IR 05000382/2025005
| ML25226A078 | |
| Person / Time | |
|---|---|
| Site: | Waterford |
| Issue date: | 08/14/2025 |
| From: | John Dixon NRC/RGN-IV/DORS |
| To: | Sullivan J Entergy Operations |
| References | |
| IR 2025005 | |
| Download: ML25226A078 (1) | |
Text
August 14, 2025
SUBJECT:
UPDATED INSPECTION PLAN FOR WATERFORD STEAM ELECTRIC STATION, UNIT 3 REPORT 05000382/2025005
Dear Joseph Sullivan:
The enclosed inspection plan lists the inspections scheduled through June 30, 2027, for Waterford Steam Electric Station, Unit 3. The U.S. Nuclear Regulatory Commission (NRC)
provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. As discussed in SECY-25-0045, Recommendations for Revising the Reactor Oversight Process, dated June 5, 2025 (ML25042A278), the NRC determined that a broad, comprehensive review of the Reactor Oversight Process (ROP) is necessary to reflect improvements in industry performance and advancements in technology. The outcome of the comprehensive review and recommendations to revise the ROP baseline inspection program, when approved by the NRC Commission, will require a revision to this inspection plan. The NRC will contact you as soon as possible to discuss any revisions after the new baseline inspection program is implemented.
Waterford Steam Electric Station, Unit 3s current performance is in the Regulatory Response column of the NRCs Action Matrix, effective the second quarter of 2025, as communicated in NRC inspection report 05000382/2025091, Waterford Steam Electric Station, Unit 3 - Final Significance Determination of a White Finding, Notice of Violation, and Follow-up Assessment Letter. Therefore, we plan to conduct a supplemental inspection using Inspection Procedure 95001, Supplemental Inspection Response to Action Matrix Column 2 (Regulatory Response) Inputs, when your staff has notified us of your readiness for this inspection. This inspection procedure is conducted to provide assurance that the root cause and contributing causes of risk significant performance issues are understood, the extent of condition and the extent of cause are identified, and the corrective actions are sufficient to preclude repetition. This letter and its enclosure will be made available for public inspection and copying at ADAMS Public Documents l NRC.gov and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Please contact me at 817-200-1574 with any questions you have regarding this letter.
Sincerely, John L. Dixon, Jr., Chief Reactor Projects Branch D Division of Operating Reactor Safety Docket No. 05000382 License No. NPF-38 Enclosure: Inspection Plan cc w/encl: Distribution via LISTSERV Signed by Dixon, John on 08/14/25
Non-Sensitive
Sensitive
Publicly Available
Non-Publicly Available OFFICE SPE:DORS/PBD BC:DORS/PBD NAME ASanchez JDixon SIGNATURE
/RA/
/RA/
DATE 08/14/25 08/14/25
Site Inspection Activity Plan Waterford 07/01/2025 - 06/30/2027 Unit Start End Activity CAC Title Staff Count Cybersecurity-WF3
3 7/6/2025 7/12/2025 IP 71130.10 000741 Cybersecurity W3 2025 BRQ
3 7/13/2025 7/19/2025 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Security Protective Strategy (71130.05) and Target Sets (71130.14)
3 8/4/2025 8/7/2025 IP 71130.05 000737 Protective Strategy Evaluation
8/4/2025 8/7/2025 IP 71130.14 000743 Review of Power Reactor Target Sets
8/4/2025 8/7/2025 IP 71153 001341 Follow Up of Events and Notices of Enforcement Discretion RP 5,8 - WF3
3 8/18/2025 8/22/2025 IP 71124.05 000729 Radiation Monitoring Instrumentation
8/18/2025 8/22/2025 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Commercial Grade Dedication Inspection - Waterford
3 9/8/2025 9/12/2025 IP 71111.21N.03 001808 Commercial Grade Dedication
9/22/2025 9/26/2025 IP 71111.21N.03 001808 Commercial Grade Dedication RP 6,7 - WF3
3 9/8/2025 9/12/2025 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment
9/8/2025 9/12/2025 IP 71124.07 000731 Radiological Environmental Monitoring Program Waterford ISFSI Part 50 feeder for CBS Q3
3 9/29/2025 9/30/2025 IP 60855 Operation Of An ISFSI EP 2025 Biennial Exercise & PI Inspection - WF3
3 11/17/2025 11/21/2025 IP 71114.01 000716 Exercise Evaluation
11/17/2025 11/21/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes
11/17/2025 11/21/2025 IP 71151 001397 Performance Indicator Verification Waterford 2026 PI&R
3 2/9/2026 2/13/2026 IP 71152B 000747 Problem Identification and Resolution
2/16/2026 2/27/2026 IP 71152B 000747 Problem Identification and Resolution Security 71130.02/.07./08
3 4/13/2026 4/16/2026 IP 71130.02 000734 Access Control
4/13/2026 4/16/2026 IP 71130.07 000739 Security Training
4/13/2026 4/16/2026 IP 71130.08 000740 Fitness-For-Duty Program
4/13/2026 4/16/2026 IP 71130.09 001656 Security Plan Changes
4/13/2026 4/16/2026 IP 71151 001338 Performance Indicator Verification Prepared on 8/13/2025 1:39:05 PM 1 of 3
Site Inspection Activity Plan Age-Related Degradation Inspection - Waterford
3 5/4/2026 5/8/2026 IP 71111.21N.04 001832 Age-Related Degradation
5/18/2026 5/22/2026 IP 71111.21N.04 001832 Age-Related Degradation W3 2026 INITIAL EXAM
3 7/19/2026 7/25/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)
8/16/2026 8/22/2026 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)
Inservice Inspection - WF3
3 10/5/2026 10/16/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
3 10/26/2026 10/30/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
10/26/2026 10/30/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation
10/26/2026 10/30/2026 IP 71151 000746 Performance Indicator Verification EP Program & PI Inspection (2026) - W3
3 11/30/2026 12/4/2026 IP 71114.02 000717 Alert and Notification System Testing
11/30/2026 12/4/2026 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System
11/30/2026 12/4/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes
11/30/2026 12/4/2026 IP 71114.05 000720 Maintenance of Emergency Preparedness
11/30/2026 12/4/2026 IP 71151 001397 Performance Indicator Verification MC&A - WF3
3 2/1/2027 2/5/2027 IP 71130.11 000742 Material Control and Accounting (MC&A)
FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - WAT
3 2/22/2027 2/26/2027 IP 71130.03 000735 Contingency Response - Force-On-Force Testing
3/22/2027 3/26/2027 IP 71130.03 000735 Contingency Response - Force-On-Force Testing RP 1,4,PI - WF3
3 3/8/2027 3/12/2027 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
3/8/2027 3/12/2027 IP 71124.04 000728 Occupational Dose Assessment
3/8/2027 3/12/2027 IP 71151 000746 Performance Indicator Verification Security 71130.01/.02/.04
3 4/12/2027 4/16/2027 IP 71130.01 000733 Access Authorization
4/12/2027 4/16/2027 IP 71130.02 000734 Access Control
4/12/2027 4/16/2027 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance
4/12/2027 4/16/2027 IP 71130.09 001656 Security Plan Changes
4/12/2027 4/16/2027 IP 71151 001338 Performance Indicator Verification Prepared on 8/13/2025 1:39:05 PM 2 of 3
Site Inspection Activity Plan Waterford 07/01/2025 - 06/30/2027 Unit Start End Activity CAC Title Staff Count Waterford ISFSI Part 72, CBS Closeout
7/23/2025 9/30/2025 IP 60855 001001 Operation Of An ISFSI Prepared on 8/13/2025 1:39:05 PM 3 of 3