Confirms Equipment Qualification Insps 50-250/87-08 & 50-251/87-08 Scheduled for 870223-27,per Alexander Telcons.Review Items Listed.Insp Team Roster Encl.W/O Encl
ML20210E234
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 02/06/1987
From: Merschoff E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To: Woody C
FLORIDA POWER & LIGHT CO.
References
NUDOCS 8702100255
Download: ML20210E234 (2)


Text

"'

/ ~

o UNITED STATES .

! n NUCLEAR REGULATORY COMMISSION

{ g WASHINGTON, D. C. 20656

\*****/ February 6, 1987 Docket No. 50-250,251 Florida Power and Light Company ATTN: Mr. C. O. Woody, Group Vice President Nuclear Energy Department Post Office Box 14000 JNE, JB Juno Beach, Florida 33408-0420 Dear Mr. Woody SUBJECT: EQUIPMENT QUALIFICATION INSPECTION OF TURKEY POINT NUCLEAR GENERATING STATION (Inspection Nos. 50-250/87-08,251/87-08)

This letter confirms the dates of February 23 through 27, 1987 for the NRC equipment qualification (EQ) inspection for Turkey Point. These dates were established during previous telephone conversations with your staff by Pr.

S. Alexander of this office. The inspection will take place at the FP&L Engi-neering Offices in Juno Beach on February 23, 24, 26 and 27 and at at the plant site on February 25, 1987.

A management entrance meeting is scheduled for 1:00 p.m. on February 23, 1987 at the FP&L Engineering Offices. A management exit meeting is tentatively scheduled for 10:00 a.m. on February 27, 1987 at the Engineering Offices. A plant walkdown inspection is planned for Wednseday, February 25, 1987.

The inspection will include the following:

1. Review of your implementation of a 10 CFR 50.49 program including preser-vation of the qualified status of qualified eouipment.

2. Review of your implementation of Technical Evaluation Report / Safety Eval-uation Report EQ corrective action cemitments.

3. Review of EQ documentation files.

4 Physical inspection of selected plant equipment and selected field wiring. j B702100255 870206 PDR ADOCK 05000250 0 PDR i

. -. .-

-

y

. %

Florida Power and Light Company -2- February 6, 1987 Your cooperation with us during this inspection will be appreciated. Should you have any questions regarding this inspection, please contact Mr. Stephen Alexander of NRC IE, the lead inspector, at (301) 492-7155 or Mr. Albert Ruff of NRC RII at (404) 331-4875.

Sincerely, original signed by:

Ellis W. Merschoff, Acting Chief Vendor Program Branch Division of Quality Assurance, Vendor and Technical Training Center Programs Office of Inspection and Enforcement

Enclosure:

Inspection Team Roster

REGION II DISTRIBUTION:

AGibson, D:DRS AHerdt, C:EB, DRS TConlon, C:PSS, EB ARuff, PSS, EB NMerriweather, PSS, EB BWilson, SC:PS2C, RPB2, DRP DBrewer, SRI, USNRC, Turkey Point Nuclear Generating Station, P. O. Box 57-1185, Miami, FL 33257-1185 VPB b SC/VP QAVT PB:DQAVT SAlexander:tt UPotapovs hoff 2/,(/87 2/$/87 (/87