Comment Supporting NEI Comments on Proposed Rule 10CFR73 Re Changes to NPP Security Requirements Associated W/ Containment Access Control
ML20085E591
Person / Time
Site: Hatch, Vogtle  Southern Nuclear icon.png
Issue date: 06/06/1995
From: Beckham J
GEORGIA POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
FRN-60FR24803, RULE-PR-73 60FR24803-00016, 60FR24803-16, HL-4862, LCV-0625, LCV-625, NUDOCS 9506190035
Download: ML20085E591 (2)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

4 Georgia Power Compmy 40 inverness Cent:r Parkwsy Post Office Box 1295

. Telephone 205 877 7279 DOCKETED USHRC TD- /6 c~\\ L J. T. Beckham, Jr. 7; JN 5 A8 :34 GeorgiaPower nt Nuclear "

vgPres p,,

0FFICE Of SE0iiLT/ tRY'.996 00CKET14G & 3LRViCE Docket Nos. 50-321 50M$'" HL-4862 50-366 50-425 LCV-0625 U. S. Nuclear Regulatory Commission gg3ET t-;r06 9 gg73 ATTN: Document Control Desk Washington, D. C. 20555 (f O f k 2NO3,}

Comments on Proposed Rule

" Changes to Nuclear Power Plant Security Requirements Associated with Containment Access Control" (60 Federal Register 24803 dated May 10.1995)

Dear Sir:

Georgia Power Company has reviewed the proposed rule " Changes to Nuclear Power Plant Security Requirements Associated with Containment Access Control," published in the Federal Register on May 10,1995. In accordance with request for comments, Georgia Power Company is in total agreement with the NEI comments which are to be provided to the NRC.

Should you have any questions, please advise.

Respectfully submitted, N &

J. T. Beckham, Jr. (

JTB/JDB 9506190035 950606 n Uy/O PDR PR 73 60FR24803 PDR'

i O

GeorgiaPower d U. S. Nuclear Regulatory Commission Page Two June 6, 1995 1

cc- Georgia Power Company  ;

C. K. McCoy, Vice President - Plant Vogtle J. B. Beasley, General Manager - Vogtle Electric Generating Plant l H. L. Sumner, Jr., General Manager - Plant Hatch U. S. Nuclear Regulatory Commission. Washington. DC K. N. Jabbour, Licensing Project Manager - Hatch D. S. Hood, Licensing Project Manager, Vogtle U. S. Nuclear Reculatory Commission. Recion II l S. D. Ebneter, Regional Administrator l B. L. Holbrook, Senior Resident Inspector - Hatch B. R. Bonser, Senior Resident Inspector - Vogtle l

HL-4862 LCV-0625 File: G.02.17 l