IR 05000285/1989037
| ML19324B712 | |
| Person / Time | |
|---|---|
| Site: | Fort Calhoun |
| Issue date: | 10/31/1989 |
| From: | Westerman T NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | |
| Shared Package | |
| ML19324B707 | List: |
| References | |
| 50-285-89-37, NUDOCS 8911080059 | |
| Download: ML19324B712 (7) | |
Text
gp yr w.
- - - -
-
--
.,
e 4 p,k, s g
>
!
MK k,, ~
- y \\,
t-
,
f
\\
'l
'
w;Q,
,
y
- N M
j
.
,
,
,
\\r
,
l
'\\
j s
'%p:
it
,. APPENDIX-
.c y
p, EJ
U.S. NUCLEAR REGULATORY CO, MISSION j
,
y(
.
,
,
'
REGION IV
'
s
/;W
,
,
.)
'F
,g
,
"i F-NRC'.Assessmant Report:~ 50-285/"I-37 Operating License: DPR-40 j
I Docket:,50-285 l
v.
.
.
t-fM,.
Licensee: OmahaPublicPowerDistrict-(0 PPD)
!
A'
444 South 16th Street Mall.
+l
'
$ if, l0maha, Nebreska 68102-2247
3
,
,
1,
. Facility Name:
Fort,CalhounStation(FCS)
<
.
'
eq%u-
' /,
~'
le'l p Assessment At:
~
.
s 4 L
.3 L
&
.
.y
.
.
October 11-20."1989
-
.;
'
- [ ' Assestment conducted
>
>
_
i.
p
.
.
'
"
'
. inspector:
.i y P. Harrell,' Senior Pesident Inspector 0-1J
"
'
.
g.
,
,
'
v
. 7- [ 4 M..,
-
.W -h p.'
Appro'ed:
I
'C
'
' T F. Westerman,' CMef, Project Sect 1on B-lc.y
, Division of Reactor Projects-j
'
y 4'
,
,
'
'
{
- ' '
'
Assessment Sanmary -
.
,
-
<
'
,
.
y,,, 4 fAssessment Conducted October 11-20,1989 (Repert 50-285/89-37)
,
,,.
y..
h*
%
I$sults:1 Baded on the" assessment: performed byL the l inspector, it appeared that
,
,
the dicensee was implenenting an adequate'verificationsund validation process'
l'. - >
i y
fortthe items containedlin the Safety Enhancement Prcgrani. tiowever, seven open i"
,
ittms were ' identified during this assessment'that indicated that the licensee
,
4'%' ne,eded to provide greater oversight of the verification and validition process.
-
'
g i '.!
u Of the seven open. items identified by the inspector..the NRC.is'most concerned '
f P.-
'about the.relatively large number sf weaknestes that were classified by the fi n
'
slicensee as significant.- ' Other areas identified'during this assessment' that
.
h X
"p 'are of concern to the NRC include the lack of a procedural 12ed:progrtm to
{
,.
" address the verification and validation process, the failure to take a proactive.
'
"
y~0
' role in informing the'NRC or the status of the weaknesr.es, the failure to
-
establish acceptance criteria for an accepttble method for institutionclizatlon
%),
jot items in the Safety'Enhanc? ment Program, and the failure to establish a
'l W
'
Kg program for revalidation of 1dentified weaknesses.
'
%Q; '
'"
.
s
,
,
4-
':f
!
h 89'11000059 8910311
"
PDR 05000285 r
g Qg k, ADOCK PPh's g"
V f}p a
+
!
,
- g M.
A-
<
%
lg;
_.
j{y;h j I U f 4 M W '
.
p.
L l
. '
,
'
'
D'
_,
'
y
- ~-3;
.
,
.
, -
,
p,
~
<
.
se
.
,,
p, $,
'
'
'
,
.,.
,
g
- .
v
<
- .
,
~2-
-
..
.
,.
o
'
!!
.c s
'
.
'
DETAILS vp-
-
.
,
.e It t
>s
,
'
1..
Persons Contacted'
-
,
[q
- R.-Andrews,; Division Manager, Quality and Environmental Affairs
,
,p'
- B. Blome, Quality Assurance Engineer
',
u '
- J. Chase, Acting Manager, Nuclear Licensing and Industry Affairs F
- D. Matthews, Supervisor, Station Licensing
'
.
L
- S. Gambhir, Division Man 6ger, Production Engineering g
- M. Lazar,' Supervisor, Opetations: and Technical Training j
..
. *T. McIvor, Manager, Nuclear Projects l
L.
L
- K. Morris, Division Manager, Nuclear Operations'
.
M
- W..Orr; Manager, Quality Assurance and Quality Control
.
'
- G. Potet son, Manager, Fort Calhoun' Station
- A. Spencer, Licensing Contractor
.
k. S.
- Denotes attenaance at the' assessment exit interview.
'
,i
,
,
h, <i 2.
LAssessment of the Verification and Validation Process (92702)<
k This' assessment was performed to verify that the licensee had established
'
s an adequate' verification and validation (V&V) program for the items
"'
-
"
'
contained in the Safety Enhancement Program (SEP). The intent of the V&V
.
T
.c
.
process initiated by the licensee was to provide' assurance that each item
.
.c contained in the SEP was adequately and effectively implemented.
The
,i,,f implementation was performed by the licansee to ensure.that the items
'
,
a t
l'
would become institutionalized (i.e., a commitment placed into'a document
!!
such that the' licensee ~ would continue to perform the actions specified in
each item once the SEP was closed)..
,
,
-
1 1.
To perform this assessment, the inspector selected's sampling of Priority
.;
" '
Level I and II items that h'ad been statused to the NRC ar. complete by the'
'
,,
f>
- licensee.'>The focus of this assessment was directed toward the V&V process only'and did not verify the actual. implementation of the item. 'An L " f,
- ndepth review'of selected iters' will be_ performed.dur.ing a future
.!
,
f' i i assessment.'
e S
'
'~
'
.
,
O '.
.
'
~
During performance of the assessment, the following elements werc
,
y, reviewed, n; appropriate:
,
The V&V process had been adequately' defined.
"
,.
>
n
[w Assignment of individual responsibilities for the V&V of ench SEP
[
^
"-
h
,bg4,
item had been made
.
. s..
s a.
>
>
~
1X /W'
9'
Treaining in the V&V process had been provided for each assigred
.
1S i $T individual.
.
m i
Oj,, e),
s.
i.
g % g.C D ',
- '
'The institutionalization proccsr, for the inclusion of requirements
.
(
9-v into the appropriate docu.nentation had been defined, t
a r,,
.
'
,
W
o
,
,
.
,
~ g:[,
-
qqpyw. c ;
y
^
e
,
o
.,n,
,,
>
.
,
[ 'f h
',
c., ;f,; a
'
'
o a
>
'
j
-
-
.
.
s.
p
-y f
>
,
'
.
t
<
.
'
'
, 'y
.
- -
A tracking system had been established to address any implementation-
-
weaknesses identified during validation'of the SEP item.
,
[
Aprocessfor'revalidaticnoftheactionstakenon'ideni,1fied
'*
. eaknesses had been established.
w
.;
-
<
,
L
"
The state * -provided to the; NRC for each SEP item was accurate.
,,
,
o The inspector. identified the fo;1owing items during as'sessnient ofL the V&V
.
process.
,
4e
'
,
.m,
.
,
M
.a.-
The V&V, process had not been formally reviewed,dpproved, and-
'
proceduralized.
In 1.ieu of a formalized, documented proce' lure;.the-J ManagerE Nuclear i.icibsing and Industry Affairs, issued a memorandume i
i s w
~ on May,16, 1989, to dstablish and, implement'the V&V proc 9ss.
The
<
- '
'
'
.
E memorandum'describedjan overview of the V&V process,;how the: process i
-
was to be implemented, and assigned individual responsibilities for the verification of nach item.
In addition,- tht. memorandum stated n
,
~
'
p.
that the licensing or quality assurance (QA) organization would be-
,
,,'
' responsible:ror validation of all items.
The specific group
'
responsibic:for validation was identified for each item.
Based on n
,
c '.
the reviews performed by the inspector, it appeared that the V&V -
.
process had been adequately defined.
,
,
..
.
/
T
>
,
.
tilthougn no significant problems were identified'wid the establishment of thfi V&V process, the licensee should consider formal
,
- npprov'al and issuance of the intitrottiont, for the V&V process.
m;
/
Formal institutionalization of proceduralized requirements for the i
SEPLitems was beingeaccomplished.by the licensee; % wever, the'
'
<
i'e S>
,Ilicensee had not ' initiated action to. institutionalize the V&V process
.,
,g
,,
y ;,
- <
itself.
. Inclusion of the V&V profes's.into a formally issued '
'
,
,
%
procedure,would' t:nsure that management? maintains control over the V&V-
[h
, process! so changes could not be,madetwithout, management approval.
'
W
' It ist reguested that ethe licensee provide a response to the
[
,
.,.
- .
,ch inspector'pobservation regarding institutionalization of the V&V 4,
process.
Thisiiten will remain open pending receipt of the y
(g h.
.;F..
i'
licensee's< response and evaluation oftthe licensee's proposed action c
>
". '.'f*
by an'i,nspector.
(285/8937-01)
-
?<p.
+
?;
,
.
,
,
,
W f
b..
As part of,the, validation process, the' individual assigned ~the task j
1m for validation of an SEP item was require'd.to ensure that the items e
s&ffgiq j
,
.had t,een fully institutionalized.
Durirg review.of conpleted SEP
g$'f[W W
.,
Jw#
. items,1the' inspector noted that different individuals performing the
valiuation tetivities were applyiqg different criteria as to what
,
constituted acceptable institutionalization.
1%
s Mp i
g
J-The inspector noted that the licensee had not provided any direction
,
It i
or acceptance criteria to the individuals perforaring validation fm
kj',-
activities as Mo what.constitutec acceptable instMtionalization.
i
@% {i >,%, '
Due to the ab unce of specific criteria, each individeal was
- // aI'
!),
',,
..
v fi: gi'
.
.q[
l'
',1l :
'
,
., ) f Q, t >
.l
)
la
"
'
'
,
- GV[
.
_
_
e
,,
,
m i
>
,;
'l n
e
,
,
i +.
i
.,
y
...,
.
,
v3-e
,s.
-
-
3.
i f.
~4-
.
'
'
'
g-j s
,
,
'
establishing his/her own set of ctandards; therefere,' inconsistent
'
.
,
criteria were being applied.,
LThe licensee should establish and document the criteria for
- *
,
'
-acceptable institutionalization for use by the individuals during the
'
validation process.
The licensee is requested to provide a respon;e i
as to what actions will De taken to define'the> criteria required to'
-
' nstitutionalize an item.
This item remains-open pending issuance of
!
i c
the criteria by the licensee and a review of the criteria by an
,
,
inspector.
(285/8937-02)
,
,
,
,
U Once the institutionalization criteria have been established, the
,
> licensee should revalidate ^all SEP-items that were previously
,
completed to ensure t.dequate institutionalizatica n&d.been pe= formed.
'
,
'As discussed in paragrapt. 2.e of this report,.the licensee f
estahlished a tracking system to ensure that all weaknesses-
.
/
identified during the validation process were formally addressed by
.
the individual responsible for implementation of the SEP itene.
However, the' inspector no'ted a problem,where an SEP-item had not been
.
.~ properly institutionalized and no rction item was entered'into the
"
- tra-king system.
For this reason, it appeared the' revalidation of
~
-
ff,
the institutionalization of all completed SEP items is appropriate.
.
-
~ The licensee is requested to pNvide a response as to what actions'
,
.
will be.taken to revalidate the completed SEP items for l
institutionalization.
This, item remains open pending verification of L
the proper institutionalization of the SEP items by the licensee and lj
' review of the licensee's actions by an inspector.3 (285/8937-03)
I, c.
The inspector' reviewed the status of the V&V process for SEP Item 63,
.,
'
lA
" Complete Safety-k A ted Vendor Manual Upgrade Project," and noted
'
- that the licensee had statused the item to the NRC as closed.
The
"
/
scope of work for this item contained a Phase I and Phase II/ work scope that identified 1pecific actions that would'be completed by the
,
,
licensee.. During review of the item, the inspector.noted that
p Phase I'had been completed; however, it appeared that Phase'II had L+t'
not been completed.
Based on the documentation reviewed by the
'
inspector, it appeared that'the scope.of work centained in Phase 11
'
would not be completed until approximately 1991.
s It is requested that the licensee provide a response to this apparent inconsistency between reporting to the NRC that SEP Item 63 had been
-
completed, and documentation indicating that the Phase II work scope
r, may not have been completed.
The response should alsv contain a discussion of the licensee's review of other items to verify that the
}
item status provided to the NRC is accurate.
This item remains cpen
"
pending the'ireceipt of a response from the licensee and a review of the response by an inspector.
(285/8937-04)
,
[
d.
The inspector reviewed SEP Item 60, ")mprove Controls Over pa" Surveillance Test Program." and noted that the scope of work for the
,
'
.
n j
e
.
4'
.'
j b....#
i
,
,
'
.
p;
,, '
-
,-
,
S'
'
j
..
j.
s
,
,c
..n
- -
.
,
,
'
)i
- ..~
.
h. u:
.
-5-
'
i
!
'
~
-
item. appeared to have been changed.
In response to an NRC
'
'C Operational Safety Team Inspection, the licensee added to the scope
of work toJinclude~an action to. revise Procedure 50-G-7, " Operating
,
Manual," to address. the requirements for verbatim compliance, i
The' inspector;noted. during review of this item, that the individual-
performing the verification and the' individual performing the
,
validation'had not been informed of the change in;the work scope.
.i
,
t4nsequently, the portion of the : cop'e of work related to verbatim
'
compliance was'not verified or validated.
)
.
'
-
It is requested that the licensee provide a response to this item I
discussing what actions will be taken to ensure that a proper verification and' validation is performed when the work scope of an a
fEP' item has been revised. The response should'also include a l
discussion of the' review performed by the licensee to identify other
!
items where the work scope has changed, if any, and how the items j
will be properly verified and validated.
This is considered an open
-
item pending receipt of 1.he licensee's response and review of the t
'
response by an. inspector.
(285/8937-05)'
e.
The licensee's validation process was established'to provide an
)
independent review of the verification performed by the designated
'
responsible. individual.
The validation function provides the-licensee assurance that the individual has completed all'the action j
items co.ntained'in the work scope for the SEP item.
,
,
a The validation:of the SEP items was performed by QA or the licensing I
organization. QA was c.ssigned the items that involved hardware
.
'
s
,
,
?
- issues and licensing was assigned the items that involved software l
-
issues.. Since QA was. assigned responsibility for verification of j
-
'J'
three items, licensing was designated as the appropriate. group to validate.the items.
<;
a,
,
s
,
'S
'
'
'
'
During the validation process, the individual performing the
validation. activities may identify weaknesses in the implementation
'
of the work. scope actions.
If weaknesses are identified, the
,
,
,
'
.
individual performing the validation is required to document the
weakness and enter the weakness in the licensee's action item
,
'
5i
.q.
tracking system.
Once the item has been entered into the system, the
h.g waakness is fo warded to the responsible individual for review.
.
q The licensee has identified SS weaknesses in the tracking system for review by the responsible, indivictual.
During review of the iweaknesses, the inspector' identified the following:
,
,
(1) The licensee has.not taken a proactive approach to keeping the
,
NRC informed on the significance and types of weaknesses being identified during the validation process.
,
,
'
'
k
'
,{
y J
)
i
(,,..
'
I
1
,
-
r l
>
J
'
-6-i m
,
e
.
b a.
'
,
,
(2)- The licensee has not' estab11shed a program to adarcss how the
weaknesses will be reva11 dated to ensure that the actions l
?
i'
required to be taken by the assigned individual have been
,
properly completed.
'
It.is requested that theilicensee provide a response to the concerns
,
identified by the inspector, as discussed above. This is considered
an open. item pending receipt of the licensee's response and review by
!
-
.an inspector.
(285/8937-06)
The licensee perfomed a review of all 96 weaknesses identified to
-
, 1 date. The licensee initiated the review of the weakness due to
!
concerns identified by the inspector of the relatively large number
-
of weaknesses. The review indicated that the majority of the -
"
weaknesses rolated to relatively minor problems such as the-individual ~ not signing Form FC-1077, " Certification of Accurac/," or
!
-
the institutional 1 ration of the item not b31ng completed.
~
,.
Form FC-1077 was required to be signed by the individual assigned the
!
'
verification of an item as a certification that the item had been fully completed.- The licensee identified 23 weaknesses that were
!
significant. The weaknesses were classified'as significant because the SEP actions were not completed or the SEP work scope was not met.
The licensee stated that a QA deficiency report (DR) would be issued for each significant weakness identified. The DR process is being
used since the process had been fully procedurait ad.
-
It is requested that the licensee provide i response that discusses
the significant weaknesses'that were identified and the actions that E
'
L will be taken to correct the weaknesses. This is considered an open
item pending receipt of the licensee's response and a review of the
-
l r proposed actions to be taken to. resolve the weaknesses by an inspector.
(285/8937-07)
L
-
.
'
i L
'
The inspector did note that the validation activities' performed by QA
'
and the-licensing-organization were generally vey,ood.
It appeared
,
1-that the validation review was performed in a professional manner.
f.
The inspector reviewed records to verify that the appropriate
/
individuals had been provided training in the validation process.
The inspector also reviewed the lesson plans used for the training
!
sessior.s for adequecy. The licensee stated that training had been given in the verification process, but the inspector did not '.tview L
>
b the records for this training,
.
,
During review of this item, the inspector noted no problems other.
,
than the problem discussed in paranraph 2.b related to establishing
.
E acceptance criteria for institutionalization, end providing -
l instruction of the criteria to personnel involved in validation 1:
activities.
'
<
'
'
'
1, l
l4
- i-
- c
'
'
N
.
.
c
- -. -.
.
-
-
~
r
,
[h
,ap
J
'
J
^
]
,
t.ni f s,:
'
,s i$ ?
-
A J
,
-,
- '
,
'
i
,
x q
,
j
'
<
Overall, it appear'ed, based on'the assessment performed by the inspector,
.
that the licensee was implementing an adequate V&V process.
Based on the 3'
. limited' sample of items reviewed by-the inspector,-it appeared that the licensee needed to provide additional attention to the details of the V&V
.
process to ensure that the types of concerns identified by the inspector
.j x
?>
are identified and. corrected by the licensee.
The licensee should take a
,more proactive role in informing the NRC on the status of the weaknesses.
being' identified dLring the validation process.
The lack of a
~
,
proceduralizid program to address the V&V process, the failure to.
,
establish acceptance criteria for an acceptable method for
'
institutionalization, and the failure to establish an' appropriate method
for the validation of ider.tified weaknesses are of concern to. the'NRC.
Of
-
- particular ~ concern to the NRC is the relatively large number of significant weaknesses that' were-identified by the licensee, f One notable aspect of the V&V process was the professional approach used by QA and the licensing organization during the performance of the validation process.
l l
,
3.
Exit ~ Interview
"
Thefinspector met with Mi K. J. Morris,'(Division Manager, Nuclear
'
"
s Operations) and other: members of the licensee staff-on October 20,1989.
,
l The meeting attendees are listed in paragraph 1 of this inspection report.
,
lAt this meeting, the inspector summarized the scope of the assessment and E
i the-findings.
During the exit meeting, the licensee did not identify any
'
ct'
l 'o proprietary information to the inspector.
.
,
'y'
,
x
.
l
Tv
>
i i '
4.
A s
%
.z-y
.
h, s
'
C'
,g
,
,
,
,
l4 a
p a.
-
,
I l
<
P P
t b
$
!
'
ms a
q.
' ?, e -
' -
<--
.
.
.