07-11-2016 | past operability of the Salt Service Water ( SSW) Pump P-208B power supply breaker overload relay based on thermography results obtained on October 25, 2013. A similar high temperature condition was identified during the February 29, 2016 thermography surveillance that resulted in declaring the pump inoperable on March 4, 2016 and completing the replacement of the overload relay on March 5, 2016. SSW Pump P-208B is currently operable.
The past operability review covers the period of time between the 2013 thermography surveillance and March 5, 2016 when the pump breaker overload relay was replaced. Based on the lack of detailed information in the 2013 surveillance, past operability of the pump could not be assured. A review of out-of-service time for SSW Pumps P208A and P208C indicates that one instance occurred where less than two SSW pumps were Operable to feed the SSW A Loop Header for a period in excess of SSW Technical Specification requirements. This represents a reportable condition.
The cause of the overload relay high temperature readings was evaluated and determined to be a high resistance connection on the overload relay heater assembly. Inadequate predictive maintenance monitoring was identified as the apparent cause for not periodically assessing breaker status or replacing the breaker overload relay prior to March 5, 2016. Testing the overload relay that was removed from service is planned. This testing is expected to be completed by, ..
August 15, 2016. Results will be reported in a supplement to this report.
There was no impact to public health and safety. |
---|
|
---|
Category:Letter
MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000293/20240022024-08-21021 August 2024 NRC Inspection Report No. 05000293/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24129A1042024-05-26026 May 2024 Preapplication Readiness Assessment Plan for the Holtec Decommissioning International License Termination Plan ML24135A3212024-05-14014 May 2024 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2023 ML24136A2382024-05-14014 May 2024 Annual Radiological Environmental Operating Report for 2023 IR 05000293/20240012024-05-0707 May 2024 NRC Inspection Report No. 05000293/2024001 L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 L-24-010, Request for Preapplication Readiness Assessment of the Draft License Termination Plan2024-04-22022 April 2024 Request for Preapplication Readiness Assessment of the Draft License Termination Plan L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) IR 05000293/20230032024-02-29029 February 2024 NRC Inspection Report Nos. 05000293/2023003 and 05000293/2023004 L-24-002, Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G2024-02-0202 February 2024 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G ML23342A1182024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23334A1822023-11-30030 November 2023 Biennial Report for the Defueled Safety Analysis Report Update, Technical Specification Bases Changes, 10 CFR 50.59 Evaluation Summary, and Regulatory Commitment Change Summary – November 2021 Through October 2023 L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23306A0992023-11-0202 November 2023 And Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) ML23300A0022023-10-27027 October 2023 10 CFR 72.48 Biennial Change Summary Report IR 05000293/20234012023-08-31031 August 2023 NRC Inspection Report No. 05000293/2023401 & 2023001 (Cover Letter Only) IR 05000293/20230022023-08-0404 August 2023 NRC Inspection Report No. 05000293/2023002 ML23143A0872023-05-23023 May 2023 Correction to Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) ML23135A2152023-05-15015 May 2023 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2022 ML23136A7792023-05-15015 May 2023 Annual Radiological Environmental Operating Report, January 1 Through December 31, 2022 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML23069A2782023-03-13013 March 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1 Subsequent License Renewal Application ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000293/20220042023-02-15015 February 2023 NRC Inspection Report No. 05000293/2022004 ML22356A0712023-01-31031 January 2023 Issuance of Exemption for Pilgrim Nuclear Power Station ISFSI Regarding Annual Radioactive Effluent Release Report - Cover Letter ML22347A2782022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 L-22-041, Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension2022-12-0909 December 2022 Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension IR 05000293/20220032022-11-18018 November 2022 NRC Inspection Report No. 05000293/2022003 ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22266A1922022-09-23023 September 2022 And Pilgrim Nuclear Power Station - Request to Withdraw Prior Submissions from NRC Consideration ML22272A0352022-09-22022 September 2022 S. Lynch-Benttinen Letter Regarding U.S. Citizen Intent to Sue U.S. Fish and Wildlife and NOAA Fisheries Representing the Endangered Species (Na Right Whale) Which Will Be Adversely Affected by Holtec International Potential Actions ML22269A4202022-09-22022 September 2022 Citizen Lawsuit ML22241A1122022-08-29029 August 2022 Request for Exemption from 10 CFR 72.212(a)(2), (b)(2), (b)(3), (b)(4), (B)(5)(i), (b)(11), and 72.214 for Pilgrim ISFSI Annual Radioactive Effluent Release Report IR 05000293/20220022022-08-12012 August 2022 NRC Inspection Report No. 05000293/2022002 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22221A2592022-08-0101 August 2022 LTR-22-0217-1-NMSS - Town of Duxbury Letter Opposing the Irradiated Water Release from Pilgrim (Docket No. 05000293) ML22206A1512022-08-0101 August 2022 NRC Office of Investigations Case Nos. 1-2022-002 & 1-2022-006 ML22193A1662022-07-28028 July 2022 LTR-22-0154-1 - Heather Govern, VP, Clean Air and Water Program, Et Al., Letter Regarding Radioactive Wastewater Disposal from the Pilgrim Nuclear Power Station (Docket No. 05000293) ML22175A1732022-07-28028 July 2022 LTR-22-0153-1 - Response Letter to D. Turco, Cape Downwinders, from A. Roberts, NRC, Regarding Holtec-Pilgrim Plans to Dump One Million Gallons of Radioactive Waste Into Cape Cod Bay ML22154A4882022-06-0101 June 2022 Letter from Conservation Law Foundation Regarding Irradiated Water Release from Pilgrim ML22154A1622022-05-26026 May 2022 Letter and Email from Save Our Bay/Diane Turco Regarding Irradiated Water Release from Pilgrim ML22136A2602022-05-16016 May 2022 Submittal of Annual Radiological Environmental Operating Report for January 1 Through December 31, 2021 ML22136A2572022-05-16016 May 2022 Submittal of Annual Radioactive Effluent Release Report for January 1 Through December 31, 2021 2024-09-18
[Table view] Category:Licensee Event Report (LER)
MONTHYEARML18179A1632018-06-21021 June 2018 Retraction of Licensee Event Report 2018-002-00, Diesel Generator a Inoperability, a Condition Prohibited by the Plant Technical Specifications 05000293/LER-2017-0132018-01-25025 January 2018 1 OF 4, LER 17-013-00 for Pilgrim Nuclear Power Station Regarding Reportable Conditions Involving Standby Gas Treatment System and Secondary Containment lnoperability Not Reported During the Previous Three Years 05000293/LER-2017-0122017-11-13013 November 2017 Start-Up Transformer Degraded Voltage Relay Found Outside Technical Specification Limit, LER 17-012-00 for Pilgrim Nuclear Power Station Regarding Start-Up Transformer Degraded Voltage Relay Found Outside Technical Specification Limit 05000293/LER-2017-0112017-08-15015 August 2017 Simultaneously Opened Reactor Building Airlock Doors Caused Loss of Secondary Containment, LER 17-011-00 for Pilgrim Nuclear Power Station Regarding Simultaneously Opened Reactor Building Airlock Doors Caused Loss of Secondary Containment 05000293/LER-2017-0102017-08-0707 August 2017 Air Accumulation Creates Small Void in Core Spray Discharge Piping, LER 17-010-00 for Pilgrim re Air Accumulation Creates Small Void in Core Spray Discharge Piping 05000293/LER-2017-0012017-07-17017 July 2017 Reactor Building Isolation Dampers Failed to Isolate, LER 17-001-01 for Pilgrim Nuclear Power Station Regarding Reactor Building Isolation Dampers Failed to Isolate 05000293/LER-2017-0092017-07-17017 July 2017 Supplement to Potential Primary Containment System Inoperability Due to Relay Concerns, LER 17-009-00 for Pilgrim Nuclear Power Station Regarding Potential Primary Containment System lnoperability Due to Relay Concerns 05000293/LER-2017-0082017-06-30030 June 2017 Supplement to 480V Bus B6 Auto Transfer Function Degraded Due to Time Delay Relay Failure, LER 17-008-00 for Pilgrim re 480V Bus B6 Auto Transfer Function Degraded Due to Time Delay Relay Failure 05000293/LER-2017-0072017-06-22022 June 2017 Supplement to Potential Inoperability of Safety Relief Valve 3A, LER 17-007-00 for Pilgrim Regarding Potential Inoperability of Safety Relief Valve 3A 05000293/LER-2016-0102017-06-14014 June 2017 MSIV Inoperability Led to a Condition Prohibited by the Plant s Technical Specifications, LER 16-010-01 for Pilgrim Nuclear Power Station re MSIV Inoperability 05000293/LER-2017-0062017-06-13013 June 2017 Source Range Monitor Inoperable During Fuel Movement, LER 17-006-00 for Pilgrim Nuclear Power Station Regarding Source Range Monitor Inoperable During Fuel Movement 05000293/LER-2017-0052017-06-0707 June 2017 10 CFR 50, Appendix J, Option B, Leak Rate Criteria Exceeded, LER 17-005-00 for Pilgrim Regarding 10 CFR 50, Appendix J, Option B, Leak Rate Criteria Exceeded 05000293/LER-2017-0042017-06-0202 June 2017 Secondary Containment Testing Led to Loss of Safety Function to Both Trains of Standby Gas Treatment System, LER 17-004-00 for Pilgrim Nuclear Power Station Regarding Secondary Containment Testing Led to Loss of Safety Function to Both Trains of Standby Gas Treatment System 05000293/LER-2017-0022017-05-25025 May 2017 Isolation of HPCI, LER 17-002-00 for Pilgrim Regarding Isolation of HPCI 05000293/LER-2017-0032017-05-25025 May 2017 Supplement to Suppression Pool Declared Inoperable Due to High Water Level, LER 17-003-00 for Pilgrim Nuclear Power Station Regarding Pressure Suppression Pool Declared Inoperable Due to High Water Level 05000293/LER-2016-0082016-12-0909 December 2016 Emergency Diesel Generator 'A' Past Inoperability, LER 16-008-00 for Pilgrim Nuclear Power Station Regarding Emergency Diesel Generator 'A' Past Inoperability 05000293/LER-2016-0072016-11-0404 November 2016 Manual Reactor Scram Due To Feedwater Regulating Valve Malfunction, LER 16-007-00 for Pilgrim Nuclear Power Station Regarding Manual Reactor Scram Due To Feedwater Regulating Valve Malfunction 05000293/LER-2016-0032016-07-11011 July 2016 Spent Fuel Storage Design Feature Exceeded, LER 16-003-00 for Pilgrim Nuclear Power Station Regarding Spent Fuel Storage Design Feature Exceeded 05000293/LER-2016-0042016-07-11011 July 2016 Salt Service Water Pump B Past Operability - Operation or Condition Prohibited by Technical Specifications, LER 16-004-00 for Pilgrim Nuclear Power Station Regarding Salt Service Water Pump B Past Operability - Operation or Condition Prohibited by Technical Specifications 05000293/LER-2016-0022016-06-20020 June 2016 Online Maintenance Test Configuration Prohibited By Technical Specifications, LER 16-002-00 for Pilgrim Nuclear Power Station Regarding Online Maintenance Test Configuration Prohibited By Technical Specifications 05000293/LER-2016-0012016-06-0909 June 2016 Both Emergency Diesel Generators Inoperable, LER 16-001-00 for Pilgrim Nuclear Power Station Regarding Both Emergency Diesel Generators Inoperable ML13149A1722013-05-26026 May 2013 E-mail from Micheal Mulligan to R.Guzman, Pilgrim Evacuation Plan Broken During Blizzard Nemo and Unenforced by the Nrc. ML0613706222006-05-11011 May 2006 LER 06-01-000, Pilgrim Re Manual Scram Due to High Offgas Recombiner Temperature Resulting from Inadequate Preventive Recombiner Preheater Pressure Control Valve Controller ML0416706152004-06-0808 June 2004 LER 99-008-01 for Pilgrim Regarding Automatic Scram at 100 Percent Power Due to Turbine Trip ML0207700612002-02-27027 February 2002 LER 99-003-01 for Pilgrim Nuclear Power Station Re Local Leak Rate Test Results Exceeding Allowable Technical Specification Leakage Rates 2018-06-21
[Table view] |
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
Pilgrim Nuclear Power Station 05000293
BACKGROUND
The safety objective of the SSW system is to provide a heat sink for the Reactor Building Closed Cooling Water (RBCCW) system under normal, transient, and accident conditions. The SSW system has five SSW pumps and is designed with sufficient redundancy so that no single active system component failure can prevent the system from achieving the safety objective. The system is designed to continuously provide a supply of cooling water to the secondary side of the RBCCW heat exchangers adequate to meet the requirements of the RBCCW system under all conditions. The RBCCW system provides the necessary cooling requirements for the residual heat removal (RHR) system and ultimately the reactor and primary containment.
The SSW pumps are separated into two loops. Two pumps are connected to each loop and the fifth pump can feed either loop. Initiation of standby AC power following loss of the preferred AC power source will automatically start at least one pump in each loop during normal conditions. Following a Loss of Coolant Accident (LOCA) and loss-of-offsite power, one pump will start in each loop because of diesel load limitations.
Additional pumps are started manually by the operator as additional cooling loads are established and diesel capacity is available.
Technical Specification (TS) Limiting Condition For Operation (LCO) 3.5.13.4 requires two SSW loops to be operable whenever fuel is in the vessel and reactor coolant temperature is greater than 212 degrees F.
Operability of each loop requires at least two SSW pumps to be operable in the loop along with the associated controls to demonstrate SSW loop operability.
Thermography is part of the SSW pump breaker predictive maintenance program. SSW system TS surveillances do not require use of thermography to determine system or pump operability. The site thermography procedure requires condition reports to be written if high temperature conditions exist.
EVENT DESCRIPTION
On May 10, 2016, Condition Report CR-PNP-2016-3308 was written to perform a past operability review on the SSW Pump P-208B power supply breaker overload relay based on thermography surveillance results obtained on October 25, 2013.
The 2013 thermography surveillance indicated the breaker was in the Level II - Warning Range (a temperature rise of greater than 25 degrees F and less than 50 degrees F for 480 Volt equipment). Procedure instruction for 480 Volt breakers is to take action recommended by the Preventative Maintenance Team. Condition Report CR-PNP-2013-7196 was issued and the pump was identified as operable. No follow-up maintenance work was performed to address the potential high temperature condition. Work Order (WO) 366187 to replace the overload relay was created on October 28, 2013 but not worked until after the SSW pump was declared inoperable in March 2016.
SSW Pump P208B TS operability surveillances during the 2013 to 2016 time frame were performed with acceptable results. No actions were taken or believed necessary to replace the overload relay to demonstrate TS operability.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
Pilgrim Nuclear Power Station 05000293 i The February 29, 2016 thermography surveillance indicated high temperature in the breaker overload relay area. The high temperature readings met the procedure criteria for Level II - Warning and Preventative Maintenance Team action recommendation. A subsequent review and follow-up evaluation by engineering resulted in a delayed declaration of SSW Pump P208B inoperability on March 4, 2016 due to the high temperature readings, pump current readings, and conservative consideration for potential low voltage accident conditions. The pump overload relay was replaced via WO 366187 on March 5, 2016 and the SSW pump was restored to Operable status.
TS LCO Action Statement (AS) 3.5.B.4.A allows continued reactor operation with one inoperable SSW subsystem (loop) provided the SSW subsystem is restored to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (allowed restoration time). If the SSW subsystem is not restored to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, the TS LCO AS requires the reactor to be in Cold Shutdown within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> (shutdown completion time).
Based on the assumption that SSW Pump P-208B was inoperable from the time that the high temperature was noted on October 25, 2013 until the pump was declared operable on March 5, 2016, a review of all the other SSW pumps operability status was performed. One instance of the SSW subsystem (loop) A being inoperable for a time period that exceeded the combined allowed restoration time and shutdown completion time of 96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> was identified. This occurred from 1947 hours0.0225 days <br />0.541 hours <br />0.00322 weeks <br />7.408335e-4 months <br /> on November 8, 2015 to 1644 hours0.019 days <br />0.457 hours <br />0.00272 weeks <br />6.25542e-4 months <br /> on November 18, 2015 for a total of 236.95 hours0.0011 days <br />0.0264 hours <br />1.570767e-4 weeks <br />3.61475e-5 months <br />. Continuing to operate for a duration exceeding 96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> with the SSW loop A inoperable resulted in operation prohibited by the TS.
CAUSE OF THE EVENT
The cause of the SSW Pump P-208B overload relay high temperature readings was evaluated and determined to be a high resistance connection on the overload relay heater assembly. Inadequate predictive maintenance monitoring was identified as the apparent cause for not periodically assessing the breaker status and replacing the breaker overload relay prior to March 5, 2016.
Review of the work orders that performed thermography on the SSW pumps found that the SSW Pump P-208B breaker (52M-1544) had not had a thermography image taken for almost three years, even though the required periodicity for thermography performance on the breaker is every six months. Procedure 3.M.3-60 "Infrared Thermography" allows not performing the thermography on a component if the component is not running.
The Work Order (WO) 366187 to replace the overload relay was created on October 28, 2013 but not worked until after the SSW pump was declared inoperable in March 2016. WO 366187 was given a work priority of 3D. The guidance for scheduling a WO with work priority of 3D is to — Schedule at next available system / component outage within the Cycle Plan or based on Modification scheduled. Contrary to the scheduling guidance, the WO was not worked until after SSW Pump P-208B was declared inoperable.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
Pilgrim Nuclear Power Station 05000293
CORRECTIVE ACTIONS
Corrective action was taken to replace the installed breaker overload relay to restore SSW Pump B Operability. The breaker overload relay installed during the 2013 to 2016 timeframe was an Eaton Corp (formerly Cutler-Hammer; EIIS Code = T020), Type A, Cat Number - FH93 relay (EIIS Code = 59).
Additional corrective actions are captured in the corrective action program in Condition Reports CR-PNP-2016- 01546, - 2057, and -02061.
SAFETY CONSEQUENCES
The safety objective of the SSW system is to provide a heat sink for the reactor building closed cooling water (RBCCW) system under normal, transient, and accident conditions. The SSW system has five (5) SSW pumps and is designed with sufficient redundancy so that no single active system component failure can prevent the system from achieving the safety objective. The system is designed to continuously provide a supply of cooling water to the secondary side of the RBCCW heat exchangers adequate to meet the requirements of the RBCCVV,system under all conditions. The RBCCW system provides the necessary cooling requirements for the residual heat removal (RHR) system and ultimately the reactor and primary containment.
The SSW pumps are separated into two loops. Two pumps are connected to each loop and the fifth pump can feed either loop. Initiation of standby AC power following loss of the preferred AC power source will automatically start at least one pump in each loop during normal conditions. Following a LOCA and loss-of- offsite power one pump will start in each loop because of diesel load limitations. Additional pumps are started manually by the operator as additional cooling loads are established and diesel capacity is available.
Technical Specifications require two SSW loops to be operable whenever fuel is in the vessel and reactor coolant temperature is greater than 212 degrees F. Operability of each loop requires at least two SSW pumps to be operable in the loop along with the associated controls to demonstrate SSW loop operability.
Only one SSW loop is required to perform the safety functions. Since SSW Loop B was operable during this time period, no loss of safety function occurred.
There was no adverse impact on the public health or safety.
REPORTABILITY
This report is submitted in accordance with 10 CFR 50.73(a)(2)(i)(B), Operation or condition prohibited by Technical Specifications.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information Pilgrim Nuclear Power Station 05000293
PREVIOUS EVENTS
LERs for the previous ten years were reviewed for SSW Pumps being inoperable. These LERs are summarized as follows:
Basis Ambiguity Voltage These prior LERs involved events where SSW Pumps were declared inoperable at the same time. However, the events are different because they did not involve inadequate predictive maintenance monitoring.
ENERGY INDUSTRY IDENTIFICATION SYSTEM (EIIS) CODES The EllS codes for Components and Systems referenced in this report are as follows:
COMPONENTS
CODES
Relay - Overvoltage 59
SYSTEMS CODES
Low Voltage Power System Class lE ED
REFERENCES:
Condition Report CR-PNP-2016-01546 — 52M-1544 (SSW Pump B) thermal image hot spots Condition Report CR-PNP-2016-03308 — Comparison of 2016 to 2013 thermography surveillance results for SSW Pump B, Bkr 1544 overload relay for Past Operability Condition Report CR-PNP-2013-07196 — Thermography surveillance results on SSW Pump motor supply breakers Condition Report CR-PNP-2016-02057 — Work Management Problem Area Condition Report CR-PNP-2016-02061 — Engineering Programs Problem Area
|
---|
|
|
| | Reporting criterion |
---|
05000293/LER-2016-010 | MSIV Inoperability Led to a Condition Prohibited by the Plant s Technical Specifications LER 16-010-01 for Pilgrim Nuclear Power Station re MSIV Inoperability | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000293/LER-2016-001 | Both Emergency Diesel Generators Inoperable LER 16-001-00 for Pilgrim Nuclear Power Station Regarding Both Emergency Diesel Generators Inoperable | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor | 05000293/LER-2016-002 | Online Maintenance Test Configuration Prohibited By Technical Specifications LER 16-002-00 for Pilgrim Nuclear Power Station Regarding Online Maintenance Test Configuration Prohibited By Technical Specifications | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ix)(A), Prevented Safety Function in Multiple System | 05000293/LER-2016-003 | Spent Fuel Storage Design Feature Exceeded LER 16-003-00 for Pilgrim Nuclear Power Station Regarding Spent Fuel Storage Design Feature Exceeded | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000293/LER-2016-004 | Salt Service Water Pump B Past Operability - Operation or Condition Prohibited by Technical Specifications LER 16-004-00 for Pilgrim Nuclear Power Station Regarding Salt Service Water Pump B Past Operability - Operation or Condition Prohibited by Technical Specifications | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000293/LER-2016-005 | Ultimate Heat Sink and Salt Service Water System Declared Inoperable | 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000293/LER-2016-006 | 1 OF 4 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000293/LER-2016-007 | Manual Reactor Scram Due To Feedwater Regulating Valve Malfunction LER 16-007-00 for Pilgrim Nuclear Power Station Regarding Manual Reactor Scram Due To Feedwater Regulating Valve Malfunction | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000293/LER-2016-008 | Emergency Diesel Generator 'A' Past Inoperability LER 16-008-00 for Pilgrim Nuclear Power Station Regarding Emergency Diesel Generator 'A' Past Inoperability | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000293/LER-2016-009 | HPCI Declared Inoperable Due to Failure of 1ST Surveillance Test | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident |
|