Electrical Lineup - Unit 2 Operating

BwOP AF-M2

Operating Mechanical Lineup, Auxiliary Feedwater, Unit

BwOP DG-E3

Electrical Lineup - Unit 2 2A Diesel Generator

BwOP DG-E4

Electrical Lineup - Unit 2 2B Diesel Generator

BwOP DG-M3

Operating Mechanical Lineup Unit 2 2A D/G

BwOP DG-M4

Operating Mechanical Lineup Unit 2 2B D/G

BwOP SI-M1

Operating Mechanical Lineup Unit 1

SI-E1

Electrical Lineup - Unit 1 Operating

71111.05

Fire Plans

Pre-Fire Plan 10

1.3-2; Containment 426' - 0" Elevation, Unit 2

Containment Upper Area

Pre-Fire Plan 105

Fire Zone 11.2B-1; Auxiliary Building 346' Elevation

Containment Spray Pump 1A Room

Pre-Fire Plan 133

Fire Zone 11.4-0 North; Auxiliary Building 383' Unit 1,

Auxiliary Building General Area - North

Pre-Fire Plan 3

Fire Zone 1.1-2; Containment 377' Elevation, Unit 2

Containment Missile Shield

Pre-Fire Plan 4

Fire Zone 1.1-2; Containment 401' - 0" Elevation, Unit 2

Containment Missile Shield Unit 2

Pre-Fire Plan 7

Fire Zone 1.2-2; Containment 377' - 0" Elevation, Unit 2

Annular Area

Pre-Fire Plan 8

Fire Zone 1.2-2; Containment 401' - 0" Elevation, Unit 2

Annular Area

Pre-Fire Plan 88

Fire Zone 9.1-1, 9.4-1; DG 401' Elevation Diesel

Generator Room 1B and Day Tank Room

Procedures

BwAP 1110-1

Fire Protection Program System Requirements

BwAP-1110-3

Plant Barrier Impairment Program

BwOP PBI-1

Plant Barrier Impairment Program Pre-Evaluated

Barrier Matrix

CC-AA-201

Plant Barrier Control Program

ER-AA-600-1069

High Risk Fire Area Identification

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

ER-BR-600-1069

Site List of High-Risk Fire Areas - Braidwood Unit 1 and

Unit 2

OP-AA-201-004

Fire Prevention for Hot Work

OP-AA-201-007

Fire Protection System Impairment Control

OP-AA-201-008

Pre-Fire Plan Manual

OP-AA-201-009

Control of Transient Combustible Material

71111.07A

Work Orders

4794446

Emergency Diesel Generator 2A Lube Oil Lower Cooler

Inspection

06/01/2020

4794447

Emergency Diesel Generator 2A Lube Oil Upper Cooler

Inspection

06/01/2020

71111.08P

Corrective Action

Documents

4336361

2-OSP-A Boric Acid on 2PS9355B Regulator

04/17/2020

4336364

2-OSP-A Boric Acid at 2PS9357B Regulator

04/17/2020

4336731

2-OSP-A A2R21 Boric Acid Leak 2RC014 Seat

Leakage

04/20/2020

4336736

2-OSP-A A2R21 Boric Acid Leak - 2RC001A Packing

04/20/2020

4336742

2-OSP-A A2R21 Boric Acid Leak 2RC8042A

04/20/2020

Corrective Action

Documents

Resulting from

Inspection

4338259

NRC Inspector ID Discrepancy BTW the Weld Map and

Weld Rec

04/24/2020

Engineering

Evaluations

2CV066B

Evaluation of BACC Leakage

2/12/2019

2SI051

Evaluation of BACC Leakage

04/12/2019

2SI8810A

Evaluation of BACC Leakage

10/23/2018

NDE Reports

20-UT-011

UT Calibration/Examination

04/22/2020

20-UT-013

UT Calibration/Examination

04/22/2020

A2R21-UT-003

UT Calibration/Examination

04/24/2020

A2R21-VEN-001

2RC01R Bottom Reactor Head Visual Examination

04/21/2020

A2R21-VEN-002

Bare Metal Visual Examination of Upper Reactor Head

04/24/2020

Procedures

ER-AP-331

Boric Acid Corrosion Control (BACC) Program

ER-AP-331-1001

Boric Acid Corrosion Control (BACC) Inspection

Locations, Implementation and Inspection Guidelines

ER-AP-331-1002

Boric Acid Corrosion Control Program Identification,

Screening and Evaluation

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Work Orders

1410568

Osp-A 2RC8036A Body/Bonnet has Dry Boron (cln)

10/16/2018

1412965

Dpm Leak from CAP Downstream of Valve

2RH029A

10/27/2018

1451784

Boric Acid on 2CV066B

2/12/2019

4754836

Unit 2 Reactor Vessel Upper Head Bare Metal Visual

10/18/2018

4871866

2SI16BB Remove Minimum Flow Orifice for Internal

Inspection

01/16/2019

71111.11Q Procedures

OP-AA-101-111-1001

Operations Standards and Expectations

OP-AA-101-113

Operator Fundamentals

OP-AA-101-113-1006

4.0 Crew Critique Guidelines

OP-AA-103-102

Watch-Standing Practices

OP-AA-103-102-1001

Strategies for Successful Transient Mitigation

OP-AA-103-103

Operation of Plant Equipment

OP-AA-104-101

Communications

OP-AA-108-107-1002

Interface Procedure Between BGE/COMED/PECO and

Exelon Generation (Nuclear/Power) for Transmission

Operations

OP-AA-111-101

Operating Narrative Logs and Records

OP-AA-300

Reactivity Management

T!-AA-10

Systematic Approach to Training Process Description

TQ-AA-150

Operator Training Programs

TQ-AA-155

Conduct of Simulator Training and Evaluation

TQ-AA-201

Examination Security and Administration

TQ-AA-306

Simulator Management

TQ-BR-201-0113

Braidwood Training Department Simulator Examination

Security Actions

71111.12

Corrective Action

Documents

0699328

1FW079B Check Valve Further Closed Than Expected

11/14/2007

4165777

1FW079B Check Valve Further Closed Than 1FW079

A, C, and D

08/20/2018

291137

1FW530 Full Open Following Power Ascension

10/25/2019

4346114

1C Steam Generator Level Excursion

05/27/2020

Engineering

Changes

368412

Evaluation of Feedwater Check Valve-FW079 Failure to

Close for Braidwood Unit 1

11/20/2007

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

631749

Westinghouse Field Change Notice for Tuning 1B/1C

Turbine Driven Feedwater Pumps - PROPRIETARY

06/15/2020

Miscellaneous

Adverse Condition Monitoring Plan; Unit 1 Feedwater

Regulating Valve (FRV) Positions

10/25/2019

Procedures

ER-AA-310-1002

Maintenance Rule Functions - Safety Significant

Classification

ER-AA-320

Maintenance Rule Implementation per NEI 18-10

ER-AA-320-1001

Maintenance Rule 18-10 - Scoping

ER-AA-320-1003

Maintenance Rule 18-10 - Failure Definitions

ER-AA-320-1004

Maintenance Rule 18-10 - Performance Monitoring and

Dispositioning Between (a)(1) and (a)(2)

71111.13

Corrective Action

Documents

4337758

Control Rod Drive Shaft Funnel Core Location M12/Pen

Disengaged From Head

04/23/2020

4340361

13OSP-A: Unexpected Alarm - 2B EDG Trouble/Fail to

Start

05/02/2020

Engineering

Changes

619607

Alternate Weld Detail for Control Rod Drive Mechanism

Guide Funnel

05/11/2017

Procedures

ER-AA-330-009

ASME Section XI Repair/Replacement Program

ER-AA-335-015-2013

VT-2 Visual Examination in Accordance with ASME

2013

ER-AA-600

Risk Management

ER-AA-600-1042

On-Line Risk Management

MA-AA-716-004

Conduct of Troubleshooting

OP-AA-108-117

Protected Equipment Program

WC-AA-101-1006

On-Line Risk Management and Assessment

Work Orders

5033582

Control Rod Drive Shaft Funnel Core Location M12/Pen

Disengaged From Head

04/25/2020

5036351

Unexpected Alarm - 2A EDG Trouble/Fail to Start

05/04/2020

5036665

Unexpected Alarm - 2B EDG Trouble/Fail to Start

05/02/2020

71111.15

Corrective Action

Documents

4337719

2C Hot Leg Flow Out of Tolerance Low During

2BwOSR 5.5.8.SI-11

04/22/2020

4338522

07-OSP-X 2SI1881 Can Valve (2RH01SB) - Does Not

Pass LLRT

04/26/2020

4338772

A2R21LL: 2RH01SB Leak Rate Results

04/27/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4338921

09-OSP-A; 2SI8853B Failed As-Found Set Pressure

Test

04/27/2020

4340079

13OSP-A: Unexpected Alarm - 2A EDG Trouble/Fail to

Start

05/01/2020

Engineering

Changes

631543

Temporary Configuration Change - Defeat the 2A EDG

Cooldown Cycle Relay, 4X3A

05/02/2020

Procedures

2BwOS TRM 2.5.c.1

Unit 2 Safety Injection Pump Hot Leg Flow Balance

Safety Injection System Check Valve Stroke Test

2BwOSR 5.5.8.SI-11

Comprehensive Inservice Testing (IST) Requirements

for Unit 2 Safety Injection Pumps and Safety Injection

Check Valve Stroke Test

BwOP DG-11

Diesel Generator Startup and Operation

ER-AA-2006

Lost Parts Evaluations

ER-AA-321

Administrative Requirements for Inservice Testing

ER-AA-600-1012

Risk Management Documentation

ER-AA-600-1045

Risk Assessments of Missed or Deficient Surveillances

OP-AA-106-101-1006

Operational Decision-Making Process

OP-AA-108-111

Adverse Condition Monitoring and Contingency

Planning

OP-AA-108-115

Operability Determinations (CM-1)

Work Orders

5033577-03

Operations Post-Maintenance Testing - 2SI8816C Flow

Balance and Testing

04/28/2020

71111.18

Corrective Action

Documents

4339535

2SX150B Failed to Open During Backwash

04/29/2020

4339610

Procedure Changes Required per 2B SX Pump IST

Evaluation

04/30/2020

Drawings

405410

Unit 2A/B SX Pump Replacement Alternate Detail

07/12/2016

Engineering

Changes

040362

Westinghouse Ovation' Digital Upgrade for Balance of

Plant (BOP) Cabinets 2PA20JA and 2PA20JB

400436

Westinghouse Ovation' Digital Upgrade For 7300

NSSS Cabinets 2PA05J, 2PA06J, 2PA07J, 2PA08J

(N Outage - Unit 2)

25405

U1 Ovation Post N-Outage Backfit

26998

Rod Control (RD) Ovation' Upgrade Multiplexing Logic

and Step Counter Logic Adjustment (Unit 2)

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Procedures

SPP-20-002

U2 Ovation Startup Test

Work Orders

1845722

EC 400436: Westinghouse Ovation' Digital Upgrade

for 7300 Nuclear Steam Supply System

2/12/2020

4318716

EC 400436: Westinghouse Ovation' Digital Upgrade

for 7300 Nuclear Steam Supply System

04/07/2020

4616851

Install EC 404362: Ovation Balance of Plant (BOP)

Cabinets 2PA20JA and 2PA20JB

04/23/2020

4743474

Temporary Configuration Change - Install/Remove

Temporary Control Panel for 7300 per EC 404450

01/24/2020

4861076

IST-LT-2SI8948A-D/8819A-D-PIV Leak

05/03/2020

4883959

Replace 2SX01PB in A2R21

04/13/2020

4888961

Install EC 626998: Rod Drive Ovation Upgrade

04/23/2020

71111.19

Procedures

BwMP 3305-003

Main Steam Safety Valve Testing Using Setpoint

Verification Device

CC-AA-107

Configuration Change Acceptance Testing Criteria

ER-AA-330-001

Section XI Pressure Testing

MAT

400436/404362/404363

Westinghouse Ovation' Digital Upgrade Modification

Acceptance Test

MAT 404450

Westinghouse Ovation' Digital Upgrade Modification

Acceptance Test

MM-AA-793-044

Inspection/Certification of Portable Pressure Test

Equipment

NF-AA-330-1001

Core Verification Guideline

OU-AP-230

Newton Core Gap Data Acquisition for Byron and

Braidwood

WC-AA-101

On-Line Work Control Process

Work Orders

4836047

2B EDG Pneumatic Component Replacement or

Rebuild

05/11/2020

4844209-01

Physical Reactor Inventory Prior to Installing the

Reactor Head

04/30/2020

4847014-11

Newton Gap Measurements in A2R21

04/29/2020

4861577-01/02

Startup Physics Testing

05/05/2020

4867041-02

Testing of Main Steam Safety Valve 2MS013B

04/15/2020

4867041-17

Testing of Main Steam Safety Valve 2MS017A

04/15/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4867041-18

Testing of Main Steam Safety Valve 2MS017B

04/15/2020

71111.20

Corrective Action

Documents

4341338

2AFFSO2-6 Not Installed per Design in Mode of

Applicability

05/06/2020

Miscellaneous

BR2C21 08.0

Unit 2 Cycle 21 Coastdown Reactivity Plan

03/25/2020

BR2C21 09.0

Unit 2 Cycle 21 Main Steam Safety Valve and Auxiliary

Feedwater Full Flow Testing Reactivity Plan

04/13/2020

PORC-20-006-02

A2R21 Shutdown Safety Plan

2/28/2020

PORC-20-013

A2R21 Restart Review

05/02/2020

Procedures

2BwGP 100-1

Plant Heatup

2BwGP 100-2

Plant Startup

2BwGP 100-3

Power Ascension 5 Percent to 100 Percent

2BwGP 100-5

Plant Shutdown and Cooldown

2BwOS TRM 2.5.b.1

Unit 2: Containment Loose Debris Inspection

2BwOSR 3.1.8.2

Special Test Exceptions - Reactor Coolant System

Tave During Physics Test Surveillance

2BwOSR 3.1.8.3

Special Test Exceptions - Physics Tests Thermal Power

Hourly Surveillance

2BwOSR 3.1.8.4

Unit 2: Shutdown Margin Verification During Physics

Tests

BwAP 1450-1

Access to Containment

BwVS 500-6

Low Power Physics Test Program

BwVS TRM 3.1.h.1

Core Reload Sequence and Verification

ER-AA-600-1043

Shutdown Risk Management

HU-AA-1211

Pre-Job Briefings

LS-AA-119

Fatigue Management and Work Hour Rules

MA-AA-716-008-1008

Reactor Services: Refuel Floor FME Plan

OP-AA-108-108

Unit Restart Review

OP-AA-108-110

Evaluation of Special Tests or Evolutions

71111.22

Miscellaneous

PORC 20-012-1

Revise the Channel Operational Test (COT) of

Radiation Monitors 0PR32J, 0PR33J, 0PR34J,

1/2AR11J, 1/2AR12J, 0AR55J, 0AR56J From Once

Every 92 to Once Every 18 Months, Using Phased

Implementation

04/17/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Procedures

1BwOSR 3.6.6.2

Reactor Containment Fan Cooler Surveillance

1BwOSR 3.7.5.4-2

Unit 1 Diesel Driven Auxiliary Feedwater Pump

Surveillance

2BwOSR 3.6.7-1

Primary Containment Type C Local Leakage Rate Tests

of Containment Purge Supply Isolation Valves

2BwOSR 3.6.7-2

Primary Containment Type C Local Leakage Rate Tests

of Containment Purge Exhaust Isolation Valves

2BwOSR 3.8.1.2-1

Unit Two 2A Diesel Generator Operability Surveillance

BwOP DG-1

Diesel Generator Alignment to Standby Condition

BwOP DG-11

Diesel Generator Startup and Operation

BwOP DG-12

Diesel Generator Shutdown

Work Orders

4842753

Primary Containment Type C LLRT of Containment

Purge Exhaust Isolation Valves

04/24/2020

4848777

U-2 Containment Type C LLRT of Containment Purge

Supply Isolation Valves

04/24/2020

71114.06

Procedures

EP-AA-1000

Standardized Radiological Emergency Plan

EP-AA-1001

Radiological Emergency Plan Annex for Braidwood

Station

71124.01

ALARA Plans

BW-02-20-00521

Task 4 2RC8042A Emergent Work

04/22/2020

Corrective Action

Documents

AR 04337024

MMD Individual Receives Unplanned Dose Alarm

04/20/2020

AR 04339312

Dose Exceeds 25 Percent of ALARA Plan Estimate

BW-02-20-00645

04/29/2020

AR 4337129

Level 1 PCE on 2RY45

04/20/2020

Radiation

Surveys

20-071688

Unit 2 Containment Elevation 377' Inside Missile Barrier 04/26/2020

Radiation Work

Permits (RWPs)

BW-02-20-00510

A2R21 Containment/Aux Building Outage Valve Work

with Added Controls

BW-02-20-00521

Task 4 2RC8042A Emergent Work

BW-02-20-00613

Task 1, Reactor Head Disassembly, Reactor Head

Reassembly/Task 2, Conoseal Work, RVLS and O-Ring

Replacement

71151

Miscellaneous

NRC Performance Indicator Data; Mitigating Systems -

Mitigating System Performance Index for Emergency

AC Power

04/2019 -

03/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NRC Performance Indicator Data; Mitigating Systems -

Mitigating System Performance Index for High Pressure

Injection

04/2019 -

03/2020

NRC Performance

Indicator Data;

Mitigating Systems -

Safety System

Functional Failures

04/2019 - 03/2020

Procedures

LS-AA-2001

Collecting and Reporting of NRC Performance Indicator

Data

LS-AA-2200

Mitigating System Performance Index Data Acquisition

and Reporting

SL-AA-2080

Monthly Data Elements for NRC Safety System

Functional Failures

71152

Corrective Action

Documents

4304787

Part 21-Westinghouse Thermal Sleeves

2/18/2019

20102

WEC NSAL-20-1, RVH CRDM Penetration Thermal

Sleeve Failure

2/21/2020

Engineering

Changes

24381

Review of Westinghouse CRDM Thermal Sleeve Part

24381

Review of Westinghouse CRDM Thermal Sleeve Part

630255

CRDM Thermal Sleeve Lowering to the Acceptance

Criteria in PWROG-16003-P Rev 2 to Determine the

Current Condition of CRDM Thermal Sleeve Wear

Miscellaneous

Nuclear Safety

Advisory Letter (NSAL)-

20-1

Reactor Vessel Head Control Rod Drive Mechanism

Penetration Thermal Sleeve Cross-Sectional Failure

2/14/2020

Procedures

NO-AA-10

Quality Assurance Topical Report (QATR)

PI-AA-120

Issue Identification and Screening Process

PI-AA-125

Corrective Action Program (CAP) Procedure

PI-AA-125-1001

Root Cause Analysis Manual

PI-AA-125-1003

Corrective Action Program Evaluation Manual

5