MONTHYEARGO2-24-109, Summary of Changes and Analysis for Revision 42 of Plant Procedures Manual 13.8.1, Emergency Dose Projection System Operations2024-11-0404 November 2024 Summary of Changes and Analysis for Revision 42 of Plant Procedures Manual 13.8.1, Emergency Dose Projection System Operations GO2-24-110, Summary of Changes and Analysis for Revision 45 of Plant Procedures Manual 13.4.1, Emergency Notification2024-11-0404 November 2024 Summary of Changes and Analysis for Revision 45 of Plant Procedures Manual 13.4.1, Emergency Notification GO2-24-088, Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-24024 September 2024 Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan GO2-24-051, Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2024-09-23023 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements GO2-24-082, Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-10010 September 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan GO2-24-060, Reply to a Notice of Violation, EA-21-170 and EA-23-0542024-07-30030 July 2024 Reply to a Notice of Violation, EA-21-170 and EA-23-054 GO2-24-070, Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program2024-07-29029 July 2024 Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program GO2-24-063, Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan2024-07-15015 July 2024 Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan GO2-24-057, Notice of Readiness for Supplemental Inspection2024-06-19019 June 2024 Notice of Readiness for Supplemental Inspection GO2-24-056, Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing2024-06-11011 June 2024 Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing GO2-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-13013 May 2024 2023 Annual Radiological Environmental Operating Report GO2-24-050, Annual Environmental Operating Report2024-04-30030 April 2024 Annual Environmental Operating Report GO2-24-042, 2023 Annual Radioactive Effluent Release Report2024-04-22022 April 2024 2023 Annual Radioactive Effluent Release Report GO2-24-044, Voluntary Response to Regulatory Issue Summary 2024-012024-04-11011 April 2024 Voluntary Response to Regulatory Issue Summary 2024-01 GO2-24-034, Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan2024-03-20020 March 2024 Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan GO2-24-041, Level of Financial Protection - Annual Reporting Requirement2024-03-12012 March 2024 Level of Financial Protection - Annual Reporting Requirement GO2-24-039, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462024-03-11011 March 2024 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 GO2-24-036, Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate2024-03-11011 March 2024 Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate GO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing GO2-24-014, Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-01-15015 January 2024 Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-126, Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-012023-11-28028 November 2023 Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-01 GO2-23-121, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-27027 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation GO2-23-097, In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26)2023-09-0606 September 2023 In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26) GO2-23-100, Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication2023-08-31031 August 2023 Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication GO2-23-056, Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2023-08-29029 August 2023 Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 GO2-23-068, Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation2023-07-19019 July 2023 Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation GO2-23-073, Notification of NPDES Permit Issuance2023-06-26026 June 2023 Notification of NPDES Permit Issuance GO2-23-072, Cycle 27 Core Operating Limits Report2023-06-0505 June 2023 Cycle 27 Core Operating Limits Report GO2-23-055, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications GO2-23-053, 2022 Annual Environmental Operating Report2023-04-26026 April 2023 2022 Annual Environmental Operating Report GO2-23-057, 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 2022 Annual Radioactive Effluent Release Report GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report GO2-23-041, Generation Station - Level of Financial Protection - Annual Reporting Requirement2023-03-15015 March 2023 Generation Station - Level of Financial Protection - Annual Reporting Requirement GO2-23-034, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462023-03-13013 March 2023 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 GO2-23-035, Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-03-0909 March 2023 Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling GO2-23-019, Emergency Plan - Summary of Changes and Analysis for Revision 68 of the EP-012023-02-0808 February 2023 Emergency Plan - Summary of Changes and Analysis for Revision 68 of the EP-01 GO2-22-131, Guarantee of Payment of Deferred Premium2022-12-19019 December 2022 Guarantee of Payment of Deferred Premium GO2-22-122, Response to Request for Additional Information Related to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-11-28028 November 2022 Response to Request for Additional Information Related to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GO2-22-076, Status of License Renewal Commitments2022-10-31031 October 2022 Status of License Renewal Commitments 2024-09-24
[Table view] Category:Licensee Response to Notice of Violation
MONTHYEARGO2-24-060, Reply to a Notice of Violation, EA-21-170 and EA-23-0542024-07-30030 July 2024 Reply to a Notice of Violation, EA-21-170 and EA-23-054 GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 ML23206A2442023-07-25025 July 2023 Energy Northwest Columbia Generating Station, Response to Apparent Violation in NRC Inspection Report 05000397/2023092; EA-23-054 GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation GO2-18-146, Response to Inspection Report 05000397/20180032018-11-29029 November 2018 Response to Inspection Report 05000397/2018003 GO2-17-173, Revised Response to a Notice of Violation; EA-17-0282017-10-11011 October 2017 Revised Response to a Notice of Violation; EA-17-028 GO2-17-141, Reply to a Notice of Violation; EA-17-0282017-08-0303 August 2017 Reply to a Notice of Violation; EA-17-028 GO2-17-100, Response to Inspection Report 05000397/20160092017-05-0909 May 2017 Response to Inspection Report 05000397/2016009 GO2-15-179, Response to Inspection Report 05000397/20150032015-12-22022 December 2015 Response to Inspection Report 05000397/2015003 GO2-11-137, Supplemental Information Provided to Report 0500397/20100072011-08-11011 August 2011 Supplemental Information Provided to Report 0500397/2010007 GO2-08-107, Reply to Notice of Violation; EA-08-1832008-07-16016 July 2008 Reply to Notice of Violation; EA-08-183 GO2-08-099, Reply to a Notice of Violation, EA-04-1452008-07-0202 July 2008 Reply to a Notice of Violation, EA-04-145 GO2-05-142, Response to Inspection Report 05000397-05-0072005-08-15015 August 2005 Response to Inspection Report 05000397-05-007 GO2-05-065, Review of NRC Violation 50-397/04-05-022005-04-0404 April 2005 Review of NRC Violation 50-397/04-05-02 ML0411803842004-04-16016 April 2004 Reply to Non-Cited Violation from IR 05000397/03-007 GO2-02-134, Energy Northwest, Docket No. 50-397, NRC Inspection Report 50-397/02-05, Response to Notice of Violation2002-08-21021 August 2002 Energy Northwest, Docket No. 50-397, NRC Inspection Report 50-397/02-05, Response to Notice of Violation GO2-02-016, Operating License NPF-21 Reply to Final Significance Determination for a Yellow Finding and Notice of Violation (NRC IR 05000397/2001-008)2002-02-28028 February 2002 Operating License NPF-21 Reply to Final Significance Determination for a Yellow Finding and Notice of Violation (NRC IR 05000397/2001-008) IR 05000397/20010082002-02-20020 February 2002 Reply to Final Significance Determination for a Yellow Finding and Notice of Violation (NRC Inspection Report 50-397/01-008) 2024-07-30
[Table view] |
Text
ENERGY William G. Hettel Vice President, Operations P.O. Box 968, Mail Drop PE23 NORTHWEST Richland, WA 99352-0968 Ph. 509-377-2425 F. 509-377-4674 wghettel@energy-northwest.com August 3, 2017 G02-17-141 10 CFR 2.201 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
COLUMBIA GENERATING STATION, DOCKET NO. 50-397 REPLY TO A NOTICE OF VIOLATION; EA-17-028
Reference:
Letter EA-17-028 from K Kennedy (NRC) to ME Reddemann (Energy Northwest), "Columbia Generating Station - Final Significance Determination of a White Finding, Notice of Violation, Follow-Up Assessment Letter and NRC Inspection Report 05000397/2017009,
dated July 6, 2017.
Dear Sir or Madam:
As required by 10 CFR 2.201, this letter provides Energy Northwest's reply to Notice of Violation EA-17-028 cited in the referenced Nuclear Regulatory Commission (NRC) inspection report (Reference). The response, as described in the enclosure, includes the reason for the violation, the corrective steps that have been taken and the results achieved, the corrective steps that will be taken, and the date when full compliance was achieved .
There are no commitments being made to the NRC by this letter. Should you have any questions, please contact OM Wolfgramm, Regulatory Compliance Supervisor, at (509) 377-4792.
Executed this 6~ day of A w;,1t"kT , 2017 Respectfully, W. G. Hettel Vice President, Operations
GO2-17-141 Page 2 of 2
Enclosure:
Response to EA-17-028 Notice of Violation cc:
NRC Director-Division of Reactor Safety, Region IV NRC Region IV Administrator NRC NRR Project Manager NRC Sr. Resident Inspector/988C CD Sonoda - BPA/1399 w/o enclosure WA Horin - Winston & Strawn w/o enclosure
GO2-17-141 Enclosure Cover Page Columbia Generating Station Reply to EA-17-028 Notice of Violation
GO2-17-141 Enclosure Page 1 of 2 Notice of Violation NRC letter EA-17-028 dated July 6, 2017, cited the violation as stated below.
10 CFR 71.5(a) requires, in part, that each licensee who transports licensed material outside the site of usage, as specified in the NRC license, or where transport is on public highways, shall comply with the applicable requirements of the Department of Transportation regulations in 49 CFR Parts 171 through 180.
49 CFR 173.427(a)(1) requires, in part, that low specific activity material must be transported in accordance with the condition that the external dose rate may not exceed an external radiation level of 10 mSv/hr (1 rem/hr) at 3 meters (10 feet) from the unshielded material.
Contrary to the above, on November 9, 2016, the licensee failed to transport low specific activity material in accordance with the condition that the external dose rate may not exceed an external radiation level of 10 mSv/hr (1 rem/hr) at 3 meters (10 feet) from the unshielded material. Specifically, the licensee transported a package as low specific activity material with an external radiation level of 2.1 rem/hr at a distance of 3 meters from the unshielded material.
Energy Northwest accepts this violation, has taken prompt action to return to full compliance, and has implemented comprehensive corrective actions for long-term sustained compliance.
Reason for Violation The root cause of the violation was determined to be that station procedures to implement spent fuel pool clean-up activities and the associated radioactive waste surveys, processing, and shipping activities were not sufficient to ensure compliance with all requirements, specifically 10 CFR 71.5(a) and 49 CFR 173.427(a)(1).
Contributing causes were that key decisions lacked rigorous challenge and vetting and were non-conservative, and a lack of adequate management oversight for the clean-up activities as well as the Radioactive Waste Shipping and Handling Program.
Corrective Steps and Results Achieved Upon notification of the non-conforming condition immediate action was taken to return the shipment to Columbia which arrived onsite at 1545 PST on November 9, 2016 restoring compliance.
GO2-17-141 Enclosure Page 2 of 2 The following are corrective actions that have been taken:
The station has developed and issued a detailed procedure for spent fuel pool clean-up activities integrated with associated Radioactive Waste Shipping and Handling procedures and ensures all roles and responsibilities for all affected departments are clearly defined, including who has decision-making authority; Prior to the detailed procedure implementation, radioactive waste shipments were reviewed and approved by the Radiation Protection Manager prior to transport; A peer self-assessment was performed of the Radioactive Waste Shipping and Handling Program with an industry peer and expert to identify performance vulnerabilities in the current program and to identify where gaps existed between Columbia radioactive waste shipping practices and industry standard practices. Recommendations have been evaluated and actioned appropriately; Filters located in the spent fuel pool were inventoried for proper tracking and disposal; Past radioactive waste shipments were reviewed for evidence of any incorrect characterizations, problems with documentation or violations that were not adequately addressed or that would warrant additional actions. Several minor documentation issues were identified and for one shipment a corrected manifest was provided to US Ecology; Self-Assessments were performed or are scheduled for three infrequently performed processes or projects, involving high risk and potential impact.
Since the event which led to the notice of violation there have been no events in which radioactive waste was transported with external dose rates contrary to 49 CFR Part 173.427(a)(1).
Corrective Steps that Will be Taken Energy Northwest will systematically remove and inventory all items from the container in question and will perform characterization of the items prior to transportation and disposal.
Date of Full Compliance Full compliance with 10 CFR 71.5(a) and 49 CFR 173.427(a)(1) was achieved on November 9, 2016 at 1545 PST when the container in question was received at Columbia following notification of the non-conforming condition.