IR 05000263/2025002

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000263/2025002
ML25218A046
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 08/06/2025
From: Dariusz Szwarc
NRC/RGN-III/DORS/RPB3
To: Hafen S
Northern States Power Company, Minnesota
References
IR 2025002
Download: ML25218A046 (1)


Text

SUBJECT:

MONTICELLO NUCLEAR GENERATING PLANT - INTEGRATED INSPECTION REPORT 05000263/2025002

Dear Shawn Hafen:

On June 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Monticello Nuclear Generating Plant. On July 16, 2025, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Dariusz Szwarc, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket No. 05000263 License No. DPR-22

Enclosure:

As stated

Inspection Report

Docket Number:

05000263

License Number:

DPR-22

Report Number:

05000263/2025002

Enterprise Identifier:

I-2025-002-0058

Licensee:

Northern States Power Company, Minnesota

Facility:

Monticello Nuclear Generating Plant

Location:

Monticello, MN

Inspection Dates:

April 01, 2025, to June 30, 2025

Inspectors:

Z. Fleming, Project Engineer

T. Hartman, Senior Resident Inspector

C. Norton, Senior Resident Inspector

S. Orth, Senior Health Physicist

E. Rosario, Trans & Storage Safety Inspector

Approved By:

Dariusz Szwarc, Chief

Reactor Projects Branch 3

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Monticello Nuclear Generating Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

The unit began the inspection period at full achievable power as they were coasting down toward the refueling outage. The following power changes were performed during the inspection period:

  • On April 2, 2025, the licensee reduced power to approximately 83 percent power for a routine rod pattern adjustment. Power was subsequently restored to full achievable power the same day.
  • On April 3, 2025, the licensee reduced power to approximately 85 percent to clean the main condenser tubes. On April 4, 2025, the licensee increased power to full achievable power.
  • On April 9, 2025, the licensee reduced power to approximately 76 percent for a routine rod pattern adjustment. Power was subsequently restored to full achievable power the same day.
  • On April 18, 2025, the licensee shutdown the unit and began refueling outage 32.
  • Following completion of the refueling outage, the reactor was restarted and taken to critical on May 24, 2025. The unit reached full power operation on May 27, 2025.
  • On June 1, 2025, the licensee commenced a shutdown to replace the C safety relief valve. The licensee restarted the reactor and reached approximately 30 percent power on June 4, 2025. The licensee held power steady at around 30 percent until June 9, 2025, when they increased power to 100 percent.

The unit remained at or near 100 percent power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of summer temperatures for emergency diesel generators (EDGs) and safety-related bus 15

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk significant systems from impending severe weather including lightning and tornado watch on May 15, 2025

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Division 2 control room ventilation/emergency filtration train (CRV/EFT) system on April 8, 2025
(2) Division 1 EDG starting air system on May 15, 2025
(3) Reactor core isolation cooling (RCIC) system on May 20, 2025
(4) Control rod drive hydraulic control units, banks 1 and 4 on May 21, 2025

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the standby liquid control system on May 20, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone (FZ) 17, turbine building north cable corridor 941' on April 2, 2025
(2) FZ 16, corridor, turbine building east & west (elevations 911' and 931'),

on April 3, 2025

(3) FZ 9, control room on April 4, 2025
(4) FZ 2B, east hydraulic control unit (HCU) area on April 7, 2025
(5) FZ 19C, feedwater pipe chase on April 9, 2025

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an announced fire drill on April 6, 2025

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated internal flooding mitigation protections outside the lower 4kV room

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Main condenser during dredging of service water intake bay on April 07, 2025

71111.08G - Inservice Inspection Activities (BWR)

BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01)

The inspectors evaluated boiling-water reactor nondestructive testing, flaw evaluation, and welding activities by reviewing the following examinations from April 21, 2025, to May 22, 2025:

(1)

1. Visual examinations of reactor recirculation (RR) seismic support and restraint

for component identifications (IDs): H6, H10, and H11

2. Visual examinations of main steam (MS) valve internal surfaces and bolts

for component IDs: V4 and B8

3. Visual examinations of the reactor vessel internals associated with the

InVessel Visual Inspections (IVVI)

4. Relevant indication to BWRVIP18 Rev. 2A accepted for continued service

on pipe to junction box weld of core spray piping component ID: CSP-P3a

5. Ultrasonic examination of the RR pipe-topipe weld component IDs:

W23 LS U and W30 LS U

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during control rod pattern adjustment on April 2, 2025

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated just in time training (JITT) for reactor startup and reactor vessel pressure test in the simulator on April 15, 2025

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Drywell structure walkdown during refueling outage on April 24, 2025
(2) Licensee actions after failure to schedule monthly division 2 diesel generator surveillance test outside the division 1 emergency bus maintenance window on April 29, 2025
(3) Removal of load test cart for Y81 inverter replacement on May 05, 2025

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) Work Order 7001285290075, Replacing safety-related 200 Amp fuse with 150 Amp fuse on April 30, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Secondary containment reactor building equipment hatch operation on April 03, 2025
(2) Failure of Division 2 control room ventilation recirculation fan damper to modulate on April 08, 2025
(3) Torus instrument air isolation valve exercise on April 08, 2025
(4) Control rod drive (CRD) changeout on May 03, 2025
(5) Planning and risk management of manually backseating high pressure core injection (HPCI) inboard isolation valve (MO2034) on May 20, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1)

===501000096997, VD9175B not functioning properly (2)501000096788, Recirculation inboard sample valve failed diagnostic test (3)501000099278, Alternate N2 relief valve leaking

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

=

The inspectors evaluated the following temporary or permanent modifications:

(1) For over 90 days, HPCI pressure gauge PI23117 not reading properly and is compensated by a temporary flow meter for the purpose of ensuring the line is full of water
(2) Placement of a jumper to temporally allow opening the RR system out board sample valve while a Group 1 Isolation signal is inserted

Severe Accident Management Guidelines Update (IP Section 03.03) (1 Sample)

(1) The inspectors verified the site Severe Accident Management Guidelines were updated in accordance with the BWR generic sever accident technical guidelines and validated in accordance with NEI 14-01, Emergency Response Procedures and Guidelines for Beyond Design Basis Events and Severe Accidents, Revision 1.

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (2 Samples)

(1) The inspectors evaluated refueling outage activities for RFO32 from April 18, 2025, to May 23, 2025.
(2) The inspectors evaluated forced outage FO3301 to replace the C safety relief valve from June 1, 2025, to June 3, 2025.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (17 Samples)

(1) Work Order (WO) 7001360850070, A reactor protection system (RPS)

MG set after installation of temporary power supply modification on April 1, 2025

(2) WO 7001285290095, Load test after Y81 inverter replacement on May 04, 2025
(3) WO 7000409790020, EDG 11 governor after replacement on May 4, 2025
(4) WO 7001140080020, Emergency service water pump 11, following preventive maintenance on May 4, 2025
(5) WO 7000725210050, Stack gas dilution fan inlet damper, following preventive maintenance on May 5, 2025
(6) WO 70012072220040, RCIC steam line inboard isolation valve, MO2075, following preventive maintenance on May 5, 2025
(7) WO 7000409790020, EDG 11 governor after second replacement on May 06, 2025
(8) WO 7000770560140, EDG 11 voltage regulator after replacement on May 06, 2025
(9) WO 7001418960030, Recirc sample line inboard isolation valve, MO2790, following preventive maintenance on May 08, 2025
(10) WO 7001134250020 PMT of core spray pump 11 discharge check valve after maintenance on May 9, 2025
(11) WOs 700090273005, 700135316100, and 700113996040 Stroke timing division 1 LPCI inboard injection valve for partial PMT following maintenance on May 9, 2025
(12) Various WOs, Final PMTs of control rod drives following maintenance that included drive replacements and HCU hydraulic control unit maintenance on May 13, 2025.
(13) WO 7001224820070, Control rod drive timing test after CRD replacements on May 13, 2025
(14) WO 7001380240110, Inboard main steam isolation valve local leak rate testing on May 13, 2025
(15) WO 7001208290040, HPCI outboard isolation local leak rate testing after maintenance on May 14, 2025
(16) WO 7001207010020, Outboard main steam isolation valve (MSIV) 11 after maintenance on May 14, 2025
(17) WO 7001207530030, Drywell personnel airlock interlock test after interlock restoration on May 23, 2025

Surveillance Testing (IP Section 03.01) (4 Samples)

(1)0003, Drywell high pressure scram and group 2, 3, & SCTMT isolation test and calibration on April 14, 2025 (2)

===013702-06, Primary containment double-gasketed seals local leak rate testing (LLRT) on April 28, 2025 (3)013727, Transversing incore probe (TIP) system isolation valves pressure and LLRT on April 28, 2025

(4) OSP-RHR0564, LPCI swing bus test on May 7, 2025 Inservice Testing (IST) (IP Section 03.01)===

(1)0214, Drywell-tosuppression chamber vacuum breaker cycle pressure and leakage test, on May 23, 2025

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) Outboard main steam isolation valves A and B LLRT on April 19, 2025

Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)

(1) WO 7001205450035, Portable fire pump operation on April 29, 2025

71114.06 - Drill Evaluation

Required Emergency Preparedness Drill (1 Sample)

(1) Hostile action based drill on June 17,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels, identifies the concentrations and quantities of radioactive materials, and assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1) Workers exiting the radiologically controlled area (RCA)
(2) Workers exiting the drywell access point

Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)

The inspectors evaluated the licensees control of radiological hazards for the following radiological work:

(1)

1R32 - Torus - diving - inspect/clean (RWP 255119) and associated as low

as reasonably achievable (ALARA) plan (2)

1R32 - Reactor water cleanup (RWCU) E201C heat exchanger (HX) repair

(RWP 255121) and associated ALARA plan (3)

1R32 - RWCU - Replace drain pipes & RC valve (RWP 255126) and associated ALARA plan (4)

1R32 - Drywell (DW) CRD changeout (RWP 255509) and associated ALARA plan

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)

The inspectors evaluated licensee controls of the following high radiation areas and very high radiation areas:

(1) Reactor building 935' TIP cubicle (Door 60)
(2) Reactor building 935' drywell access area
(3) Material stored within the spent fuel pool (control of suspension lines)

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)

(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.03 - InPlant Airborne Radioactivity Control and Mitigation

Temporary Ventilation Systems (IP Section 03.02) (2 Samples)

The inspectors evaluated the configuration of the following temporary ventilation systems:

(1) Reactor building 1027' reactor head stand
(2) Reactor building 962' reactor water cleanup area

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees use of respiratory protection devices.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures Sample (IP Section 02.04)===

(1) April 01, 2024, through March 31, 2025 BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (1 Sample)
(1) May 01, 2024, through March 31, 2025

BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)

(1) April 01, 2024, through March 31, 2025

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) May 01, 2024, through March 31, 2025 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) May 01, 2024, through March 31, 2025

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Licensee failure to promptly identify portions of the reactor pressure vessel (RPV)exceeded the limiting cooldown rate specified in the Pressure Temperature Limits Report
(2) The licensees inability to manually open rollup doors of FLEX buildings

INSPECTION RESULTS

Observation: Corrective Actions to Address Procedural Deficiencies in Monitoring Reactor Pressure Vessel Cooldown Rates 71152A On February 28, 2024, following a reactor scram accompanied by a trip of the recirculation pumps, the licensee did not promptly identify that the reactor vessel (RPV) bottom exceeded the limiting cooldown rate specified in the pressure temperature limits report. As a result, the licensee did not complete the required technical specification action to determine if the reactor coolant system was acceptable for continued operation prior to starting the reactor and progressing to Mode 1. A non-cited violation for this issue was documented in Inspection Report 2024002. The inspectors selected this sample to follow up on the licensees corrective actions in response to the issue.

The licensee subsequently determined that procedure 0118, Reactor Vessel Temperature Monitoring, utilized a computer program that monitored only RPV belt line temperature during cool down but did not account for the RPV temperature stratification that occurs without recirculation. Corrective actions included modifying procedure 0118 to monitor temperatures for the entire RPV and display the point with the highest cool down rate.

On April 19, 2025, the inspectors observed the licensee cool down the RPV for RFO 32 utilizing the revised 0118. The cool down rate for all points on the RPV was monitored and the point with the highest cooldown rate prominently displayed. The inspectors identified no issues of concern associated with the licensees corrective actions.

Observation: Corrective Actions to Address Inability to Manually Open FLEX Building Doors 71152A On November 17, 2021, the licensee identified that the rope used to manually open the rollup doors of the FLEX building was missing. During loss of offsite power or station blackout, the inability to quickly open the rollup doors manually could hinder the ability to use the FLEX equipment as designed. The inspectors selected this issue as a sample based on the importance of the FLEX equipment and the strategies that could potentially be impacted by the identified issue.

Corrective actions included replacing the rope used to manually open the doors, as well as modifying OSP-FIR1489, B.5.B/FLEX Equipment Inventory, to include verification of the ability to manually open the rollup doors.

On April 29, 2025, the inspectors observed an inventory of FLEX equipment and verified the presence of the rope and the use of the updated inventory sheet. The inspectors identified no issues of concern and assessed that the corrective actions were adequate.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 16, 2025, the inspectors presented the integrated inspection results to S. Hafen, Site Vice President, and other members of the licensee staff.
  • On April 24, 2025, the inspectors presented the radiation protection inspection results to S. Hafen, Site Vice President, and other members of the licensee staff.
  • On May 22, 2025, the inspectors presented the inservice inspection activities for Monticello M1R32 outage inspection results to S. Hafen, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

OWI01.01

Operations Group Organization and Responsibility

Assignments

2000034760

1444, Pre and Post Severe Weather Inspection Checklist

7001349890010

1150, Summer Checklist

71111.01

Procedures

A.6

Act of Nature

Corrective Action

Documents

Resulting from

Inspection

501000099079

RCIC Barometric Cond Insulation Damage

05/20/2025

NH170037

Main Control Room CRV/EFT System

Drawings

NX92164

Monticello Nuclear Generating Plant Air Starting System

E

215407

Standby Liquid Control System Prestart Valve Checklist

215413

RCIC System Prestart Valve Checklist

71111.04

Procedures

215437

Control Rod Drive System Prestart Valve and Hydraulic

Control Unit Checklist

STRATEGY

A.302-B

Fire Zone 2B, East HCU Area

STRATEGY

A.309

Fire Zone 9, Control Room

STRATEGY

A.316

Fire Zone 16, Corridor, Turbine Building East & West

(Elevations 911' and 931')

STRATEGY

A.317

Fire Zone 17, Turbine Building North Cable Corridor 941'

STRATEGY

A.319-C

Fire Zone 19C, F.W. Pipe Chase

Fire Plans

STRATEGY

A.343

Fire Zone 43, Compressed Air Building

71111.05

Miscellaneous

A.343

Fire Brigade Drill Guide, 17 Compressor B Cooling Pump

Motor Fire, Drill Guide 43.01

04/06/2025

71111.06

Procedures

Ops Man

B.09.0605

G.15. Operation of the HELB Flood Barrier Lower 4kV

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Engineering

Changes

EC

6030000001641

DBD-S.04 Intake Structure

25PM

East Service Water Bay Inspection/Dredging

71111.07A

Procedures

26PM

West Service Water Bay Inspection/Dredging

501000097684

Light Particulate Inside Reactor Vessel

04/23/2025

501000097737

Bent Lift Tab on Jet Pump 15 WD1

04/25/2025

501000097771

Welded Attachment Drawing Discrepancy

04/25/2025

501000097842

RFO32 IVVI Indication: Core Spray P3a

04/25/2025

Corrective Action

Documents

501000097996

RFO32 IVVI Indication: TGGB

04/29/2025

Drawings

PEI01.02.04

Recirculation Loop A ISI Isometric Drawings (Figure 5.2)

MN25UT-003

Ultrasonic Examination of RR Pipe-toPipe Component ID:

W23 LS U

04/24/2025

MN25UT-004

Ultrasonic Examination of RR Pipe-toPipe Component ID:

W30 LS U

04/24/2025

MN25VT-013

Visual Examination (VT3) of RR Clevis, Lugs, and

Constant-Support Component ID: H6

04/25/2025

MN25VT-014

Visual Examination (VT3) of RR Sway Brace Component

ID: H11

04/25/2025

MN25VT-015

Visual Examination (VT3) of RR Double Spring and Lugs

Support Component ID: H10

04/25/2025

MN25VT-016

Visual Examination (VT1) of MS Valve Bolts Component ID:

B8

04/26/2025

MN25VT-017

Visual Examination (VT3) of MS Valve Internal Surfaces

Component ID: V4

04/26/2025

NDE Reports

MN25VT-028

Visual Examination (VT1) of New MS Valve Bolts

Component ID: B8

05/01/2025

FPPE-NDE402

Ultrasonic Examination of Austenitic Pipe Welds

PDI-UT2

Generic Procedure for the Ultrasonic Examination of

Austenitic Pipe Welds

J

71111.08G

Procedures

PEI02.05.05

Vessel Examination of Monticello Reactor Vessel Interior

71111.11Q

Miscellaneous

SEG MTLOR-

JIT20250025

Startup JITT

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SEG MTLOR-

JIT20250115

Reactor Vessel Pressure Test

2300

Reactivity Adjustment

28A

Procedures

C.205

Power Operation

84C

Engineering

Evaluations

MT2025EDG06

Stride to Extend the Emergency Diesel Generator (EDG)

Monthly Test Frequency

04/30/2025

3487

Drywell Entry Checklist

Procedures

FPOP-SFCP01

Surveillance Frequency Control Program

Radiation Work

Permits (RWPs)

255500

1R32 - DW GENERAL ACTIVITIES

04/24/2025

7001285290075

Replace 200A Fuse With 150A Fuse

04/30/2025

71111.12

Work Orders

7001285290095

Y81 Inverter Replacement

501000096997

VD9175B Not Functioning Properly

04/07/2025

Corrective Action

Documents

501000098321

Incorrect information on 2270

05/04/2025

NH170037

Main Control Room CRV/EFT Systems

Drawings

NH170037

Main Control Room CRV/EFT System

Miscellaneous

Operating Instruction Placard for Railroad Doors in Reactor

Building

04/03/2025

25517-IA1

Instrument Air System Valve Exercise

270

Critical Safety System Checklist

3487

Drywell Entry Checklist

2000038003

9309, Changeout Selected CRDs - Maintenance

9007

Procedure for Moving Fuel Into, Out of, and Within the Core

FPIH-SAF01

Heat and Cold Stress Control Guidelines

Procedures

Ops Man D.205

Reactor and Core Components Handling Equipment

71111.13

Work Orders

7001401230040

HPCI Steam Line Isolation Inboard, Manually Backseat

Valve for 900# Inspection

501000087225

MO 2012 Failed to Cycle as Expected

06/28/2024

501000094127

MO 2012 Past Operability

04/03/2025

501000096788

Recirculation Inboard Sample Valve Failed Diagnostic Test

04/02/2025

501000096997

VD9175B Not Functioning Properly

04/07/2025

71111.15

Corrective Action

Documents

501000099278

Alt N2 Relief Valve Leaking

05/26/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

Resulting from

Inspection

501000099416

Calculation Error in AN2 Leak Analysis

05/29/2025

501000093404

HPCI Pressurizing Station Low Pressure

2/17/2024

Corrective Action

Documents

501000096952

104701 50.59 Review Required

04/04/2025

Drawings

NH36250

P&ID (Water Side) High Pressure Coolant Injection System

71111.18

Procedures

8154, page 90

Installation of Electrical Jumpers/Block to Allow Stroking of

MOVs

25520-IIC1

Reactor Coolant Pressure Boundary Leakage Test

2167

Plant Startup

2

204

Plant Shutdown

270

Critical Safety System Checklist

267

Tension RPV Studs

Procedures

292

Clean Reactor Pressure Vessel Head Flange And replace

ORings

71111.20

Self-Assessments 602000022178

QF1123, Shutdown Safety Assessment Contingency

Planning Form

Corrective Action

Documents

501000098076

FLEX Equipment Missing

04/30/2025

Corrective Action

Documents

Resulting from

Inspection

501000098031

Inconsistent Guidance in 0137 Procedure

04/29/2025

Drawings

NX783467-7

Reactor Protection System

Engineering

Evaluations

2000027874

QF0957, IST Evaluation / 96 Hour Evaluation / Rebaseline

05/08/2025

0003

Drywell, High Pressure Scram and Group 2, 3, & SCMT

Isolation Test and Calibration Procedure

0074

Control Rod Drive Exercise

0075

Control Rod Drive Coupling Test

71111.24

Procedures

013702-06

X35A, X35B, X35C, X35D & X35E Primary Containment

Double-Gasketed Seals Local Leak Rate Test

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

013707A

Reactor Steam Supply Valves Leak Rate Testing

013727

TIP System Isolation Valves Pressure and Local Leak Rate

Test

214

Drywell-toSuppression Chamber Vacuum Breaker Cycle

Pressure and Leakage Test

25503-IA11

Core Spray Loop A Quarterly Pump and valve Tests

25507-IA2

Main Steam Isolation Valve Functional Checks Test

22

CRD-Withdrawal Stall Flow Test

1054

Control Rod Drive Normal Drive Timing Test

27

CRD-Insert Stall Flow Test

417103-PM

Off Gas Dilution Fan Damper Position

2000010244

456102-OCD, Uninterruptible Power Supply Inverter (Y81)

9019

Changeout Selected CRDs - Operations

9051

Changeout Selected CRDs-Operations

B.08.0805

Emergency Diesel Generator Start Up

B.09.1205

Reactor Protection Power Supplies

ESP-

MST013707E

Reactor Steam Supply Valve Line Leak Rate Test

G4A

RPS MG Set 480 VAC Supply

NSP-MSC0137F

LLRT-LRM-Makeup Flow Method (Graftel 96237)

NSP-

MSC0137G

LLRT-LRM-Makeup Flow Method (Graftel EV)

OSP-RHR0564

LPCI Swing Bus Test

7000409790020

Emergency Diesel Generator Governor PMT

7000725210050

Stack Gas Dilution Fan Inlet Damper, VD8000J29

Post-Maintenance Test

7000770560140

EDG Voltage Regulator Replacement

7001140080020

Emergency Service Water Pump Discharge

Check Valve PMT

7001205450035

Use P505 Portable Fire Pump to Pressurize Fire Header

04/27/2025

7001207010020

OTBD MSIV

70012072220040

RCIC Steam Line Inboard Isolation, MO 2075

Work Orders

7001207530030

0447, Primary Containment Personnel Airlock Interlock Test

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

7001208290040

HPCI Steam Line Isolation Outboard

7001224820070

Master PMT for CRD

05/13/2025

7001285290095

Y81 Inverter Replacement

700135316

PMT RHR DIV 1 LPCI INJ INBBD

7001360850070

Monticello Nuclear Generating Plant PMT/RTS Instructions

700138018

Repack AO280D

05/13/2025

7001380240110

Disassemble and Reassemble AO280A

05/03/2025

7001418960030

RECIRC SX LINE INBD ISOL

71114.06

Miscellaneous

6/17/25 HAB Drill

Controller Guide

Full Scale Practice Drill

RWP 255119

Torus Dive and Filter Transfer Activities

RWP 255121

RWCU HX E201C Repair

RWP 255126

RWCU HX Drain Line & RC Valve Replacements

ALARA Plans

RWP 255509

Control Rod Drives Changeout

501000090824

Elevated Dose Rates for Upcoming Work

10/07/2024

501000096909

Adverse Trend in RP Performance

04/04/2025

Corrective Action

Documents

501000097618

Trend in Radworker Performance

04/23/2025

501000097641

Three ARGOS Exit Gates Locks

04/23/2025

Corrective Action

Documents

Resulting from

Inspection

501000097946

Dose Measurement Set Points Higher

04/29/2025

Procedures

FPRP-SEN02

Radiological Work Planning and Controls

255119

1R32 - Torus - Diving - Inspect/Clean

255121

1R32 - RWCU E201C HX Repair

255126

1R32 - RWCU - Replace Drain Pipes & RC Valve

Radiation Work

Permits (RWPs)

255509

1R32 - DW CRD Changeout

71124.01

Work Orders

700152706

TBNWS Rad Mon High Alarm

03/23/2025

Reactor Chemistry Results

2/03/2024

Reactor Chemistry Results

03/11/2025

Reactor Chemistry Results

03/19/2025

71151

Miscellaneous

Monticello Nuclear Generating Plant - 2024 Annual Dose

Summary

04/01/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Monticello Nuclear Generating Plant - 2025 Annual Dose

Summary

04/01/2025

Electronic Dosimeter Transaction Log (>100 mrem Entries)

04/21/2025

QF0445

Safety System Functional Failures (April 01, 2024, through

March 31, 2025)

QF0445

RCS Leakage (April 01, 2024, through March 31, 2025)

Corrective Action

Documents

501000058393

FLEX Building Equipment

11/17/2021

Miscellaneous

2000036059

OSP-FIR1489, B.5.B/FLEX Equipment Inventory

71152A

Procedures

0118

Reactor Vessel Temperature Monitoring

25