IR 05000346/1986013

From kanterella
Jump to navigation Jump to search
Partially Withheld Physical Security Insp Rept 50-346/86-13 on 860312 & 17 (Ref 10CFR73.21).Violation Noted:Failure to Adequately Control Access to Vital Area & Rept Loss of Security Effectiveness
ML20197E492
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 05/08/1986
From: Creed J, Madeda T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20197E478 List:
References
50-346-86-13, NUDOCS 8605150270
Download: ML20197E492 (1)


Text

, -

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No. 50-346/86013(DRSS)

Docket No. 50-346 License No. NPF-3 Safeguards Group IV

'

Licensee: Toledo Edison Company Edison Plaza 300 Madison Avenue Toledo, OH 43652 Facility Name: Davis-Besse Nuclear Power Station, Unit 1 Inspection At: Davis-Besse Site, Oak Harbor, OH Inspection Conducted: March 12 and 17, 1986 Date of Last Physical Security Inspection: January 6-10, 1986 Type of Inspection: Announced, Special Physical Security Inspection Inspector: m k f/inds, S/ Wet T.J./,ageda

~~

D(te PhysicaY Security Inspector Approved By: hh 8/8[a (f. R. Creed, Chief Date Safeguards Section Inspection Summary Inspection on March 12 and 17, 1986 (Report No. 50-346/86013(DRSS))

Areas Inspected: Included a review of a security incident involving a Vital Area (VA) barrier degradation that occurred between March 4 and 5,198 Results: Based on this inspection, two apparent violations were identified: Access Control - Personnel: The licensee failed to adequately control access to a vital are . Records and Reports: The licensee failed to report to the NRC a major loss of security effectiveness, uncompensated for, within the one hour requirement specified in 10 CFR 73.71(c). The event was reported lat (Details: UNCLASSIFIED )

,

Enclosure contains 8605150270 860509 pon separation this PDR ADOCK 05000346 Page is Decontrolled G PDR