IR 05000382/2025402

From kanterella
Jump to navigation Jump to search
Security Baseline Inspection Report 05000382/2025402
ML25233A240
Person / Time
Site: Waterford 
Issue date: 08/26/2025
From: Jesse Rollins
NRC/RGN-IV/DRSS/PSB
To: Sullivan J
Entergy Operations
References
IR 2025402
Download: ML25233A240 (1)


Text

August 26, 2025

SUBJECT:

WATERFORD STEAM ELECTRIC STATION, UNIT 3SECURITY BASELINE INSPECTION REPORT 05000382/2025402

Dear Joseph Sullivan:

On August 7, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Waterford Steam Electric Station and discussed the results of this inspection with John Twarog, Regulatory Assurance Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

If you contest the minor violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 205550001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at the Waterford Steam Electric Station.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Jesse M. Rollins, Chief Physical Security Branch Division of Radiological Safety & Security Signed by Rollins, Jesse on 08/26/25 Docket No. 05000382 License No. NPF-38

Enclosure:

As stated

Inspection Report

Docket Number:

05000382

License Number:

NPF-38

Report Number:

05000382/2025402

Enterprise Identifier:

I-2025-402-0008

Licensee:

Entergy Operations, Inc.

Facility:

Waterford Steam Electric Station, Unit 3

Location:

Killona, LA

Inspection Dates:

August 4, 2025, to August 7, 2025

Inspectors:

M. Hein, Physical Security Inspector

C. Jewett, Senior Enforcement Specialist

M. Ordoyne, Physical Security Inspector

Approved By:

Jesse M. Rollins, Chief

Physical Security Branch

Division of Radiological Safety & Security

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Waterford Steam Electric Station,

Unit 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000382/2025-S01-00 71153 Closed LER 2025-S01-00 for Waterford Steam Electric Station, Unit 3, Follow-up Report for a 10 CFR 73 Security Report on January 31, 2025

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

SAFEGUARDS

71130.05 - Protective Strategy Evaluation

The inspectors evaluated the licensee's protective strategy through completion of the following

procedure elements: Protective Strategy Evaluation

(1)

  • Tier I: 13 Requirements (02.01 b, d, h, i, k; 02.02 a, c, f; 02.03 a 02.04 b-e)
  • Tier II: 9 Requirements (02.06 d, f, i, n; 02.07 a-e)
  • Tier III: 1 Requirement (02.08)
(2) The inspectors assessed the licensee's annual force on force exercise on August 5, 2025

71130.14 - Review of Power Reactor Target Sets

The inspectors evaluated the Security Target Set Program. The following elements were evaluated:

Review of Power Reactor Target Sets

(1)

  • 8 Requirements (03.01 a; 03.02b, d, e; 03.03 a; 03.04 a, b; 03.05 a)

OTHER ACTIVITIES

BASELINE

71153 - Follow Up of Events and Notices of Enforcement Discretion Follow Up of Events and Notices of Enforcement Discretion

(1) The inspectors evaluated the following licensee event report (LER) which can be accessed at https://lersearch.inl.gov/LERSearchCriteria.aspx LER 50-382/2025-S01-00 for Waterford Steam Electric Station, Unit 3, Follow-up Report for a 10 CFR 73 Security Report on January 31, 2025 (ADAMS Accession ML25091A241)

The inspectors determined that the cause of the condition in the LER was a minor violation.

INSPECTION RESULTS

Minor Violation 71153 Failure to complete access authorization refresher training.

The inspectors reviewed LER 50-382/2025-S01-00 dated April 1, 2025, regarding an actual entry of unauthorized personnel into the protected area (PA). In this LER, the licensee reported that two employees had retained their unescorted access to the site despite having expired plant access training. This training covers individual fitness-for-duty (FFD) and behavior observation program (BOP) responsibilities and must be completed on a nominal 12-month frequency for individuals maintaining unescorted access to the PA.

Of the two individuals, both made entries into the licensees PA unescorted without meeting all the requirements for maintaining unescorted access. The licensee reported this as an actual entry of unauthorized personnel into the PA. The inspectors determined that the individuals had received initial FFD and BOP training and were still subject to other required elements of the licensees access authorization program that provide assurance of trustworthiness and reliability.

10 CFR 73.56(f)(2)(ii) states, in part, Behavioral observation training must be: (C) Maintained in a current status during any period of time an individual possesses unescorted access or unescorted access authorization in accordance with paragraph (f)(2)(iv) of this section.

10 CFR 73.56(f)(2)(iv) states, in part, Individuals shall complete refresher training on a nominal 12-month frequency, or more frequently where the need is indicated.

Contrary to the above, from November 29, 2024, to February 6, 2025, the licensee failed to ensure that behavioral observation training was maintained in a current status during any period of time an individual possesses unescorted access or unescorted access authorization. Specifically, two individuals with unescorted access to Waterford Steam Electric Station were allowed to retain their access to the site despite having expired training.

These individuals failed to complete behavior observation refresher training within a nominal 12-month frequency. Both individuals made entry into the sites protected area.

Screening: The inspectors determined the performance deficiency was minor. The inspectors determined the performance deficiency was minor because it could not be viewed as a precursor to a significant event, would not have the potential to lead to a more significant safety concern if left uncorrected, and did not adversely affect the security cornerstone objective.

Enforcement:

This failure to comply with 10 CFR 73.56(f)(2)(ii) constitutes a minor violation that is not subject to enforcement action in accordance with the NRCs Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On August 7, 2025, the inspectors presented the security baseline inspection results to John Twarog, Regulatory Assurance Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

CR-WF3-2025-

00401; CR-WF3-

25-00454; CR-

WF3-2025-

00443; CR-WF3-

25-00524; CR-

WF3-2025-

00548; CR-WF3-

25-00677; CR-

WF3-2025-

00946; CR-WF3-

25-01229; CR-

WF3-2025-

01680; CR-WF3-

25-01755; CR-

WF3-2025-

01779; CR-WF3-

25-01963; CR-

WF3-2025-

2374; CR-WF3-

25-02645; CR-

WF3-2025-

296; CR-WF3-

25-01489; CR-

WF3-2025-

01473; CR-WF3-

25-02124

71130.05

Corrective Action

Documents

Resulting from

Inspection

CR-WF3-2025-

03791; CR-WF3-

25-03789; CR-

WF3-2025-

03790; CR-WF3-

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

25-03788

Miscellaneous

SGI-WF3-2011-

Security Drill Scenario Book

06/23/2025

EN-NS-215

Conduct of Security Force Exercises and Drills

EN-NS-215-01

Tactical Response Drills

EN-NS-215-02

Annual Force on Force Exercises

EN-NS-215-03

Triennial Force on Force Exercises

EN-NS-216

Controller Responsibilities Guidelines

EN-NS-220

Managing the Safety/Security interface

005

EN-NS-234

Force on Force Mock Adversary Program

EN-NS-239

Security Patrols, Tours, and Inspections

001

OP-901-523

Off Normal Procedure Security Events

29

PS-015-101

Security Patrols

310

Procedures

PS-018-115

Defensive Strategy and Tactical Deployment

Corrective Action

Documents

CR-WF3-2024-

2958; CR-WF3-

24-05260; CR-

WF3-2025-

01769; CR-WF3-

25-02940

Corrective Action

Documents

Resulting from

Inspection

CR-WF3-2025-

03801

Vital Target Set Identification Basis

05/01/2000

Miscellaneous

Critical target Sets

EN-NS-306

Development and Maintenance of Target Sets

71130.14

Procedures

OP-901-523

Security Events

29