IR 05000327/1986038

From kanterella
Jump to navigation Jump to search
Design Baseline & Verification Program Insp Repts 50-327/86-38 & 50-328/86-38 on 860609-13 & 16-20. Weaknesses Noted:Scope of Walkdowns Does Not Include Physical Verification of Instrumentation Aspects
ML20210A739
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 09/11/1986
From: Architzel R, Imbro E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To:
Shared Package
ML20210A737 List:
References
50-327-86-38, 50-328-86-38, NUDOCS 8609170328
Download: ML20210A739 (21)


Text

, .

  • ...

.

U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT Division of Quality Assurance, Vendor, and Technical Training Center Programs Report ~Nos.: 50-327/86-38;50-328/86-38 Docket Nos.: 50-327;50-328 Licensee: TennesseeValleyhuthority

<

6N, 38A Lookout Place 1101 Market St'.

Chattanooga, TN 37402-2801

Facility Name: Sequoyah Nuclear Plant, Units 1 & 2 Inspection At: Soddy Daisy and Knoxville, TN Inspection Conducted: June 9-13 and 16-20, 1986 Ins,pection Team Members:

Team Leader: R. E. Architzel, Senior Inspection Specialist, 'IE Mechanical Systems: F. Mollerus Consultant, Mollerus Engineering In Mechanical Components: A. V. duBouchet, Consulting Engineer Civil / Structural: A. Unsal, Harstead Engineering Electrical Power: S. V. Athaval_e, Inspection Specialist, IE Instrumentation &

Control: L. Stanley, Consultant, Zytor In Nuclear Systems: J. M. Leivo, Consulting Engineer Operations: P. Holmes-Ray, Senior Resident Inspector, RII ,

P. E. Harmon, Resident Inspector, SQN f&f

' Ralph E. Ar6hitzel / '

f'll~ 8b Date Team Leader Approved by: 7O Eugene V. Imbro 9-//Y/

Date Section Chief Quality Assurance Branch 8609170328 860915 PDR ADOCK 05000327 G PDR

. _ - . '__ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ . - _ . - _ _ . _____

.-

,* , . .

.

LIST OF ABBREVIATIONS ANSI American National Standards Institute CFR Code of Federal Regulations DBVP Design Baseline and Verification Program DNE Divisfon of Nuclear Engineering EA Engineering Assurance ECN Engineering Change Notice ESF Engineered Safety Features EQ Environmental Qualification FCN Field Change Notice FSAR Final Safety Analysis Report . .

HVAC Heating, Ventilation and Air Conditioning IEEE Institute of Electrical and Electronics Engineers LOCA Loss of Coolant Accident NRC U.S. Nuclear Regulatory Commission *

NSSS Nuclear Steam Supply System P&ID Piping and Instrumentation Diagram RHR Residual Heat Removal SLE System Lead Engineer SQN Sequoyah Nuclear Plant TACF Temporary Alteration Control Form TVA Tennessee Valley Authority USQ Unreviewed Safety Question .

WDP Walkdown Package l

l

. .

. . . . .

. _ _ _ . _ _ _ _ . . - -

.. a . . .

SEQUOYAH NUCLEAR POWER PLANT Design Baseline and Verification Program (D8VP)

Inspection Report 50-327/86-27 8 50-328/86-27 June 9 through June 20, 1986

. INTRODUCTION AND BACKGROUND This program was developed by the Division of Nuclear Engineering to resolve design control issues described in several evaluations and audits including:

Comprehensive review of the existing progra Studies / evaluations performed by TVA and otheg Interviews of key personnel within the TVA organizatio *

The preliminary results of the NRC design control team inspection (Report 50-327;50-328/86-27).

Two reviews performed by Gilbert / Commonwealt The corporate evaluation conducted by INP The Sequoyah Design Baseline and Verification Program will be used by TVA to provide the required level of confidence that the plant modifications, imple-mented since receipt of the operating ifcense, have not resulted in the violation of the plant's licensing basi The program is described in the " Program Plan for the Engineering Assurance Independent Oversight Review for the Sequoyah Nuclear Plant Design Baseline and Verification Program," dated May 9,1986 and forwarded to the NRC as an enclosure to Mr. R. L. Gridley's letter dated June 27, 198 NRC inspection activities-related to the TVA's D8VP and associated Engineering Assurance (EA) independent technical oversight of Sequoyah Nuclear plant are planned to be conducted in several phases:

(1) Inspection of program preparation and initial implementation (EA Review plans and procedures, D8VP procedures, walkdown results).

(2) Inspection of program implementation, including design criteria prepara-tion, Engineering Change Notice (ECN) and system evaluation (3) Inspection of DBVP and EA oversight results and corrective action . PURPOSE This was the first in a series of inspections planned to evaluate the D8V The purpose of this inspection was to assess (1) the overall DBVP plan and scope; (2) the implementing procedures for both the project and the associated independent Engineering Assurance (EA) oversight; (3) conduct and results of the walkdowns; and (4) perform a preliminary inspection of the preparation of I

__ _ ___ _

____

, , t! ,=.

design criteria. Specifically, the NRC evaluated EA review plans for each technical discipline to ensure that the review plans were in accordance with the program plan and also that they were in sufficient technical depth to achieve the program objectives. The NRC also reviewed project work to date, including definition of program boundaries and completion of system walkdown The NRC reviewed procedures for the DBVP to verify that technical attributes were properly addressed, and also performed a cursory overview of TVA's program for generation and updating of the design criteria, including the creation of a commitment / requirement data base, for the Sequoyah Nuclear plan The timing of the inspection was such that the walkdowns were nearing completion and substantial technical evaluation had not begun. A decision was made to perform an inspection at this time to evaluate the content and conduct of the walkdowns. The team could not extensively review technical products of the program except for walkdown packages and certain technical procedures / calculation . INSPECTION ACTIVITIES The following activities were generally performed by all team member (1) Review of TVA Calculation SQN-0SG7-048 " Identification of Systems Required for Restart."

(2) Review of TVA's EA Oversight Program Plan and related DBVP procedure (3) Interviews with key EA Oversight and DBVP project team personne (4) Review of selected walkdown packages, governing procedures and maintenance instruction (5) Preliminary scoping and review of select ECNs which are candidates for subsequent direct inspectio (6) Qualification of DNE project and EA personne TVA's program plan for the Design Baseline and Verification Program (attachment B reference 2) was evaluated. The objectives of the pro adequacy of changes made since operating license (0L)togram are to systems verify the required to mitigate design basis events and to provide for safe shutdown of the plan This program document breaks the overall program down into five major areas:

o Interim Change Control o Design Criteria / Design Basis o System Walkdown/ Test o Evaluation of ECN and Other System Changes o System' Evaluations and Corrective Actions The document further requires that procedures be issued on many of the program activities including Engineering Assurance Oversight Revie The team was also provided with a copy of the program plan for Engineering Assurance Oversight Review (attachment B reference 6). This plan establishes a team of experienced technical personnel to monitor, on a sample basis, every aspect of the pre-restart phase of the-design baseline and verification progra The independent review by Engineering Assurance is to:

1

_ ____ - _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _

..

o ...

.

o Confirm and validate that engineering activities are being conducted in accordance with the overall approved program plan, in accordance with the approved procedures established for the design baseline and verification program, and by personnel trained for the specific activity being confirmed / validate o . Confirm the technical adequacy of the system evaluations and the completeness / correctness of the supporting documentation, o Verify that the corrective actions resulting from the evaluation have been implemented and documente . SUMMARY OF FINDINGS

, Several weaknesses in implementation were pointed out to TVA. These were identified as observations during the inspection and presented to TVA ma_nagement during the exit meeting held on June 20, 1986. The following items were among those discussed at this meetin .1 Overall DBVP Plan and Scope In general, the team concluded that the overall program plan and plan for oversight review by EA appear to contain the elements and program areas necessary to adequately address DBVP objective The team was concerned that in some areas the DBVP scope might inadvertently exclude issues or items significant to safe restart. For example, the calculation defining program boundaries did not provide a rationale for excluding certain events (Observation No. 4.1). TVA advised the team that the calculation was being revised, based on a similar concern identified by the EA oversight group. The team also noted that some system boundaries are not specifically defined in the calculation, such as those for the reactor protection system (Observation No. 4.2).

The team found that, if properly implemented, the EA Oversight Review program plan should provide confirmation that Sequoyah design baseline documentation required for systems within program boundaries is current and verified for correctness. The program should also confinn that methods used to implement engineering work needed for plant restart are controlled and appropriat ,

Sampling of implemented engineering work by EA should confirm the adequacy of the methods used and products such as design drawings and calculation .2 Implementing Procedures for Both the Project and the Associated Independent Engineering Assurance (EA) Oversight During reviews of the walkdown packages, the team noted that some portions of walkdown limits were less inclusive than the DBVP boundaries (Observation N .2). Although this was allowed by the program, documentation regarding the basis for such decisions was only required at the time of system evaluatio The procedure for performing system evaluations had not yet been written, but was referenced in the walkdown procedure as the governing procedure for documenting differences between walkdown scope and program boundaries.

'

The NRC team observed that many procedures and criteria needed to complete the 1 DBVP were not yet issued and approved. TVA is developing procedures and

- _ - - - . - _ _ . _

__ .- .. _ _ _ _

,

,. v ...

-

I criteria as the program progresses. The team was concerned that this may result in accommodation of the procedures to the actual work performe Regarding the EA Oversight review, the team considered that more explicit criteria for sampling work products was required. The program plan only states the required sample size (5%) and does not give guidance regarding safety significance or other relevant attributes of effective sample selection (Observation No. 4.3).

4.3 Conduct and Results of the Walkdowns Inconsistencies between Units' I and 2 walkdowns were identified, stemming from latitude left to systems engineers on attributes to be included (Observations Nos. 1.1, 3.1, 6.3 and 7.1). The team also noted that the program lacked verification of portions of system drawings where portions of the system appeared on more than one drawing (Observation No. 1.3). The team also determined that the actual system walkdowns performed did not ascertain dimensional information. Therefore, the configuration information was of limited use in evaluation of civil / structural aspects. The licensee informed the team that dimensional data would be obtained as needed, follorring a determination by engineers reviewing.ECN packages, during the conduct of supplemental walkdown The team noted that the scope of the walkdowns does not include physical

'

verification of instrumentation and electrical aspects, such as conformance of system functionality to single-line elementary or schematic diagrams, cable separation, etc. (Observation No. 5.1). TVA stated that they intend to assess the adequacy of these aspects by review of test documentation (including surveillance tests) or other controlled documentation which is available. The rationale to support TVA's position needs to be documented. The team noted that the electrical test evaluation procedure did not specifically require modification of pre-operational testing acceptance criteria as needed to adequately assess modified systems or components (Observation No. 5.3).

4.4 Preparation of Design Criteria A cursory overview of the preparation of design criteria at the DNE offices in Knoxville, Tennessee was also conducted. The team noted that several TVA Civil Engineering Branch General Design Criteria specified reduced margins of safety (below those committed to in the FSAR) to be allowed for restart (Observation No. 3.1). The licensee was informed that these reduced margins of safety would need to be reviewed and approved by the NRC. The team also noted lack of a tracking system to assure equipment requalification following use of such interim acceptance criteria (Observation No. 3.2).

TVA contracted with IMPELL to generate a set of commitment / requirements to be used in the preparation of a data base. Outputs of this data base are to be used as design input in the development of system and general design criteria.

The team noted (Observation No. 5.4) that the IMPELL work had not been indepen-

! dently verified, and thus questioned the validity of the derivative design criteri .5 Summary

,

Based on the nature of the findings discussed above, the team concluded that

,

there do not appear to be any major flaws, provided TVA addresses the concerns

. ._ -

__ _ - - _ _ -

-

_ - _ _ -- - . . - - _ - - . _ _ _

_ _ _ _ _

,

. o , . .

~

identified in this report in subsequent programmatic or implementation l activities. Due to the limited amount of technical work accomplished as of the time of the inspection, a final determination of overall program adequacy must-be made following substantial program implementatio ,

'

,

- SPECIFIC COMMENTS Specific comments of individual NRC discipline inspectors are categorized as observations. The observations and a description of the activities performed by each discipline of the NRC team are provided in Attachment A of this repor Responses to individual. observations will be reviewed by the NRC during its inspections of program implementation or corrective actions. These observations elaborate on the general comments stated in the cover letter and in some cases provide additional comments not considered to be of a general natur . MEETING SUMMARIES - REFERENCES A summary of the meetings held relating to the DBVP inspection and a list of references is provided in Attachment B.

i

-

i

l

.

h

5

- - - - - _ _ _ . _ . _ _ . _ _ _ _ _ . _ - _ _ _ _ - _ _ . _ - . _ - _ _ _ _ _ _ - _ , - _ - - - -

.

,o ,. .

Attachment A - Inspection Activities and Observations

  • ' OPERATIONS The objective of this portion of the inspection was to overview the Design Baseline and Verification Program (DBVP) to ascertain if operational consideration was being given to the system walkdown findings and how operational concerns were being resolve The controlling documents for the DBVP were reviewed, including:

- SQEP-08, Packaging and Controlling of Walkdown/ Test Documentation

- SQEP-12, Procedure for Evaluating ECNs and FCNs

- SMI-0-317-30, Systems Walkdown The procedure which will evaluate the findings of the system walkdowns, SQEP-16, was not issued and therefore could not be' reviewed. With this procedure not issued, what is to be done with the walkdown findings and the extent of Opera-tions Department involvement in the evaluation process could not be determine Several completed walkdown packages (WDP) were reviewed to examine the scope of the findings and to check if items of operational impact were being discovere The packages reviewed were:

- 87 Upper Head Injection

- 26 High Pressure Fire Protection

- 65 Emergency Gas Treatment

- 43 Sampling

- 15 Steam Generator Blowdown

- 01 Main Steam

- 74 Residual Heat Removal (RHR)

- 03 Auxiliary Feedwater (AFW)

An independent walkdown of portions of the RHR and AFW systems was accomplished to get an understanding of the completeness of the project and EA walkdown Four observations were identified relating to the impact of the walkdown findings on operational procedures, differences between the walkdown boundaries and the calculation that defines the system boundaries in the scope of the DBVP, assessment of system interfaces on drawings, and the justification for not including optional attributes in walkdowns (Observations Nos. 1.1 - 1.4).

Observation No. 1.1 - Impact of Walkdown Findings on Operating Procedures No specific DBVP procedure exists that clearly identifies the extent of Opera-tions Department review of the system walkdown findings for impact on operating procedures, valve lineups, surveillance procedures, emergency operating procedures, etc. Three different cases were noted by the team:

Pressure transmitters PT-3-145 and PT-3-168 were found to be labeled reversed. A review of which functions each of these transmitters serve should be performed to ensure that no surveillance frequency or functional

,

requirement was missed due to the reversal of the labelin A-1

. _ _ _ _ - _ _ . .. . - - .. , . -. __

'

.

i

,.a .. .

l

,

'

Attachment A - Insp;ction Activities and Observations

'

"

l Penetrations X78 and X51 in the high pressure fire protection system do not show on the system drawin A review of local leak rate testing and in-service inspection requirements should be performed to assure that the penetrations which are not shown on the drawing are in the required testing j program !

In the upper head injection walkdown package it was reported that several valves were found to exist in the plant that did not show on~the system i diagram. A review of operating procedures, valve lineups, etc., should be made to ensure that all valves in the plant appear in the appropriate documents for this syste Observation No. 1.2 - Differences between Walkdown Boundaries and Calculation ,

SQN-0SG7-048, " Identification of Systems . Required for '

Restart"

. There is no justification documentation for the differences between the cal-culation that defines the scope of the.DBVP and the walkdown boundaries in the walkdown package Differences also exist between the boundaries as defined in 1 the walkdown packages for Unit 1 and Unit 2 for the same system (RHR for example).

L No justification is included in the walkdown packages for this differenc Procedure SQEP-08, Packaging and Controlling of Walkdown/ Test Documentation, paragraph 3.1.3, requires justification and documentation in accordance with SQEP-16 (not yet issued) for differences between the calculation and walkdown packag No specific instructions exist for documentation of justification of differences between the same system in Unit 1 and Unit 2. There is currently no documentation of differences in the walkdown packages. The licensee stated that the required documentation would be added to the walkdown packages following issuance of SQEP-1 Observation No. 1.3 - System Interfaces on Drawings No DBVP procedure.is in place with instructions regarding how the drawing

<

interface between systems is to be assured accurate. Many system flow diagrams include more than one system and/or unit. For example, the diagram

'

may be titled RHR System - Unit 1 and be used to walkdown the RHR system in Unit 1 but may also include some portions of the safety injection (SI) syste Depending on the system engineer who marked the boundaries of the walkdown on the RHR diagram, the portions of the SI system shown thereon may or may not have been included for walkdown. If the SI system portion shown on the RHR diagram were not walked.down using the RHR diagram then this depiction of the SI system could be in error, even though a walkdown of the same run of piping

!

during a SI walkdown with a different drawing may yield no configuration problems.

r The team noted that RHR system drawing 47W810-1 includes a portion of the SI system with flow control valve 63-1 and check valve 63-502. Walkdown package 74 (RHR) included these valves within the walkdown boundaries for Unit 1. The walkdown found that the configuration in the plant is different from that shown on the RHR drawing. The walkdown boundaries for Unit 2 excluded this portion i

' of the SI system, therefore whether the same disagreement of arrangement between the drawing and plant exists for unit 2 is unknown. No program was in place which would assure that this type of error is to be corrected.

!

L A-2

_

.

.

, . . . , . .

'

Attachment A - InspIction Activities and Obssrvations

  • '

Observation No. 1.4 - Diesel Fuel Oil Line Pipe Size The NRC team reviewed the walkdown package for the emergency diesel generator fuel oil system. The DBVP walkdown team had noted a discrepancy in the fuel oil transfer pump discharge line. The walkdown package drawing listed the line size as 1.5 inch pipe. The actual size was found to be 1.0 inch. This discre-pancy was noted even though determining pipe size was not a specified attribute in this package. The walkdown team considered it significant enough to note without being required to do so. In fact, pipe size for this particular section could be significant to the functional capability of the diesel generator during periods of extended full power runs. In this instance, the system engineer's decision to exclude pipe size as an attribute is questionabl Regarding this item, during review of Systems Walkdown Procedure SMI 0-317-30, the NRC noted that attributes assighed to the individual walkdown packages were allowed to be excluded without justification. The team noted that of the 14 attributes only 4 were required for all walkdowns, the others were omitted at the discretion of the systern engineer. The team recognizes that not all attri-butes are necessary for each specific walkdown, however attribute omission should be justified and documente . MECHANICAL SYSTEMS During the period of June 9-20, 1986, the team accomplished the following:

Conducted partial walkdown inspections of the residual heat removal and diesel fuel oil system Reviewed several TVA walkdown packages, including auxiliary feedwater, residual heat removal, diesel fuel oil and component cooling wate Reviewed several TVA Sequoyah Engineering Procedure Reviewed information from TVA Engineering ECN file Two observations were identified relating to the walkdown scope and the recording of nameplate and dimensional data (Observations Nos. 2.1 and 2.2).

Observation No. 2.1 - Walkdown Scope TVA's walkdown results for WDP-74, Residual Heat Removal System, Unit 1, identi-fied that valve 1-FCV-74-2 has a stem leakoff piping and valve that is not shown on the flow diagram used for the walkdown. A walkdown of part of the Unit 1 RHR

.

by the NRC inspection team found that valve 1-PCV-74-3 also has a stem leakoff valve and piping that was not shown on the flow diagram. This condition was not identified on the TVA walkdown action lis In another case, the TVA walkdown of Unit 2 identified that local gauges, actually located outside of the pump cubicle, were shown as inside the cubicle A-3

. _ . _ .- _ - _ _ _ - - _ _ _ _ - _ - - . _ . _ _ - . .. -

.

.,. ...

~

' Attachment A - Inspection Activities and Observations

'

on the walkdown drawin The NRC inspection team observed that Unit 1 has a similar configuratio However, the TVA walkdown of Unit 1 did not identify this discrepanc These two examples indicate inconsistency in the approach being taken by the various TVA walkdown team Observation No. 2.2 -_ Nameplate and Dimensional Data The team observed that a sampling program initially planned for nameplate data has been deleted. A sampling program was proposed in lieu of taking down all nameplate data during walkdown Instead of such a program, ECNs, TACFs and other change documents will be used to identify equipment which has been modified or replaced since operating license. This list will then be reduced to changes requiring resolution before restart. Supplemental walkdowns will be used to collect nameplate data and dimensional data required to support the engineering evaluation. This determination of whether a supplemental walkdown is necessary is to be made by the system engineer. Some guidelines should be issued to assure consistency in the scope of supplemental walkdowns in this area and that all data important to the DBVP is obtaine . MECHANICAL COMPONENTS

'

In the mechanical components discipline (which for TVA is a part of the Civil / Structural Engineering Branch), the team reviewed the following elements of the DBVP for the Sequoyah Nuclear Plant:

The documentation and procedures governing the DBVP (References 1-3).

The procedures governing the preparation and control of system walkdown packages (References 4-5).

The procedures governing the TVA Engineering Assurance program in the civil / structural area (References 6-7).

System walkdown packages 15 (also reviewed by EA); 43 and 26 (partially reviewed by EA); and 18, 72 and 87 (not reviewed by EA).

Twenty-six ECNs (partially reviewed by EA).

Interim revisions to Civil Engineering Branch general design criteria (References 8-11).

Three observations were identified relating to the documentation of containment penetrations on walkdown packages, the use of interim acceptance criteria, and control of dual qualification criteria application (Observations Nos. 3.1, and 3.3).

Observation N .1 - Documentation of Containment Penetrations The Sequoyah Nuclear Plant Unit 2 walkdown packages for systems 26 (fire pro-tection), 43 (post-accident sampling) and 87 (upper head injection) did not document containment penetrations consistently:

A-4

.

. . .

4 .

, .

"

  • Att:chment A - Insp;ction Activities and Observaticns

.

.

(1) Flow diagrams were not consistently marked up to add missing penetration identification number (2) Location sketches were not co'nsistently prepared for penetrations which lacked identification tag (3) Walkdown packages did not consistently reference the containment penetration schedule, which tabulates penetration identification numbers, elevations and azimuth (4) Some sketches specified penetration locations which were incomplete or did not agree with the locations specified on the penetration schedul ,

(5) Work requests were not consistently ~ issued to provide identification tags for penetrati.ons which lacked the Observation N .2 - Margins of Safety for Restart i

The TVA Civil Engineering Branch has issued interim revisions to several general design criteria to be used for the restart of Sequoyah Nuclear Plant which specify reduced margins of safety. These interim revisions specify that hardware qualified to these interim criteria are to be requalified to the original general design criteria during the interim acceptance period. Some examples of interim revisions to general design criteria are:

(1) DIM-SQN-DC-V-13.3-3, an interim revision to Design Criteria SQN-DC-V-13.3, Detailed Analysis of Category I Piping System (2) DIM-SQN-DC-V-1.3.4-3, an interim revision to Design Criteria SQN-DC-V-1.3.4, Category I Cable Tray Support System (3) PM86-03 (CEB), an interim revision to Design Criteria SQN-DC-V-24.1, Location and Design of Piping Supports and Supplemental Steel in Category I Structures (in draft form on June 18).

(4) QIR CEB-86-001, an interim revision to Civil Design Standard 05-C1.7.1, General Anchorage to Concret The team noted that TVA must obtain NRC review and approval of any interim

,

criteria which constitute a reduction in licensing commitment Observation No. 3.3 - Control of Dual Qualification Criteria The TVA Civil Engineering Branch does not have a procedure to ensure that hard-ware qualified to interim design criteria which specify reduced margins of safety will be requalified to the original requirements of the general design criteri . NUCLEAR SYSTEMS In the nuclear systems discipline, the following specific activities were examined by the NRC, in addition to the general inspection team activities.

i A-5

- - _

. .- . - - -.- . --_ . ----_-.-- . .. -

-

.

.

...... ,

'

Attcchment A - Insp:ction Activitics and Observations  !

.

!

.

Review of the residual heat removal (RHR) system walkdown packages, and ,

a partial walkdown of the RHR System by the NRC inspection tea '

Review of ongoing Engineering Assurance (EA) oversight and DBVP project activity for Nuclear Steam Supply Systems, including the reactor pro-tection syste While technical details were examined in the review, the inspection was programmatic in nature. The three resulting observations all focus on obtain-ing assurance that the TVA DBVP program process will not inadvertently exclude issues or items significant to the safe restart of the Sequoyah Nuclear Plant (Observation Nos. 4.1, 4.2, and 4.3).

.

Observation No. 4.1 - Rationale for Selection of Design Basis Events TVA Calculation SQN-0SG7-048, " Identification of Systems Required for Restart" establishes

"

the systems required for safe restart. The calculation states that,

...certain selected events described in Chapter 15 of the FSAR" form the basis for identifying systems required for restart and that, " events were selected based on the event severity to the plant." ,

The calculation does not provide a rationale for excluding certain events, does not identify which events have been excluded and does not provide criteria for determining event severity. In addition, based on interviews with fVA's EA and .

project staff, the calculation does not appear to include indication of variables important to operator actions that are necessary to the detection of and recovery from the postulated event The NRC inspection team understands that a revision of this calculGtion is in progress that is intended to clarify the rationale for selecting design basis events in establishing the scope of systems required for restart. The above items should be addressed in the revised calculatio Observation No. 4.2 - Definition of Reactor Protection System and Neutron Monitoring System Scop TVA Calculation SQN-0SG7-048 establishes the boundaries for systems required for restart. As required by Attachment A to the TVA DBVP program description, marked drawings provided with this calculation are to be used for delineating exact portions of the systems require Based on interviews with EA and project personnel, it appears that no such explicit definition of system boundaries exists or is planned for the reactor protection system and neutron monitoring system. Because of the variety of pro-cess, electrical, and supporting system interfaces that exist relative to the reactor protection system, the team believes it is important to define system boundaries as explicitly as was done for other systems defined by the calculation, so that no items are inadvertently omitted from the review scope. To a lesser degree, this explicit definition is also important for the neutron monitoring syste A-6

_ _ , - _ _ _ . _ _ _ . . _ _ . _ _ . _ _ _ . _ _ _ . _ . . - . ~ . _ .

,. ...

Attachnient A - Insp;ction Activities and Obs;rvations

"

Observation No. 4.3 - Criteria for Sampling Project Work Prod 0 cts for EA Oversigh The TVA Program Plan for the EA Independent Oversight Review provides guidance for determining sample size for reviewing each aspect of the engineering process, but does not provide guidance in determining which products should be sampled so as to effectively measure assurance of safe restar For example, no guidance is provided for considering:

(1) systems that dominate in assuring safety, (2) complexity of the work product reviewed, or (3) the history of industry or plant specific problems in implementing certain modification Interviews with TVA's EA staff indicate that the sample size guidance (5%) is generally being followed, but that different disciplines appear to use different rationale in selecting work products for oversight revie The NRC inspection team believes generic criteria should be established for selecting work products for EA oversight, in addition to the sample size guide-lines already provided by the TVA Program Pla . ELECTRICAL POWER In the electrical power discipline, the NRC team reviewed the following:

Design verification procedures SQEP 8,11,12,14, and 18, checking for technical attribute Engineering Assurance procedures and checklist Completed EA review plans for review procedure ll, " Evaluation of Change Documents," assessing ECNs 2768, 2777 and L587 Walkdown Package 67, Rev. 1, for the essential raw cooling water syste The process for generation of design criteri Four observations were identified relating to the walkdown scope, the technical attributes required for evaluation of ECNs, the use of appropriate test acceptance criteria, and the design verification of the commitments and requirements data base (Observations Hos. 5.1 - 5.4).

Observation No. 5.1 - Walkdown Scope The NRC team noted that initial walkdown process does not address verification of the electrical aspects of the plant installation, such as correctness of wiring, condition of electrical items such as cables, trays, junction boxes, terminal blocks, fuses, etc., and application of separation criteria. For instruments, the walkdown scope ends at the root valves and does not address verification of the correct tap connection The team was informed that testing A-7

_

.

l

l

[ ,. , . .

Att chment A - Inspection Activities and Observations i *

of the systems verifies some of the electrical attribute For verification of the remaining attributes, several other programs are in plac The team believes that cross reference to such programs should be provided in the DBVP documentatio , TVA rationale should be provided as to the acceptability of this approac Observation No. 5.2 - Technical Attributes of Design Verification Procedures  !

The team noticed that a draft revision (Rev. 1) to procedure SQEP 12 proposed deletion of requirements for evaluation of effects of the component failure and I requirements to consider the thermal loading of the power cables. Following I discussions with the NRC team, TVA agreed not to drop these attributes from the scope of review of the procedur Observation No. 5.3 - Test Acceptance Criteria During review of the procedure SQEP 14, " Electrical Test Evaluation," the team noted that the procedure directs the reviewer to use test acceptance criteria of the old pre-operational tests for eealuating the results of the tests on the

'

modified system. The team believes that use of old test acceptance criteria for the modified system may not be correci:. The modification to the system may change its static and dynamic characteristics, such as uncertainties, drift, response time, and therefore the test results acceptance criteria for modified system tests should reflect these change Tne team does consider examination and evaluation of preoperational test data to be a useful tool for evaluation j of the adequacy of subsequent modification Observation No. 5.4 - Design Criteria During initial NRC review of the process for generation of the commitment /

requirement data base, the team noticed that the existing program did not have provisions for independently verifying or assuring the accuracy of the design /

licensing commitments input to the system. The NRC will evaluate TVA's control

, and use of this data base information during future DBVP inspection . INSTRUMENTATION AND CONTROL

,

a The team discussed the planned scope and depth of review by the TVA EA oversight instrumentation and control discipline, and it was determined that the auxiliary l feedwater, sampling, component cooling water, and a fourth as yet undesignated l system out of the 31 safety-related systems would be included. The team reviewed

'

the EA oversight review *and resultant action items for the turbine driven auxil-iary feedwater system (46) walkdown package. In addition, walkdown packages for

'

the demineralized water system (59), steam generator blowdown system (15), ice condenser system (61), and motor driven auxiliary feedwater system (3B) were reviewed for their instrumentation and control aspects. Preoperational test

records for the auxiliary feedwater system and recent engineering change notices l affecting this system were also reviewed. The team reviewed several technical
concerns, discussed below, regarding the safety system boundary calculation l SQN-0SG7-048 and neutron monitoring excore detector qualification requirements

'

with TVA and Westinghouse personnel.

l

.

A-8

. - - _ - - . - - - - - - - _-_--_ - ___.__ - -_ - _ - -

'

." \A'ttrchmentA-Insp;cticnActiviticsandObservations

. The Oversight Review Program generally appears to be comprehensive in terms of its scope and depth of review. A discipline specific review plan (#3100, +

revision 2 ) was reviewed by the team. Using written checklists, this plan commits to a review of the following item ;

(1) Walkdown results for four system (2) Ten representative commitment / requirements from the Sequoyah C/R data bas (3) Three design criteria and several discipline specific sections of the '

design basis documen (4) Approximately.15 engineering change notice '

(5) Approximately 7 field change notice !

'

(6) A sample of control room drawings from the four selected system '

(7) An unspecified number of test evaluation result ,

(8) An unspecified number of system evaluation l The team identified four concerns regarding manually initiated safety related actions (Observation 6.1), neutron monitoring detector qualification basis (Observation 6.2), consistency in turbine driven auxiliary feedwater system walkdown reviews (Observation 6.3), and conduit box covers (Observation 6.4).

Observation No. 6.1 - Manually Initiated Safety-Related Actions TVA calculation SQN-0SG7-048 provides the basis for a technical adequacy review of design changes made since the Sequoyah operating license was issued. This calculation does not specify the safety related operator actions and associated Class 1E display instrumentation needed by the operator during and after a design basis event which are in fulfillment of Regulatory Guide 1.97 provision In 1982, TVA prepared a licensing basis for compliance with Regulatory Guide 1.97, and identified 18 operator action Type A variables in Appendix A to TVA design criteria SQN-DC-V-19.0. TVA is currently reassessing the commitments

,

made in this document in anticipation of a planned 1987 hardware implementatio However, the team could not confirm whether a definitive plan exists to assure that the operator actiori instrumentation would be reviewed for technical adequacy in a similar manner to the design modifications whose review is deemed necessary for plant restar Observation No. 6.2 - Neutron Monitoring Detector Qualification Basis TVA calculation SQN-0SG7-048 stated that the neutron monitoring detectors were i

not qualified for a loss of coolant accident environment, but also indicated

!

that the detectors were required to initiate reactor trip for a rod ejection accident. Because these detectors provide input signals to the reactor trip system, the team explored the issue of detector qualification that would assure their operability following end-of-life exposure to operating temperature and A-9

. . - - - _ - - _ - . - . - . -- --- --- . - . - - - ---

i .

+

,.o ;. .

~

' Attachment A - Insp;ction ctivities and Obs:rvations

.

radiation levels inside containment as required by IEEE Std. 279-1971 and dis-cussed in NUREG-0800 Branch Technical Position ICSB 2 The team determined that TVA had assigned these detectors to qualification category "C" in TVA calculation SQN-OSG7-0014, based on information provided in Westinghouse letter WAT-D-5709 dated September 22, 1983. Equipment assigned to category "C" is not required to function to mitigate harsh environment accidents, and whose failure (in any mode) is deemed not detrimental to plant safet However, Westinghouse recently provided TVA with documentation to indicate that use of the qualification category "C" designation was incorrect because of a previously unanalyzed control and protection system interactic In the postulated event scenario developed by Westinghouse, a small steam line rupture inside containment could cause an adverse failure of the neutron moni-toring detectors. This failure could initiate automatic control rod withdrawal because of a control and protection system interaction present in the Westing-house design. In this situa. tion, reactor trip would occur from overpower delta temperature measurements approximate 1.y 20 to 40 seconds after event initiatio Based on this information, TVA initiated Significant Condition Report SQN-NEB-8609 for corrective action to the Sequoyah environmental qualification progra As a minimum, the team believes that TVA should have selected qualification category "B" for these detectors to eliminate the possibility of an adverse control and protection systen interaction. This category would have required that the detectors not fail in a manner detrimental to plant safety through a demonstration of their capability to withstand the accident environment with safety margin to failur Observation No. 6.3 - Consistency in AFW Turbine Centrols Walkdown Scope An identical scope of review was required for the walkdown of auxiliary feedsater system turbine instrumentation and control for Sequoyah Units 1 and 2. However, approximately six components, including handswitches, transfer switches, turbine overspeed switches, and flow control valves, were inspected on one unit but not on the other unit. TVA stated in response to Action Item I-3 that when instru-mentation and control components lacked panel designations on the drawings, they were excluded from the walkdown; however, the actual walkdown practice has not been consistent in this area. Similar inconsistencies were noted in the instrumentation walkdowns of the Unit 2 essential raw cooling water and turbine driven auxiliary feedwater systems. No resolution of the inconsistencies in walkdown inspection practices was eviden Sequoyah procedure SQEP-17, revision 0, used for the DBVP origination and categorization of configuration control drawings, states that test data may be used instead of field walkdown data to verify control diagrams, logic diagrams, and single-line drawing configurations. Procedure SQEP-14 identifies functional tests, post-modification tests, pre-operational tests, and surveillance instruction periodic tests as sources of such dat Because of inconsistencies noted by the team in the amount and type of data collected during instrwrentation and control walkdowns, the use of test data tn verify accuracy and correctness of control and instrumentation diagrarts will be examined during future inspections. This will include examination of DBVP supplemental walkdown A-10

..

.. _ _ _ _ _ _ _ _ _ - _ _ - _ _ .

-

.

,

-

.a ;. -

Attachment A - Insp:ction Activitics and Obssrvations

'

.

-

. ,

Observation No. 6.4 - Conduit Box Covers and Installed Cable Pull Rope -

During a brief walkdown conducted by the team of the Unit I residual heat removal system, a cable pull rope was found hanging from an open conduit box above rack 1- L-55 A. TVA determined that no modifications were currently in process for this rack, and stated that the pull rope would be inserted into the box prior to rein- ,

stallation of the cover plat However, the team believes that current TVA in-stallation and maintenance instructions would not permit flammable materials, such 1 as the cable pull rope, to be present with electrical cables inside a safety-related conduit. In addition, two ECNs have been written about missing junction box cover plates or installed cover plates that do not conform to the design drawing The team was concerned with this item because deviations regarding these cover plates can impact equipment qualificatio . CIVIL / STRUCTURAL In the Civil / Structural area, the NRC team reviewad various documents that were developed by the project and the EA team. This review was primarily a documen-tation review, because the project and the EA team had performed limited techni-cal evaluations in the Civil / Structural are The team reviewed the pertinent sections of Sequoyah engineering procedures 8, 11, 12 and special maintenance instruction SMI-0-317-30 for walkdowns.

1 The team also reviewed Civil / Structural review plan 5100 R1. The attributes for various items, including the review of walkdown packages, ECNs, FCNs, -

FCRs, TACFs, SCRs and NCRs were reviewe i The team reviewed walkdown packages 01, 30A, 308, 30C, 31A, 62 74, and 7 i Since the walkdown packages did not contain any dimensiondi information, t structural items could not be located or assessed. Nevertheless, a che:k of -

penetration location markups by the team revealed that one arawing did not depict a containment penetration (Observation 7.1).

'

The NRC team reviewed the 26 ECNs which had been evaluated by the EA teami No technical aspects were assessed in the EA rev h w. The EA teert had issued 6

,

'

action items to date in the Civil / Structural discipline. The NRC team reviewed  ;

these action items. All of these items were related to documentation reviews, '

since the technical evaluations had not starte '

l The NRC team also reviewed the design and seismic qualification of HVAC ducts  ;

and duct supports. This, issue w3s raised by the Watts Bar project and also ic generic to the Sequoyah Plant. The NRC team met with TVA Civil Engineering Branch to determine the steps taken for the resolution of this issue f (Significant Condition Report SQNCEB6602). During this interview and a sample *

walkdown of the problem areas, the NRC team confirrced that this issue will De resolved before restart. It appears that TVA's seismic evaluation of the HVAC duct systems will lead to hardware modifications of various duc,t supports,

'

Observation No. 7.1 - Inconsistency in Walkdowns  ;

.

r During the review of walkdown package 77 (Waste Olsposcl. Unit 2), the hCC team noted that a boundary line is shown for inside contair. ment on drawing 47W809-7 R At this boundary the drawing does not show a penetr3 tion. Further review *

showed that this penetration was identified on another drawing within the same ,

walkdown package. Drawing 47W909-7 should be revised to show the penetration, '

so that both drawings will be consistent regarding the location of the pene- ,

tration in questio A-11

,

- -- ..,,n ----..n ,._m

- ~ , , , . ~ , . ye .--,,.-,-,--.--.,,m - - . - - _ . ..,~-,.-,.,-*_--,,a,-,p

--

, , , , - - - - - - , ,.

-

- - _ _ _- _ - - _

,

-

.. ; . .

Attachment B - Me2 tings and R3forcnces

' '

B.1 Meetings Inspection activities were conducted at the ONE offices in Knoxville and at the Sequoyah sit Several meetings were held between TVA and NRC to plan and schedule inspection activities. Entrance and exit meetings were held to discuss the inspection plans and findings, respectively. The following describes the general purpose of the various meetings. Table A.1 is provided as a matrix of meeting attendanc Meeting 1: The purpose of this meeting, held on April 23, 1986, was to obtain background for future NRC overview of TVA design control activities and to understand the actions proposed and taken by TVA to address design control problem Meeting 2: The purpose of this meeting, held on May 13, 1986, was to assess conduct of TVA system walkdowns, obtain background for future NRC inspection of TVA design control activities, and assess the early implementation of the Design Baseline and Verification Program and associated Engineering Assurance independ-ent oversigh Meeting 3: The entrance meeting for the EA independent oversight team was attended by the NRC on May 14, 198 Meeting 4: On June 6, 1986, an entrance meeting was held at the Sequoyah site. The NRC explained the plans for the assessment of TVA's program for Design Baseline and Verification and the Engineering Assurance oversight.

I Engineering Assurance personnel presented the methodology, scope and status of l their revie Meeting 5: On June 20, 1986 an exit meeting was held at the Sequoyah sit NRC management discussed the scope and findings of the inspection. The team members presented the more significant findings within each disciplin B-1

_ _ _ _ _ _ _ _ _________-_--____------___-.__--.-----a

.

  • '. -

,,. a

-

Attachment B - Me: tings and Referenc;s

TABLE B.1 MEETINGS (cont.) -

Name Organization Title Meeting Attended 1 2 3 4 5 MASkarzinski TVA Elec. Maintenance Sup x RHBuchitioz TVA Site Re x DLWidner TVA Modification Eng x RJFaubert TVA Reviewer x x x TGCarson TVA Reviewer x x x RH0'Donnell TVA Staff Engineer x-BMPatterson TVA Maintenance Eng x DGRenfro TVA Principal Eng x x x JThompson TVA QA Engineer x AHRitter TVA EA Engineer x x x H0Elkins TVA Instru. Mtn. Sup ~

x HGBird TVA EA Engineer x CEGrass TVA EA Engineer x x BGore TVA EA Reviewer Lead x x x TESpink TVA EA Engineer x x x WSWilburn TVA Maintenance x x TMGalbargh TVA Site Re x RPSvarney TVA EA Reviewer x x x MTTormey TVA Restart Task Force x x x MRMathews TVA Restart Task Force x SShuman TVA EA Reviewer x x RTucker TVA EA Reviewer x x JWSemore TVA EA Reviewer x x JWKelly TVA EA Reviewer x x x JWeisenstein . TVA EA Engineer x x ABSavery TVA EA Engineer x x KFLiao TVA EA Engineer x CK8uck TVA EA Engineer x TLHoward TVA QA Engineer x CYWang TVA DNE Project x EJJiskin TVA Task Group x

.

B-3

'

.

-

ga ;.

'

-

'Attichment B - Meetings and R3fer;nc';s l

'

'

TABLE B.1 MEETINGS Name Organization Title Meeting Attended 1 2 3 4 5 JMTaylor USNRC-IE Director, OIE x BKGrimes USNRC-IE Director,DQAVT/0IE x x EVImbro USNRC-IE Section Chief, QAB/01E x x x x RHeishman USNRC-IE Branch Chief, VP x REArchitzel USNRC-IE Team Leader x x x x x SVAthavale USNRC-IE NRC-Electric Power x x BTDebs USNRC-RII Section Chief x x x RPHolmes USNRC-RII Sr. R. Inspector-Hatch x x KMJenison USNRC-RII Sr. Resident Ins x x x LJWatson USNRC-RII Resident Insp., SQN x x PEHarmon URNRC-RII Resident Insp.,SQN x x DPLoveless USNRC-RII Resident Insp. SQN x ADuBouchet NRC-Consultant NRC-Mech. Components x x FJMollerus NRC-Consultant NRC-Mech. Systems x x AIUnsal NRC-Consultant NRC-Civil / Structural x x JMLeivo NRC-Consultant NRC-Instr./ Controls x x LStanley NRC-Consultant NRC-Instr./ Controls x x WCDrotleff TVA Dir. Nuc. Engineering x x HLAbercrombie TVA Site Director x x RPWallace TVA Plant Manager x RCParker TVA Site Quality Manager x JEHuston TVA DY. Dir. Nuc. QA x JFWeinhold TVA EA Manager x x x x HLJones TVA Program Manager-DBVP x x x MRHarding TVA Site Licensing Manager x x x WEAndrews TVA Site Quality Manager x x x x SLong TVA Walkdown Manager x x x x HLJones TVA DNE Program Manager x LMNobles TVA Supdt. (0&E) x x x CNJohnson TVA Civil Project Manager x JBlankenship TVA Manager Info. Services x RGDomer TVA Manager Pro. Eng x GTHall TVA Elec. Project Eng x DWWilson TVA Project Engineer x x x x APCapozzi TVA/S&W Asst. Chief Engineer x x x x MPBerardi TVA EA Oversight Team Lead x x x x GBKirk TVA- Compliance Supervisor x x x JEStaub TVA I&C Supervisor x RMMooney TVA System Engr. Sup x FEDenny TVA QA Engineer x x RCBirchell TVA Mechanical Engineer x x x x AWLatti TVA DNE Management x x B-2

-

.... f .

Attachment B - Meetings and References

-

.

B.2 REFERENCES: TVA Design Basis Program for TVA Nuclear Plants, dated March 28, 198 . TVA Baseline and Verification Program for Sequoyah Nuclear Plant, Rev. O, dated May 1, 198 . TVA OE Calculation SQN-OSG7-048, Identification of Systems Required for Sequoyah Restart, Rev. O, dated April 29, 198 . TVA Sequoyah Engineering Procedure SQEP-08, Packaging and Controlling of Walkdown/ Test Documentation, Rev. 2, dated May 29, 198 . TVA Special Maintenance Instruction SMI-0-317-30, Systems Walkdown, Units 0, 1 and 2, Rev. O, dated April 29, 198 . TVA Program Plan for the Engineering Assurance Independent Oversight Review for the Sequoyah Nuclear Plant Design Baseline and Verification Program, Rev. O, dated May 9, 198 . TVA Engineering Assurance Oversight Civil / Structural Review Plan N , Rev. 1, dated June 9, 198 . DIM-SQN-DC-V-13.3-3, dated June 10, 198 . DIM-SQN-DC-V-1.3.4-3, dated June 13, 198 . PM86-03 (CE3), dated June 9, 198 . QIR CEB-86-001, dated April 29, 198 .

B-4