Forwards IE Insp Rept 50-333/80-05 on 800407-11 & Notice of Violation
ML19344E777
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 05/16/1980
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Pasternak R
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
Shared Package
ML19344E762 List:
References
NUDOCS 8009110301
Download: ML19344E777 (2)


Text

-

U

-.

,

,

  1. " N UNITED STATES e

j) '*g NUCLEAR REGULATORY COMMISSION

.,

g

REGION I

y

..

es g

631 PARK AVENUE KING OF PRUS$1 A PENNSYLVANI A 19404

MAY 161980 Docket No. 50-333 Power Authority of the State of New York James A. FitzPatrick Nuclear Power Plant ATTN: Mr. R. J. Pasternak Resident Manager P. O. Box 41 Lycoming, New York 13093

.

Gentlemen:

Subject:

Inspection No. 50-333/80-05 This refers to the inspection conducted by Mr. N. Blumberg of this office on April 7-11, 1980, at James A. Fitzpatrick Nuclear' Power Plant, Scriba, New York of activities authorized by NRC License No. DPR-59 and to the discussions of our findings held by Mr. N. Blumberg with Mr. R. Pasternack and other members of your staff at the conclusion of the inspection, and to a subsequent telephone discussion between Mr. H. Keith of your staff and Mr. Blumberg on April 17, 1980.

Areas examined during this inspection are described in the Office of Inspection and Enforcement Inspection Report which is enclosed with this letter.

Within these areas, the inspection consisted of selective examinations of procedures and representative records, interviews with personnel, and observations by the inspector.

Our inspector also verified the steps you have taken to correct the items of noncompliance brought to your attention in letters dated October 30, 1978 and May 4, 1979. We have no further questions regarding your action at this time.

Based on the results of this inspection, it appears that certain of your activi-ties were not conducted in full compliance with NRC requirements, as set forth

,

in the Notice of Violation, enclosed herewith as Appendix A.

These items of noncompliance have been categorized into the levels as described in our corre-spondence to you dated December 31, 1974.

This notice is sent to you pursuant I

to the provisions of Section 2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.

Section 2.201 requires you to submit to this office, within twenty (20) days of your receipt of this notice, a written statement or explanation in reply including:

(1) corrective steps which have been taken by you and the results achieved; (2) corrective steps which will be taken to avoid further items of noncompliance; and (3) the date when full com-

!

pliance will be achieved.

l l

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations, a copy of this letter and the enclosures I

l will be placed in the NRC's Public Document Room.

If this report contains any l

,

800911050(

+

-

.

.

Power Auth:rity of th2 Stats of New York

WY 1 6 19 M information that you (or your contractor) believe to be proprietary, it is necessary that you make a written application within 20 days to this office to withhold such information from public disclosure. Any such application must be accompanied by an affidavit executed by the owner of the.information, wh!ch identifies the document ce part sought to be withheld, and which contains a statement of reasons which addresses with specificity the items which will be considered by the Commission as listed in subparagraph (b) (4) of Section 2.790.

The information sought to be withheld shall be incorporated as far as possible into a separate part of the affidavit.

If we do not hear from you in this regard within the specified period, the report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely, O C. LCA p. /}c h 4 Eldon J. Brunner, Chief Reactor Operations and Nuclear Support Branch Encicsures:

1.

Appendix A, Notice of Violation 2.

Of fice of Inspection and Enforcement Inspection Report No. 50-333/80-05 cc w/ encl:

George T. Berry, Executive Director P. W. Lyon, Manager - Nuclear Operations A. Klausmann, Director, Quality Assurance M. C. Cosgrove, Quality Assurance Supervisor l

J. F. Davis, Chairman, Safety Review Committee

'

C. M. Pratt, Assistant General Counsel

!

G. M. Wilverding, Licensing Supervisor

!