MONTHYEARGO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan IR 05000397/20230042024-01-29029 January 2024 Integrated Inspection and Independent Spent Fuel Storage Installation Report 05000397/2023004 and 07200035/2023001 GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing ML24011A1522024-01-10010 January 2024 March 2024 Emergency Preparedness Exercise Inspection-Request for Information GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report ML23288A0002023-12-0707 December 2023 Issuance of Amendment No. 272 to Adopt TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-126, Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-012023-11-28028 November 2023 Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-01 GO2-23-121, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-27027 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000397/20230122023-11-20020 November 2023 Commercial Grade Dedication Inspection Report 05000397/2023012 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000397/20230102023-11-0909 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000397/2023010 IR 05000397/20230932023-11-0101 November 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023093 ML23299A2072023-10-26026 October 2023 Biennial Requalification Inspection Request for Information IR 05000397/20230032023-10-25025 October 2023 Integrated Inspection Report 05000397/2023003 IR 05000397/20230112023-10-0404 October 2023 License Renewal Phase 2 Report 05000397/2023011 IR 05000397/20234012023-09-11011 September 2023 Security Baseline Inspection Report 05000397/2023401 GO2-23-097, In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26)2023-09-0606 September 2023 In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26) ML24032A2182023-09-0101 September 2023 Information Request, Security IR 2024401 GO2-23-100, Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication2023-08-31031 August 2023 Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication GO2-23-056, Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2023-08-29029 August 2023 Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000397/20230052023-08-22022 August 2023 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2023005) - Mid Year Letter IR 05000397/20230022023-08-0101 August 2023 Integrated Inspection Report 05000397/2023002 GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 ML23206A2442023-07-25025 July 2023 Energy Northwest Columbia Generating Station, Response to Apparent Violation in NRC Inspection Report 05000397/2023092; EA-23-054 GO2-23-068, Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation2023-07-19019 July 2023 Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation ML23143A1202023-06-27027 June 2023 Request Number 4ISI-11 to the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Regarding Alternate Examination of Reactor Vessel Welds GO2-23-073, Notification of NPDES Permit Issuance2023-06-26026 June 2023 Notification of NPDES Permit Issuance ML23163A2502023-06-12012 June 2023 Summary of Changes and Analysis for Revision 41 of Plant Procedures Manual 13.8.1 Emergency Dose Projection System Operations GO2-23-072, Cycle 27 Core Operating Limits Report2023-06-0505 June 2023 Cycle 27 Core Operating Limits Report ML23157A2702023-06-0101 June 2023 4-2022-011 -022 Letter - OI Closure to Licensee IR 05000397/20230922023-06-0101 June 2023 NRC Inspection Report 05000397/2023092 and Preliminary White Finding IR 05000397/20230902023-06-0101 June 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023090 GO2-23-055, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report IR 05000397/20230012023-05-0505 May 2023 Integrated Inspection Report 05000397/2023001 - April 26, 2023 GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications IR 05000397/20233012023-05-0101 May 2023 NRC Examination Report 05000397/2023301 GO2-23-053, 2022 Annual Environmental Operating Report2023-04-26026 April 2023 2022 Annual Environmental Operating Report GO2-23-057, 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 2022 Annual Radioactive Effluent Release Report ML23110A2642023-04-20020 April 2023 Request for Information License Renewal Phase 2 Inspection GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-041, Generation Station - Level of Financial Protection - Annual Reporting Requirement2023-03-15015 March 2023 Generation Station - Level of Financial Protection - Annual Reporting Requirement GO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report ML23013A0812023-03-15015 March 2023 Issuance of Amendment No. 270 Revision to Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times-RITSTF Initiative 4B GO2-23-034, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462023-03-13013 March 2023 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 2024-01-08
[Table view] Category:Licensee Response to Notice of Violation
MONTHYEARGO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 ML23206A2442023-07-25025 July 2023 Energy Northwest Columbia Generating Station, Response to Apparent Violation in NRC Inspection Report 05000397/2023092; EA-23-054 GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation GO2-18-146, Response to Inspection Report 05000397/20180032018-11-29029 November 2018 Response to Inspection Report 05000397/2018003 GO2-17-173, Revised Response to a Notice of Violation; EA-17-0282017-10-11011 October 2017 Revised Response to a Notice of Violation; EA-17-028 GO2-17-141, Reply to a Notice of Violation; EA-17-0282017-08-0303 August 2017 Reply to a Notice of Violation; EA-17-028 GO2-17-100, Response to Inspection Report 05000397/20160092017-05-0909 May 2017 Response to Inspection Report 05000397/2016009 GO2-15-179, Response to Inspection Report 05000397/20150032015-12-22022 December 2015 Response to Inspection Report 05000397/2015003 GO2-11-137, Supplemental Information Provided to Report 0500397/20100072011-08-11011 August 2011 Supplemental Information Provided to Report 0500397/2010007 GO2-08-107, Reply to Notice of Violation; EA-08-1832008-07-16016 July 2008 Reply to Notice of Violation; EA-08-183 GO2-08-099, Reply to a Notice of Violation, EA-04-1452008-07-0202 July 2008 Reply to a Notice of Violation, EA-04-145 GO2-05-142, Response to Inspection Report 05000397-05-0072005-08-15015 August 2005 Response to Inspection Report 05000397-05-007 GO2-05-065, Review of NRC Violation 50-397/04-05-022005-04-0404 April 2005 Review of NRC Violation 50-397/04-05-02 ML0411803842004-04-16016 April 2004 Reply to Non-Cited Violation from IR 05000397/03-007 GO2-02-134, Energy Northwest, Docket No. 50-397, NRC Inspection Report 50-397/02-05, Response to Notice of Violation2002-08-21021 August 2002 Energy Northwest, Docket No. 50-397, NRC Inspection Report 50-397/02-05, Response to Notice of Violation GO2-02-016, Operating License NPF-21 Reply to Final Significance Determination for a Yellow Finding and Notice of Violation (NRC IR 05000397/2001-008)2002-02-28028 February 2002 Operating License NPF-21 Reply to Final Significance Determination for a Yellow Finding and Notice of Violation (NRC IR 05000397/2001-008) IR 05000397/20010082002-02-20020 February 2002 Reply to Final Significance Determination for a Yellow Finding and Notice of Violation (NRC Inspection Report 50-397/01-008) 2024-01-08
[Table view] |
Text
ary 20, 2002
SUBJECT:
COLUMBIA GENERATING STATION REPLY TO FINAL SIGNIFICANCE DETERMINATION FOR A YELLOW FINDING AND NOTICE OF VIOLATION (NRC INSPECTION REPORT 50-397/01-008)
Dear Mr. Parrish:
Thank you for your letter of January 28, 2002, in response to our December 28, 2001, letter and Notice of Violation concerning the failure to meet the requirements of 10 CFR 50.54(q) in that Columbia Generating Station did not follow and maintain emergency plans and procedures which meet the standards in 10 CFR 50.47(b). We have reviewed your reply and find it responsive to the concerns raised in our Notice of Violation. We will review the implementation of your corrective actions during a future inspection to determine that full compliance has been achieved and will be maintained.
We also acknowledge your intent to provide additional information on the subject of your procedures, processes, and programs as were in place prior to April 2001 in future correspondence.
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," Part 2, Title 10, Code of Federal Regulations, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Should you have any questions concerning this matter, we will be pleased to discuss them with you.
Sincerely,
/RA/
Gail M. Good, Chief Plant Support Branch Division of Reactor Safety
Energy Northwest -2-Docket: 50-397 License: NPF-21 cc:
Chairman Energy Facility Site Evaluation Council P.O. Box 43172 Olympia, Washington 98504-3172 Rodney L. Webring (Mail Drop PE08)
Vice President, Operations Support/PIO Energy Northwest P.O. Box 968 Richland, Washington 99352-0968 Greg O. Smith (Mail Drop 927M)
Vice President, Generation Energy Northwest P.O. Box 968 Richland, Washington 99352-0968 D. W. Coleman (Mail Drop PE20)
Manager, Regulatory Affairs Energy Northwest P.O. Box 968 Richland, Washington 99352-0968 Albert E. Mouncer (Mail Drop 1396)
General Counsel Energy Northwest P.O. Box 968 Richland, Washington 99352-0968 Paul Inserra (Mail Drop PE20)
Manager, Licensing Energy Northwest P.O. Box 968 Richland, Washington 99352-0968 Thomas C. Poindexter, Esq.
Winston & Strawn 1400 L Street, N.W.
Washington, D.C. 20005-3502
Energy Northwest -3-Bob Nichols State Liaison Officer Executive Policy Division Office of the Governor P.O. Box 43113 Olympia, Washington 98504-3113 Lynn Albin Washington State Department of Health P.O. Box 7827 Olympia, WA 98504-7827 Training, Exercises, & Evaluation Branch Chief FEMA Region X Federal Regional Center 130 228th Street, S.W.
Bothell, WA 98021-9796
Energy Northwest -4-Electronic distribution from ADAMS by RIV:
Regional Administrator (EWM)
DRP Director (KEB)
DRS Director (ATH)
Branch Chief, DRS/PSB (GMG)
Inspector, DRS/PSB (PJE)
Senior Resident Inspector (GDR)
Branch Chief, DRP/E (WBJ)
Senior Project Engineer, DRP/E (GAP)
Staff Chief, DRP/TSS (PHH)
RITS Coordinator (NBH)
Regional State Liaison Officer (WAM)
DOCUMENT NAME: R:\_COL\COL0201EP-L00.WPD RIV:DRS/PSB C:PSB PJElkmann:nlh GMGood MPShannon for MPShannon for 02/20/02 02/20/02 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax
Energy Northwest -5-