rch 4, 2005

SUBJECT:

ERRATA FOR ARKANSAS NUCLEAR ONE NRC INTEGRATED INSPECTION REPORT 05000313/2004003 AND 05000368/2004003

Dear Mr. Forbes:

Please add Section 1R17, Permanent Plant Modifications (Enclosure), to NRC Inspection Report 05000313/2004003 and 05000368/2004003, dated July 27, 2004. The purpose of this change is to provide information that was inadvertently omitted from the Report Details section of this report.

In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

/RA/

Troy W. Pruett, Chief Project Branch D Division of Reactor Projects Dockets: 50-313 50-368 Licenses: DPR-51 NPF-6

Entergy Operations, Inc. -2-Enclosure:

Errata of NRC Inspection Report 05000313/2004003 and 05000368/2004003 cc w/enclosure:

Senior Vice President

& Chief Operating Officer Entergy Operations, Inc.

P.O. Box 31995 Jackson, MS 39286-1995 Vice President Operations Support Entergy Operations, Inc.

P.O. Box 31995 Jackson, MS 39286-1995 Manager, Washington Nuclear Operations ABB Combustion Engineering Nuclear Power 12300 Twinbrook Parkway, Suite 330 Rockville, MD 20852 County Judge of Pope County Pope County Courthouse 100 West Main Street Russellville, AR 72801 Winston & Strawn 1400 L Street, N.W.

Washington, DC 20005-3502 Bernard Bevill Radiation Control Team Leader Division of Radiation Control and Emergency Management Arkansas Department of Health 4815 West Markham Street, Mail Slot 30 Little Rock, AR 72205-3867 James Mallay Director, Regulatory Affairs Framatome ANP 3815 Old Forest Road Lynchburg, VA 24501

Entergy Operations, Inc. -3-Technological Services Branch Chief FEMA Region VI Dept. of Homeland Security 800 North Loop 288 Federal Regional Center Denton, TX 76201-3698

Entergy Operations, Inc. -4-Electronic distribution by RIV:

Regional Administrator (BSM1)

DRP Director (ATH)

DRS Director (DDC)

DRS Deputy Director (MRS)

Senior Resident Inspector (RWD)

Branch Chief, DRP/D (TWP)

Senior Project Engineer, DRP/D (GEW)

Team Leader, DRP/TSS (RLN1)

RITS Coordinator (KEG)

DRS STA (DAP)

J. Dixon-Herrity, OEDO RIV Coordinator (JLD)

ANO Site Secretary (VLH)

W. A. Maier, RSLO (WAM)

J. Anderson, NSIR/EPPO (JDA1)

SISP Review Completed: _twp____ADAMS: / Yes G No Initials: __twp___

/ Publicly Available G Non-Publicly Available G Sensitive / Non-Sensitive R:\_ANO\2004\AN2004-03RP Errata.wpd ML050630156 RIV:SPE:DRP/D SRI:DRS/EB C:DRS/EB C:DRP/D GEWerner CJPaulk JAClark TWPruett

/RA/ /RA/ /RA/ /RA/

3/3/05 3/3/05 3/4/05 3/4/05 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

ENCLOSURE REPORT DETAILS 1R17 Permanent Plan Modifications (71111.17B)

a. Inspection Scope The inspection procedure required the biennial review of 5 to 10 permanent plant modifications affecting risk-significant structures, systems, and components. The inspectors reviewed 12 risk-significant permanent plant modifications listed in the attachment. For the modifications selected, the inspectors verified that: the designs for modifications were adequate; implementation of the modifications did not impair key safety functions; postmaintenance testing was appropriate for validating that the modification performance met the intended design bases; and documentation, including design documents and significant plant procedures, was updated to reflect the effects of the modification.

The inspectors also reviewed permanent plant modification-related condition reports issued during the past year and verified that the licensee identified, evaluated, corrected, and trended problems identified with the modifications. As part of this effort, the inspectors evaluated the effectiveness of the corrective action process, including the adequacy of the technical resolutions.

b. Findings No findings of significance were identified.