IR 05000289/1973027

From kanterella
Jump to navigation Jump to search
Insp Rept 50-289/73-27 on 731219-21 & 26-28. Noncompliance Noted:Failure to Follow Test Instruction 9 During Performance of Parts of Preoperational Test Tp 600/20,loss of Electrical Power Test
ML19256D411
Person / Time
Site: Crane Constellation icon.png
Issue date: 01/30/1974
From: Davis A, Spessard R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML19256D405 List:
References
50-289-73-27, NUDOCS 7910180757
Download: ML19256D411 (11)


Text

..

.'

U. S. ATOMIC ENERGY C0 DlISS10:1

.

DIRECTORATE OF REGULATORY OPERATIONS

.

.

.

REGION.I nv RO Inspection.,2 port No.: 50-289/73-27 Docket No.:

50-289

-

Licensce: Metropolitan E.*is m vo'P-License No.: CPPR-40

-

Three Mile " land - Unit 1 Priority:

.

B.1

~

.'

.

Category:

.

Middletown, Pennsylvania

,

i B&W 871 MWe PWR Type of Licensec:

,

,

.

Routine - Announced

Type of Inspection:

-

.

'

December 19-21 and.26-28, 1973 Dates of Inspection:

-

i December 12-14, 1973 Dates of Previous Inspection:

Q.

i

{}

cd/ (Ll ^

/k1/W

.

l Reporting Inspector:

'DATE g R. L. Spessard, Reactor Inspector

.

,

,.

,

.

..

!

DATE I

'

.

i NONE Accc=panying Inspectors:

DATE

.

DATE

.

.

NONE Other Accc=panying Personnel:

DATE

//~ll/ 7 V7

Revicued By:

  1. DATE A. B. Davis, Senior Reactor Inspector Reacter Operations Branch

,

7910180) [ 2 1449 038

.

_.

_

- -..

.. -

_

-...

.

--

-.

...

. _ - _

.

.

.

.

SINMARY OF FINDINGS Enforcement Action A.

Violations The licensee failed to follow Test Instruction No. 9 during the per-formance of parts of Preoperational Test TP 600/20 Loss of Electrical Power Test (without E.S.) in apparent violation of 10 CFR 50, Appendix B, Criterion V.

The licensee corrected this violation and took corrective steps to avoid further violations prior to the completion of the inspection.

This matter is closed.

(Paragraph 7.e)

!

B.

Safety Items

.

None Identified

Licensee Action on Previously Identified Enforcement Items

'

.

A.

Not Inspected

i

,

's Unusual Occurrences

-

,

A.

Failure of the Static Auto Transfer Switch associated with the lA Invertet during preoperational testing.

(Paragraph 7.e)

Other Significant Findings A.

Current 1.

Hot Functional Testing commenced on December 19, 1973.

CParagraph 7)

2.

The licensee's scheduled fuel load date is March 13, 1974.

.,

3.

A significant personnel change has occurred in the. Met Ed organi-zation.

(Paragraph 2)

B.

Status of Previously Reported Unresclved Items No Change Management Interview An exit interview was conducted on December 28, 1973 at the conclusion of

-

the inspection.

Items discussed and personnel in attendance were as

'_/

follows:

,

i449 J39

.

-. - _

-

.

.-

--

..

-

- -.

.-._.

.

!.

.

.

-2-O

_t t

Licensee Representatives

.

J. Herbein, Station Superintendent, Met Ed J. Floyd, Supervisor of Operations, Met F.d R. Summers, Plant Engineer, Met Ed W. Potts, Quality Control Supervisor, Met Ed

'

J. Barton, Startup and Test Manager, GPUSC G. Miller, Test Superinteadent, GPUSC S. Levin, Unit 1 Project Engineer, GPUSC G. Kopp, QA Specialist, GFUSC T. Sturgeon, QA Specialist, GPUSC

_

i RO:I Reoresentative

.

L. Spessard

.

A.

Preoperational Test Procedures Inspection findings relative to the review of preoperational test pro-cedures, test results, and previously reported test procedure deficien-

cies were discussed.

(Paragraphs 3, 4, and 5)

(

B.

Shift Test Engineers Log.

,

Inspection findings relative to th3 review of this log were discussed.

(Paragraph 6)

>

C.

Hot Functional Testing (HFT) Program Inspection findings relative to the review of HFT program activities

'

were discussed.

This included the apparent violation of 10 CFR 50, Appendix B. Criterion V and the licensee's corrective action.

(Paragraph 7)

D.

Timeliness of Test Procedure Approva,1, The inspector expressed his concern relative to slippages in the licensee's schedule for completion of pr, operational and initial startup test procedures.

The inspector ointed out that 4 pro-cedures relative to hot functional testing had not been approved and that none of the initial startup procedures had been approved.

The inspector discussed Regulatory Guide 1.68 Preoperational and Initial Startup Test Programs for Water-Cooled Power Reactors relative to having procedures written 30 days prior to the scheduled

-

performance o? a test, but not less than 90 days prior to the scheduled fuel loading date.

i

~

g 1449 J40

'

'

_.

.

-

-

.

..

.

.

.

.

.

-3-

]

-

The licensee representatives indicated that their schedcles had been established to meet the intent of this guide and that prtblens causing the slippages had been resolved.

The representatives indicated priorf ry attention was being given to this matter.

The representa-tives indicated the 4 HFT procedures would be approved by January 9, 1974 and the initial startup procedure would be written and available for the inspector's review by January 7, 1974.

According to the representatives, preliminary and/or final TWG 2pproval of the initial startup procedures woulc be accomplished by February 15, 1974.

1449.)4l

'

e

\\.)

.

.

.

.

a

e

^S

,

  • )

.

_._ _. ~ __... _ _ _ _.

_. -

. _ _ _ ___

_ _ _. _

_ _.

_... _.. _

.

.

-

DETAILS 1.

Persons Contacted Metrooolitan Edison Company J. Herbein, Station Superintendent J. Floyd, Supervisor of Operations M. Ross, Shift Supervisor M. Beers, Shift Supervisor

.

B. Smith, Shift Foreman

,

i General Public Utilities Service Corporation J. Barton, Startup and Test Manager

,

'

G. Miller, Test Superintendent

R. Toole, Assistant Test Superintendent

.

M. Nelson, Technical Engineer

!

W. Bateman, Lead Engineer - Mechanical

.

!

W. Behrle, HFT and PET Program Coordinator l

(}

T. Faulkner, Senior Test Planner

'

S. Poje, Shift Test Engineer

'

I. Porter, Shift Test Engineer Gilbert' Associates, Inc.

l D. Diener, Structural Enginee"

2.

Personnel Changes A licensee representative informed the inspector of the following change in the Met Ed organization which is to be effective Jamuary

,

1, 1974:

Mr. R. Klingaman, formerly the Station Superintendent, is promoted to Manager - Generation Operations, a position that was previously vacant.

In this position Mr. Klingaman reports directly to Mr. R. Arnold, Manager - Generation.

Mr. J. Herbein, formerly the Assistant Station Superintendent, is promoted to Station Superintendent, and he reports directly to Mr. Klingaman.

There are no plans at the present time to fill the position of Assistant Station Superintendent.

3.

K0:1 Review of Preocerational Test Procedures The inspector discussed his review of the following preoperational test procedures:

',

J 1449 J42

-

- _.

- -

.

-

-

-

..-

-

._ _.

._.

___

_ _ _ _ _ _.

__

,

.

-5-

,-

-

TP 600/6A Liquid Waste Disposal System Operational Test TP 600/14 Pipe and Component Hanger Hot Deflection and Inspection Test TP 600/29 Reactor Coolant System Thermal Expansion Functional Test The deficiencies identified during this review were corrected by issuance of a Test Change Notice and/or test exception change to the affected procedure.

RO:I has no further questions on these

~

procedures at this time.

4.

RO:I Review of Preoperational Test Results The inspector reviewed the completed test package as accepted by the licensee and la satisfied with the documentation of performance and results of the following tests:

-

SP 330/1 Control Rod Drive Pre-Op Calibration TP 330/2 Control Rod Dr*ve Control System Operational Test SP 53.9 500 KVA Transformer Load Test F1104/15C Nuclear Services Closed Cooling / Decay Heat Pumps Area Ventilation Functional Verification

-

'/

F1106/8 Hydrogen Seal Oil System Functional Verification

.

.

F1106/9 Turbine Lube 011 System Functional Verification

}

5.

RO:I Review of Previously Reported Test Procedure Deficiencies a.

TP 250/2 Testing and Checking of Mechanical and Electrical Equipment The inspector reviewed TCN-4 to TP 250/2 dated December 7, 1973 which was approved on December 21, 1973 by the Test Working Group (TWG) in accordance with the Test Manual. The two deficiencies, as identified in RO Inspection Report No. 50-289/73-23,Section II, Paragraph 3.a. and b., were corrected by this TCN.

RO:I has no further comments on this procedure at this time.

6.

Shift Test Engineers (STE) Log

.

The inspector reviewed the STE Log covering the period December 1-20, 1973. No deficiencies with respect to the requirements of Test In-struction No. 17 were identified.

1449.)43

.>

_

_ _ _

_ ___.

__

_ _.

-

_ _... _ _..

._.

__. _..

.

-

.

-6-s 7.

Hot Functional Testing (HFT) Procram a.

TP 600/28 Controlling Procedure for HFT The inspector discussed the purpose and scope of this procedure with cognizant GPU Startup personnel. Additionally, on December 28, 1973 the inspector reviewed the official field copy of this i

procedure and, while in the Control Room, observed plant activi-ties in progress being controlled by this procedure.

The follow-

,

ing observations were made:

(1) This procedure establishes a sequential logic schedule for

'

test and event performance beginning with initial steam bubble formation in the pressurizer and ending with fuel loaded in the reactor vessel.. Additionally, various data

>

sets throughout HFT that have not been included in indivi-dual HFT procedures are recorded in this procedure. The

,

HFT program is divided into eight (3) phases as follows :

(a) Phase I

- Pressurizer Bubble Formation R

(b) Phase II

- First RCS (Reactor Coolant System) Heatup fV to 5320F, 2155 psig j

(c) Phase III - 5320F, 2155 psig Testing (d) Phase IV

- First RCS Cooldown

'(e) Phase V

- Second RCS Heatup to 5320F, 2155 psig (f) Phase VI

- 5320F, 2155 psig Testing (g) Phase VII - Second RCS Cooldown (h) Phase VIII - Post Cooldown Testing

Following completion of Phase IV, a maintenance outage is scheduled to correct identified problems.

Additionally, any tests not completed during Phases I-IV will be rescheduled for performance during the remaining phases.

(2) A partial issue of this procedure was approved by the TWG on December 14, 1973, and this action permitted the commencement of Phase I on December 19, 1973.

(3) A complete issue of this procedure less the sequential logic schedule for Phases V-VIII was approved by tSe TWG on December 22, 1973.

The sequential logic schedule for r>hases V-VIII will be issued by a TCN to TP 600/28 on a later date.

1449 J44 v

-

_-

_._ -

-..

... -.

_.. - -

.. -.

_

.

.

.

-7-m J

(4) Phase II First Plant Heatup (1300 - 532 F) was in progress.

The RCS was at 1960F and 450 psie, and plant heatup uas be-ing conducted in accordance with TP 600/1 Unit Heatup Test.

(5) Activities in progress and documentation contained in TP 600/28 were in accordance with the requirements of Test Instruction No. 9.

b.

Prerequisite List for HFT The Test Manual and Test Instruction No. 10 establish requirements for the prerequisite list, which contains all items that must bethe satisfactorily completed or in a state of readiness to support start of major events.

The list is also required to be periodically The updated and reviewed prior to commencing the associated event.

official field copy of the prerequisite list for HFT was approved

by the TWG on November 21, 1973 and was periodically reviewed and updated by GPU Startup and Met Ed personnel prior to its final approval by the TWG on December 26, 1973.

This prerequisite list was in conformance with Enclosure 1 of Test Instruction No. 10.

During the licensee's periodic reviews, deficiencies and exceptions (~

were identified, and the resolution and evaluation of each item was

-

documented as required by Test Instruction No. 10.

,

'/

Documentation contained is. the official field copy of this list was

'

discussed with cognizant GVU Startup personnel.

Additionally, the systems employed by GPU Startup.in order to complete the required signofts in this list were reviewed with these personnel. No deficiencies were identified.

c.

Test Manning Assignment Document _

The Test Manual and Test Instruction No. 3 establish requirements for a Test Manning Assignment Document which provides a listing of stations to be manned by designated personnel during major test evolutions. The Test Manning Assignment Document for HFT (Phases II-IV) was prepared, approved and issued on December 26, 1973 in accordance with the requirements of Test Instruction No. 3.

The Test Manning Assignment Document for HFT (Phases V-VIII) will be issued cn a later date.

1449 J45 m

me-,.

e

-

-

- - -. -

... - - -

.,-----aw

.--w-

.-.

-

.-.

.

.

.

-

-8-q

'

..,

d.

Pipe Haneers and Restraints The licensee's program relative to pipe hangers and restraints was reviewed by the inspector. This review included discussions with cognizant licensee representatives and examination of pro-cedures and documents to implement the program. The folicwing observations were made:

.

(1) Preoperational Test Procedure TP 600/14 Pipe and Component Hanger Hot Deflection and Inspection Test and TP 600/29 Re-actor Coolant System Thermal Expansion Functional Test and Construction Procedure MCP-15 Adjustment of Hangers establish

,

the requirements for the program.

Additionally, the perfor-mance of these procedures is controlled by TP 600/28 Controll-ing Procedure for HFT.

(2) The program provides for the following:

I (a) Verification of correct installation, i.e., location, type and cold setting prior to starting HFT (RCS temperature i

>2000F) by UE&C Construction and Quality Control.

'

c3 l

\\:

(b) Verification of correct hot setting during HFT by UE&C Quality Control under the direction of a GAI Engineer.

Tc) Observation of piping movement in the Reactor Building during HFT by UE&C Construction, GPU Startup and GAI

,

to insure adequate clearance between piping and any

-

!

portion of a building, other objects, structural members, t

and other pipes.

(d) Verification, check and measurement, where necessary, of the travel indication of large diameter pipe lines within their Loss of Coolant Accident (LOCA) Restraints and parts of the LOCA restraint system of the Reactor Coolant Pumps (RCP) prior to and during HFT by GPU Startup and GAI.

(e) Verification of predicted travel of RCP motor constant

. load supports and steam generator auxiliary feedwater header supports during HFT by GPU Startup and GAI.

(3) GAI provided a nucleus of piping engineers to carry out the necessary GAI designed het system checks in support of a commitment to GPU and the AEC.

Additionally, these personnel will provide technical support during the power escalation testing program.

1449.M6

-

-

_.

-

-

_-

.

-

.

-

.

.

.

-9-nJ (4) Pipe supports which had not been installed were evaluated by UE&C Construction, GPU Startup and GAI, and, where necessary, temporary supports were installed.

RO:I has no further qt estions on the licensee's program at this time.

e.

TP 600/20 Loss of Electrical Power Test (W thout E.S.)

-

l TP 600/20 was performed during Phase I of HFT, and Part B (simu-lated failure of Auxiliary Transformer IB) of this test was witnessed by the inspector on December 21, 1973. Additionally,

'

the official field copy of TP 600/20 was reviewed on December 21, 1973. The following deficiencies were identified and discussed

,

with cognizant licensee representatives:

,

.

(1) The referenced drawings in Paragraph 2.1 of TP 600/20 were

not initialed and/or excepted by the STE or his designate f

prior to starting the test, thus documenting the review and evaluation of drawing changes issued after the procedure

.

l vas approved. This action is required by Paragraph 3.3.1.7 of Test Instruction No. 9.

.

(2) For Parts A (simulated failure of Auxiliary Transformer lA)

and 3 (simulated failure of Auxiliary Transformer 1B) of

'

this test, test exception changes, verification of Pre-requisite System Conditions, and data recording and signoff

,

i were not always properly documented, as required by Para-graphs 3.3.2,6, 3.3.1.1, and 3.3.2.4 of Test Instruction No. 9.

These deficiencies were observed in the following procedural steps and data sheets, as appropriate:

Steps 8.2.1.4, 8.2.6.1.b. (a) and (b), 8.3.1.4, 8.3.5.1, 8.3.6.1.b.

(a) and (b), and 8.3.6.2.b. (a) and (b); Data Sheets 5A (Section 2.4), 9A (Section 2.4),19A (Sections 1.2 and 3.1), 20A (Sec-tions 3.0 - 3.4), 21A (Sections 2.0 - 2.2), 22A, 23A (Sections

.

1.0 - 1.1, 6.2, and 8.2) and 24A (Sections 4.0 - 4.2).

During the performance of the simulated failure of Auxiliary Trans-former 1B, the Static Auto Transfer Switch associated with the lA Inverter, which was lined up to the back-up regulated a-c power system for this test, failed to transfer the ICS and NNI loads to the lA Inverter during the loss of power.

Therefore, these loads were lost for approximately 10 seconds until Diesel Generator lA started and powered the Engineered Safeguards Control Center lA.

I449 347

'

-

.

--

-

--.

._

_

.

..

,.

-

-10-

-

The cause of the switch failure was being investigated by cognizant licensee representatives.

Resolution of this problem and test data review will be accomplished during a subsequent R0 inspection.

On December 28, 1973 the inspector reviewed the of ficial field copy of TP 600/20 which had been completed and documentation contained in this procedure was discussed with a cognizant licensee represen-tative.

The inspector observed that each deficiency identified in

-

j (1) and (2) above had been corrected.

Additionally, the inspector i

reviewed a memo, dated December 27, 1973, from the GPU Test Superin-l tendent to GPU Test personnel which discussed these deficiencies and stressed the importance and requirements for adherence to ad-ministrative procedures. The inspector was informed that a cognizant engineer had been assigned to review (on a daily basis) test pro-

-

cedures as they are performed to insure documentation requirements are being met and problems are promptly identified.

During the

.

i inspector's review of TP 600/28 (Refer to Paragraph 7.a. above),

he observed the assigned cognizant engineer performing this function.

I i

.

i O

.

,

1449 J48

-

I i

4

.

-

..

_.

..

.-

. - _,

, - - _ _.

. _ _, _ - _ -

_-

-

- - _.