IR 05000261/1991028

From kanterella
Jump to navigation Jump to search
Insp Rept 50-261/91-28 on 911210-920113.No Violations or Deviations Noted.Major Areas Inspected:Operational Safety Verification,Surveillance Observation & Maint Observation
ML14178A184
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 01/17/1992
From: Christensen H, Garner L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14178A183 List:
References
50-261-91-28, NUDOCS 9202050036
Download: ML14178A184 (6)


Text

rEcGy UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, ATLANTA, GEORGIA 30323 Report No.:

50-261/91-28 Licensee:

Carolina Power and Light Company P. 0. Box 1551 Raleigh, NC 27602 Docket No.:

50-261 License No.: DPR-23 Facility Name: H. B. Robinson Inspection Conducted: December 10, 1991 - January 13, 1992 Lead Inspector: >2.

,

,,

,<

/ /7172!

L. W. Garner, Senior R eiit nspector Date Signed Other Inspectors: M. D. Hunt, Reactor Engineer K. R. Oury, Resident Inspector Approved by:

-7/

4 v. Christensen, Section Chtied ate igned Division of Reactor Projects SUMMARY Scope:

This routine, announced inspection was conducted in the areas of operational safety verification, surveillance observation, and maintenance observatio Results:

There were no violations or deviations identifie The routine involvement of system engineering in facilitating repair of malfunctioning control room instrumentation and related equipment was considered a good practice, paragraph PDR ADOCK 05000261 G

PDR

REPORT DETAILS 1. Persons Contacted

  • C. Baucom, Senior Specialist, Regulatory Compliance
  • R. Beverage, Manager, Quality Control
  • W. Biggs, Manager, Nuclear Engineering Department Site Unit
  • R. Chambers, Plant General Manager, Robinson Nuclear Project T. Cleary, Manager - Balance of Plant Systems and Reactor Engineering, Technical Support D. Crook, Senior Specialist, Regulatory Compliance C. Dietz, Vice President, Robinson Nuclear Project R. Femal, Shift Supervisor, Operations
  • W. Gainey, Manager, Plant Support
  • J. Kloosterman, Manager, Regulatory Compliance D. Knight, Shift Supervisor, Operations A. McCauley, Manager - Electrical Systems, Technical Support R. Moore, Shift Supervisor, Operations
  • A. Padgett, Manager, Environmental and Radiation Control
  • M. Page, Manager, Technical Support
  • R. Prunty, Manager, Robinson Licensing D. Seagle, Shift Supervisor, Operations
  • R. Smith, Manager, Maintenance
  • V. Smith, Nuclear Assessment Department W. Stover, Shift Supervisor, Operations
  • A. Wallace, Manager, Operation Coordination D. Winters, Shift Supervisor, Operations Other licensee employees contacted included operators, engineers, mechanics, security force members, and office personne *Attended exit interview on January 14, 199 Acronyms and initialisms used throughout this report are listed in the last paragrap. Operational Safety Verification (71707)

The inspectors evaluated licensee activities to confirm that the facility was being operated safely and in conformance with regulatory requirement These activities were confirmed by direct observation, facility tours, interviews and discussions with licensee personnel and management, verification of safety system status, and review of facility record To verify equipment operability and compliance with TS, the inspectors reviewed shift logs, Operations' records, data sheets, instrument traces, and records of equipment malfunction Through work observations and discussions with Operations staff members, the inspectors verified the staff was knowledgeable of plant conditions, responded properly to alarms, adhered to procedures and applicable administrative controls, cognizant of in-progress surveillance and maintenance activities, and aware of

inoperable equipment statu The inspectors performed channel verifications and reviewed component status and safety-related parameters to verify conformance with T Shift changes were observed, verifying that system status continuity was maintained and that proper control room staffing existe Access to the control room was controlled and operations personnel carried out their assigned duties in an effective manner. Control room demeanor and communications were appropriat Plant tours and perimeter walkdowns were conducted to verify equipment operability, assess the general condition of plant equipment, and to verify that radiological controls, fire protection controls, physical protection controls, and equipment tagging procedures were properly implemente Plant Shutdown Initiated Due To Inoperable BATP On December 24, 1991, at 9:57 a.m.,

a plant shutdown was initiated as required by TS 3.2.3.b. due to an inoperable BAT TS 3.2.3.b. required the unit to be placed in hot shutdown condition utilizing normal operating procedures if a BATP is not restored to operable status within 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> The unit was at 90 percent power when the shutdown commence After the BATP was replaced and successfully tested, the shutdown was terminated at 51 percent power and the TS action statement was exited at 3:59 p.m. The BATP was inoperable due to the pump's motor tripping on thermal overload during routine BAT mixing. Due to the unavailability of a spare motor and pump assembly, one had to be assembled from stock part This evolution was the primary reason for the expiration of the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> allowable out-of-service time, which resulted in the initiation of the plant shutdow Several ACRs were generated as a result of the pump tripping and problems encountered during subsequent troubleshooting and installatio The inspectors will monitor the associated corrective actions during routine ACR review Blue Dots Status The Operations Unit utilizes round blue stickers (blue dots) in the control room to identify malfunctioning instrumentation and plant equipmen The number of blue dots is routinely tracked and associated items are reviewed by a system enginee The routine involvement of system engineering in facilitating repair of equipment associated with blue dots continues to be a good practic The inspectors reviewed the blue dot data base report dated January 2, 199 The report listed 11 items currently available for work, 1 item on maintenance hold, 3 items on engineering hold, 3 items awaiting parts, 12 items available for work during a forced outage, and 6 items requiring a refueling outage to wor Even though maintenance has continuously worked the available items, the number of items has remained in the mid-thirties since early fal The number of items was indicative of an older plant late in an operating cycl No violations or deviations were identifie. Monthly Surveillance Observation (61726, 92701)

The inspectors observed certain safety-related surveillance activities on systems and components to ascertain that these activities were conducted in accordance with license requirement For the surveillance test procedures listed below, the inspectors determined that precautions and LCOs were adhered to, the required administrative approvals were obtained prior to test initiation, testing was accomplished by qualified personnel in accordance with an approved test procedure, the tests were completed at the required frequency, and that the tests conformed to TS requirement Upon test completion, the inspectors verified that the recorded test data was complete, accurate, and met TS requirements; test discrepancies were properly documented and rectified; and that the systems were properly returned to servic Specifically, the inspectors witnessed/reviewed portions of the following test activities:

OST-151 Safety Injection System Component Test OST-401 Emergency Diesels (Slow Speed Start)

OST-101 Chemical and Volume Control System Component Test OST-406 TSC/EOF/PAP Diesel Generator Test EDG KVA Testing Through the review of industry events and NRC Information Notice N,

Inadequate Testing Of Emergency Diesel Generators, the licensee identified that KVA loading capability was not being verified during EDG periodic testing. In response to a similar finding described in IR 91-21, the licensee indicated that applicable test procedures would be revised and EDG KVA loading at nameplate rating (3125 KVA) would be performed by December 9, 199 On December 9, the inspectors observed testing of the A EDG in accordance with revised test procedure OST-40 Testing was performed at or slightly above 3125 KVA. However, during the test the El emergency bus voltage increased by approximately 35 volts to 520 volt The increase in voltage, greater than expected, was attributed to transformer impedance between the emergency bus and the onsite ED Due to the magnitude of the voltage increase, KVA nameplate testing of the B EDG was not performed. Emergency bus E2 routinely operates at 15 to 20 volts higher than El, thus a 35 volt voltage increase could result in unacceptably high voltage on E At the end of the report period, NED was reviewing the issue to determine how and under what plant conditions EDG KVA nameplate testing can be performed. The results of this review will be inspected as part of URI 91-21-09. Until this review is completed, EDG testing will be performed as it had been prior to the above mentioned revisio B EDG Insulation Fire On December 11, 1991, the inspectors observed B EDG monthly surveillance testing. During operation of the EDG, a small fire (lasting approximately 2 minutes before it was extinguished) occurred on the insulating material which surrounds the transition pipe from the exhaust manifold to the turbocharger inlet pip The EDG was shutdown and the fire was investigated by the Operations fire technicia The insulating material had absorbed a small quantity of lube oil from a nearby lube oil lea Apparently, the lube oil was held next to the hot pipe for a sufficient time to allow combustion. The insulation was subsequently removed and the testing was successfully complete The insulating material involved had been recently installed to correct a fire hazard similar to that described abov The previous material had been a fire retardant fabric insulating type material which had also absorbed lube oi This had caused a similar small fire on the A EDG in the same general area in October 199 The insulation involved in the December 11 fire was a metallic covered fabric material which was impervious to lube oi However, to attach the insulation around to the transition pipe, holes were punched in the material. These holes allowed lube oil to enter the insulating material under the metallic liner. Until a suitable insulating material can be procured, this section of exhaust piping will remain uninsulate No violations or deviations were identifie. Monthly Maintenance Observation (62703)

The inspectors observed safety-related maintenance activities on systems and components to ascertain that these activities were conducted in accordance with TS, approved procedures, and appropriate industry codes and standard The inspectors determined that these activities did not violate LCOs and that required redundant components were operabl The inspectors verified that required administrative and testing controls were adhered t In particular, the inspectors observed/reviewed the following maintenance activities:

PIC-103 Electrical Indicators WR/JO 92BUD031 Calibration of PZR PORV Relief Line Temperature Monitors No violations or deviations were identifie. Exit Interview (30703)

The inspection scope and findings were summarized on January 14, 1992, with those persons indicated in paragraph 1. The inspectors described the areas inspected and discussed in detail the inspection result Dissenting comments were not received from the licensee. The licensee did

not identify as proprietary any of the materials provided to or reviewed by the inspectors during this inspectio. List of Acronyms and Initialisms Ante Meridiem ACR Adverse Condition Report BAT Boric Acid Tank BATP Boric Acid Transfer Pump EDG Emergency Diesel Generator EDS Electrical Distribution System EOF Emergency Operating Facility IR

Inspection Report

KVA

Kilovolts-amperes

LCO

Limiting Condition for Operation

NED

Nuclear Engineering Department

NRC

Nuclear Regulatory Commission

OST

Operations Surveillance Test

PAP

Primary Access Portal Post Meridiem

PIC

Process Instrument Calibration

PORV

Power Operated Relief Valve

PZR

Pressurizer

TS

Technical Specification

TSC

Technical Support Center

URI

Unresolved Item

WR/JO

Work Request/Job Order