CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions

From kanterella
(Redirected from CNL-24-074)
Jump to navigation Jump to search
Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions
ML24297A600
Person / Time
Site: Browns Ferry, Sequoyah, Watts Bar  Tennessee Valley Authority icon.png
Issue date: 10/23/2024
From: Edmondson C
Tennessee Valley Authority
To:
Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation, Document Control Desk
References
CNL-24-074
Download: ML24297A600 (1)


Text

1101 Market Street, Chattanooga, Tennessee 37402

CNL-24-074

October 23, 2024

10 CFR 50.54(q) 10 CFR 72.44(f)

ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001

Browns Ferry Nuclear Plant, Units 1, 2, and 3 Renewed Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, 50-296, and 72-052

Sequoyah Nuclear Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327, 50-328, and 72-034

Watts Bar Nuclear Plant, Units 1 and 2 Facility Operating License Nos. NPF-90 and NPF-96 NRC Docket Nos. 50-390, 50-391, and 72-1048

Subject:

Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions

In accordance with the requirements of Title 10 of the Code of Federal Regulations (10 CFR) 50.54(q) and 10 CFR 72.44(f), Tennessee Valley Authority (TVA) is submitting a description of changes to the TVA Radiological Emergency Plan (REP). The affected documents are the Central Emergency Control Center (CECC) Emergency Plan Implementing Procedure (EPIP) and fleet procedure listed below.

Document Revision Title Effective Date

CECC EPIP-7 50 CECC Radiological Assessment 10/3/2024 Staff Procedure for Alert, Site Area Emergency, and General Emergency

NPG-SPP-18.3.7 5 Alternate Facility Activation 10/10/2024 and Operation

U.S. Nuclear Regulatory Commission CNL-24-074 Page 2 October 23, 2024

Description of Changes and Summary Analysis

CECC EPIP-7

TVA revised this EPIP as follows.

Attachment 2, Radiological Asse ssment Managers Checklist

An editorial change was made to correct a page roll by adding a page break.

Attachment 3, Radiological Assessment Coordinators Checklist

Editorial changes were made to update the procedure reference in General Operations step 7, to correct the pagination for the page 1 attachment heading, and to add a heading for page 2 of this attachment.

NPG-SPP-18.3.7

TVA updated the cover page of this fleet procedure to reflect the performance of a 4-year cadence review. No other changes were made.

The above changes were evaluated in accordance with 10 CFR 50.54(q)(3). TVA determined that the changes did not reduce the effectiveness of the TVA REP. The TVA REP, as revised, continues to meet the requirements in Appendix E to 10 CFR 50 and the planning standards of 10 CFR 50.47(b).

There are no new regulatory commitments in this letter. Please address any questions regarding this submittal to Amber V. Aboulfaida, Senior Manager, Fleet Licensing, at avaboulfaida@tva.gov.

Respectfully,

Kimberly D. Hulvey General Manager, Nuclear Regulatory Affairs & Emergency Preparedness

cc:

NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant NRC Project Manager - Browns Ferry Nuclear Plant NRC Project Manager - Sequoyah Nuclear Plant NRC Project Manager - Watts Bar Nuclear Plant NRC Director - Division of Spent Fuel Management, NMSS