 Issue dateFromTitleProject stage
3F0811-04, Response to Request for Additional Information to Support NRC Probabilistic Risk Assessment Licensing Branch Acceptance Review of the CR-3 Extended Power Uprate LAR11 August 2011Progress Energy Florida
Franke J
Response to Request for Additional Information to Support NRC Probabilistic Risk Assessment Licensing Branch Acceptance Review of the CR-3 Extended Power Uprate LARResponse to RAI
3F0811-02, Response to Request for Additional Information to Support NRC Balance of Plant Branch Acceptance Review of the CR-3 Extended Power Uprate LAR11 August 2011Progress Energy Florida
Franke J
Response to Request for Additional Information to Support NRC Balance of Plant Branch Acceptance Review of the CR-3 Extended Power Uprate LARResponse to RAI
3F0811-01, Response to Request for Additional Information to Support NRC Instrumentation and Controls Branch Acceptance Review of the CR-3 Extended Power Uprate LAR18 August 2011Progress Energy Co
Florida Power Corp
Swartz J
Response to Request for Additional Information to Support NRC Instrumentation and Controls Branch Acceptance Review of the CR-3 Extended Power Uprate LARResponse to RAI
3F0811-03, Response to Request for Additional Information to Support NRC Mechanical and Civil Branch Acceptance Review of the CR-3 Extended Power Uprate LAR25 August 2011Progress Energy Florida
Swartz J
Response to Request for Additional Information to Support NRC Mechanical and Civil Branch Acceptance Review of the CR-3 Extended Power Uprate LARResponse to RAI
ML11259A01214 September 2011Progress Energy Florida
Westcott D
NRR E-mail Capture - Clarification for August 25 Emcb RAI Acceptance Review LetterOther
ML11286A09211 October 2011Progress Energy Florida
Franke J
Florida Power Corp
Response to Request for Additional Information to Support NRC Reactor Systems Branch Acceptance Review of the CR-3 Extended Power Uprate LARResponse to RAI
ML11300A22625 October 2011Progress Energy Florida
Progress Energy Co
Franke J
Feedwater Line Break Overpressure Protection Analysis to Support NRC Reactor Systems Branch Acceptance Review of the CR-3 Extended Power Update LAR and LAR Approval ScheduleOther
3F1011-08, ANP-3052, Rev. 0, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip25 October 2011AREVAANP-3052, Rev. 0, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade TripOther
ML11326A2317 December 2011Siva Lingam
Plant Licensing Branch II
Request for Additional Information for Extended Power Uprate License Amendment RequestRAI
ML12205A35715 December 2011Progress Energy Florida
AREVA
Uyeda G
Esquillo V
Jirapongmed A
Mancini A
O'Brian J
Spontarelli A
Attachment a to 3F0712-03, CR-3 LOCA Summary Report - EPU/ROTSG/Mark-B-HTP, Revision 4Other
3F1211-05, Response to Request for Additional Information to Support NRC Health Physics and Human Performance Branch Technical Review of the CR-3 Extended Power Uprate LAR15 December 2011Progress Energy Florida
Franke J
Response to Request for Additional Information to Support NRC Health Physics and Human Performance Branch Technical Review of the CR-3 Extended Power Uprate LARResponse to RAI
3F1211-06, Response to Request for Additional Information to Support NRC Vessels and Internals Integrity Branch Technical Review of the CR-3 Extended Power Uprate LAR15 December 2011Progress Energy Florida
Franke J
Response to Request for Additional Information to Support NRC Vessels and Internals Integrity Branch Technical Review of the CR-3 Extended Power Uprate LARResponse to RAI
3F1211-10, Response to Request for Additional Information to Support NRC Fire Protection Branch Technical Review of the CR-3 Extended Power Uprate LAR21 December 2011Progress Energy Florida
Franke J
Response to Request for Additional Information to Support NRC Fire Protection Branch Technical Review of the CR-3 Extended Power Uprate LARResponse to RAI
3F0112-04, Response to Request for Additional Information to Support NRC Steam Generator Tube Integrity and Chemical Engineering Branch Technical Review of the CR-3 Extended Power Uprate LAR5 January 2012Progress Energy Co
Franke J
Response to Request for Additional Information to Support NRC Steam Generator Tube Integrity and Chemical Engineering Branch Technical Review of the CR-3 Extended Power Uprate LARResponse to RAI
ML12030A2095 January 2012Progress Energy Florida
Franke J
Response to Request for Additional Information to Support NRC Instrumentation and Control Branch Technical Review of the CR-3 Extended Power Uprate LARResponse to RAI
ML11342A1956 January 2012Siva Lingam
Plant Licensing Branch II
Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for a Hearing and Order Imposing Procedures for Document Access to Sensitive Unclassified Non-safeguards InformationOther
ML12024A30019 January 2012Progress Energy Florida
Franke J
Response to Request for Additional Information to Support NRC Component Performance and Testing Branch Technical Review of the CR-3 Extended Power Uprate LARResponse to RAI
3F0112-06, Response to Request for Additional Information to Support NRC Piping and NDE Branch Technical Review of the CR-3 Extended Power Uprate LAR19 January 2012Progress Energy Florida
Franke J
Florida Power Corp
Response to Request for Additional Information to Support NRC Piping and NDE Branch Technical Review of the CR-3 Extended Power Uprate LARResponse to RAI
3F0112-11, Corrections to the Extended Power Uprate LAR 309 Vendor Affidavit and Technical Report31 January 2012Progress Energy Florida
Franke J
Corrections to the Extended Power Uprate LAR #309 Vendor Affidavit and Technical ReportOther
ML12003A2178 February 2012Siva Lingam
Plant Licensing Branch II
Nuclear Generating Plant - Request for Additional Information for Extended Power Uprate License Amendment RequestRAI
ML12052A1302 March 2012Siva Lingam
Plant Licensing Branch II
Request for Additional Information for Extended Power Uprate License Amendment RequestRAI
ML12053A2312 March 2012Siva Lingam
Plant Licensing Branch II
Request for Withholding Proprietary Information from Public Disclosure Related Extended Power Uprate Technical ReportOther
3F0312-02, Response to Second Request for Additional Information to Support NRC Instrumentation and Controls Branch (Eicb) Technical Review of the CR-3 Extended Power Uprate LAR19 March 2012Progress Energy Florida
Franke J
Florida Power Corp
Response to Second Request for Additional Information to Support NRC Instrumentation and Controls Branch (Eicb) Technical Review of the CR-3 Extended Power Uprate LARRequest
3F0312-01, Response to Request for Additional Information to Support NRC PRA Licensing Branch Technical Review of the CR-3 Extended Power Uprate LAR22 March 2012Progress Energy Florida
Franke J
Response to Request for Additional Information to Support NRC PRA Licensing Branch Technical Review of the CR-3 Extended Power Uprate LARResponse to RAI
ML12031A03226 March 2012Siva Lingam
Plant Licensing Branch II
Request for Withholding Proprietary Information from Public Disclosure Related to Extended Power Uprate Technical ReportOther
ML12107A0684 April 2012Progress Energy Co
Westcott D
NRR E-mail Capture - Crystal River, Unit 3 EPU LAR - Clarifications for Component Performance & Testing Branch (Eptb)Other
3F0412-05, Response to Second Request for Additional Information to Support NRC Health Physics and Human Performance Branch (Ahpb) Technical Review of the CR-3 Extended Power Uprate LAR4 April 2012Progress Energy Florida
Franke J
Response to Second Request for Additional Information to Support NRC Health Physics and Human Performance Branch (Ahpb) Technical Review of the CR-3 Extended Power Uprate LARRequest
3F0412-04, Response to Request for Additional Information to Support NRC Mechanical and Civil Engineering Branch (Emcb) Technical Review of the CR-3 Extended Power Uprate LAR4 April 2012Progress Energy Co
Franke J
Response to Request for Additional Information to Support NRC Mechanical and Civil Engineering Branch (Emcb) Technical Review of the CR-3 Extended Power Uprate LARResponse to RAI
3F0412-07, Response to Request for Additional Information to Support NRC Containment and Ventilation Branch (Scvb) Technical Review of the CR-3 Extended Power Uprate LAR12 April 2012Progress Energy Florida
Franke J
Response to Request for Additional Information to Support NRC Containment and Ventilation Branch (Scvb) Technical Review of the CR-3 Extended Power Uprate LARResponse to RAI
3F0412-06, Response to Request for Additional Information to Support NRC Electrical Systems Branch (Eeeb) Technical Review of the CR-3 Extended Power Uprate LAR16 April 2012Progress Energy Florida
Franke J
Response to Request for Additional Information to Support NRC Electrical Systems Branch (Eeeb) Technical Review of the CR-3 Extended Power Uprate LARResponse to RAI
3F0412-09, Response to Request for Additional Information to Support NRC Accident Dose Branch (Aadb) Technical Review of the CR-3 Extended Power Uprate LAR26 April 2012Progress Energy Florida
Franke J
Response to Request for Additional Information to Support NRC Accident Dose Branch (Aadb) Technical Review of the CR-3 Extended Power Uprate LARResponse to RAI
ML12102A0444 May 2012Siva Lingam
Plant Licensing Branch II
Request for Additional Information for Extended Power Uprate License Amendment RequestRAI
ML12314A39131 May 2012Curtiss-Wright Flow Control Corp
SCIENTECH
Hirt M
17877-0002-100, CR-3 Inadequate Core Cooling Mitigation System Reliability Assessment 2Other
ML12205A35831 May 2012Progress Energy Florida
AREVA NP
Attachment D to 3F0712-03, Technical Report, ANP-3114(NP), Rev. 0, CR-3 EPU - Feedwater Line Break Analysis Sensitivity Studies.Other
3F0612-05, Response to Request for Additional Information to Support NRC Nuclear Performance and Code Review Branch (Snpb) Technical Review of the CR-3 Extended Power Uprate LAR18 June 2012Progress Energy Florida
Franke J
Response to Request for Additional Information to Support NRC Nuclear Performance and Code Review Branch (Snpb) Technical Review of the CR-3 Extended Power Uprate LARResponse to RAI
3F0712-03, Attachment E to 3F0712-03, Technical Report, ANP-3052, Rev. 2, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip.30 June 2012Progress Energy Florida
AREVA NP
Attachment E to 3F0712-03, Technical Report, ANP-3052, Rev. 2, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip.Other
ML12184A3442 July 2012Progress Energy Co
Westcott D
NRR E-mail Capture - Crystal River, Unit 3 EPU LAR - Discussion/Clarification of Emcb Draft RAIsDraft Other
ML12174A2925 July 2012Siva Lingam
Plant Licensing Branch II
Request for Additional Information for Extended Power Uprate License Amendment RequestRAI
ML12171A3475 July 2012Siva Lingam
Plant Licensing Branch II
Request for Additional Information for Extended Power Uprate License Amendment RequestRAI
ML12205A35617 July 2012Progress Energy Florida
Franke J
Supplement to the Extended Power Uprate License Amendment Request #309Supplement
3F0712-06, Response to Second Request for Additional Information to Support NRC Steam Generator Tube Integrity and Chemical Engineering Branch (Esgb) Technical Review of the CR-3 Extended Power Uprate LAR17 July 2012Progress Energy Florida
Franke J
Response to Second Request for Additional Information to Support NRC Steam Generator Tube Integrity and Chemical Engineering Branch (Esgb) Technical Review of the CR-3 Extended Power Uprate LARRequest
ML12194A41717 July 2012Siva Lingam
Plant Licensing Branch II
Generating Plant - Request for Additional Information for Extended Power Uprate License Amendment RequestRAI
3F0712-07, Response to Third Request for Additional Information to Support NRC Health Physics and Human Performance Branch (Ahpb) Technical Review of the CR-3 Extended Power Uprate LAR31 July 2012Progress Energy Carolinas
Franke J
Response to Third Request for Additional Information to Support NRC Health Physics and Human Performance Branch (Ahpb) Technical Review of the CR-3 Extended Power Uprate LARRequest
3F0712-08, Response to Second Request for Additional Information to Support NRC PRA Licensing Branch (Apla) Technical Review of the CR-3 Extended Power Uprate LAR31 July 2012Progress Energy Co
Franke J
Response to Second Request for Additional Information to Support NRC PRA Licensing Branch (Apla) Technical Review of the CR-3 Extended Power Uprate LARRequest
ML12125A1621 August 2012Siva Lingam
Plant Licensing Branch II
Nuclear Generating Plant - Request for Additional Information for Extended Power Uprate License Amendment RequestRAI
ML12202A7341 August 2012Siva Lingam
Plant Licensing Branch II
Request for Withholding Proprietary Information from Public Disclosure Related to Extended Power Uprate Technical ReportOther
ML12202A0602 August 2012Siva Lingam
Plant Licensing Branch II
Request for Additional Information for Extended Power Uprate License Amendment RequestRAI
ML12213A3033 August 2012Siva Lingam
Plant Licensing Branch II
Request for Additional Information for Extended Power Uprate License Amendment Request (Srxb)RAI
ML12219A19116 August 2012Siva Lingam
Plant Licensing Branch II
Request for Additional Information for Extended Power Uprate License Amendment RequestRAI
3F0812-02, Response to Second Request for Additional Information to Support NRC Electrical Engineering Branch (Eeeb) Technical Review of the CR-3 Extended Power Uprate LAR21 August 2012Progress Energy Carolinas
Franke J
Response to Second Request for Additional Information to Support NRC Electrical Engineering Branch (Eeeb) Technical Review of the CR-3 Extended Power Uprate LARRequest