MONTHYEARML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24017A1582024-01-17017 January 2024 Submittal of Emergency Plan Revision 50 IR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 ML23354A0022023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment IR 05000313/20234052023-12-12012 December 2023 Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 ML23341A0832023-12-11011 December 2023 Material Control and Accounting Program Inspection Report 05000313/368/2023404- Cover Letter ML23305A0922023-12-0707 December 2023 Summary of Regulatory Audit Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23325A1412023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23243B0452023-11-13013 November 2023 Request for Withholding Information from Public Disclosure ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000313/20230112023-10-10010 October 2023 Commercial Grade Dedication Inspection Report 05000313/2023011 and 05000368/2023011 IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle IR 05000313/20243012023-08-14014 August 2023 Notification of NRC Initial Operator Licensing Examination 05000313/2024301 IR 05000313/20230022023-08-11011 August 2023 Integrated Inspection Report 05000313/2023002 and 05000368/2023002 and Notice of Violation ML23209A6022023-08-0909 August 2023 Regulatory Audit Plan in Support of License Amendment Request to Revise Technical Specifications to Adopt Risk- Informed Completion Times IR 05000416/20230022023-08-0808 August 2023 Integrated Inspection Report 05000416/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200050/2023001 ML23208A2132023-08-0303 August 2023 Regulatory Audit Summary Concerning Review of License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23208A2112023-07-27027 July 2023 Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23188A1732023-07-12012 July 2023 Request for Withholding Information from Public Disclosure ML23142A2022023-06-29029 June 2023 Issuance of Amendment Nos. 279 and 332 Emergency Plan Staffing Requirements IR 05000313/20234032023-06-28028 June 2023 Security Baseline Inspection Report 05000313/2023403 and 05000368/2023403 ML23178A0892023-06-26026 June 2023 August 2023 Emergency Preparedness Program Inspection-Request for Information ML23166B0902023-06-21021 June 2023 Request for Relief ANO1 ISI 036 Regarding Volumetric Examination Requirements ML23180A1082023-06-20020 June 2023 ANO Unit 1 SAR Amendment 31, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report IR 05000313/20234012023-06-13013 June 2023 Cyber Security Inspection Report 05000313/2023401 and 05000368/2023401 ML23130A2972023-05-17017 May 2023 Notification of Inspection (NRC Inspection Report 05000313/2023003) and Request for Information ML23121A3012023-05-10010 May 2023 Regulatory Audit Plan in Support of License Amendment Request to Revise Technical Specifications to Adopt Risk - Informed Completion Times ML23114A3572023-05-10010 May 2023 Regulatory Audit Summary Concerning Review of Request for Alternative ANO-CISI-002 Regarding Containment Inservice Inspection Frequency ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000313/20230012023-05-0909 May 2023 Integrated Inspection Report 05000313/2023001 and 05000368/2023001 ML23118A3202023-05-0808 May 2023 Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000313;05000368/2023010) IR 05000368/20233012023-05-0101 May 2023 NRC Examination Report 05000368/2023301 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23108A1362023-04-24024 April 2023 Approval of Request for Half-Nozzle Repair of Reactor Vessel Closure Head Penetration No. 46 ML23110A1122023-04-20020 April 2023 Annual Report for Entergy Quality Assurance Program Manual Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d). Notification of Application of Approved Appendix B to 10 CFR 72 Subpart G 2024-01-24
[Table view] Category:License-Operator Examination Report
MONTHYEARIR 05000313/20223012022-06-15015 June 2022 NRC Examination Report 05000313/2022301 IR 05000368/20213012021-05-17017 May 2021 NRC Examination Report 05000368/2021301 IR 05000313/20183012018-04-0404 April 2018 NRC Examination Report 05000313/2018301 IR 05000368/20173012017-03-22022 March 2017 NRC Examination Report 05000368/2017301 ML16011A1792016-01-11011 January 2016 Notification of NRC Initial Operator Licensing Examination 05000313/2016301 IR 05000368/20153012015-09-24024 September 2015 Er 05000368/2015301; 08/24/2015 - 09/15/2015; Arkansas Nuclear One, Unit 2; Initial Operator Licensing Examination Report IR 05000368/20143022014-09-0404 September 2014 Er 050003682014302; on 07/30/2014 - 08/21/2014; Arkansas Nuclear One, Unit 2; Initial Operator Licensing Retake Examination Report IR 05000368/20143012014-04-17017 April 2014 Er 05000368-14-301, on February 10 - March 19, 2014, Arkansas Nuclear One, Unit 2, Initial Operator Licensing Examination Report IR 05000313/20133012013-03-29029 March 2013 Er 05000313-13-301; February 22 - March 18, 2013; Arkansas Nuclear One, Unit 1; Initial Operator Licensing Examination Report ML12054A1172012-02-23023 February 2012 Notification of NRC Initial Operator Licensing Examination 05000368/12-301 IR 05000313/20113022011-10-26026 October 2011 Er 05000313-11-302; August 26 to September 19, 2011; Arkansas Nuclear One, Unit 1; Initial Operator Licensing Examination Report IR 05000368/20113012011-03-17017 March 2011 Er 05000368-11-301 on 01/28/2011 - 02/17/2011, Arkansas Nuclear One, Unit 2 IR 05000313/20103012010-04-12012 April 2010 Er 05000313-10-301, on 03/08/2010 to 3/16/2010, Arkansas Nuclear One, Unit 1, Initial Operator Licensing Examination Report IR 05000368/20093022009-10-0505 October 2009 Er 05000368-09-302; on 08/07/2009, Arkansas Nuclear One, Unit 2; Initial Operator Licensing Examination Report IR 05000313/20093012009-02-20020 February 2009 Er 50-313/09-301, 50-368/09-301 on 01/26/09 - 02/03/09 for Arkansas Nuclear One, Unit 1 ML0828001112008-10-0606 October 2008 2008 -09 - Examination Report ML0824801592008-09-0303 September 2008 Er 05000313-08-301, on 09/08/2008, Arkansas Nuclear One, Unit 1 - NRC Initial Operator Licensing Examination Approval IR 05000368/20083012008-03-14014 March 2008 Er 05000368-08-301, on February 25-28, 2008; Arkansas Nuclear One, Unit 2; Initial Operator Licensing Examination Report IR 05000313/20073012007-04-25025 April 2007 Er 05000313-07-301, on 03/5-8/2007, Arkansas Nuclear One, Unit 1; Initial Operator Licensing Examination Report ML0409200332004-03-30030 March 2004 Generic Fundamentals Section of the Written Operator Licensing Examination IR 05000313/20043012004-02-0909 February 2004 Er 05000313-04-301 on 01/12/2004 - 01/15/2004; Arkansas Nuclear One, Unit 1, Initial Operator Licensing Examination IR 05000368/20033012003-08-27027 August 2003 Er 05000368-03-301, on 07/11/03 - 07/18/03; Entergy Operations, Inc., Arkansas Nuclear One, Unit 2; Initial Operator Licensing Examination IR 05000368/20023012002-03-0505 March 2002 IR 05000368/2002-301, on 2/11-15/2002, Entergy Operations, Inc., Arkansas Nuclear One, Unit 2, Initial Examination of Applicants for Operator Licenses. Fifteen of Sixteen Applicants Satisfied the Requirements of 10 CFR Part 55 2022-06-15
[Table view] |
Text
ary 9, 2004
SUBJECT:
ARKANSAS NUCLEAR ONE, UNIT 1 - NRC EXAMINATION REPORT 05000313/2004-301
Dear Mr. Forbes:
On January 15, 2004, the US Nuclear Regulatory Commission (NRC) completed an initial operator licensing examination at your Arkansas Nuclear One, Unit 1. The enclosed report documents the examination findings, which were discussed on January 15, 2004, with Mr. John Miller Jr. and other members of your staff.
The examination included an evaluation of five applicants for operator licenses and four applicants for senior operator licenses. The license examiners determined that all applicants satisfied the requirements of 10 CFR Part 55, and the appropriate licenses have been issued.
No findings of significance were identified.
In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter, its enclosure(s), and your response will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Anthony T. Gody, Chief Operations Branch Division of Reactor Safety Dockets: 50-313 Licenses: DPR-51
Enclosure:
Examination
Entergy Operations, Inc. -2-Report 05000313/2004-301
REGION IV==
Docket: 50-313 License: DPR-51 Report No.: 05000313/2004-301 Licensee: Entergy Operations, Inc.
Facility: Arkansas Nuclear One, Unit 1 Location: Junction of Hwy. 64W and Hwy. 333 South Russellville, Arkansas Dates: January 12 to 15, 2004 Inspectors: P. Gage, Senior Operations Engineer T. McKernon, Senior Operations Engineer M. Murphy, Senior Operations Engineer Accompanying K. Clayton, Operations Engineer Personnel:
Approved By: Anthony T. Gody, Chief Operations Branch Division of Reactor Safety
-2-SUMMARY OF FINDINGS ER 05000313/2004-301 on January 12 to 15, 2004; Arkansas Nuclear One, Unit 1, initial operator licensing examination.
NRC examiners evaluated the competency of five applicants for operator licenses and four applicants for senior operator licenses. The licensee and the NRC developed the examination using NUREG-1021, "Operator Licensing Examination Standards for Power Reactors,"
Revision 8, Supplement 1. The licensee provided proctors for the administration of the written examination to all applicants on January 9, 2004, in accordance with instructions provided by the chief examiner. The NRC examiners administered the operating test on January 12-15, 2004.
No findings of significance were identified.
REPORT DETAILS 4. OTHER ACTIVITIES 4OA4 Initial License Examination
.1 Operator Knowledge and Performance a. Examination Scope The NRC examination team administered the operating test to the nine applicants on January 12-15, 2004. Most of the applicants participated in two dynamic simulator scenarios, a control room and facilities walkthrough test consisting of ten system tasks, and an administrative test consisting of one task or two questions in five areas. The three applicants for upgrading their operator license to a senior operator license participated in two scenarios and took a control room and facilities walkthrough test consisting of five system tasks. The administrative test for the senior operator applicants consisted of performing tasks in five areas.
On January 9, 2004, the licensee proctored the administration of the written examinations to all nine applicants and forwarded the proposed grades together with the performance analysis to the NRC for approval.
b. Findings All applicants passed all parts of the examinations. For the written examinations, the average score for the operator applicants was 90.8 percent, and the average score for senior operator applicants was 92.5 percent. The operator applicant scores ranged from 86 to 95 percent, and the senior operator applicant scores ranged from 89 to 96 percent.
The licensee conducted a performance analysis for the written examinations with emphasis on six questions missed by half or more of the applicants. After reviewing the licensees analysis, the examiners concluded that all questions were valid and that there were no apparent training deficiencies requiring the licensee to address in its corrective action program. There were no post-examination comments on examination questions.
The text of the examination questions and the performance analysis may be accessed in the ADAMS system as noted in the attachment.
.2 Initial Licensing Examination Development The licensee developed their assigned portion of the operating test in accordance with NUREG-1021, Revision 8, Supplement 1. Licensee facility training and operations staff involved in examination development were on a security agreement.
-2-
.2.1 Operating Examination Outline and Examination Package a. Examination Scope The NRC staff completed the operating test outlines on September 17, 2003.
Examiners reviewed the submittal against the requirements of NUREG-1021, Revision 8, Supplement 1. The outlines were reviewed by the licensee staff and minor comments were returned to the NRC on October 1, 2003. The draft examination package was reviewed by the licensee staff on November 24, 2003. Examiners reviewed the licensees comments against the requirements of NUREG-1021, Revision 8, Supplement 1, and provided comments to the licensee on December 4, 2003. The chief examiner conducted an onsite validation of the examinations and provided further comments during the week of December 15, 2003.
b. Findings Examiners approved the initial examination outline with minor comments and advised the licensee to proceed with the operating examination development.
The chief examiner determined that the operating test initially submitted by the licensee staff were within the range of acceptability expected for a proposed examination.
No findings of significance were identified.
.2.2 Simulation Facility Performance a. Scope The examination team observed simulator performance with regard to plant fidelity during the examination validation and administration.
b. Findings No findings of significance were identified.
2.3 Examination Security a. Scope The examiners reviewed examination security both during the onsite preparation and examination administration weeks with respect to NUREG-1021 requirements. Written plans for simulator security and applicant control were reviewed and discussed with licensee personnel.
-3-b. Findings No findings of significance were identified.
4OA6 Meetings, Including Exit On January 15, 2004, the examiners presented the examination results to Mr. John Miller Jr. and other members of your staff who acknowledged the findings. The inspectors confirmed that proprietary information was not provided or reviewed during the examination process.
ATTACHMENT KEY POINTS OF CONTACT Licensee personnel J. Bradford, Training A. Clinkingbeard, Assistant Manager, Operations G. Giles, Supervisor, Operations Training Unit 1 M. Goad, Training P. Harris, Training P. Higgins, Training T. Mayfield, Supervisor, Operations Training Unit 2 J. Miller, Manager, Training S. Pullin, Training D. Smith, Training NRC personnel K. Clayton T. McKernon M. Murphy ADAMS DOCUMENTS REFERENCED Accession No.: ML040340097 - Reactor operator written examination Accession No.: ML040340104 - Senior operator written examination Accession No.: ML040340111 - Written examination performance analysis and applicant questions