U. S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT Region I
.
Report No. 50-293/79-17
.
Docket No. 50-293
-
License No. DPR-35 Priority Category C
--
Licensee: Boston Edison Company M/C Nuclear 800 Boylston Street Boston, Massachusetts 02199
-
Facility Name: Pilgrim Nuclear Power Station, Unit 1 Meeting at:
Region I Office, King of Prussia, Pennsylvania Meeting conducted:
September 5, 1979
-
NRC Personnel:
.M
[ f Cw-G/y /r 2
'
J. M.i Allan,' Deputy Director date signed
,
l l
-
T/J/79 E."JI. Br0nner, Chief, Reactor Operations and
'date ' signed Nu ear Support Branch date signed E. C. McCab Jr. Chief, Reactor Dr ' 2 cts No. 2, RO&NS Branch date signed ThDY f
.
~ date signed R. Architzel, Reactor Inspector Approved by:
O. 9.
h 9 [r7 f7)
E. C. McCabe, Jr. Chief. Reactor Projects No. 2, RO&NS Branch Meeting Summary:
-
Management Meeting on September 5, 1979 (Report No. 50-293/79-17),
Areas Covered: Meeting held at the Region I Office to discuss the violation of primary containment integrity which occurred on June 12, 1979 and was identified during NRC Inspection 293/79-16.
1146 118
,
Region I Form 12-1
'
(Rev. August 77)
7 910150 / d d
,
-
.
DETAILS 1.
Licensee Personnel Present P. J. McGuire, Pilgrim Station Manager E. Cobb, Chief Operating Engineer C. Mathis, Senior Plant Engineer 2.
Areas Discussed The licensee commented on the sequence of events and corrective actions taken or planned as discussed in their response dated August 17, 1979, to the Region I telephone conversation and Immediate Action Letter on August 10, 1979.
The Region expressed concern over the number of violations of Limiting Conditions of operation which have occurred during the recent past at Pilgrim Station.
The licensee described the effects of certain correcLive actions including licensed operator responsibility changes with respect to oversight of maintenance activities, provision of administrative assistance for the senior licensed operator, and implementation of a training program for maintenance personnel.
.