|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000254/19990011999-10-0707 October 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990721-0908.No Violations Noted.Major Areas Inspected:Initiating Events, Mitigating Sys & Barrier Integrity IR 05000254/19990171999-09-15015 September 1999 Insp Repts 50-254/99-17 & 50-265/99-17 on 990823-27.No Violations Noted.Major Areas Inspected:Pilot Baseline Insp for Annual Review of Changes to Safety Analysis Rept & Biennial Review Permanent Plant Mod IR 05000254/19990161999-09-0909 September 1999 Errata to Insp Repts 50-254/99-16 & 50-265/99-16 Conducted on 990819.Administrative Error Was Corrected on Page 8 of Subj Rept.One Open Item Was Deleted & re-numbering of Two Other Items Were Identified IR 05000254/19990151999-08-25025 August 1999 Insp Repts 50-254/99-15 & 50-265/99-15 on 990816-20.No Violations Noted.Major Areas Inspected:Maint Rule Implementation IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site ML20211D2031999-08-19019 August 1999 Insp Repts 50-254/99-16 & 50-265/99-16 on 990719-22. Violations Noted.Major Areas Inspected:Physical Protection Cornerstone,Including Review of Access Authoization Program & Changes to Security Plan IR 05000254/19990121999-08-13013 August 1999 Insp Repts 50-254/99-12 & 50-265/99-12 on 990628-0716. Violations Noted.Major Areas Inspected:Corrective Action Process Which Included Methods Used for Identification, Cause Investigation & Correction of Quality Related Items IR 05000254/19990111999-08-13013 August 1999 Insp Repts 50-254/99-11 & 50-265/99-11 on 990601-0720.NCVs Noted.Major Areas Inspected:Performance in Initiating Events,Mitigating Sys,Barrier Integrity Cornerstones & Performance Indicator Verification IR 05000254/19990141999-07-30030 July 1999 Insp Repts 50-254/99-14 & 50-265/99-14 on 990713-15.One Violation Noted & Treated as Ncv.Major Areas Inspected: Heat Sink Performance,Which Covers Inspectable Area Under Initiating Events & Mitigation Sys IR 05000254/19990131999-07-29029 July 1999 Insp Repts 50-254/99-13 & 50-265/99-13 on 990628-0702.No Violations Noted.Major Areas Inspected:Public Radiation Safety & Review of Gaseous & Liquid Radiological Effluents & of Radiological Environmental Monitoring Program IR 05000254/19990091999-06-23023 June 1999 Insp Repts 50-254/99-09 & 50-265/99-09 on 990421-0531.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000254/19990061999-05-14014 May 1999 Insp Repts 50-254/99-06 & 50-265/99-06 on 990307-0420.Three Violations Noted & Being Treated as non-cited Violations. Major Areas Insptected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000254/19990081999-05-11011 May 1999 Insp Repts 50-254/99-08 & 50-265/99-08 on 990419-23.No Violations Noted.Major Areas Inspected:Adequacy of Licensee Programs,Procedures,Training & Supporting Documentation IR 05000254/19990031999-04-0909 April 1999 Insp Repts 50-254/99-03 & 50-265/99-03 on 990308-12.No Violations Noted.Major Areas Inspected:Maint & Engineering ML20205J2951999-04-0101 April 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990121-0306. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19990071999-03-31031 March 1999 Radiation Protection Insp Repts 50-254/99-07 & 50-265/99-07 on 990309-12.No Violations Noted.Major Areas Inspected:Solid Radwaste Processing & Control Program & Radioactive Matls Shipping Program IR 05000254/19980211999-03-0505 March 1999 Insp Repts 50-254/98-21 & 50-265/98-21 on 981112-1218. Violation Noted:Major Areas Inspected:Isi Activities at Plant During Refueling Outage 15 IR 05000254/19990041999-02-26026 February 1999 Insp Repts 50-254/99-04 & 50-265/99-04 on 990201-05.No Violations Noted.Major Areas Inspected:Emergency Prepardeness Program as Aspect of Plant Support IR 05000254/19990021999-02-25025 February 1999 Insp Repts 50-254/99-02 & 50-265/99-02 on 990125-29.No Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Program Included Water Chemistry Control, Instrument Quality Control & internal-lab Comparison ML20199E9431999-01-14014 January 1999 Partially Withheld Security Insp Repts 50-254/98-24 & 50-265/98-24.Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Quad Cities Facility.Details Withheld (Ref 10CFR2.790) IR 05000254/19980201998-12-28028 December 1998 Insp Repts 50-254/98-20 & 50-265/98-20 on 981014-1201.No Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000254/19980221998-12-28028 December 1998 Insp Repts 50-254/98-22 & 50-265/98-22 on 981130-1204.No Violations Noted.Major Areas Inspected:Radiation Protection Staff Preparation for Q1R15 Refueling Outage,Including Review of ALARA Planning & Work Plan Integration IR 05000254/19980191998-12-18018 December 1998 Insp Repts 50-254/98-19 & 50-265/98-19 on 981019-1106. Violations Noted.Major Areas Inspected:Effectiveness of Engineering & Technical Support Provided to Plant in Performance of Routine & Reactive Site Activities IR 05000254/19980171998-11-0505 November 1998 Insp Repts 50-254/98-17 & 50-265/98-17 on 980902-1014.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19980181998-10-15015 October 1998 Partially Withheld Insp Repts 50-254/98-18 & 50-265/98-18 on 980914-18 (Ref 10CFR73.71).No Violations Identified.Major Areas Inspected:Review of Plant Support Activities,Security Activities Re Onsite Personnel Access & Communications IR 05000254/19980131998-09-22022 September 1998 Insp Repts 50-254/98-13 & 50-265/98-13 on 980716-0901.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980141998-09-17017 September 1998 Insp Repts 50-254/98-14 & 50-265/98-14 on 980825-28.No Violations Noted.Major Areas Inspected:Evaluation of Licensee Performance During Plant Biennial Exercise of Emergency Plan IR 05000254/19980161998-09-0404 September 1998 Insp Repts 50-254/98-16 & 50-265/98-16 on 980810-14.No Violations Noted.Major Areas Inspected:Radiation Protection Program Included External & Internal Exposure Control,Whole Body Counting & Contamination & Survey Monitoring Program IR 05000254/19980121998-08-11011 August 1998 Insp Repts 50-254/98-12 & 50-265/98-12 on 980529-0716. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000254/19980151998-07-31031 July 1998 Insp Repts 50-254/98-15 & 50-265/98-15 on 980721-24.No Violations Noted.Major Areas Inspected:Aspects of Licensee Corrective Actions & Engineering Involvement in Corrective Actions Process IR 05000254/19980111998-07-0202 July 1998 Insp Repts 50-254/98-11 & 50-265/98-11 on 980504-22. Violations Noted.Major Areas Inspected:Quad Cities Safe Shutdown Analysis & Supporting Procedures IR 05000254/19980091998-07-0202 July 1998 Insp Repts 50-254/98-09 & 50-265/98-09 on 980401-0529. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980081998-05-11011 May 1998 Insp Repts 50-254/98-08 & 50-265/98-08 on 980407-09 & 14-17. No Violations Noted.Major Areas Inspected:Maint,Quality Assurance & Engineering IR 05000254/19982011998-05-0606 May 1998 Insp Repts 50-254/98-201 & 50-265/98-201 on 980216-0327.No Violations Noted.Major Areas Inspected:Evaluation of Capability of Selected Sys to Perform Safety Functions Required by Design Bases IR 05000254/19980101998-05-0606 May 1998 Insp Repts 50-254/98-10 & 50-265/98-10 on 980413-17.No Violations Noted.Major Areas Inspected:Liquid & Gaseous Effluent Programs,Annual Effluent Rept,Continuous Air & Area Radiation Monitors ML20217G3401998-04-23023 April 1998 Insp Repts 50-254/98-04 & 50-265/98-04 on 980211-0331. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support ML20217G2481998-04-23023 April 1998 Insp Repts 50-254/98-05 & 50-265/98-05 on 980216-0326. Violations Noted.Major Areas Inspected:Engineering,Including Allowances for Development of Emergency & Immediate Mods IR 05000254/19980071998-04-22022 April 1998 Insp Repts 50-254/98-07 & 50-265/98-07 on 980330-0403.No Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Plant,Adequacy of Security Procedures & Event Logs ML20216C2601998-03-0606 March 1998 Insp Repts 50-254/97-28 & 50-265/97-28 on 971224-980210. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering ML20202G3071998-02-13013 February 1998 Insp Repts 50-254/97-22 & 50-265/97-22 on 971027-1121. Violations Noted.Major Areas Inspected:Hpci Sys Operational Performance for Operations,Maintenance & Engineering ML20202B0501998-02-0505 February 1998 Insp Repts 50-254/98-02 & 50-265/98-02 on 980112-16. Violations Noted.Major Areas Inspected:Review of ALARA Planning,Radiation Work Permits & Observations of Radworker Performance ML20198T5071998-01-21021 January 1998 Insp Repts 50-254/97-26 & 50-265/97-26 on 971103-1223. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19970241998-01-13013 January 1998 Insp Repts 50-254/97-24 & 50-265/97-24 on 971124-1202.No Violations Noted.Major Areas Inspected:Licensed RO & SRO Requalification Training Programs ML20197F5741997-12-23023 December 1997 Insp Repts 50-254/97-27 & 50-265/97-27 on 971103-07 & 1204. Violations Noted.Major Areas Inspected:Maint & Engineering ML20197B2641997-12-16016 December 1997 Insp Repts 50-254/97-14 & 50-265/97-14 on 970729-0922.NOV & Deviations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support Re Troubleshooting Resulting in Discovery of Long Standing Problem W/Fire Pump IR 05000254/19970251997-12-0909 December 1997 Insp Repts 50-254/97-25 & 50-265/97-25 on 971103-07.No Violations Noted.Major Areas Inspected:Respiratory Protection Plan,Source Term Reduction Efforts & Follow Up on Several Open Items IR 05000254/19970211997-12-0909 December 1997 Insp Repts 50-254/97-21 & 50-265/97-21 on 970923-1103.No Violations Noted.Major Areas Inspected:Operation,Maint, Engineering & Plant Support IR 05000254/19970191997-11-18018 November 1997 Insp Repts 50-254/97-19 & 50-265/97-19 on 971006-10.No Violations Noted.Major Areas Inspected:Ep Program IR 05000254/19970181997-11-10010 November 1997 Insp Repts 50-254/97-18 & 50-265/97-18 on 970922-25. Violations Noted.Major Areas Inspected:Maintenance & Engineering IR 05000254/19970161997-11-0505 November 1997 Insp Repts 50-254/97-16 & 50-265/97-16 on 970825-29. Violations Noted.Major Areas Inspected:Fire Protection Program & Several App R Issues 1999-09-09
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000254/19990011999-10-0707 October 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990721-0908.No Violations Noted.Major Areas Inspected:Initiating Events, Mitigating Sys & Barrier Integrity IR 05000254/19990171999-09-15015 September 1999 Insp Repts 50-254/99-17 & 50-265/99-17 on 990823-27.No Violations Noted.Major Areas Inspected:Pilot Baseline Insp for Annual Review of Changes to Safety Analysis Rept & Biennial Review Permanent Plant Mod IR 05000254/19990161999-09-0909 September 1999 Errata to Insp Repts 50-254/99-16 & 50-265/99-16 Conducted on 990819.Administrative Error Was Corrected on Page 8 of Subj Rept.One Open Item Was Deleted & re-numbering of Two Other Items Were Identified IR 05000254/19990151999-08-25025 August 1999 Insp Repts 50-254/99-15 & 50-265/99-15 on 990816-20.No Violations Noted.Major Areas Inspected:Maint Rule Implementation IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site ML20211D2031999-08-19019 August 1999 Insp Repts 50-254/99-16 & 50-265/99-16 on 990719-22. Violations Noted.Major Areas Inspected:Physical Protection Cornerstone,Including Review of Access Authoization Program & Changes to Security Plan IR 05000254/19990121999-08-13013 August 1999 Insp Repts 50-254/99-12 & 50-265/99-12 on 990628-0716. Violations Noted.Major Areas Inspected:Corrective Action Process Which Included Methods Used for Identification, Cause Investigation & Correction of Quality Related Items IR 05000254/19990111999-08-13013 August 1999 Insp Repts 50-254/99-11 & 50-265/99-11 on 990601-0720.NCVs Noted.Major Areas Inspected:Performance in Initiating Events,Mitigating Sys,Barrier Integrity Cornerstones & Performance Indicator Verification IR 05000254/19990141999-07-30030 July 1999 Insp Repts 50-254/99-14 & 50-265/99-14 on 990713-15.One Violation Noted & Treated as Ncv.Major Areas Inspected: Heat Sink Performance,Which Covers Inspectable Area Under Initiating Events & Mitigation Sys IR 05000254/19990131999-07-29029 July 1999 Insp Repts 50-254/99-13 & 50-265/99-13 on 990628-0702.No Violations Noted.Major Areas Inspected:Public Radiation Safety & Review of Gaseous & Liquid Radiological Effluents & of Radiological Environmental Monitoring Program IR 05000254/19990091999-06-23023 June 1999 Insp Repts 50-254/99-09 & 50-265/99-09 on 990421-0531.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000254/19990061999-05-14014 May 1999 Insp Repts 50-254/99-06 & 50-265/99-06 on 990307-0420.Three Violations Noted & Being Treated as non-cited Violations. Major Areas Insptected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000254/19990081999-05-11011 May 1999 Insp Repts 50-254/99-08 & 50-265/99-08 on 990419-23.No Violations Noted.Major Areas Inspected:Adequacy of Licensee Programs,Procedures,Training & Supporting Documentation IR 05000254/19990031999-04-0909 April 1999 Insp Repts 50-254/99-03 & 50-265/99-03 on 990308-12.No Violations Noted.Major Areas Inspected:Maint & Engineering ML20205J2951999-04-0101 April 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990121-0306. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19990071999-03-31031 March 1999 Radiation Protection Insp Repts 50-254/99-07 & 50-265/99-07 on 990309-12.No Violations Noted.Major Areas Inspected:Solid Radwaste Processing & Control Program & Radioactive Matls Shipping Program IR 05000254/19980211999-03-0505 March 1999 Insp Repts 50-254/98-21 & 50-265/98-21 on 981112-1218. Violation Noted:Major Areas Inspected:Isi Activities at Plant During Refueling Outage 15 IR 05000254/19990041999-02-26026 February 1999 Insp Repts 50-254/99-04 & 50-265/99-04 on 990201-05.No Violations Noted.Major Areas Inspected:Emergency Prepardeness Program as Aspect of Plant Support IR 05000254/19990021999-02-25025 February 1999 Insp Repts 50-254/99-02 & 50-265/99-02 on 990125-29.No Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Program Included Water Chemistry Control, Instrument Quality Control & internal-lab Comparison ML20199E9431999-01-14014 January 1999 Partially Withheld Security Insp Repts 50-254/98-24 & 50-265/98-24.Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Quad Cities Facility.Details Withheld (Ref 10CFR2.790) IR 05000254/19980201998-12-28028 December 1998 Insp Repts 50-254/98-20 & 50-265/98-20 on 981014-1201.No Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000254/19980221998-12-28028 December 1998 Insp Repts 50-254/98-22 & 50-265/98-22 on 981130-1204.No Violations Noted.Major Areas Inspected:Radiation Protection Staff Preparation for Q1R15 Refueling Outage,Including Review of ALARA Planning & Work Plan Integration IR 05000254/19980191998-12-18018 December 1998 Insp Repts 50-254/98-19 & 50-265/98-19 on 981019-1106. Violations Noted.Major Areas Inspected:Effectiveness of Engineering & Technical Support Provided to Plant in Performance of Routine & Reactive Site Activities IR 05000254/19980171998-11-0505 November 1998 Insp Repts 50-254/98-17 & 50-265/98-17 on 980902-1014.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19980181998-10-15015 October 1998 Partially Withheld Insp Repts 50-254/98-18 & 50-265/98-18 on 980914-18 (Ref 10CFR73.71).No Violations Identified.Major Areas Inspected:Review of Plant Support Activities,Security Activities Re Onsite Personnel Access & Communications IR 05000254/19980131998-09-22022 September 1998 Insp Repts 50-254/98-13 & 50-265/98-13 on 980716-0901.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980141998-09-17017 September 1998 Insp Repts 50-254/98-14 & 50-265/98-14 on 980825-28.No Violations Noted.Major Areas Inspected:Evaluation of Licensee Performance During Plant Biennial Exercise of Emergency Plan IR 05000254/19980161998-09-0404 September 1998 Insp Repts 50-254/98-16 & 50-265/98-16 on 980810-14.No Violations Noted.Major Areas Inspected:Radiation Protection Program Included External & Internal Exposure Control,Whole Body Counting & Contamination & Survey Monitoring Program IR 05000254/19980121998-08-11011 August 1998 Insp Repts 50-254/98-12 & 50-265/98-12 on 980529-0716. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000254/19980151998-07-31031 July 1998 Insp Repts 50-254/98-15 & 50-265/98-15 on 980721-24.No Violations Noted.Major Areas Inspected:Aspects of Licensee Corrective Actions & Engineering Involvement in Corrective Actions Process IR 05000254/19980111998-07-0202 July 1998 Insp Repts 50-254/98-11 & 50-265/98-11 on 980504-22. Violations Noted.Major Areas Inspected:Quad Cities Safe Shutdown Analysis & Supporting Procedures IR 05000254/19980091998-07-0202 July 1998 Insp Repts 50-254/98-09 & 50-265/98-09 on 980401-0529. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980081998-05-11011 May 1998 Insp Repts 50-254/98-08 & 50-265/98-08 on 980407-09 & 14-17. No Violations Noted.Major Areas Inspected:Maint,Quality Assurance & Engineering IR 05000254/19982011998-05-0606 May 1998 Insp Repts 50-254/98-201 & 50-265/98-201 on 980216-0327.No Violations Noted.Major Areas Inspected:Evaluation of Capability of Selected Sys to Perform Safety Functions Required by Design Bases IR 05000254/19980101998-05-0606 May 1998 Insp Repts 50-254/98-10 & 50-265/98-10 on 980413-17.No Violations Noted.Major Areas Inspected:Liquid & Gaseous Effluent Programs,Annual Effluent Rept,Continuous Air & Area Radiation Monitors ML20217G3401998-04-23023 April 1998 Insp Repts 50-254/98-04 & 50-265/98-04 on 980211-0331. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support ML20217G2481998-04-23023 April 1998 Insp Repts 50-254/98-05 & 50-265/98-05 on 980216-0326. Violations Noted.Major Areas Inspected:Engineering,Including Allowances for Development of Emergency & Immediate Mods IR 05000254/19980071998-04-22022 April 1998 Insp Repts 50-254/98-07 & 50-265/98-07 on 980330-0403.No Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Plant,Adequacy of Security Procedures & Event Logs ML20216C2601998-03-0606 March 1998 Insp Repts 50-254/97-28 & 50-265/97-28 on 971224-980210. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering ML20202G3071998-02-13013 February 1998 Insp Repts 50-254/97-22 & 50-265/97-22 on 971027-1121. Violations Noted.Major Areas Inspected:Hpci Sys Operational Performance for Operations,Maintenance & Engineering ML20202B0501998-02-0505 February 1998 Insp Repts 50-254/98-02 & 50-265/98-02 on 980112-16. Violations Noted.Major Areas Inspected:Review of ALARA Planning,Radiation Work Permits & Observations of Radworker Performance ML20198T5071998-01-21021 January 1998 Insp Repts 50-254/97-26 & 50-265/97-26 on 971103-1223. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19970241998-01-13013 January 1998 Insp Repts 50-254/97-24 & 50-265/97-24 on 971124-1202.No Violations Noted.Major Areas Inspected:Licensed RO & SRO Requalification Training Programs ML20197F5741997-12-23023 December 1997 Insp Repts 50-254/97-27 & 50-265/97-27 on 971103-07 & 1204. Violations Noted.Major Areas Inspected:Maint & Engineering ML20197B2641997-12-16016 December 1997 Insp Repts 50-254/97-14 & 50-265/97-14 on 970729-0922.NOV & Deviations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support Re Troubleshooting Resulting in Discovery of Long Standing Problem W/Fire Pump IR 05000254/19970251997-12-0909 December 1997 Insp Repts 50-254/97-25 & 50-265/97-25 on 971103-07.No Violations Noted.Major Areas Inspected:Respiratory Protection Plan,Source Term Reduction Efforts & Follow Up on Several Open Items IR 05000254/19970211997-12-0909 December 1997 Insp Repts 50-254/97-21 & 50-265/97-21 on 970923-1103.No Violations Noted.Major Areas Inspected:Operation,Maint, Engineering & Plant Support IR 05000254/19970191997-11-18018 November 1997 Insp Repts 50-254/97-19 & 50-265/97-19 on 971006-10.No Violations Noted.Major Areas Inspected:Ep Program IR 05000254/19970181997-11-10010 November 1997 Insp Repts 50-254/97-18 & 50-265/97-18 on 970922-25. Violations Noted.Major Areas Inspected:Maintenance & Engineering IR 05000254/19970161997-11-0505 November 1997 Insp Repts 50-254/97-16 & 50-265/97-16 on 970825-29. Violations Noted.Major Areas Inspected:Fire Protection Program & Several App R Issues 1999-09-09
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000254/19990011999-10-0707 October 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990721-0908.No Violations Noted.Major Areas Inspected:Initiating Events, Mitigating Sys & Barrier Integrity IR 05000254/19990171999-09-15015 September 1999 Insp Repts 50-254/99-17 & 50-265/99-17 on 990823-27.No Violations Noted.Major Areas Inspected:Pilot Baseline Insp for Annual Review of Changes to Safety Analysis Rept & Biennial Review Permanent Plant Mod IR 05000254/19990161999-09-0909 September 1999 Errata to Insp Repts 50-254/99-16 & 50-265/99-16 Conducted on 990819.Administrative Error Was Corrected on Page 8 of Subj Rept.One Open Item Was Deleted & re-numbering of Two Other Items Were Identified IR 05000254/19990151999-08-25025 August 1999 Insp Repts 50-254/99-15 & 50-265/99-15 on 990816-20.No Violations Noted.Major Areas Inspected:Maint Rule Implementation IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site ML20211D2031999-08-19019 August 1999 Insp Repts 50-254/99-16 & 50-265/99-16 on 990719-22. Violations Noted.Major Areas Inspected:Physical Protection Cornerstone,Including Review of Access Authoization Program & Changes to Security Plan IR 05000254/19990121999-08-13013 August 1999 Insp Repts 50-254/99-12 & 50-265/99-12 on 990628-0716. Violations Noted.Major Areas Inspected:Corrective Action Process Which Included Methods Used for Identification, Cause Investigation & Correction of Quality Related Items IR 05000254/19990111999-08-13013 August 1999 Insp Repts 50-254/99-11 & 50-265/99-11 on 990601-0720.NCVs Noted.Major Areas Inspected:Performance in Initiating Events,Mitigating Sys,Barrier Integrity Cornerstones & Performance Indicator Verification IR 05000254/19990141999-07-30030 July 1999 Insp Repts 50-254/99-14 & 50-265/99-14 on 990713-15.One Violation Noted & Treated as Ncv.Major Areas Inspected: Heat Sink Performance,Which Covers Inspectable Area Under Initiating Events & Mitigation Sys IR 05000254/19990131999-07-29029 July 1999 Insp Repts 50-254/99-13 & 50-265/99-13 on 990628-0702.No Violations Noted.Major Areas Inspected:Public Radiation Safety & Review of Gaseous & Liquid Radiological Effluents & of Radiological Environmental Monitoring Program IR 05000254/19990091999-06-23023 June 1999 Insp Repts 50-254/99-09 & 50-265/99-09 on 990421-0531.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000254/19990061999-05-14014 May 1999 Insp Repts 50-254/99-06 & 50-265/99-06 on 990307-0420.Three Violations Noted & Being Treated as non-cited Violations. Major Areas Insptected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000254/19990081999-05-11011 May 1999 Insp Repts 50-254/99-08 & 50-265/99-08 on 990419-23.No Violations Noted.Major Areas Inspected:Adequacy of Licensee Programs,Procedures,Training & Supporting Documentation IR 05000254/19990031999-04-0909 April 1999 Insp Repts 50-254/99-03 & 50-265/99-03 on 990308-12.No Violations Noted.Major Areas Inspected:Maint & Engineering ML20205J2951999-04-0101 April 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990121-0306. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19990071999-03-31031 March 1999 Radiation Protection Insp Repts 50-254/99-07 & 50-265/99-07 on 990309-12.No Violations Noted.Major Areas Inspected:Solid Radwaste Processing & Control Program & Radioactive Matls Shipping Program IR 05000254/19980211999-03-0505 March 1999 Insp Repts 50-254/98-21 & 50-265/98-21 on 981112-1218. Violation Noted:Major Areas Inspected:Isi Activities at Plant During Refueling Outage 15 ML20207G1771999-03-0505 March 1999 Notice of Violation from Insp on 99112-1218.Violation Noted:Licensee Had Not Included in Revised ISI Program,Basis for Determination That Code Required Exam Was Impractical For,Unit 2 Reactor Pressure Vessel Nozzle Weld Nsb IR 05000254/19990041999-02-26026 February 1999 Insp Repts 50-254/99-04 & 50-265/99-04 on 990201-05.No Violations Noted.Major Areas Inspected:Emergency Prepardeness Program as Aspect of Plant Support IR 05000254/19990021999-02-25025 February 1999 Insp Repts 50-254/99-02 & 50-265/99-02 on 990125-29.No Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Program Included Water Chemistry Control, Instrument Quality Control & internal-lab Comparison ML20199E9431999-01-14014 January 1999 Partially Withheld Security Insp Repts 50-254/98-24 & 50-265/98-24.Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Quad Cities Facility.Details Withheld (Ref 10CFR2.790) IR 05000254/19980201998-12-28028 December 1998 Insp Repts 50-254/98-20 & 50-265/98-20 on 981014-1201.No Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000254/19980221998-12-28028 December 1998 Insp Repts 50-254/98-22 & 50-265/98-22 on 981130-1204.No Violations Noted.Major Areas Inspected:Radiation Protection Staff Preparation for Q1R15 Refueling Outage,Including Review of ALARA Planning & Work Plan Integration ML20198G2901998-12-18018 December 1998 Notice of Violations from Insp on 981019-1106.Violations Noted:As of 980327,performance of Listed Test Procedures Did Not Demonstrate Equipment Could Perform Satisfactorily Under Design Conditions IR 05000254/19980191998-12-18018 December 1998 Insp Repts 50-254/98-19 & 50-265/98-19 on 981019-1106. Violations Noted.Major Areas Inspected:Effectiveness of Engineering & Technical Support Provided to Plant in Performance of Routine & Reactive Site Activities IR 05000254/19980171998-11-0505 November 1998 Insp Repts 50-254/98-17 & 50-265/98-17 on 980902-1014.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19980181998-10-15015 October 1998 Partially Withheld Insp Repts 50-254/98-18 & 50-265/98-18 on 980914-18 (Ref 10CFR73.71).No Violations Identified.Major Areas Inspected:Review of Plant Support Activities,Security Activities Re Onsite Personnel Access & Communications IR 05000254/19980131998-09-22022 September 1998 Insp Repts 50-254/98-13 & 50-265/98-13 on 980716-0901.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980141998-09-17017 September 1998 Insp Repts 50-254/98-14 & 50-265/98-14 on 980825-28.No Violations Noted.Major Areas Inspected:Evaluation of Licensee Performance During Plant Biennial Exercise of Emergency Plan ML20154G4301998-09-11011 September 1998 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $88,000.Violation Noted:As of 970926,licensee Failed to Provide Alternate Shutdown Capability for Some Fire Areas of Facility Containing Safe Shutdown Equipment ML20195D1951998-09-0808 September 1998 EN-98-057B:on 980911,notice of Proposed Imposition of Civil Penalty in Amount of $88,000 Issued to Licensee.Action Based on One Severity Level II Problem Involving Very Significant Inadequacies in Comm Ed Capability to Shut Down IR 05000254/19980161998-09-0404 September 1998 Insp Repts 50-254/98-16 & 50-265/98-16 on 980810-14.No Violations Noted.Major Areas Inspected:Radiation Protection Program Included External & Internal Exposure Control,Whole Body Counting & Contamination & Survey Monitoring Program IR 05000254/19980121998-08-11011 August 1998 Insp Repts 50-254/98-12 & 50-265/98-12 on 980529-0716. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support ML20237D6671998-08-11011 August 1998 Notice of Violation from Insp on 980529-0716.Violation Noted:On 980622,while Performing Quad Cities Operating Surveillance Procedure 6600-01,rev 24,operator Failed to Position Throttle Air Box Drain Valve One Turn ML20195D2341998-08-11011 August 1998 EN-98-057:on 980814,notice of Proposed Imposition of Civil Penalty in Amount of $143,000 Issued to Licensee.Action Based on One Severity Level II Problem & One Severity Level III Violation IR 05000254/19980151998-07-31031 July 1998 Insp Repts 50-254/98-15 & 50-265/98-15 on 980721-24.No Violations Noted.Major Areas Inspected:Aspects of Licensee Corrective Actions & Engineering Involvement in Corrective Actions Process IR 05000254/19980111998-07-0202 July 1998 Insp Repts 50-254/98-11 & 50-265/98-11 on 980504-22. Violations Noted.Major Areas Inspected:Quad Cities Safe Shutdown Analysis & Supporting Procedures ML20236M0831998-07-0202 July 1998 Notice of Violation from Insp on 980401-0529.Violation Noted:On 980501,Interim Procedure 98-0035 Was Not Implemented When Change Was Made to Personnel Out-of Svc Number 98-512 Which Was Not Reviewed & Approved IR 05000254/19980091998-07-0202 July 1998 Insp Repts 50-254/98-09 & 50-265/98-09 on 980401-0529. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20237E7051998-06-0505 June 1998 EN-98-043:informs Commission That Staff Intends to Exercise Enforcement Discretion Per Section VI.B.6 of Enforcement Policy & Not Issue NOV to Util for Failure to Provide Complete & Accurate Info to NRC ML20248L7951998-06-0505 June 1998 Notice of Violation from Investigation on 970530.Violations Noted:Licensee Provided to Commission on 960825,operability Determination Checklist.Info Inaccurate Because Supporting Calculations Showed FICs to Be Excess of 1.0 ML20247P4551998-05-15015 May 1998 Notice of Violation from Insp on 971014-980415.Violation Noted:On 971215,inspector Identified That Licensee Failed to Provide Training of Personnel Performing Activities Affecting Quality IR 05000254/19980081998-05-11011 May 1998 Insp Repts 50-254/98-08 & 50-265/98-08 on 980407-09 & 14-17. No Violations Noted.Major Areas Inspected:Maint,Quality Assurance & Engineering IR 05000254/19980101998-05-0606 May 1998 Insp Repts 50-254/98-10 & 50-265/98-10 on 980413-17.No Violations Noted.Major Areas Inspected:Liquid & Gaseous Effluent Programs,Annual Effluent Rept,Continuous Air & Area Radiation Monitors IR 05000254/19982011998-05-0606 May 1998 Insp Repts 50-254/98-201 & 50-265/98-201 on 980216-0327.No Violations Noted.Major Areas Inspected:Evaluation of Capability of Selected Sys to Perform Safety Functions Required by Design Bases ML20217G2341998-04-23023 April 1998 Notice of Violation from Insp on 980216-0326.Violation Noted:Between 971006 & 10,work Package 970104149-03 Replaced 2A Recirculation Loop Sample Pci Valve AO-2-0220-44,activity Affecting Quality,Prepared & Installed Prior to 971014 ML20217G2481998-04-23023 April 1998 Insp Repts 50-254/98-05 & 50-265/98-05 on 980216-0326. Violations Noted.Major Areas Inspected:Engineering,Including Allowances for Development of Emergency & Immediate Mods ML20217G3101998-04-23023 April 1998 Notice of Violations from Insp on 980211-0331.Violations Noted:On 980314,non-licensed Operators Performing Plant Operating Procedure 6600-7,rev 6,attachment H,Failed to Charge Breaker Closing Spring for Unit 2 ML20217G3401998-04-23023 April 1998 Insp Repts 50-254/98-04 & 50-265/98-04 on 980211-0331. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support IR 05000254/19980071998-04-22022 April 1998 Insp Repts 50-254/98-07 & 50-265/98-07 on 980330-0403.No Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Plant,Adequacy of Security Procedures & Event Logs 1999-09-09
[Table view] |
Text
m
.
,
U.S. NUCLEAR REGULATORY COMMISSION L REGION III Reports No.~ 50-254/89019(DRSS); 5'0-265/89019(DRSS)
Docket Nos. 50-254; 50-265 Licenses No. DPR-29; DPR-30 Licensee: Commonwealth Edison Company Post Office Box 767 Chicago, IL 60690 Facility Name: Quad Cities Nuclear Power Station, Units 1 and 2-Inspection At: Quad Cities Site, Cordova, Illinois Inspection Conducted: August 21-September 12, 1989 Inspector: G.}J.knuskaUL A. YaS/S 9 Date
$Y M Approved By: M. C. Schumacher, Chief I Radiological Controls and Date Chemistry Section Inspection Summary Inspection on August 21-September 12, 1989 (Reports No. 50-254/89019(DRSS);
50-265/89019(DRSS))
Areas Inspected: Routine unannounced inspection of confirmatory measurements and radiologi_ cal environmental monitoring including: review of open items (IP 92701); audits and appraisals; changes in organization, equipment, facilities and instrumentation; implementation of the quality assurance and confirmatory ,
measurements program; post-accident sample analyses; implementation of the '
Radiological Environmental Monitoring Program (REMP) and the REMP quality'
assurance program (IP 84750).
Results: Confirmatory measurements sample results were good. The licensee expended extra effort to analyze vendor cross-check samples on all five detectors also with good result PDR ADDCK 05000254 O PNU _ __
_ _
.
_
b,.
, .
..,
. .
,
v..
ha
- , DETAILS k
" Persons Contacted
' 1 T. Barber, Regulatory Assurance-1 R.;Bax, Station Manage ~2P. Behrens, Chemistry Supervisor
!> .J. Burkhead, Quality Assurance
B. Eklin, Health Physics' "
.R.~Hebeler, Chemistry Foreman 2 .R. Luczak, CECO R.. Moore, Chemistry Foreman
R. Robey, Technical Superintendent
R. Stols, Nuclear Licensing Administrator
'J. Wooldridge, . General Chemist
.
J. Wethington, Quality Assurance Superintendent R. Wiebenga, Chemist
,
R. Higgins, Senior Resident Inspector,'NRC 1 Present at the Exit Meeting on August 25, 198 Telephone Conversation on September 12, 198 . Licensee Action on Previous Inspection Findings (IP 92701)' (0 pen) Open Item (50-254/88008-01; 50-265/88009-01):
Licensee.to analyze a liquid sample for gross beta, H-3, Sr-89,-
Sr-90 and Fe-55 and. report the results to Region III. Gross beta and H-3 results were in agreement; however, strontium and Fe-55 were not' compared because of poor statistics. A river discharge tank sample was later split and sent for Fe-55 analyses to both laboratories under contract to the licensee. One laboratory's result was a factor
'of 4.2 higher than the NRC. Reference . laboratory's result (disagreement);
and the other.. laboratory a factor of 89% (agreement). The licensee ,
agreed to have at spike to be supplied by the NRC' analyzed by both laboratories. A sample split from this inspection will also be analyzed by the laboratory that achieved agreement. The licensee also informed appropriate station personnel to use that laboratory in the' future for waste stream and technical specification analyse (0 pen) Open Item (50-254/88008-02; 50-265/88009-02):
Licensee to audit the analytical contractors' procedures paying particular attention to Fe-55, and observe the analysis of a discharge tank sample for Fe-55. A licensee representative visited one of the laboratories in early 1989 and a quality assurance audit was performed in mid 1989. Results of the trip and the audit and an audit scheduled for the other laboratory will be reviewed when available.
i-
_ - _ _ _ - - _ _ _ -
__ _
.
s .,
-
.
.
'
l' (Closed) Open Item (50-254/88008-03; 50-265/88009-03:
l' Calibrate marinelli gas geometry within two weeks af ter receipt of gas standard (tentatively 04-25-88). The geometry was calibrated
as' required. Gas ~ analyses using this geometry during this inspection resulted in all agreement . Changes in Organization, Equipment, Facilities and Instrumentation (IP 84750)
The management structure of the Chemistry Section was changed to conform to the Chemistry and Health Physics split which took place on January 1, 1989. The Chemistry and the Health Physics Sections are each headed by a Supervisor who report to the Technical Superintendent. Two Foremen and five Chemists report to the Chemistry Supervisor. Chemistry Technicians (cts), currently 13, are under the direction of the Chem Foreme Technician training involves initial general studies, site specific information and annual continuing training. Requalification for all
"A" cts will be required annuall The inspector discussed the need for continuing training for the Foremen at the exit intervie No violations or deviations were identifie . Confirmatory Measurement (IP 84750) Sample Split ;
Six samples (reactor vent air particulate and charcoal, charcoal spike, gas, reactor coolant and liquid) were analyzed for gamma emitting isotopes by the licensee and in the Region III Mobile Laboratory on site. Comparisons were made.on combinations of the licensee's four normally used count room detectors and the Post Accident Radionuclides Analysis Portable System (PARAPS).
Results of the sample comparisons are given in Table 1; the comparison criteria are given in Attachment 1. The licensee achieved 74 agreements out of 75 comparison The charcoal filter had only one detectable nuclid To verify this geometry a charcoal standard was counted as an unknown which resulted in all agreements. A portion of the liquid waste sample will be analyzed for gross beta, H-3, Sr-89, Sr-90 and Fe55 by the licensee and the results reported to Region III for comparison with an analysis by the NRC Reference Laboratory on a split of the sample (Discussed in Section 2).
The only disagreement was for Ba-139 in a primary sample. The analysis on detector 25-P844 resulted in an agreement but a disagreement resulted when analyzed on detector 25-60RA. No reason for the disagreement could be foun Audits The inspector reviewed audits 04-89-02 and 04-88-II, surveillance QAS 04-89-039, 04-89-047 and 04-89-124 and auditor qualification The audits and surveillance placed emphasis on observing performance l
_ _ _ _ _ _ - _ _ _ _ _ _ _ _ - _ _ _
__ _
.
.<
.
..
and appeared to be in sufficient depth. Responses to the audit findings appeared to be timely and adequate. The qualifications of auditors who participated in the chemistry audits and surveillance indicated that they were qualified in chemistry and that backgrounds, experience and professional development was adequat The inspector discussed auditing for performance and the need for continuing training for auditors at the exit intervie Quality Assurance The inspector' reviewed the radioactivity measurements laboratory quality assurance program including physical facilities and laboratory operation Housekeeping was generally good; laboratory and counting room work space was adequat Chemistry Technicians were observed taking appropriate precautions when handling radioactive material The licensee participates in an intercomparison cross-check program with an outside vendor. The inspector examined the third quarter 1988 results through and including the second quarter of 1989 and noted only two disagreements. The inspector also noted that in-addition to the cross-check comparison, the licensee compares four detector results against the one used for cross-check submittal. The results of the comparison between the five detectors were very goo Daily implementation of the instrument quality control program was examine Tests were run as required. The inspector saw evidence that the counting room is checked daily but noted that sign off of the review of data is often not timely. The necessity of that review, especially for those instruments whose results are not automatically entered into the computer based QC program was discussed with a license representative who acknowledged the inspector's commen No violations of deviations were identified Post Accident Sampling (IP 84750)
The inspector discussed the High Radiation Sampling System (HRSS)
and its operation with the license In-line monitors are checked weekl The HRSS is prepared to accept accident samples and an inventory of supplies is performed quarterly. Various samples are collected and radiochemical analyses performed at this tim Semiannually, samples are collected for gamma spectroscopy and chemistry equipment is calibrated. The inspector saw data of an annual analysis performed to verify the liquid dilution valve siz No violations or deviations were identifie I l
l l
l
_ - - _ _ _ - _ - _ _ _ _ _ _ __ _ _ ___ __. _
_ _ _ _ ,
. _ _ . _
..
&
-
.
. Radiological Environmental Monitoring Program (REMP)(IP 84750)
The inspector reviewed the 1988 Annual Environmental Report. The Report appeared to comply with the_REMP requirements. All required samples were i collected and analyzed except as noted in the report. The results do not indicate any significant contribution to the environment due to plant operation. The inspector examined the quarterly collection schedule and completed weekly sample collection data sheets, and discussed the Program with a Station Health Physicist who has the Program oversight as'part of his normal duties. The individual was very knowledgeable of the workings of the Progra No violations of deviations were identified Exit Interview The scope and findings of the inspection were reviewed with licensee representatives (Section 1) at the conclusion of the inspection on August 25, 1989. The inspectors discussed the following:
1. sample split results 2. audits 3. retraining for auditors and foremen 4. the HRSS system 5. the REMP program During the exit interview, the inspector discussed the likely informational content of the inspection report with regard to documents or processes reviewed by the inspector during the inspection. Licensee representatives did not identify any such documents or processes as proprietar Attachments:
1. Table 1, Radiological Interlaboratory Split. Sample Results, 3rd Quarter 1989 Attachment 1, Criteria for Comparing Radiological Measurements
5
________ _______________ _ _ -
, ,a %. . ~ , <. _
-
_<
-.
, 4.. p
- . q c -g -
., ?
O T > '
' TABLE 1-L U S NUCLEAR REGULATORY COMMISSION o1
~ OFFICE OF INSPECTION AND ENFORCEMENT CONFIRMATORY..MEASUREl/ENTS PROGRAM FACILITY-QUAD CITIES
'FOR THE'3 QUARTER OF 1989-NRC---' LICENSEE ---LICENSEE:NRC--
. SAMPLE -ISOTOPE RESULT- ERRO RESULT ERROR- RATIO RES T-PRIMARY. NA-24 6.9E-03 5.2E-05 6.2E-03 0.OE-01 9.0E-01 1.3E 02 A Jappgqd CR-51 4.4E-03 1.3E-04; 4.0E-03 0.0E-01 9.0E-01 3. 5E O l ' A MN-54' 1.5E-04 1.6E-05 1.3E-04 0.0E-01 8.5E-01 9.4E 00- A MN-56: 9.6E-04 1.1E-04: 8.1E-04 0.0E-01 8.5E-01 8.6E'00 'A CO-58 1~.5E-04 2.0E-05 -1.5E-04 0.0E-01 1.0E 00 7.5E 00 A-CO-6 .7E-04 1;5E-05' 2.5E-04 0.0E-01 9.1E-01 1.9E 01- A ZN-65 6.8E-05 2.5E-05 4.6E-05 0.0E-01 6.8E-01 12.7E 00 A-AS-76 1.2E-0 .5E-05 1.1E-04 0.0E-01- 9.3E-01 4.7E 00 A I-132 9.OE-04- 4.5E-05 8.2E-04 0.0E-01 9.1E-01 2.0E 01 A I-133 2.8E-04 1.3E-05- 2.6E-04 0.0E-01 9.1E-01- 2.2E 01 A I-134 3.3E-03 3.2E-04 2.6E-03 :0.0E-01 7.9E-01 1.0E 01 A I-135 9.7E-04 '9.6E-05 6.6E-04 0.0E-01 6.8E-01 1.0E 01 A BA-139 9.9E-04 1.5E-04 5.3E-04 0.0E-01 5.4E-01 6.4E 00 A C FELTER I-131 '1.2E-12 3.3E-13 5.0E-13 0.OE-01 4.2E-01 3.6E 00 A 2S-botA P FILTER NA-24 1.3E-10 5.5E-11 1.3E-10 0.0E-01 9.9E-01 2.4E 00 A 14 4218F CR-51 4.3E-11 1.7E-12 4.5E-11 0.0E-01 1.OE 00 2.5E'01 A MN-54 6.3E-12 3.3E-13 5.3E-12 0.0E-01 8.4E-01 1.9E 01 A CO-58 8.2E-12 3.7E-13' 7.3E-12 0.0E-01 8.9E-01 2.2E 01 A CO-60- 2.5E-11 5.5E-13 2.5E-11 0.0E-01 1.0E-00 4.5E 01 A ZN-65 6.OE-12 8.4E-13 5.6E-12 0.0E-01 9.4E-01' 7.1E 00 A
- PRIMARY NA-24 6.9E-03 5.2E-05 6.2E-03 0.0E-01 9.0E-01 1.3E 02 A 4.5E-03 1.2E-04 3.8E-03 0.0E-01 8.5E-01 3.8E 01 A af. sot 4 CR-51 8.1E 00 A MN-54 1.6E-04 2.0E-05 1.0E-04 0.0E-01 6.1E-01 MN-56 9.8E-04 1.7E-04 7.4E-04 0.0E-01 7.5E-01 5.8E 00 A
.CO-58 1.7E-04 1.7E-05 1.5E-04 0.0E-01 8.7E-01 1.0E 01 A
.CO-60 2.7E-04 1.7E-05 2.3E-04 0.OE-01 8.6E-01 1.6E 01 A AS-7 .3E-04 2.1E-05 1.0E-04 0.0E-01 7.7E-01 6.2E 00 A I-131 '3.3E-05 9.4E-06 2.0E-05 0.0E-01 6.1E-01 3.5E 00 A I-132 -9.9E-04 4.8E-05 7.9E-04 0.0E-01 8.0E-01 2.1E 01 A
=T TEST RESULTS:
A= AGREEMENT
'D= DISAGREEMENT o= CRITERIA ~ RELAXED N=NO' COMPARISON
?
- _ _ - _ _ _
, _ - _ _ _ _ _ .__ - - _ ._. ._. _ _ _ _ _ _ _ _ _ - _ .
I, b" ,
.'
TABLE 1 U S NUCLEAR REGULATORY COMMISSION
' OFFICE OF INSPECTION AND ENFORCEMENT l
CONFIRMATORY MEASUREMENTS PROGRAM FACILITY: QUAD CITIES FOR THE 3 QUARTER OF 1989
-
NRC ====
LICENSEE---- LICENSEE:NRC---- !
SAMPLE ISOTOPE RESULT ERROR RESULT ERROR RATIO RES T
. PRIMARY I-133 3.0E-04 1.2E-05 2.6E-04 0.0E-01 8.8E-01 2.4E 01 A I I-134 3.1E-03 3.8E-04 2.4E-03 0.0E-01 7.7E-01 8.2E 00 A I-135 8.7E-04 6.7E-05 6.5E-04 0.0E-01 7.4E-01 '1.3E 01 A BA-139 1.0E-03 2.3E-04 4.5E-04 0.0E-01 4.3E-01 4.6E 00 D l
C FILTER I-131 1.2E-12 3.3E-13 5.8E-13 0.0E-01 4.9E-01 3.6E 00 A 13-s o q o P FZLTER NA-24 1.3E-10 5.5E-11 1.3E-10 0.0E-01 9.9E-01 2.4E 00 A 4.3E-11 1.7E-12 4.5E-11 0.0E-01 1.0E 00 2.5E 01 A Ji - SotA CR-51 A MN-54 6.3E-12 3.3E-13 5.3E-12 0.0E-01 8.4E-01 1.9E 01 CO-58 8.2E-12 3.7E-13 7.3E-12 0.0E-01 8.9E-01 2.2E 01 A CO-60 2.5E-11 5.5E-13 2.4E-11 0.0E-01 9.6E-01 4.5E 01 A ZN-65 6.0E-12 8.4E-13 6.0E-12 0.0E-01 1.0E 00 7.1E 00 A ,
C SPIKED CO-57 3.8E-02 '
oE-04 3.9E-02 0.0E-01 1.0E 00 8.4E 01 A 8.2E-02 9.8E-04 8.3E-02 0.0E-01 1.0E 00 8.4E 01 A I S -l od o CO-60 4.6E 00 A HG-203 1.OE-01 2.3E-02 8.1E-02 0.0E-01 7.8E-01 ,
Y-88 1.5E-01 4.3E-03 1.5E-01 0.0E-01 9.8E-01 3.6E 01 -A i
~
CD-109 1.6E 00 1.2E-02 1.5E 00 0.0E-01 9.3E-01 1.4E 02 A SN-113 1.1E-01 3.2E-03 1.1E-01 0.0E-01 9.6E-01 3.5E 01 A ;
CS-137 6.9E-02 7.6E-04 6.6E-02 0.0E-01 9.5E-01 9.1E 01 A <
CE-139 4.3E-02 1.0E-03 4.5E-02 0.0E-01 1.0E 00 4.2E 01 A l
I L WASTE CR-51- 2.3E-06 5.6E-07 1.6E-06 0.0E-01 6.9E-01 4.2E 00 A a f.? gqq MN-54 8.5E-07 7.7E-08 6.5E-07 0.0E-01 7.7E-01 1.1E 01 A CO-60 3.5E-06 1.4E-07 2.8E-06 0.0E-01 8.1E-01 2.5E 01 A CS-137 1.1E-06 9.1E-08 8.3E-07 0.0E-01 7.8E-01 1.2E 01 A i
C EPIKED CO-57 3.8E-02 4.6E-04 3.7E-02 0.0E-01 9.7E-01 8.4E 01 A I gg.gogg CO-60 8.2E-02 9.8E-04 8.OE-02 0.0E-01 9.7E-01 8.4E 01 A HG-203 1.0E-01 2.3E-02 1.1E-01 0.0E-01 1.1E 00 4.6E 00 A Y-88 1.5E-01 4.3E-03 1.5E-01 0.0E-01 9.8E-01 3.6E 01 A l T TEST RESULTS:
A= AGREEMENT D= DISAGREEMENT o= CRITERIA RELAXED N=NO COMPARISON l l
'
-2-
- . _ _ - _ _ _ _ _ - _ _ _
_ _ _ _ _ _ _ _ _ _ _ _
<
.
-
.
..
TABLE 1 U S NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT CONFIRMATORY MEASUREMENTS PROGRAM FACILITY: QUAD CITIES FOR THE 3 OUARTER OF 1989
--NRC--- - -
LICENSEE- LICENSEE:NRC----
SAMPLE ISOTOPE RESULT ERROR- RESULT ERROR RATIO RES T C SPIKED CD-109 1.6E 00 1.2E-02 1.5E 00 0.0E-01 9.3E-01 1.4E 02 A SN-113 1.1E-01 3.2E-03 1.0E-01 0.0E-01 8.8E-01 3.5E 01 A CE-137 6.9E-02 7.6E-04 6.4E-02 0.0E-01 9.3E-01 9.1E 01 A CE-139 4.3E-02 1.0E-03 4.3E-02 0.0E-01 1.0E 00 4.2E 01 A OFF GAS KR-85M 2.0E-04 4.6E-06 2.1E-04 0.0E-01 1.1E 00 4.3E 01 A gg. gag;pKR-87 3.2E-04 2.5E-05 2.6E-04 0.0E-01 8.2E-01 1.3E 01 A KR-88 4.8E-04 1.8E-05 5.1E-04 0.0E-01 1.1E 00 2.7E 01 A XE-131M 2.7E-04 8.4E-05 2.9E-04 0.0E-01 1.1E 00 3.2E 00 A XE-133 1.7E-04 5.7E-06 1.8E-04 0.0E-01 1.1E 00 3.0E 01 A XE-135 1.6E-03 9.9E-06 1.7E-03 0.0E-01 1.1E 00 1.6E 02 A L WASTE CR-51 2.1E-06 4.1E-07 1.7E-06 0.0E-01 8.2E-01 5.0E 00 A gg.gos A MN-54 6.9E-07 8.5E-08 7.3E-07 0.0E-01 1.0E 00 8.1E'00 A CO-60 3.5E-06 1.4E-07 2.BE-06 0.0E-01 8.1E-01 2.4E 01 A CS-137 9.7E-07 8.9E-08 7.7E-07 0.0E-01 8.0E-01 1.1E 01 A OFF GAS KR-85M~ 1.9E-04 5.5E-06 2.4E-04 0.0E-01 1.2E 00 3.5E 01 A 13 -f oq o KR-87 2.9E-04 3.0E-05 3.2E-04 0.0E-01 1.1E 00 9.6E 00 A KR-88 5.1E-04 2.3E-05 5.5E-04 0.0E-01 1.1E 00 2.2E 01 A XE-133 1.7E-04 5.5E-06 2.0E-04 0.0E-01 1.2E 00 3.2E 01 A XE-135 1.6E-03 1.0E-05 1.BE-03 0.0E-01 1.1E 00 1.6E 02 A T TEST RESULTS:
A= AGREEMENT-D= DISAGREEMENT o= CRITERIA RELAXED N=NO COMPARISON-3-
_ _______ ___ _ -
.
, ,,
-
.
..
.
ATTACHMENT 1 CRITERIA FOR COMPARING ANflYTICAL MEASUREMENTS .
This attachment provides criteria for comparing results of capability tests and verification measurements. The criteria are based on an empirical relationship which combines prior experience and the accuracy needs of this progra In these criteria, the judgment limits are variable in relation to the comparison of the NRC's value to its associated one sigma uncertainty. As that ratio, referred to in this program as " Resolution", increases, the acceptability of a licensee's measurement should be more selectiv should be considered acceptable as the resolution decreases. Conversely, poorer agre The values in the ratio criteria may be rounded to fewer significant figures reported by the NRC Reference Laboratory, unless such rounding will result in a narrowed category of acceptanc RESOLUTION RATIO = LICENSEE VALUE/NRC REFERENCE VALUE ei Agreement
<4 0.4 - .5 - .6 - 1.66 16 - 50 0.75 - 1.33 '
51 - 200 0.80 - 1.25 200 - 0.85 - 1.18 Some discrepancies may result from the use of different equipment, techniques, and for some specific nuclides. These may be factored into the acceptance criteria and identified on the data shee .
b
.