Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in IE Insp Rept 50-341/79-25.Notes Supplemental Info Will Be Submitted Re Site QA & Integration of Engineers W/Contractor Personnel
ML19309C475
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 03/24/1980
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Hines E
DETROIT EDISON CO.
Shared Package
ML19309C476 List:
References
NUDOCS 8004080645
Download: ML19309C475 (1)


Text

.y t.

,

A

[ ga ns co, s

o UNITED STATES Pg

',

[1*

'j NUCLEAR REGULATORY COMMISSION

.r7 c

REGION ill o, h "*I J..[

799 ROOSEVELT ROAD s'?

%, s......f GLEN ELLYN, ILLINOIS 60137 NSR24 %

.

Docket No. 50-341 Detroit Edison Company ATTN:

Mr. Edward Hines, Assistant Vice President and Manager 2000 Second Avenue Detroit, MI 48226 Gentlemen:

Thank you for your letter dated February 28, 1980, informing us of the steps you have taken to correct the items of noncompliance which we brought to your attention in Inspection Report No. 50-341/79-25 for-warded by our letter dated January 14, 1980. You did not respond to the fifth paragraph of our letter.

Per a conversation on March 20, 1980, with your construction Quality Assurance Section Head we under-stand you will supplement your response letter. We further understand that you will explain the actions you have taken to control conditions adverse to quality, for example, the reorganization of site quality assurance - control functions and the integration of your engineering forces with site contractor personnel. We will examine these matters during a subsequent' inspection.

Your cooperation with us is appreciated.

Sincerely,

~

G. Fiorelli, Chief Reactor Construction and Engineering Support Branch cc w/1tr dtd 2/28/80:

Central Files Reproduction Unit NRC 20b PDR NSIC

.

8004080