Revised Commitment for Supplement to the Extended Power Uprate License Amendment Request #309
ML12286A329
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 10/11/2012
From: Franke J
Duke Energy Corp, Florida Power Corp
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
3F1012-07, TAC ME6527
Download: ML12286A329 (5)


Text

PDuke WEnergy Crystal River Nuclear Plant Docket No. 50-302 Operating License No. DPR-72 October 11, 2012 3F1012-07 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

Subject:

Crystal River Unit 3 - Revised Commitment for Supplement to the Extended Power Uprate License Amendment Request #309 (TAC No. ME6527)

References:

1. FPC to NRC letter dated June 15, 2011, "Crystal River Unit 3 - License Amendment Request #309, Revision 0, Extended Power Uprate" (ADAMS Accession No. ML112070659)
2. FPC to NRC letter dated June 29, 2012, "Crystal River Unit 3 - Response to Second Request for Additional Information to Support NRC Accident Dose Branch (AADB) Technical Review of the CR-3 Extended Power Uprate LAR (TAC No. ME6527)" (ADAMS Accession No. ML12206A337)

Dear Sir:

By letter dated June 15, 2011, Florida Power Corporation (FPC) requested a license amendment to increase the rated thermal power level of Crystal River Unit 3 (CR-3) from 2609 megawatts to 3014 megawatts (Reference 1). In an FPC response to an NRC staff request for additional information associated with the CR-3 Extended Power Uprate License Amendment Request (Reference 2), a regulatory commitment was included to provide, by October 12, 2012, revisions to the main control room (MCR) atmospheric dispersion factors (X/Q) and associated dose results.

The attachment, "List of Regulatory Commitments," to this correspondence revises the content and date of the regulatory commitment included in FPC to NRC letter dated June 29, 2012 (Reference 2); and hereby, supersedes the previous regulatory commitment.

The regulatory commitment is being revised for the following reasons:

  • The due date is being revised from October 12, 2012 to December 20, 2012, in part, due to the primary resources performing the necessary analytical work being unavailable for several weeks.
  • To more effectively implement the guidance of Regulatory Guide 1.194, "Atmospheric Relative Concentrations for Control Room Radiological Habitability Assessments at Nuclear Power Plants," the input assumptions associated with the MCR X/Q calculations have been re-evaluated and will be revised, as applicable, to more accurately represent the resulting dose to the MCR environment. As a result, additional time is required to revise the input Crystal River Nuclear Plant 15760 W. Powerline Street Crystal River, FL 34428

U.S. Nuclear Regulatory Commission Page 2 of 3 3F1012-07 assumptions and re-perform the MCR X/Q calculations and determine the impact on the associated MCR dose calculations. As applicable, revised input assumptions associated with the MCR X/Q calculations will be provided along with the updated MCR X/Q values.

  • The isolation of the MCR from outside air, upon receipt of a MCR intake high radiation signal, and subsequent operation of the Control Room Emergency Ventilation System will[ be credited during a fuel handling accident (FHA). As a result of this additional FIA assumption, the CR-3 Improved Technical Specifications and associated Bases are being revised as necessary to ensure the Control Room Emergency Ventilation System is available during a FHA. The applicable Improved Technical Specifications and Bases changes will be provided along with the revised MCR FHA dose results.

If you have any questions regarding this correspondence, please contact Mr. Dan Westcott, Superintendent, Licensing and Regulatory Programs at (352) 563-4796.

Crystal River Nuclear Plant JAF/gwe

Attachment:

List of Regulatory Commitments xc: NRR Project Manager Regional Administrator, Region II Senior Resident Inspector State Contact

U.S. Nuclear Regulatory Commission Page 3 of 3 3F1012-07 STATE OF FLORIDA COUNTY OF CITRUS Jon A. Franke states that he is the Vice President, Crystal River Nuclear Plant for Florida Power Corporation; that he is authorized on the part of said company to sign and file with the Nuclear Regulatory Commission the information attached hereto; and that all such statements made and matters set forth therein are true and correct to the best of his knowledge, information, and belief.

ZJ ý . Franke Vice President Crystal River Nuclear Plant The foregoing document was acknowledged before me this / day of 6,{j C 9,A., , 2012, by Jon A. Franke.

Signature of Notary Public State o - ".... .. ....

1 . CAROLYN E.PORTMANN

. Commission # DD 937553 r' Expires March 1,2014 I (Print, type, or stamp Commissioned Name of Notary Public)

Personally Produced Known V -OR- Identification

FLORIDA POWER CORPORATION CRYSTAL RIVER UNIT 3 DOCKET NUMBER 50-302 / LICENSE NUMBER DPR-72 ATTACHMENT LIST OF REGULATORY COMMITMENTS

U. S. Nuclear Regulatory Commission Attachnent 3F1012-07 Page 1 of 1 List of Regulatory Commitments The following table identifies those actions committed to by Florida Power Corporation (FPC) in this document. Other statements in this correspondence are provided for information purposes and are not considered to be regulatory commitments. Please notify the Superintendent, Licensing and Regulatory Programs of any questions regarding this document or any associated regulatory commitments.

Regulatory Commitment Due date/event FPC will provide: December 20, 2012

1. revised main control room (MCR) atmospheric dispersion factors (X/Q) for each design basis event reported in Section 2.9.2, "Radiological Consequences Analyses," of the CR-3 EPU Technical Report based on ARCON96 methodology described in Regulatory Guide 1.194;
2. as applicable, revised input assumptions associated with the MCR X/Q calculations;
3. revised MCR dose results for the loss of coolant accident and fuel handling accident; and
4. associated revisions to the applicable CR-3 Improved Technical Specifications and associated Bases.