Letter Sequence Request |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
Other: 3F0112-11, Corrections to the Extended Power Uprate LAR 309 Vendor Affidavit and Technical Report, 3F0113-08, Attachment D: ANP-3195(NP), Revision 0, Response for Crystal River Unit 3, EPU Licensing Amendment Report NRC Reactor Systems Branch Requests for Additional Information (Non-Proprietary) and Attachment E: Location of Reactor Systems RAI Re, 3F0712-03, Attachment E to 3F0712-03, Technical Report, ANP-3052, Rev. 2, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip., 3F0912-01, ANP-3156 Np, Crystal River 3 EPU Boric Acid Precipitation RAI Responses, Attachment C, 3F1011-08, ANP-3052, Rev. 0, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip, 3F1112-02, 17877-0001-100, Rev. 1, CR-3 Inadequate Core Cooling Mitigation System Reliability Assessment, Task 1, Page 174 of 250 Through Page 250 of 250, ML11259A012, ML11300A226, ML11342A195, ML12031A032, ML12053A231, ML12107A068, ML12202A734, ML12205A357, ML12205A358, ML12240A119, ML12255A409, ML12262A385, ML12314A391, ML12314A392, ML12314A393, ML13032A540
|
MONTHYEAR3F0811-04, Response to Request for Additional Information to Support NRC Probabilistic Risk Assessment Licensing Branch Acceptance Review of the CR-3 Extended Power Uprate LAR2011-08-11011 August 2011 Response to Request for Additional Information to Support NRC Probabilistic Risk Assessment Licensing Branch Acceptance Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0811-02, Response to Request for Additional Information to Support NRC Balance of Plant Branch Acceptance Review of the CR-3 Extended Power Uprate LAR2011-08-11011 August 2011 Response to Request for Additional Information to Support NRC Balance of Plant Branch Acceptance Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0811-01, Response to Request for Additional Information to Support NRC Instrumentation and Controls Branch Acceptance Review of the CR-3 Extended Power Uprate LAR2011-08-18018 August 2011 Response to Request for Additional Information to Support NRC Instrumentation and Controls Branch Acceptance Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0811-03, Response to Request for Additional Information to Support NRC Mechanical and Civil Branch Acceptance Review of the CR-3 Extended Power Uprate LAR2011-08-25025 August 2011 Response to Request for Additional Information to Support NRC Mechanical and Civil Branch Acceptance Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI ML11259A0122011-09-14014 September 2011 NRR E-mail Capture - Clarification for August 25 Emcb RAI Acceptance Review Letter Project stage: Other ML11286A0922011-10-11011 October 2011 Response to Request for Additional Information to Support NRC Reactor Systems Branch Acceptance Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI ML11300A2262011-10-25025 October 2011 Feedwater Line Break Overpressure Protection Analysis to Support NRC Reactor Systems Branch Acceptance Review of the CR-3 Extended Power Update LAR and LAR Approval Schedule Project stage: Other 3F1011-08, ANP-3052, Rev. 0, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip2011-10-25025 October 2011 ANP-3052, Rev. 0, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip Project stage: Other ML11326A2312011-12-0707 December 2011 Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI ML12205A3572011-12-15015 December 2011 Attachment a to 3F0712-03, CR-3 LOCA Summary Report - EPU/ROTSG/Mark-B-HTP, Revision 4 Project stage: Other 3F1211-05, Response to Request for Additional Information to Support NRC Health Physics and Human Performance Branch Technical Review of the CR-3 Extended Power Uprate LAR2011-12-15015 December 2011 Response to Request for Additional Information to Support NRC Health Physics and Human Performance Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F1211-06, Response to Request for Additional Information to Support NRC Vessels and Internals Integrity Branch Technical Review of the CR-3 Extended Power Uprate LAR2011-12-15015 December 2011 Response to Request for Additional Information to Support NRC Vessels and Internals Integrity Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F1211-10, Response to Request for Additional Information to Support NRC Fire Protection Branch Technical Review of the CR-3 Extended Power Uprate LAR2011-12-21021 December 2011 Response to Request for Additional Information to Support NRC Fire Protection Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0112-04, Response to Request for Additional Information to Support NRC Steam Generator Tube Integrity and Chemical Engineering Branch Technical Review of the CR-3 Extended Power Uprate LAR2012-01-0505 January 2012 Response to Request for Additional Information to Support NRC Steam Generator Tube Integrity and Chemical Engineering Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI ML12030A2092012-01-0505 January 2012 Response to Request for Additional Information to Support NRC Instrumentation and Control Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI ML11342A1952012-01-0606 January 2012 Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for a Hearing and Order Imposing Procedures for Document Access to Sensitive Unclassified Non-safeguards Information Project stage: Other ML12024A3002012-01-19019 January 2012 Response to Request for Additional Information to Support NRC Component Performance and Testing Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0112-06, Response to Request for Additional Information to Support NRC Piping and NDE Branch Technical Review of the CR-3 Extended Power Uprate LAR2012-01-19019 January 2012 Response to Request for Additional Information to Support NRC Piping and NDE Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0112-11, Corrections to the Extended Power Uprate LAR 309 Vendor Affidavit and Technical Report2012-01-31031 January 2012 Corrections to the Extended Power Uprate LAR #309 Vendor Affidavit and Technical Report Project stage: Other ML12003A2172012-02-0808 February 2012 Nuclear Generating Plant - Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI ML12052A1302012-03-0202 March 2012 Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI ML12053A2312012-03-0202 March 2012 Request for Withholding Proprietary Information from Public Disclosure Related Extended Power Uprate Technical Report Project stage: Other 3F0312-02, Response to Second Request for Additional Information to Support NRC Instrumentation and Controls Branch (Eicb) Technical Review of the CR-3 Extended Power Uprate LAR2012-03-19019 March 2012 Response to Second Request for Additional Information to Support NRC Instrumentation and Controls Branch (Eicb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Request 3F0312-01, Response to Request for Additional Information to Support NRC PRA Licensing Branch Technical Review of the CR-3 Extended Power Uprate LAR2012-03-22022 March 2012 Response to Request for Additional Information to Support NRC PRA Licensing Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI ML12031A0322012-03-26026 March 2012 Request for Withholding Proprietary Information from Public Disclosure Related to Extended Power Uprate Technical Report Project stage: Other ML12107A0682012-04-0404 April 2012 NRR E-mail Capture - Crystal River, Unit 3 EPU LAR - Clarifications for Component Performance & Testing Branch (Eptb) Project stage: Other 3F0412-05, Response to Second Request for Additional Information to Support NRC Health Physics and Human Performance Branch (Ahpb) Technical Review of the CR-3 Extended Power Uprate LAR2012-04-0404 April 2012 Response to Second Request for Additional Information to Support NRC Health Physics and Human Performance Branch (Ahpb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Request 3F0412-04, Response to Request for Additional Information to Support NRC Mechanical and Civil Engineering Branch (Emcb) Technical Review of the CR-3 Extended Power Uprate LAR2012-04-0404 April 2012 Response to Request for Additional Information to Support NRC Mechanical and Civil Engineering Branch (Emcb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0412-07, Response to Request for Additional Information to Support NRC Containment and Ventilation Branch (Scvb) Technical Review of the CR-3 Extended Power Uprate LAR2012-04-12012 April 2012 Response to Request for Additional Information to Support NRC Containment and Ventilation Branch (Scvb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0412-06, Response to Request for Additional Information to Support NRC Electrical Systems Branch (Eeeb) Technical Review of the CR-3 Extended Power Uprate LAR2012-04-16016 April 2012 Response to Request for Additional Information to Support NRC Electrical Systems Branch (Eeeb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0412-09, Response to Request for Additional Information to Support NRC Accident Dose Branch (Aadb) Technical Review of the CR-3 Extended Power Uprate LAR2012-04-26026 April 2012 Response to Request for Additional Information to Support NRC Accident Dose Branch (Aadb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI ML12102A0442012-05-0404 May 2012 Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI ML12314A3912012-05-31031 May 2012 17877-0002-100, CR-3 Inadequate Core Cooling Mitigation System Reliability Assessment 2 Project stage: Other ML12205A3582012-05-31031 May 2012 Attachment D to 3F0712-03, Technical Report, ANP-3114(NP), Rev. 0, CR-3 EPU - Feedwater Line Break Analysis Sensitivity Studies. Project stage: Other 3F0612-05, Response to Request for Additional Information to Support NRC Nuclear Performance and Code Review Branch (Snpb) Technical Review of the CR-3 Extended Power Uprate LAR2012-06-18018 June 2012 Response to Request for Additional Information to Support NRC Nuclear Performance and Code Review Branch (Snpb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0712-03, Attachment E to 3F0712-03, Technical Report, ANP-3052, Rev. 2, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip.2012-06-30030 June 2012 Attachment E to 3F0712-03, Technical Report, ANP-3052, Rev. 2, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip. Project stage: Other ML12184A3442012-07-0202 July 2012 NRR E-mail Capture - Crystal River, Unit 3 EPU LAR - Discussion/Clarification of Emcb Draft RAIs Project stage: Draft Other ML12174A2922012-07-0505 July 2012 Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI ML12171A3472012-07-0505 July 2012 Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI ML12205A3562012-07-17017 July 2012 Supplement to the Extended Power Uprate License Amendment Request #309 Project stage: Supplement 3F0712-06, Response to Second Request for Additional Information to Support NRC Steam Generator Tube Integrity and Chemical Engineering Branch (Esgb) Technical Review of the CR-3 Extended Power Uprate LAR2012-07-17017 July 2012 Response to Second Request for Additional Information to Support NRC Steam Generator Tube Integrity and Chemical Engineering Branch (Esgb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Request ML12194A4172012-07-17017 July 2012 Generating Plant - Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI 3F0712-07, Response to Third Request for Additional Information to Support NRC Health Physics and Human Performance Branch (Ahpb) Technical Review of the CR-3 Extended Power Uprate LAR2012-07-31031 July 2012 Response to Third Request for Additional Information to Support NRC Health Physics and Human Performance Branch (Ahpb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Request 3F0712-08, Response to Second Request for Additional Information to Support NRC PRA Licensing Branch (Apla) Technical Review of the CR-3 Extended Power Uprate LAR2012-07-31031 July 2012 Response to Second Request for Additional Information to Support NRC PRA Licensing Branch (Apla) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Request ML12125A1622012-08-0101 August 2012 Nuclear Generating Plant - Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI ML12202A7342012-08-0101 August 2012 Request for Withholding Proprietary Information from Public Disclosure Related to Extended Power Uprate Technical Report Project stage: Other ML12202A0602012-08-0202 August 2012 Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI ML12213A3032012-08-0303 August 2012 Request for Additional Information for Extended Power Uprate License Amendment Request (Srxb) Project stage: RAI ML12219A1912012-08-16016 August 2012 Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI 3F0812-02, Response to Second Request for Additional Information to Support NRC Electrical Engineering Branch (Eeeb) Technical Review of the CR-3 Extended Power Uprate LAR2012-08-21021 August 2012 Response to Second Request for Additional Information to Support NRC Electrical Engineering Branch (Eeeb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Request 2012-03-26
[Table View] |
|
---|
Category:Letter type:
MONTHYEAR3F0623-01, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-06-0101 June 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G 3F0423-03, 2022 Annual Radiological Environmental Operating Report2023-04-18018 April 2023 2022 Annual Radiological Environmental Operating Report 3F0423-02, 2022 Annual Radioactive Effluent Release Report2023-04-18018 April 2023 2022 Annual Radioactive Effluent Release Report 3F0423-01, 2022 Individual Monitoring NRC Form 5 Report2023-04-0404 April 2023 2022 Individual Monitoring NRC Form 5 Report 3F0323-03, Decommissioning Funding Plan for Independent Spent Fuel Storage Installation2023-03-31031 March 2023 Decommissioning Funding Plan for Independent Spent Fuel Storage Installation 3F0323-02, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20222023-03-29029 March 2023 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2022 3F0323-01, Onsite Property Insurance Coverage2023-03-0202 March 2023 Onsite Property Insurance Coverage 3F0123-01, Proof of Financial Protection2023-01-26026 January 2023 Proof of Financial Protection 3F1222-01, Nuclear Power Station - License Amendment Request 262 Addition of License Condition 2.C.21, License Termination Plan2022-12-12012 December 2022 Nuclear Power Station - License Amendment Request 262 Addition of License Condition 2.C.21, License Termination Plan 3F0522-03, Notification of Revised Decommissioning Cost Estimate2022-05-26026 May 2022 Notification of Revised Decommissioning Cost Estimate 3F0522-01, Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 20222022-05-17017 May 2022 Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 2022 3F0422-02, 2021 Annual Radiological Environmental Operating Report2022-04-0606 April 2022 2021 Annual Radiological Environmental Operating Report 3F0322-01, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20212022-03-30030 March 2022 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2021 3F0322-03, Drug and Alcohol Testing Error at HHS-Certified Laboratory, Per 10CFR26.719(c)(1)2022-03-10010 March 2022 Drug and Alcohol Testing Error at HHS-Certified Laboratory, Per 10CFR26.719(c)(1) 3F0322-02, 2021 Individual Monitoring NRC Form 5 Report2022-03-0707 March 2022 2021 Individual Monitoring NRC Form 5 Report 3F0222-01, ADP CR3, LLC - Update to Irradiated Fuel Management Program Pursuant to 10 CFR 50.54(bb)2022-02-0909 February 2022 ADP CR3, LLC - Update to Irradiated Fuel Management Program Pursuant to 10 CFR 50.54(bb) 3F0222-02, Onsite Property Insurance Coverage2022-02-0909 February 2022 Onsite Property Insurance Coverage 3F0122-01, License Amendment Request to Remove from the Facility Operating License, Appendix B, Environmental Protection Plan (Non-Radiological) Technical Specifications2022-01-26026 January 2022 License Amendment Request to Remove from the Facility Operating License, Appendix B, Environmental Protection Plan (Non-Radiological) Technical Specifications 3F0122-02, Proof of Financial Protection2022-01-17017 January 2022 Proof of Financial Protection 3F0122-03, Complex - Environmental Protection Plan Report: 2021 Sea Turtle Rescue and Recovery Summary Report2022-01-17017 January 2022 Complex - Environmental Protection Plan Report: 2021 Sea Turtle Rescue and Recovery Summary Report 3F1021-01, Report of Investigation Pursuant to 10 CFR 20, Appendix G2021-10-21021 October 2021 Report of Investigation Pursuant to 10 CFR 20, Appendix G 3F0921-02, Reporting Related to the National Pollutant Discharge Elimination System (NPDES) Permit Id FL0A00004 (Minor) (Rev. C)2021-09-29029 September 2021 Reporting Related to the National Pollutant Discharge Elimination System (NPDES) Permit Id FL0A00004 (Minor) (Rev. C) 3F0921-01, to License Amendment Request, Revision 0, ISFSI Security Plan, Revision a2021-09-14014 September 2021 to License Amendment Request, Revision 0, ISFSI Security Plan, Revision a 3F0721-01, Report of Investigation Pursuant to 10 CFR 20, Appendix G2021-07-13013 July 2021 Report of Investigation Pursuant to 10 CFR 20, Appendix G 3F0621-02, Reporting Related to the National Pollutant Discharge Elimination System (NPDES) Permit Id FL0A00004-001-IW1S2021-06-16016 June 2021 Reporting Related to the National Pollutant Discharge Elimination System (NPDES) Permit Id FL0A00004-001-IW1S 3F0421-05, 2020 Individual Monitoring NRC Form 5 Report2021-04-27027 April 2021 2020 Individual Monitoring NRC Form 5 Report 3F0421-04, ADP CR3, LLC - Supplement to Application for Order Approving Indirect Transfers of Control of Licenses in Connection with Internal Corporate Reorganization2021-04-13013 April 2021 ADP CR3, LLC - Supplement to Application for Order Approving Indirect Transfers of Control of Licenses in Connection with Internal Corporate Reorganization 3F0421-03, Proof of Financial Protection2021-04-0707 April 2021 Proof of Financial Protection 3F0421-01, 2020 Annual Radioactive Effluent Release Report2021-04-0606 April 2021 2020 Annual Radioactive Effluent Release Report 3F0421-02, 2020 Annual Radiological Environmental Operating Report2021-04-0606 April 2021 2020 Annual Radiological Environmental Operating Report 3F0321-07, (XEG)-DOE/NRC Forms 741 742 and 743C2021-03-30030 March 2021 (XEG)-DOE/NRC Forms 741 742 and 743C 3F0321-06, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20202021-03-29029 March 2021 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2020 3F0321-01, License Amendment Request, Revision to Independent Spent Fuel Storage Installation (ISFSI)-Only Emergency Plan, Draft a, and ISFSI Only Emergency Action Level Bases Manual2021-03-17017 March 2021 License Amendment Request, Revision to Independent Spent Fuel Storage Installation (ISFSI)-Only Emergency Plan, Draft a, and ISFSI Only Emergency Action Level Bases Manual 3F0321-02, License Amendment Request, Rev. 0, ISFSI Security Plan, Rev. a2021-03-17017 March 2021 License Amendment Request, Rev. 0, ISFSI Security Plan, Rev. a 3F0321-05, Onsite Property Insurance Coverage2021-03-15015 March 2021 Onsite Property Insurance Coverage 3F0321-03, Report of Investigation Pursuant to 10 CFR 20, Appendix G2021-03-0909 March 2021 Report of Investigation Pursuant to 10 CFR 20, Appendix G 3F0221-02, Report of Investigation Pursuant to 10 CFR 20, Appendix G2021-02-17017 February 2021 Report of Investigation Pursuant to 10 CFR 20, Appendix G 3F0221-01, ADP CR3, Llc., Crystal River Energy Complex - Environmental Protection Plan Report: 2020 Sea Turtle Rescue and Recovery Summary Report2021-02-0202 February 2021 ADP CR3, Llc., Crystal River Energy Complex - Environmental Protection Plan Report: 2020 Sea Turtle Rescue and Recovery Summary Report 3F0121-02, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E2021-01-19019 January 2021 Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E 3F0121-01, Report of Investigation Pursuant to 10 CFR 20, Appendix G2021-01-19019 January 2021 Report of Investigation Pursuant to 10 CFR 20, Appendix G 3F1120-02, and Crystal River Nuclear Plant - Application for Order Approving Indirect Transfers of Control of Licenses in Connection with Internal Corporate Reorganization2020-11-19019 November 2020 and Crystal River Nuclear Plant - Application for Order Approving Indirect Transfers of Control of Licenses in Connection with Internal Corporate Reorganization 3F0920-02, Request to Transfer the Quality Assurance Program Approval Form for Radioactive Material Packages2020-09-15015 September 2020 Request to Transfer the Quality Assurance Program Approval Form for Radioactive Material Packages 3F0920-01, License Transfer - Notification of Transfer Date2020-09-15015 September 2020 License Transfer - Notification of Transfer Date 3F0720-03, ISFSI Only Emergency Plan and Implementing Procedure2020-07-21021 July 2020 ISFSI Only Emergency Plan and Implementing Procedure 3F0720-02, License Transfer - Insurance Required of a Licensee Under 10 CFR 140.11(a)(4) and 10 CFR 50.54(w)2020-07-15015 July 2020 License Transfer - Insurance Required of a Licensee Under 10 CFR 140.11(a)(4) and 10 CFR 50.54(w) 3F0520-01, Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 20202020-05-18018 May 2020 Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 2020 3F0420-03, Supplemental Information in Support of Crystal River Unit 3 License Transfer Application - Amended License Conditions2020-04-22022 April 2020 Supplemental Information in Support of Crystal River Unit 3 License Transfer Application - Amended License Conditions 3F0420-01, 2019 Annual Radioactive Effluent Release Report2020-04-0707 April 2020 2019 Annual Radioactive Effluent Release Report 3F0420-02, 2019 Radiological Environmental Operating Report2020-04-0707 April 2020 2019 Radiological Environmental Operating Report 3F0320-04, Decommissioning Funding Plan for Independent Spent Fuel Storage Installation2020-03-19019 March 2020 Decommissioning Funding Plan for Independent Spent Fuel Storage Installation 2023-06-01
[Table view] |
Text
Duke Energy@
Crystal River Nuclear Plant Docket No. 50-302 Operating License No. DPR-72 December 18, 2012 3F1212-08 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Crystal River Unit 3 - Response to Third Request for Additional Information to Support NRC Vessels and Internals Integrity Branch (EVIB) Technical Review of the CR-3 Extended Power Uprate LAR (TAC No. ME6527)
References:
- 1. FPC to NRC letter dated June 15, 2011, "Crystal River Unit 3 - License Amendment Request #309, Revision 0, Extended Power Uprate" (ADAMS Accession No. ML112070659)
- 2. FPC to NRC letter dated September 27, 2012, "Crystal River Unit 3 -
Response to Second Request for Additional Information to Support NRC Vessels and Internals Integrity Branch (EIVB) Technical Review of the CR-3 Extended Power Uprate LAR (TAC No. ME6527)" (ADAMS Accession No. ML12272A344)
- 3. Email from S. Lingam (NRC) to D. Westcott (FPC) dated October 2, 2012, "RE: Crystal River, Unit 3 EPU LAR - Draft RAIs from EVIB (TAC No.
ME6527)"
- 4. Email from S. Lingam (NRC) to D. Westcott (FPC) dated October 9, 2012, "RE: PHONE CALL WITH FPL FOR CRYSTAL RIVER EPU RAI response submitted on 9/27/12 (EVIB) - ME6527"
- 5. Email from S. Lingam (NRC) to D. Westcott (FPC) dated November 1, 2012, "RE: EIVB RAI follow-up questions" (ADAMS Accession No. ML12313A112)
Dear Sir:
By letter dated June 15, 2011, Florida Power Corporation (FPC) requested a license amendment to increase the rated thermal power level of Crystal River Unit 3 (CR-3) from 2609 megawatts (MWt) to 3014 MWt (Reference 1). On September 27, 2012, FPC provided a response to the NRC request for additional information (RAI) regarding the CR-3 pressure and temperature limits and the CR-3 Materials Reliability Program inspection requirements (Reference 2). On October 2, 2012 and October 9, 2012, via electronic mail, the NRC provided clarifying questions regarding the FPC RAI responses (References 3 and 4) and a teleconference was conducted between the NRC and FPC on October 10, 2012, to discuss the clarifications. On October 11, 2012, following the teleconference, additional clarifications were provided via electronic mail Crystal River Nuclear Plant 15760 W. Powerline Street Crystal River, FL 34428
U.S. Nuclear Regulatory Commission Page 2 of 3 3F1212-08 needed to complete the EVIB evaluation of the CR-3 Extended Power Uprate (EPU) License Amendment Request (LAR) and confirmed by the NRC staff via electronic mail on November 1, 2012 (Reference 5).
The attachment to this correspondence, "Response to Third Request for Additional Information -
Vessels and Internals Integrity Branch Technical Review of the CR-3 EPU LAR," provides the formal response to the RAI.
This correspondence contains no new regulatory commitments.
If you have any questions regarding this submittal, please contact Mr. Dan Westcott.
Superintendent, Licensing and Regulatory Programs at (352) 563-4796.
Since~O. ,
Jon YA ranke Pyig President (Crystal River Nuclear Plant JAF/gwe
Attachment:
Response to Third Request for Additional Information -Vessels and Internals Integrity Branch Technical Review of the CR-3 EPU LAR xc: NRR Project Manager Regional Administrator, Region II Senior Resident Inspector State Contact
U.S. Nuclear Regulatory Commission Page 3 of 3 3F1212-08 STATE OF FLORIDA COUNTY OF CITRUS Jon A. Franke states that he is the Vice President, Crystal River Nuclear Plant for Florida Power Corporation; that he is authorized on the part of said company to sign and file with the Nuclear Regulatory Commission the information attached hereto; and that all such statements made and matters set forth therein are true and correct to the best of his knowledge, information.,
and belief. ----
JO,?{A. Franke
/Vice President Crystal River Nuclear Plant The foregoing document was acknowledged before me this I day of
. 2012, by Jon A. Franke.
Signature of Notary Public State of Florida (Print, type, or stamp Commissioned Name of Notary Public)
Personally Produced Known -OR- Identification
FLORIDA POWER CORPORATION CRYSTAL RIVER UNIT 3 DOCKET NUMBER 50-302 / LICENSE NUMBER DPR-72 ATTACHMENT RESPONSE TO THIRD REQUEST FOR ADDITIONAL INFORMATION -VESSELS AND INTERNALS INTEGRITY BRANCH TECHNICAL REVIEW OF THE CR-3 EPU LAR
U. S. Nuclear Regulatory Commission Attachment 3F1212-08 Page 1 of 8 RESPONSE TO THIRD REQUEST FOR ADDITIONAL INFORMATION
- VESSELS AND INTERNALS INTEGRITY BRANCH TECHNICAL REVIEW OF THE CR-3 EPU LAR By letter dated June 15, 2011, Florida Power Corporation (FPC) requested a license amendment to increase the rated thermal power level of Crystal River Unit 3 (CR-3) from 2609 megawatts (MWt) to 3014 MWt (Reference 1). On September 27, 2012, FPC provided a response to the NRC request for additional information (RAI) regarding the CR 3 pressure and temperature limits and the CR 3 Materials Reliability Program inspection requirements (Reference 2). On October 2, 2012 and October 9, 2012, via electronic mail; the NRC provided clarifying questions regarding the FPC RAI responses and a teleconference was conducted between the NRC and FPC on October 10, 2012, to discuss the clarifications. On October 11, 2012, following the teleconference, additional clarifications were provided to complete the Vessels and Internals Integrity Branch (EVIB) evaluation of the CR-3 Extended Power Uprate (EPU) License Amendment Request (LAR) and confirmed by the NRC staff on November 1, 2012.
For tracking purposes, each item related to this RAI is uniquely identified as EVIB X-Y, with X indicating the RAI set and Y indicating the sequential item number.
- 1. (EVIB 3-1)
Regarding the last paragraph of FPC's response to RAI EVIB-1 (EVIB 2-1), please provide clarification relative to areas of geometric discontinuities in the RPV considering irradiation embrittlement under EPU. Specifically:
(a) Provide the initial RTNDT, the copper (Cu) and nickel (Ni) content values, and estimated fluence for the outlet nozzle. If these values are not available, please provide the generic.
values that were used in generating the current P-T limits. For estimated fluence, interpolation is permissible.
Response
Per 10 CFR 50, Appendix G, the initial RTNDT is to be determined in accordance with Section III, NB-2331 "Material for Vessels," of the American Society of Mechanical Engineers (ASME) Boiler Code. However, NRC Branch Technical Position (BTP) 5-3, "Fracture Toughness Requirements," provides acceptable alternative methods of determining the initial RTNDT for plants with construction permits prior to August 15, 1973. The two CR-3 reactor pressure vessel (RPV) outlet nozzle forgings were fabricated on September 22, 1970, and the construction permit for CR-3 is dated prior to August 15, 1973. The certified material test reports (CMTRs) for the CR-3 RPV outlet nozzle forgings provide data for Charpy V-notch tests performed at 100 F, but the sample orientation, transverse or longitudinal, is not specified. However, since transverse is the weak orientation, it is assumed that the test data provided in the CMTRs corresponds to samples tested in the more conservative longitudinal orientation. Per Section B. 1.1(4) of BTP 5-3, the test temperature of 10°F can be used for the initial RTNDT because all Charpy values were above 45 ft-lbs for both outlet nozzle forgings at this temperature.
The standard deviation for the initial RTNDT used for the adjusted reference temperature (ART) calculation is 00 F. The two outlet nozzle forgings were tested a total of four times, twice for each material heat, at a temperature of 100 F. Since the four tests meet the 45 ft-lb
U. S. Nuclear Regulatory Commission Attachment 3F1212-08 Page 2 of 8 requirement of BTP 5-3, each test results in an initial RTNDT of 10°F. As a result, the standard deviation of the four tests is 0°F because the four tests have the same initial RTNDT-value.
The Cu content in the the CR-3 specific outlet nozzle forgings is not available. A Cu content of 0.11 weight-percentage (wt%) was selected based on a review of available Cu content values from the specific forging supplier that provided the CR-3 outlet nozzle forgings. A statistical determination was performed to obtain a lower tolerance generic value with 95 percent confidence that at least 95 percent of the population is greater than the tolerance limit. The mean was 0.06 wt%, the standard deviation (o) was 0.01 wt%, and the one-sided factor (k) was 3.187. The generically calculated Cu content value, using the mean plus ka, was 0.11 wt%.
The Ni content for the CR-3 outlet nozzle forgings was obtained from the CMTRs. From the two material heats, the highest Ni content value was 0.80 wt%.
The current P-T limits at 32 effective full power years (EFPY) are valid through 27.5 EFPY considering EPU conditions. At 27.5 EFPY, the 1/4T fluence at the outlet nozzle comer region was conservatively assumed to be 7.6E+16 n/cm2 , which is the peak wetted surface fluence of the outlet nozzle forgings. The fluence factor equation from Regulatory Guide 1.99, "Radiation Embrittlement of Reactor Vessel Materials," Revision 2, was used to estimate any shift in the P-T limits due to a change in RPV material embrittlement. Since this equation is valid at fluence values > 1E+ 17 n/cm 2 , the equation is also considered acceptable to Frovide a reasonable approximation of the fluence factor at a fluence value of 7.6E+ 16 n/cm.
(b) Estimate the 1/4T ART value of the outlet nozzle forging comer region using the values identified in (a).
Response
For the current CR-3 P-T limits, an adjusted reference temperature (ART) of 60'F was used for the CR-3 RPV outlet nozzle forgings. The ART value for the comer region of the CR-3 RPV outlet nozzle forgings at the 1/4T wall depth has been estimated using the methodology of Regulatory Guide 1.99, Revision 2, and the values cited herein for the initial RTNDT, the Cu and Ni content values, and an estimated fluence of 7.6E+16 n/cm 2 .
The following assumptions were made:
" The fluence factor equation from Regulatory Guide 1.99, Revision 2 is considered a reasonable approximation at a fluence value of 7.6E+16 n/cm2;
" The 1/4T fluence at the outlet nozzle comer region is conservatively assumed to be the peak wetted surface fluence of the RPV outlet nozzle forging, i.e., the bottom of the outlet nozzle forging to lower nozzle belt forging weld; and
- A chemistry factor of 77°F was determined based on a Cu content of 0.11 wt% and a Ni content of 0.80wt%.
U. S. Nuclear Regulatory Commission Attachment 3F1212-08 Page 3 of 8 The 1/4T ART value for the comer region of both CR-3 outlet nozzle forgings was estimated to be 24.0'F at 27.5 EFPY, which is well below the 60'F value used for the current CR-3 P-T limits.
(c) Generate P-T limits (heatup, cooldown, and hydrostatic/leak test) for the outlet nozzle using information in (b) and demonstrate that the current P-T limits remain bounding for EPU conditions. Adjust the EPFY value for the current P-T limits if necessary.
Response
The P-T limits for the CR-3 RPV outlet nozzle have been determined based on the 1/4T ART value of 247F. The outlet nozzle P-T limits have been generated for heatup, cooldown, and inservice leak and hydrostatic (ISLH) test. These limits were compared against the current respective P-T limits at 32 EFPY as shown in Figure 1, "Location Corrected Normal Heatup P-T Limits at 32 EFPY," Figure 2, "Location Corrected Normal Cooldown P-T Limits at 32 EFPY," and Figure 3, "Location Corrected ISLH P-T Limits at 32 EFPY." The results show that the RPV outlet nozzle P-T limits are conservative with respect to the current CR-3 P-T limits for each of the three transient conditions; heatup, cooldown, and ISLH test. FPC concludes that the outlet nozzle material is not the limiting material for the CR-3 P-T limits at EPU conditions. As such, no further adjustment to the EFPY of the current P-T limit curves is required.
Figure 1: Location Corrected Normal Heatup P-T Limits at 32 EFPY 2800 2600 2400 2200 C 2000 0
1800 0
" 1600 E
o 1400 C
o 1200 a
,0 1000 800 0
400 200 0
0 50 100 150 200 250 300 350 400 450 500 550 600 RV Downcomer Temperature, F
U. S. Nuclear Regulatory Commission Attachment 3F1212-08 Page 4 of 8 Figure 2: Location Corrected Normal Cooldown P-T Limits at 32 EFPY 2800 2600 2400 2200
'. 2000
'A 1800 0
. 1600 E
o 1400 1200 a
, 1000 800
< 600 400 200 0
200 250 300 350 RV Downcomer Temperature, F Figure 3: Location Corrected ISLH P-T Limits at 32 EFPY 3800 3600 3400 3200 3000 20
'F 2800 260 0 2400 0
2200 E 2000 0
0 E 1800 0 1600
> 1400
. 1200 o 1000
< 800 600 400 200 0
0 50 100 150 200 250 300 350 400 450 500 550 600 RV Downcomer Temperature, F
U. S. Nuclear Regulatory Commission Attachment 3F1212-08 Page 5 of 8 (d) Demonstrate that closure head is not the limiting material in any portion of the composite P-T limits.
Response
The original CR-3 RPV closure head limits used the generic ART value of 60'F and were compared against the composite P-T limits shown in Figure 4, "Location Corrected Composite P-T Limits at 32 EFPY." During refueling outage R13, the RPV closure head was replaced at CR-3. The replacement RPV closure head has an ART value of minus
(-) 40'F. As illustrated in Figure 4, the replacement RPV closure head (RVCH) limits are conservative with respect to the current CR-3 composite P-T limits. Hence, the replacement RPV closure head material is not the limiting material in any portion of the composite P-T limits at EPU conditions.
Figure 4: Location Corrected Composite P-T Limits at 32 EFPY 2800 2600 2400 -- e- Composite P-T Umits
--- Odinal RVCHU 2200 - - Repkacement RVCH 2000
-I-C- 1600 II E
0 1400
_ 4- 4---
C _ __ _ I I _
0 1200
' 1000 I- - -
~800 _________!_________
R 600 1!
400 200 0
0 50 100 150 200 250 300 350 400 450 500 550 600 RV Downcomer Temperature, F
- 2. (EVIB 3-2)
With regard to ferritic RCPB materials other than those in the RPV, the licensee's current 32 EFPY P-T limits allow the RCS temperature as low as 60 'F, but the licensee indicates in their response to EVIB-1 (EVIB 2-1) that the lowest service temperature cannot be lower than 150 'F for the piping. ASME Code,Section III, NB-2332 (b) states, "The lowest service temperature shall not be lower than RTNDT + 100 'F unless a lower temperature is justified by following methods similar to those contained in Appendix G." Please clarify how you meet this requirement.
U. S. Nuclear Regulatory Commission Attachment 3F1212-08 Page 6 of 8
Response
The lowest service temperature is defined in Footnote 1 of Subsection NB-2332(a)(1) in Section.
III of the ASME Code, 1974 Edition. Footnote 1 states, "Lowest service temperature is the minimum temperature of the fluid retained by the component, or alternatively, the calculated volumetric average metal temperature expected during normal operation, whenever the pressure within the component exceeds 20% of the preoperational system hydrostatic test pressure." For CR-3, the preoperational Reactor Coolant System (RCS) hydrostatic test pressure is 3125 psig.
Thus, at CR-3, the calculated volumetric average metal temperature expected during normal operation is based on a preoperational system hydrostatic test pressure of 625 psig. At temperatures ranging from 60'F up to the lowest service temperature of 150'F, the allowable pressures reported in the CR-3 P-T limit curves are demonstrated to remain below 625 psig.
Hence, the lowest service temperature requirement for the RCS piping has been demonstrated to have been met.
- 3. (EVIB 3-3)
Please provide the edition (year) of the ASME Code,Section III (Construction Code) based on which that the RCPB (e.g., piping, pumps, and valves) was constructed and identify whether the NB-2332 (b) cited above was already in that edition of the Construction Code.
Response
Subsection NB-2332, "Material for Piping, Pumps, and Valves, Excluding Bolting Material,"
was included in Section III of the Summer 1972 edition of the ASME Code. The construction code and code case interpretations for the respective CR-3 RCS components are listed in Table 4-2, "Reactor Coolant System Component Codes," of the CR-3 Final Safety Analysis Report.
As noted, most of the RCS components (e.g., the RPV, control rod drive nozzles, etc...) were constructed to ASME Section III Class A, Summer 1967 edition. The RCS piping was constructed to USA Standard (USAS) B31.7-1968. The Summer 1967 edition of the ASME Section III and USAS B31.7-1968 did not include a requirement consistent with the requirement cited in Subsection NB-2332(b), rather Subsection N-332 of the ASME Section III stated that impact tests results are considered suitable for materials of vessels to be pressure tested at a temperature of not less than 60'F higher than RTNDT.
The RPV closure head was constructed to ASME Section III Class I, Subsections NCA and NB, 1989 edition. Also, the replacement steam generators were constructed to ASME Section III Class I, 2000 edition. However, ASME Code,Section III, Subsection NB-2332 does not apply to the RPV closure head or the replacement steam generators, rather Subsection NB-2331 applies to these components.
A portion of the upper RCS hot leg and flowmeter were replaced during the CR-3 steam generator replacement activity. This portion of the RCS piping conforms to the requirements of ASME Code,Section III, Subsection NB for Class 1 piping, 1998 Edition through 2000 Addenda, including NB-2332.
U. S. Nuclear Regulatory Commission Attachment 3F1212-08 Page 7 of 8
- 4. (EVIB 3-4)
Regarding the first paragraph of FPC's response to EVIB-2 (EVIB 2-2), please clarify whether the program was developed and implemented.
Response
An aging management program (AMP) has been developed for the CR-3 reactor vessel internals; WCAP-17113-NP, "PWR Vessels Internal Program Plan for Aging Management for Reactor Internals at Crystal River Unit 3." The CR-3 reactor vessel internals AMP has been implemented with one deviation as cited in RAI Response EVIB 2-2 in the FPC to NRC letter dated September 27, 2012 (Reference 2) and further clarified in RAI Response EVIB 3-5 of this attachment.
- 5. (EVIB 3-5)
Regarding the last paragraph of FPC's response to EVIB-2 (EVIB 2-2), please clarify your response to Item (2) of the RAI in relation to the deferred ultrasonic testing of the accessible RPV core barrel bolts. Would such deferral require relief from the ASME Code?
Response
The deviation of the ultrasonic examination of the accessible RPV lower core barrel bolts and their locking devices was processed in accordance with the guidelines of Nuclear Energy Institute (NEI) 03-08, "Guideline for the Management of Materials Issues," to delay the ultrasonic examination until the next scheduled removal of the core support assembly (CSA).
FPC plans to perform the initial ultrasonic examination of the accessible RPV lower core barrel bolts and their locking devices during refueling outage R17. Refueling outage R17 has been further delayed as a result of the CR-3 containment repair activities. In addition, the examination cannot be readily performed during the current extended outage period because the polar crane, which is required for this examination, is unavailable due to the physical condition of the CR-3 containment structure. This further delay in the performance of the ultrasonic examination is considered acceptable since the material properties and conditions of the RPV lower core barrel bolts and their locking devices are unlikely to change during the current extended outage period with the CR-3 RPV in the defueled condition.
A relief from the ASME Code, as allowed by 10 CFR 50.55a(a)(3), is not required for the MRP-227 deferment of an ultrasonic examination of the lower core barrel bolts and their locking devices. Ultrasonic examination of the lower core barrel bolts and their locking devices is not required by the ASME Code. The RPV lower core barrel bolts are part of the CSA. ASME Section XI, Subsection IWB-2000, Category B-N-3, Item No. B13.70, requires a visual examination of accessible areas of the CSA every inservice inspection (ISI) interval, typically during the 10-year ISI. The accessible areas of the lower core barrel bolts and their locking devices are included in this visual examination of the CSA. The previous visual examination of the accessible areas of the CSA was completed in 2007 during refueling outage R15 and the next visual examination is not required per ASME Section XI until the end of the fourth CR-3 10-year ISI interval. Therefore, relief from ASME Code compliance is not required for the MRP-227 deferment of the lower core barrel bolts ultrasonic examination.
U. S. Nuclear Regulatory Commission Attachment 3F1212-08 Page 8 of 8 References
- 1. FPC to NRC letter dated June 15, 2011, "Crystal River Unit 3 - License Amendment Request #309, Revision 0, Extended Power Uprate." (ADAMS Accession No. MLl 12070659)
- 2. FPC to NRC letter dated September 27, 2012, "Crystal River Unit 3 - Response to Second Request for Additional Information to Support NRC Vessels and Internals Integrity Branch (EVIB) Technical Review of the CR-3 Extended Power Uprate LAR (TAC No. ME6527)."
(ADAMS Accession No. ML12272A344)