IR 05000032/2025010

From kanterella
Jump to navigation Jump to search
Fire Protection Team Inspection (FPTI) Report 0500032/2025010 and 05000366/2025010
ML25349A704
Person / Time
Site: Hatch, 05000032 Southern Nuclear icon.png
Issue date: 12/28/2025
From: Daniel Bacon
NRC/RGN-II/DORS/EB2
To: Coleman J
Southern Nuclear Operating Co
References
IR 2025010
Download: ML25349A704 (0)


Text

SUBJECT:

EDWIN I. HATCH NUCLEAR PLANT - FIRE PROTECTION TEAM INSPECTION (FPTI) REPORT 05000321/2025010 AND 05000366/2025010

Dear Jamie Coleman:

On December 9, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at EDWIN I. HATCH NUCLEAR PLANT UNITS 1 & 2. On October 9, 2025, the NRC inspectors discussed the results of this inspection with the Engineering Director, Fleet and Site fire protection personnel, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

Due to the temporary cessation of government operations, which commenced on October 01, 2025, the NRC began operating under its Office of Management and Budget-approved plan for operations during a lapse in appropriations. Consistent with that plan, the NRC operated at reduced staffing levels throughout the duration of the shutdown. However, the NRC continued to perform critical health and safety functions and make progress on other high-priority activities associated with the ADVANCE Act and Executive Order 14300. On November 13, 2025, following the passage of a continuing resolution, the NRC resumed normal operations.

However, due to the 43-day lapse in normal operations, the Office of Nuclear Reactor Regulation granted the Regional Offices an extension on the issuance of the calendar year 2025 inspection reports that should have been issued by November 13, 2025, to December 31, 2025. The NRC resumed the routine cycle of issuing inspection reports on November 13, 2025.

December 28, 2025 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Daniel M. Bacon, Chief Engineering Branch 2 Division of Operating Reactor Safety Docket Nos. 05000321 and 05000366 License Nos. DPR-57 and NPF-5

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000321 and 05000366

License Numbers:

DPR-57 and NPF-5

Report Numbers:

05000321/2025010 and 05000366/2025010

Enterprise Identifier:

I-2025-010-0047

Licensee:

Southern Nuclear Operating Co., Inc

Facility:

EDWIN I. HATCH NUCLEAR PLANT UNITS 1 & 2

Location:

Baxley, GA

Inspection Dates:

September 08, 2025 to December 09, 2025

Inspectors:

P. Braaten, Senior Reactor Inspector

W. Monk, Senior Reactor Inspector (Lead)

B. Stuckart, Reactor Inspector

I. Wang, Observing Inspector

Approved By:

Daniel M. Bacon, Chief

Engineering Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a fire protection team inspection at EDWIN I. HATCH NUCLEAR PLANT UNITS 1 & 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.05 - Fire Protection Team Inspection (FPTI) Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)

The inspectors verified that components and/or systems will function as required to support the credited functions stated for each sample. Additional inspection considerations are located in the fire hazards analysis (FHA) or safe shutdown analysis (SSA).

a. Review deficiencies or open fire protection impairments for the selected system, including any temporary modifications, operator workarounds, or compensatory measures.

b. Verify that operator actions can be accomplished as assumed in the licensees FHA, or as assumed in the licensees fire probabilistic risk assessment (FPRA)analysis and SSA.

c. Review repetitive or similar maintenance work requests which could be an indicator of a design deficiency and could affect the ability of the components to perform their functions, when needed.

d. Ensure that post maintenance and/or surveillance activities are performed as scheduled.

e. Perform a walkdown inspection to identify equipment alignment discrepancies.

Inspect for deficient conditions such as corrosion, missing fasteners, cracks, and degraded insulation.

f. Ensure the selected SSCs that are subject to aging management review (AMR)pursuant to 10 CFR Part 54 are being managed for aging (e.g., loss of material, cracking, reduction of heat transfer) in accordance with appropriate aging management programs. Verify that the licensees aging management program activities (such as, Fuel Oil Analysis or Selective Leaching Aging Management Program) associated with FP equipment are being implemented.

g. If a review of operating experience issues will be completed for the selected inspection sample, verify that the licensee adequately reviewed and dispositioned the operating experience in accordance with their processes.

(1) SSC #1 (Fire Prevention) - Transient Combustible Controls Program
(2) SSC #2 (Detection/Suppression) - U1/U2 Low Pressure CO2 Systems
(3) SSC #3 (SSD) - U1/U2 EDG System and 4160V Emergency Distribution
(4) SSC #4 (SSD) - U1/U2 Low Pressure Coolant Injection (LPCI) Systems

Fire Protection Program Administrative Controls (IP Section 03.02) (2 Samples)

The inspectors verified that the selected control or process is implemented in accordance with the licensees current licensing basis. If applicable, ensure that the licensees FPP contains adequate procedures to implement the selected administrative control. Verify that the selected administrative control meets the requirements of all committed industry standards.

(1) FP Admin Program #1 - Hot Work Program
(2) FP Admin Program #2 - Fire Brigade Drills and Training Program

Fire Protection Program Changes/Modifications (IP Section 03.03) (2 Samples)

The inspectors verified the following:

a. Changes to the approved FPP do not constitute an adverse effect on the ability to safely shutdown.

b. The adequacy of the design modification, if applicable.

c. Assumptions and performance capability stated in the SSA have not been degraded through changes or modifications.

d. The FPP documents, such as the Updated Final Safety Analysis Report, fire protection report, FHA, and SSA were updated consistent with the FPP or design change.

e. Post-fire SSD operating procedures, such as abnormal operating procedures, affected by the modification were updated.

(1) FPP Change #1: LDCR23-37 - Update to Hatch TRM Appendix B to Align Compensatory Actions to RER SNC1524271 and RER SNC1524271 - Basis for Risk Informed Compensatory Actions for Fire System Impairments in NFPA 805 Licensed Plants
(2) FPP Change #2: RER SNC1244102 - Performance Based Evaluation of Fire Damper Configurations

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On December 9, 2025, the inspectors presented the Fire Protection Team Inspection Exit Meeting inspection results to Jeremy Torrez, Engineering Director and other members of the licensee staff.

THIRD PARTY REVIEWS No review of third-party documentation during the inspection period.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

H-RIE-FIREPRA-

U00-012

Hatch Fire PRA Task 12, Human Reliability Analysis

(HRA)

Rev. 6.0

SMNH-05-011

Determine Diesel Generator Building Switchgear Room

heatup due to a loss of cooling transient

Rev. 1.0

SMNH-05-014

Post LOCA Time Elapsed RHR and CN NPSH Margin

Long Term Operation (>600 Sec)

Rev. 2.0

SMNH-05-015

Post LOCA Time Elapsed RHR and CN NPSH Margin

Long Term Operation (>600 Sec)

Rev. 2.0

SMNH-13-005

Hatch Switchgear Room on Control Building Elevation 130

Heatup Evaluation during an Extended Loss of all AC

Power (ELAP)

Rev. 2

SMNH-16-025

NFPA 12 Code Compliance Review

Rev 2.0

2/10/2024

SMNH-16-080

DGB CO2 Suppression System Calculation

Rev. 2

SMNH-16-084

Documents the evaluation of MOV Pressure Boundary

(PB) components to determine the impact of the

Information Notice 92-18 type "hot short" (motor stall)

event.

Rev. 3.0

SMNH-16-085

Documents the evaluation of MOV Operator Manual

Actions (OMA) components to determine impact of the

Information Notice 92-18 "hot short" motor stall event.

Rev. 2.0

SX11992

FP-LP CO2-FLOW CALCULATIONS-CABLE

SPREADING ROOM

2/01/1973

Calculations

SX11992

FP-LP CO2 Flow Calculation - Cable Spread Room

Rev. 1

Corrective Action

Documents

CR 11142973

Individual Fire Brigade Member Drill Failures

01/16/2025

CR 11208487

25 FPTI - Fire Protection Program References in NMP-

ES-063-GL01 Need Updating

09/03/2025

CR 11210429

25 FPTI - One Fire Drill in 2024 Did Not Meet Program

Requirements

09/10/2025

71111.21N.05

Corrective Action

Documents

Resulting from

Inspection

CR 11210511

25 FPTI - Diesel Generator Recovery Procedure

Correction

09/10/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR 11210943

25 FPTI - CO2 Nozzle Inspection NPFA 12

09/11/2025

CR 11210952

25 FPTI - 52SV-FPX-010-0 Procedural Enhancement

09/11/2025

CR 11233548

25 FPTI - Use of Grace Periods for Fire Protection

Surveillances

2/08/2025

B-11988

E.I. HATCH PLANT UNIT NO.1 FIRE PROTECTION FCD

COMPUTER RM (1/2), (2/2)

Rev. 0

H-41508

U1 Turbine & Control Building - Fire Protection Piping -

CO2 System P&ID

Rev. 9

H-41509

U1 & U2 Diesel Generator BLD CO2 System P&ID

Rev. 7

SX11786

Computer Room CO2 Schematic

10/05/1973

Drawings

SX11937

FP-LP CO2-HOSE REEL INFO

Rev. 0

LDCR23-37

Update to Hatch TRM Appendix B, to align Compensatory

Action to RER SNC 1524271

Rev. 1.0

SNC1244102

Performance Based Evaluation of Fire Damper

Configurations

Rev. 1.0

Engineering

Changes

SNC1524271

Basis for Risk Informed Compensatory Actions for Fire

System Impairments in NFPA 805 Licensed Plants

replacing RER SNC1133273

Rev. 2.0

NMP-ES-035-

019-GL02-F03

CONTROL BUILDING EL 147 Pre Fire Plan

Rev. 1

NMP-ES-035-

019-GL02-F06

DIESEL GENERATOR BLDG Pre Fire Plan

Rev. 1

NMP-ES-035-

019-GL02-F12

U1 REACTOR BUILDING EL 130 Pre Fire Plan

Rev. 1

Fire Plans

NMP-ES-035-

019-GL02-F29

U2 REACTOR BUILDING EL 130 Pre Fire Plan

Rev. 1

Miscellaneous

NMP-OS-014-

2-TCAF201

Operator Response Time Validation Sheet

06/30/2023

31RS-OPS-001-1

Shutdown from Outside Control Room

Rev. 6.6

31RS-OPS-002-2

Shutdown from Outside Control Room

Rev. 7.5

34AB-X43-001-1

Fire Procedure

Rev. 18.9

34AB-X43-001-2

Fire Procedure

Rev. 23.9

34SO-E11-010-1

Residual Heat Removal System

Rev. 46.9

Procedures

2SV-SUV-007-0

CO2 FIRE SUPPRESSION EQUIPMENT INSPECTION

Rev 1.7

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2SV-FPX-010-0

LOW PRESSURE CO2 SYSTEM SURVEILLANCE

08/21/2025

NMP-ES-035

Fire Protection Program

Rev. 7

NMP-ES-035-014

Fleet Transient Combustible Controls

Rev. 8

NMP-ES-063-

GL01

Hatch License Renewal Program Manual

Rev. 3

NMP-FLS-017

Compressed Gas Safety

Rev. 2

NMP-OS-007-

001

Conduct of Operations Standards and Expectations

Rev. 19

NMP-OS-014-

2

HNP Time Critical Operator Action Program

Rev. 4.1

NMP-TR-425

Fire Drill Program

Rev. 14

NMP-TR-426

Fire Training Program

Rev. 10

WO

SNC0571621

EDDY CURRENT TEST OF 1E1 1 BOO1B (1B RHR

HEAT EXCHANGER)

2/22/2018

WO

SNC0662592

LOW PRESSURE CO2 SYS SURVEILLANCE

HYDROSTATIC HOSE TEST

01/10/2020

WO

SNC0893926

D/G ROOM 1A 52SV-FPX-010-0 D/G ONLY LOW-

PRESSURE CO2 SYS SURVEILLANCE

10/29/2021

WO

SNC0963578

2SV-FPX-010-0 CABLE SPREAD & COMPUT ROOM

LOW PRESSURE CO2 SYS SURVEILLANCE

06/28/2023

WO

SNC1017433

LOW PRESSURE CO2 SYS SURVEILLANCE

HYDROSTATIC HOSE TEST

08/18/2025

WO

SNC1025311

D/G ROOM 1B 52SV-FPX-010-0 D/G ONLY LOW-

PRESSURE CO2 SYS SURVEILLANCE

10/15/2021

WO

SNC1025312

D/G ROOM 1B 52SV-FPX-010-0 D/G ONLY LOW-

PRESSURE CO2 SYS SURVEILLANCE

04/02/2024

WO

SNC1025313

D/G ROOM 1C 52SV-FPX-010-0 D/G ONLY LOW-

PRESSURE CO2 SYS SURVEILLANCE

11/01/2021

WO

SNC1025314

D/G ROOM 1C 52SV-FPX-010-0 D/G ONLY LOW-

PRESSURE CO2 SYS SURVEILLANCE

04/02/2024

WO

SNC1025315

D/G ROOM 2A 52SV-FPX-010-0 D/G ONLY LOW-

PRESSURE CO2 SYS SURVEILLANCE

10/20/2021

Work Orders

WO

SNC1025316

D/G ROOM 2A 52SV-FPX-010-0 D/G ONLY LOW-

PRESSURE CO2 SYS SURVEILLANCE

04/02/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

WO

SNC1025317

D/G ROOM 2C 52SV-FPX-010-0 D/G ONLY LOW-

PRESSURE CO2 SYS SURVEILLANCE

11/01/2021

WO

SNC1025318

D/G ROOM 2C 52SV-FPX-010-0 D/G ONLY LOW-

PRESSURE CO2 SYS SURVEILLANCE

04/02/2024

WO

SNC1037250

2SV-FPX-010-0 CABLE SPREAD & COMPUT ROOM

LOW PRESSURE CO2 SYS SURVEILLANCE

06/11/2025

WO SNC970250

D/G ROOM 1A 52SV-FPX-010-0 D/G ONLY LOW-

PRESSURE CO2 SYS SURVEILLANCE

03/27/2024