Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in IE Insp Repts 50-282/79-21 & 50-306/79-18
ML19253C508
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 11/30/1979
From: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Wachter L
NORTHERN STATES POWER CO.
Shared Package
ML19253C509 List:
References
NUDOCS 7912050667
Download: ML19253C508 (1)


Text

t p* 8f 0 UNITED STATES

NUCLEAR REGULATORY COMMISSION f',,f

[

P o

REGION ill

,

799 ROOSEVELT ROAD

[

GLEN ELLYN, ILLINOIS 6013 7 HOV30 E Docket No. 50-282 Docket No. 50-306 Northern States Power Com,,a.1y ATTN:

Mr. Leo Wachter Vice President Power Production and System Operation 414 Nicollet Mall Minneapolis, MN 55401 Gentlemen:

Thank you for your letter dated October 31, 1979, informing us of the steps you have taken to correct the noncompliance identified in our letter dated October 9, 1979.

_

With respect to your response to Infraction 2, we understand that on November 21, 1979 your site representatives stated that within 20 days you will provide us with tta date that total implementation of corrective actions will be achieved relating to the collection, con-version, storage, and maintenance of records. We will exm.ine your corrective action during a future inspection.

Your cooperation with us is appreciated.

Sincerely, R. F. Heishman, Chief Reactor Operations and Nuclear Support Branch cc:

Mr. F. P. Tierney, Jr.,

Plant Manager cc w/1tr dtd 10/31/79:

Central Files Reproduction Unit NRC 20b PDR Local PDR 1503 346 NSIC TIC John W. Ferman, Ph.D.,

Nuclear Engineer, MPCA 7912050b3