IR 05000395/1988025

From kanterella
Jump to navigation Jump to search
Insp Rept 50-395/88-25 on 881001-31.No Violations or Deviations Noted.Major Areas Inspected:Monthly Surveillance Observations,Monthly Maint Observation,Operational Safety Verification & Onsite Followup of Events
ML20196A115
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 11/22/1988
From: Dance H, Hopkins P, Prevatte R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20196A113 List:
References
50-395-88-25, NUDOCS 8812050262
Download: ML20196A115 (8)


Text

.

p~%

.

y*.'

1 UNITED STATES

'g

,j NUCLEAR REGULATORY COMMISSION

"'

o

REGION 11

\\?

j[

101 MARIETTA ST., N.W.

ATLANTA. GEORGIA 30323

.,,,

Report No.:

50-395/88-25 Licensee: South Carolina Electric and Gas Company Columbia, SC 29218 Docket No.: '50-395 License No.:

NPF-12 Facility Name:

V. C. Summer Inspection Conducted: October 1-31, 1988 Inspectors:

[L

/'

FI-r v Rithard L. Prevatte Date Signed

'

NC.dadCu vh/w Perry C. Hopk'ns

/ Dat( Signed Approved by:

<d' x b h

//

Hugh C6 Dance, Section Chief

'Dat( Signed Division of Reactor Projects SUMMARY Scope:

This routine, announced inspection was conducted by the resident inspector.; onsite, in the areas of monthly surveillance observations, monthly maintenance observation, operational safety verification, engineered safety features system walkdown, onsite followup of events and subsequent written reports, design, design changes and modifica-tions and other areas.

Results:

The licensee was in the forty-fif th day uf the outage as of October 31, 1988, and are within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of the schedule. Appar-ently the efforts spent on scheduling before the outage have contri-buted to the ability of staying on schedule at this time.

Of over 300 environmental qualification tasks scheduled during the outage, 133 have been completed.

Over 11,000 tasks were scheduled and approximately 6,000 have been completed SG ecidy current testing has been completed with on going plugging operations and tube pulling completed.

Outage radioactivity exposure has been controlled very well with the large amount of steam generator work taking place. The exposure is at 317 person-rems.

Emergency DG "A" wo k was slow due to leaking water jacket seals.

However, the diesel was operational on time.

Diesel Generctor "B",

"B" train work such as SW, CCS, reactor building spray pump and sump suction, and "B" train RHRS work is in progress. Critical path work on the schedule centers around "B" train work and reloading of fuel that began October 30, 1988.

Within the areas inspected, no violations or deviations were identi-fied.

.

8G12050262 G81122 PDR ADOCK 0U000395 O

PDC k

_ _

- _ - _ _ _ _ _ _ _ _

i

!

.,

.

l REPORT DETAILS 1.

Persons Contacted i

Licensee Employees l

W. Baehr, Manager, Chemistry and Health Physics

  • K. Beale, Manager, Nuclear Protection Services 0. Bradham, Vice President, Nuclear Operations C. Bowman, Manager, Scheduling and Modifications
  • H. Browne, General Manager, Station Support W. Higgins, Supervisor, Regulatory Compliance
  • S. Hunt, Manager, Quality Systems
  • A. Koon, Manager, Nuclear Licensing
  • G. Moffatt, Marager, Maintenance Services
  • D. Moore, General Manager, Engineering Services
  • K. Nettles, General Manager, Nuclear Sac ty C. Price, Manager, Technical Oversite J. Shepp, Associate Manager, Operations J. Skolds, General Manager, Nuclear Plant Operations G. Soult, General Manager, Operations and Maintenance
  • G. Taylor, Manager, Operations
  • D. Warner, Manager, Core Engineering and Nuclear Computer Services
  • M. Williams, General Manager, Nuclear Services K. Woodward, Manager, Nuclear Operations Education and Training NRC Resident Inspectors
  • P. Hopkins, Resident Inspector R. Prevatte, Senior Resident Inspector Othei licensee employees contacted included engineers, technicians, operators, mechanics, security force members, and office personnel.
  • Attended exit interview Acronyms and initialisms used throughout this report are listed in the last paragraph.

Monthly Surveillance Observation (61726)

The inspectors observed surveillance activities of safety related systems j

and components to ascertain that these activities were conducted in i

accordance with license requirements. The inspectors observed portions of i

12 selected surveillance tests including all aspects of DG Refueling i

Inspection, STP 409.001.

The inspectors also verified that required administrative approvals were obtained prior to initiating the test, testing was accomplished by qualified personnel, required test instru-mentation was properly calibrated, data met TS requirements, test discre-pancies were rectified, and the systems were properly returned to service.

_.....

.

_ _ _ _ _ _ _ _ _

l

.

..

.

Direct observation of performance of surveillance testing took picce.

i STP's were technically adequate to perform the required testing.

STP's

'

were present in the testing location, followed step by step during performance, and completion of steps was documented by marking check off blocks as required.

Independent verification was properly performed in accordance with instructions.

Pretest activities included reviewing procedures prior to start, selecting and acquiring proper measuring and test equipment, obtaining perm'ssion from the shift supervisor or his designee, and a discussion of the test and its effect on the plant was held.

Posttest activities included the review of the completed proce-dures by the test performers for completoness and accuracy.

The shift supervisor / supervising operator reviewed the test fo completion and the final group supervisor reviewed the procedure for completeness.

Tests were suspended when required in order to satisfy and/or correct test deficiency or procedural deficiency.

Performance of test procedures appeared to be adequate.

No violations or deviations were identified.

3.

Monthly Maintenance Observation (62703)

The inspectors observed maintenance activities of safety related systems and components to ascertain that these activities were conducted in accordance with approved procedures, TS and appropriate industry codes and standards.

The inspectors also determined that the procedures used were adequate to control the activity, and that these activities were accom-plished by qualified personnel.

The inspectors independently verified that equipment was properly tested before being returned to service.

Additionally, the inspectors reviewed several outstarding job orders to determine that the licensee was giving priority to safety related mainten-ance and not developing a backlog which might affect a given syston's performance.

The following specific maintenance activities were observed:

MWR 8810342 Repair DG "A" coolant expansion tank level indicator PMTS P106196 Electrical equipment inspection and cleaning PMTS P102577 Visually inspect and cycle releys for annual inspection PMTS 108902 DG "A" annual air start compressor system MWR 10380 Replacement of electronic NA4 cards MWR 319520010 Reinstall the over current sensing relay and perform wiring change MWR 21364002 Replace / remove gating and the synchronizing of the boards PMTS P97377 Calibration of 120 volts inverter

_

_-_

_ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

-

..

PMTS P0107614 Partial teardown for 18 month PM for DG "A" MWR 88M0006 Support refueling DG 18 month inspection MWR 8801533 Repair pressure controller on instrument air PMTS P0108936 DG "A" engine partial teardown PMTS P0108934 DG "A" inservice inspection PMTS P0103279 DG "A" Jacket water heater repair PMTS P106159 DG instrumentation calibration MWR 88MG052 Remove and replace DG "A" instrumentation MWR 8801206 Repair non-functioning annunicators on DG "A" panel MWR 109010018 Repair double wall seal in trace 109ElB, 1005 and ECB1039 MWR 214290002 Repair of main steam regulator to increase efficiency and exhaust more water

.

MWR 87E0173 Replace manual and automatic voltage regulators on DG "A" PMTS P0110939 DG "A" lubrication check MWR 88M0386 Repair cylinder oil leak on DG "A" MWR 213770002 Install air duct on the air handling unit per MRF 21377 f

MWR 213770003 Fabricate and install supports for ducting for cooling l

safety harsh environment equipment MWR 21377 Install additional cooling for safety harsh environment equipment in the intermediate building for

!

the msin steam system isolation valves MWR 88M0243 Overhaul DG "A" compressor unloader and outlet valve l

l MWR 88E0070 Performance of inspection of

"A" train motor cont.o1 l

'

centers PMTS P010622 Inspect motor starter for safety injection system j

XVG 08888800 PMTS P0101950 Work cold leg injection header isolation valves XMC 10A2Y, 13DG XVG 08889

..

-

.

_.

._ _

.

'

.

.

PMTS 98341 Inspect and repair cold leg injection header isolation valve XVG 088884 PMTS P104850 Repair and repack main steam header "B" drain valve XVT 2849B-MS

"

PMTS P104849 Repair and repack main steam header "A" drain valve XVT 2849A-MS PMTS P98399 Repair hydrogen analyzer and "A" reactor building sample valve XVX 06051C-M PMTS P108166 Perform operational check on cooling water circuit breaker XW K1070 PMTS P104614 Repack high root isolation valve on main steam line IAX 126-MS PMTS P104851 Repair and repack main steam header "C" drain valve

.

XVT 2849C-MS PMTS P104613 Repair and repack high root isolation valve on main steam line ;alve IAX 001281-HR-MS PMTS P0107693 Repair operator for RHR header "B" isolation valve XVG 0870-1B-0-RH MWR 8800132 Check and repair snubber, as recessary, (MKCSH 0468)

and perform STP 403.002 MWR 8800131 Check and repair snubber, as neces sary, (MKCSH 0467)

and perform STP 403.002 PMTS P0098261 Repair and verify EQ qualification for pressurizer tank vent isolation valve XVD 08047-RC MWR 88E01731 Replace spring packs and perform M0 VATS testing No violations or deviations were identified.

4.

Operational Safety Verification (71707)

a.

The inspectors toured the control room, eviewed plant logs and

.

records, and held discussions with plant staff personnel to verify that the plant was being orerated safely and in conformance with applicable requirements.

Specific items inspected in the control room included:

adequacy of staffing and attentiveness of control room personnel, TS and procedural adherence, operability of equipment and indicated control room status, control room logs, tagout books, operating orders, jumper / bypass controls, computer printouts and J

.


m

-__ _, _ _,

.m,-.

.

'

.

.

annunciators.. Tours of other plant areas were conducted to verify equipment operability, control of ignition sources and combustible materials, the condition of fire detection and extinguishing equipment, the control of maintenance and surveillance activities in progress, the implementation of radiation protective controls and the physical security plan.

Tours were conducted during normal and random off hour periods.

b.

Section 4.4.5.5 of TS requires the results of steam generator tube inspection which fall into category C-3 be reported pursuant to 10 CFR 50.72.(b).2.(i).

Based on the completion of eddy current inspections, the results classify the steam generators as category C-3, (more than 1*.' o f t he inspected tubes are defective).

This information has been reported telephonically to the NRC regional office. The final result on 10/28/88 are as follows:

S/G A S/G B S/G C 184 plug 233 plug 176 plug 97 F*

203 F*

69 F*

25 as is 43 as is 18 as is

  • -Star

.

See LER 88-11 for further details.

c.

The plant is currently in an outage.

The control room is in the process of being painted, including the control boards, and replacing carpeting.

Discipline of control room personnel is quite good.

Disruptions have been at a minimum even with the high volume of work activity taking place.

Shif t turnovers are conducted in a profes-sional manner.

No violations or deviations were identified.

5.

ESF System Walkdown (71710)

The inspectors verified the operability of an ESF system by ;erforming a walkdown of the accessible portions of the Diesel Fuel System.

The inspectors confirmed that the licensee's system lineup procedures matched plant drawings and the as-built configuration. The inspectors looked for equipment conditions and items that might degrade performance (e.g.,

inoperable hangers and supports poor housekeeping, etc.) and inspected the interiors of electrical and instrumentation cabinets for debris, loose material, jumpers, evidence of rodents, etc. The inspectors verified that valves, including i nstrumentation isolation valves, were in proper position, power was available, and valves were locked as appropriate. The inspectors compared both local and remote position indications.

No violations or deviations were identified.

.. -

p7m

-

f---

-

,y

-_-m

,.

py

,.e-e,,-.----.a y

.. -..-

_-._m-

_ -,

,

___ _ _ _ _ _ _ _

.

'

.

,

.

6.

Onsite Follower of Events and Subsequent Written Reports (92700, 93702)

The inspectors reviewed the following SPR's to ascertain whether the licensee's review, corrective action and report of the identified event or deficic" y was in conformance with regulatory requirements, TS, license conditions, and licensoe procedures and controls. Based upon this review the following items are closed:

SPR 88-007 Lightning strike of meteorological instrumentation SPR 88-006 Fire suppression system No violations or deviations were identified.

7.

Design, Design Changes and Modifications (37700)

The inspectors reviewed design changes, listed below, not previously approved by NRR, to assure that the changes had been reviewed and approved in accordance with the TS and 10 CFR 50.59.

During the review, the inspectors verified (1) that the design changes were reviewed and approved in accordance with TS and established QA/QC controls, (2) that design changes were controlled by established procedures, (3) that the licensee conducted a review and evaluation of test results and that these test results were within previously established acceptance criteria and that any test deviations were resolved and necessary retesting was accomplished as appropriate, (4) that operating procedure modifications were made and approved in accordance with TS, and (5) that as-built drawings were changed to reflect the modifications.

The inspectors observed (1) that change activities were conducted in accordance with the appropriate specifications, drawings, and other requirements, (2) that acceptance and startup testing of modifications were conducted in accordance with technically adequate and approved procedures, and (3) that appropriate controls were implemented, (e.g.,

firewatch, portable fi re fighting equipment, welding and cutting permit, etc.).

Additionally, the inspectors reviewed the outstanding FCR's and determined that an excessive backlog was not developing.

Design changes reviewed were:

MRF 21022, this MRF work is to reduce required output of ea-h SWBP from 4000 GPM to 2000 GPM: (1) making SW valves XVC3109 A, B, C, and D, and their associated ci-cuitry "active" and (2) causing the valves l

corresponding with the se.lected to run RBCU fans to open and the other two valves to close upon receipt of an "SI" signal.

No violations or deviations were identified.

8.

Other Areas A Region II maintenance inspection team visited V.C. Summer during the week of October 17, 1988.

_

>

,

,

.

9.

Exit Interview (30703)

The inspection scope and findings were summarized on October 31, 1988, with those persons indicated in paragraph 1.

The inspectors described the areas inspect" and discussed the inspection findings.

No dissenting comments were received from the licensee.

The licensee did not identify as proprietary any of the - materials provided to or reviewed by the inspectors during the inspection.

10. Acronyms and Initialisms CCS Component Cooling System DG Diesel Generator EQ Environmental Qualification ESF Engineered Safety Feature FCR Facility Change Requests GPM Gallons Per Minute MWR Maintenance Work Request l,

MRF Modification Request Form NRC Nuclear Regulatory Commission HRR Nuclear Reactor Regulation PM Post Maintenance PMTS Preventative Maintenance Task Sheet QA Quality Assurance QC Quality Control RBCU Reactor Building Cooling Units RHRS Residual Heat Removal System SG Steam Generaeor

'

SI Safety Injection

'

STP Surveillance Test Procedures SW Service Water SWBP Service Water Booster Pump TS Technical Specifications t-i

-

!

-

.

..